Project Execution Plan for Airport Construction Details of how an Airport is constructed, and how the progress, safety and quality is monitored and controlled. Also the measures to ensure that the site is environmentally friendly. David H Moloney 1 st August 2016 Brief Description The purpose of this presentation is to give an understanding of the Methods, Plant and Sequence to construct an Airport. This presentation can be used to engage Stakeholders and to get the Site Teams commitment to the programme. Also can be used for Induction Training and as a way to capture and share knowledge. Project Execution Plan (PEP) details how a project will be executed, monitored and controlled. High in Educational Value and easily understood. Recommended for Continuing Professional Development (CPD) This Video Presentation is innovative and has many beneficial uses. YouTube https ://youtu.be/LY4gXkUgK_Y
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Project Execution Plan for Airport Construction Details of how an Airport is constructed, and how the progress, safety and quality is monitored and controlled. Also the measures to ensure that the site is environmentally friendly.
David H Moloney
1st August 2016
Brief Description
The purpose of this presentation is to give an understanding of the Methods, Plant and Sequence to construct an Airport.
This presentation can be used to engage Stakeholders and to get the Site Teams commitment to the programme. Also can be used for Induction Training and as a way to capture and share knowledge.
Project Execution Plan (PEP) details how a project will be executed, monitored and controlled.
High in Educational Value and easily understood. Recommended for Continuing Professional Development (CPD)
This Video Presentation is innovative and has many beneficial uses.
Contractors Site facilities comprise:Offices, Canteens, Toilets, Drying Rooms, Stores, Plant Yard, generators and Workshops.
Contractor’s Temporary Site Facilities
ⓒ David H Moloney
Genera
l Item
s
To see animations and clips, see my YouTube Film
Contractor’s Camp for 8,000 persons
ⓒ David H Moloney
Genera
l Item
s
Sheet Pile Temporary Shaft
ⓒ David H Moloney
Genera
l Item
s
Brief Description
Sheet Pile Temporary shaft is used to enable an excavation for a deep structure.The construction sequence is:Install sheet-piles.Excavate and install bracing.Excavate to final level.Construct concrete structure.Backfill, remove bracing and sheet-piles
Sheet pile Temporary Shaft
ⓒ David H Moloney
Genera
l Item
s
3D Animation to show Sequence
Dewatering
ⓒ David H Moloney
Genera
l Item
s
Brief Description
Construction dewatering is the removal or drainage of
groundwater and or surface / rain water usually by
pumping to keep the works dry.
Dewatering
ⓒ David H Moloney
Genera
l Item
s
Dewatering by Wellpoints
ⓒ David H Moloney
Genera
l Item
s
Water Pollution Prevention
ⓒ David H Moloney
Genera
l Item
s
Brief Description
Pumped and rain water that is contaminated with clay and
silt needs to be treated prior to discharge from site.
Settlement ponds and settlement tanks are two methods
Dewatering by Settlement Lagoon
ⓒ David H Moloney
Genera
l Item
s
Dust Suppression
ⓒ David H Moloney
Genera
l Item
s
Temporary Fence type 1
ⓒ David H Moloney
Genera
l Item
s
Brief Description
Examples of temporary security fences that are higher than the usual
Temporary Fence type 1
ⓒ David H Moloney
Genera
l Item
s
Temporary Fence type 2
ⓒ David H Moloney
Genera
l Item
s
Brief Description
Temporary fence on precast beam for airport.
Temporary Fence type 2
ⓒ David H Moloney
Genera
l Item
s
Site Hoarding examples
ⓒ David H Moloney
Genera
l Item
s
FalseworkG
enera
l Item
s
Brief Description
Falsework to support Bridge deck formwork
Climbing Tower Cranes
Brief Description
A climbing tower crane lifts itself up using a climbing
attachment with hydraulic jacks that surrounds the mast.
The climbing attachment lifts itself up off the erected mast
and inserts a new mast section.
Rail mounted Tower Cranes layout plan and photographs for
airport passenger terminal building, showing the tower
cranes locations, rail track travel range and working area
coverage.
Genera
l Item
s
Climbing Tower CranesM
iscella
ne
ous
Climbing Tower CranesG
enera
l Item
s
Tower Cranes LayoutG
enera
l Item
s
Tower Cranes on RailsG
enera
l Item
s
Staff Offices for Departments
Department Functions
Planning Planning & Progress Monitoring
HSSE Health, Safety, Security & Environmental
Quality Assurance Quality Control
Procurement Materials & Subcontractors
Engineering Shop drawings & submissions
Quantity Surveying Monthly & final accounts
Document Control Distribution of Construction Information to Site Team
Plant & Equipment Hiring, Fuelling & Maintenance of Plant
I.T. Computers, software & Internet
Administration Payments
Human Resources
Site LaboratoryG
enera
l item
s
Traffic Management
ⓒ David H Moloney
Genera
l Item
s
Brief Description
Traffic management plans are necessary when working on or beside roads
Traffic Management - Realign Motorway under new Bridges
ⓒ David H Moloney
Genera
l Item
s
Traffic Management - Realign Motorway under new Bridges
ⓒ David H Moloney
Genera
l Item
s
Traffic Management – Divert Live Traffic onto Realigned Carriageway
ⓒ David H Moloney
Genera
l Item
s
Temporary Site Entrance
ⓒ David H Moloney
Genera
l Item
s
Temporary Roads & Entrances
ⓒ David H Moloney
Genera
l Item
s
Weighbridge & Sheeting Access
ⓒ David H Moloney
Genera
l Item
s
Wheel Wash Drive-through
ⓒ David H Moloney
Genera
l Item
s
Wheel Wash Drive-throughG
enera
l Item
s
Stores for Materials
ⓒ David H Moloney
Genera
l Item
s
Stores for Materials
ⓒ David H Moloney
Genera
l Item
s
Site Layout & Locations of Temporary Facilities
ⓒ David H Moloney
Genera
l Item
s
Temporary Electricity Supply & Tower Lights
ⓒ David H Moloney
Genera
l Item
s
Welfare Facilities
ⓒ David H Moloney
Genera
l Item
s
Toilets – Washing
Canteen, Drying Room, Toilet & Generator
Geotechnical
Vibro Compaction - Sequence, Plant & Methods
ⓒ David H Moloney
Geote
chnic
al
Brief Description
Vibro compaction is used to compact granular
ground to improve its load bearing capacity and
reduces the seismic liquefaction potential. Used
for the Palm Islands in Dubai.
A vibrator suspended from a crane is used and
inserted to a triangular grid pattern.
Vibro Compaction - Sequence, Plant & Methods
ⓒ David H Moloney
Geote
chnic
al
Stone Columns ⓒ David H MoloneyG
eote
chnic
al
Brief Description
Stone columns are used to improve the load
bearing capacity of ground.
Top feed vibrators suspended from an excavator or
crane along with loading shovels are used.
The stone columns are constructed to a triangular
grid pattern.
Stone Columns
ⓒ David H Moloney
Geote
chnic
al
Earthworks
Much Shifting
Brief Description
Muck Shifting is the process of moving
large quantities of soil and rock. Eart
hw
ork
s
Excavate & Load, Cart, Tip & Return
Brief Description
Cycle Time for 7km haulage distance using an Excavator 45 tonne weight and Dumper with a 40 tonne capacity, the cycle time is 34 minutes
Eart
hw
ork
s
7 minutes
14 minutes
3 minutes
14 minutes 7 km
7 km
Spreading & CompactionE
art
hw
ork
s
Spreading & CompactionE
art
hw
ork
s
Rock - Excavability
Brief Description
The excavability of rock depends
mainly on the rock strength and the
layer thickness. This diagram shows
excavation methods for rock of
various strengths and thicknesses,
with a free face.
ⓒ David H Moloney
Eart
hw
ork
s
Rock-breakingE
art
hw
ork
s
Rock-breakingE
art
hw
ork
s
Rock Drilling & Blasting – Road CutE
art
hw
ork
s
Mass Haul DiagramE
art
hw
ork
s
Brief Description
Shows the quantities and location of
excavation and fill quantities for
motorway.
Excavation for Underground Pump stationE
art
hw
ork
s
Brief Description
Faces of excavation Battered &
Well-point Dewatering used.
Excavation for Trenches with Stepped FacesE
art
hw
ork
s
Excavation for Trenches with Battered FacesE
art
hw
ork
s
Backfill TrenchE
art
hw
ork
s
Crushed Aggregate Base CourseE
art
hw
ork
s
Brief Description
Crushed Aggregate Base Course
CABC mixing and Laying
CABC ( Crushed aggregate base course )E
art
hw
ork
s
Mixing Plant
Testing Compaction
Mixing CABCE
art
hw
ork
s
Spreading & Compaction CABCE
art
hw
ork
s
Spreading & Compaction CABC ( Crushed aggregate base course )E
art
hw
ork
s
Spreading & Compaction CABCE
art
hw
ork
s
Piling
Piling Construction - Plant & Methods
Brief Description
Piling Plant, Equipment and Material;
Crawler Crane, Piling Hammer, Temporary Casing,
Piling Rig, Concrete Pump, Concrete Mixer Trucks,
Tremie Pipe and Reinforcement Cage
Pili
ng
Piling Construction - Plant, Methods & SequenceP
iling
Piling Construction - Plant & MethodsP
iling
Piling Construction - Vertical PilesP
iling
Piling Construction - Raking PilesP
iling
Piling Construction - Raking PilesP
iling
Pile Load Test
ⓒ David H Moloney
Pili
ng
Brief Description
A jack is used to load the pile in steps and
gauges measure any settlement.
Pile Load Test
ⓒ David H Moloney
Pili
ng
Concrete
Concrete Full Scale Trial Castings of Pier
ⓒ David H Moloney
Brief Description
The full-scale trial casting(s) shall
demonstrate/document that all
requirements to the concrete and the
execution of the work are fulfilled
simultaneously using the actual
methods and performed by personnel as
for the future production.
Concre
te
BIM 3D Model Shutter Fibreglass
Concrete Full Scale Trial Castings of Bridge Deck
Brief Description
The full-scale trial casting(s) shall
demonstrate/document that all
requirements to the concrete and the
execution of the work are fulfilled
simultaneously using the actual
methods and performed by personnel as
for the future production.
Concre
te
Fresh Concrete Properties Tests
Air Content, Consistence, Density, Initial and Final Setting Time, Temperature
and Bleeding
Chloride Ion Content
Hardening and Hardened Concrete Properties Tests:
Density and Compressive Strength for 1, 3, 7, 14 and 28 Days