Top Banner
Al Ain Gharbia Emirati Housing & Infrastructure Project Client: Aldar Properties Location: Al Ain, UAE Scope of Services: Civil MEP Infrastructure Project Duration: Sept. 2011 - Ongoing Significant Features: 155 hectares 600 villas Estidama 2 Pearls 22km of internal roads Solar panels and solar water heating system. The Challenge Pivot proposed an amended design for foundations, walls, slabs, parapets and all related MEP works, for 400 villas to enable pre-cast construction in order to compress the schedule. U-values were calculated during the re-design of the pre-cast envelope to ensure that the energy conservation designed by the Consultant to achieve 2 Pearls was retained. 30% reduction in annual water consumption 25% reduction in annual energy consumption 80% of hot water is generated by solar system 20% of materials were sourced within 500km of the site 60% of construction waste was recycled Facts & Figures Estidama 2 Pearls
1

Al Ain Gharbia Emirati Housing & Infrastructure ProjectAl Ain Gharbia Emirati Housing & Infrastructure Project Client: Aldar Properties Location: Al Ain, UAE Scope of Services: Civil

Jul 28, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Al Ain Gharbia Emirati Housing & Infrastructure ProjectAl Ain Gharbia Emirati Housing & Infrastructure Project Client: Aldar Properties Location: Al Ain, UAE Scope of Services: Civil

Al Ain Gharbia Emirati Housing & Infrastructure Project

Client: Aldar Properties

Location: Al Ain, UAE

Scope of Services: Civil MEP Infrastructure

Project Duration: Sept. 2011 - Ongoing

Significant Features: • 155 hectares

• 600 villas

• Estidama 2 Pearls

• 22km of internal roads

• Solar panels and solar water heating system.

The Challenge Pivot proposed an amended design for foundations, walls, slabs, parapets and all related MEP works, for 400 villas to enable pre-cast construction in order to compress the schedule.

U-values were calculated during the re-design of the pre-cast envelope to ensure that the energy conservation designed by the Consultant to achieve 2 Pearls was retained.

30% reduction in annual water consumption

25% reduction in annual energy consumption

80% of hot water is generated by solar system

20% of materials were sourced within 500km of the site

60% of construction waste was recycled

Facts & Figures

Estidama 2 Pearls