This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
DEA&DP Ref: E18/2/3/2/2-Ptn 11 Farm 59 Meerlustkloof (s 24G) Caledon
REVISED FINAL ENVIRONMENTAL IMPACT REPORT
APPLICATION IN TERMS OF NEMA s 24G FOR RECTIFICATION OF
REVISED FINAL EIR FOR ‘MEERLUSTKLOOF’ 59/11, CALEDON
Page 5 of 111
ABBREVIATIONS
CARA Conservation of Agricultural Resources Act, 1983 (Act no. 43 of 1983)
CBA Critical Biodiversity Area
DEA&DP Department of Environmental Affairs and Development Planning
DWA Department of Water Affairs
EAP Environmental Assessment Practitioner
ECA Environment Conservation Act (Act no. 73 of 1989)
EIA Environmental Impact Assessment
EIR Environmental Impact Report
EMP Environmental Management Programme
GN Government Notice
I&APs Interested and Affected Parties
IEM Integrated Environmental Management
NEMA National Environmental Management Act (Act no. 107 of 1998)
NEMBA National Environmental Management: Biodiversity Act (Act no. 10 of 2004)
NFEPA National Freshwater Ecosystem Priority Area
NHRA National Heritage Resources Act (Act no. 25 of 1999)
NWA National Water Act (Act no. 36 of 1998)
SAHRA South African Heritage Resources Agency
SPC Spatial Planning Categories
REVISED FINAL EIR FOR ‘MEERLUSTKLOOF’ 59/11, CALEDON
Page 6 of 111
1. INTRODUCTION
A Final Environmental Assessment Report relating to the application for ‘retrospective’
authorisation of an emergency irrigation sump excavated at the end of 2008 was submitted to
the Department of Environmental Affairs and Development Planning in September 2012. This
report has, however, had to be revised to reflect the full ambit of unauthorised activities that
followed the flood in November 2008 and, more recently, flood damage in October 2012. This
report therefore replaces the final draft that was submitted to the Department of
Environmental Affairs and Development Planning in September 2012.
The application relates to emergency interventions initiated by Agrisouth Orchards (SA) (Pty) Ltd
in response to two highly destructive floods that occurred on its farm ‘Meerlustkloof’ in
November 2008 and October 2012.
‘Meerlustkloof’ is located in the Caledon magisterial district and falls within the Theewaterskloof
Local Municipality. The nearest settlement is Genadendal, some 12.5 km to the east. The farm is
about 32 km from Caledon by road. See Figure 1.
Figure 1:
REVISED FINAL EIR FOR ‘MEERLUSTKLOOF’ 59/11, CALEDON
Page 7 of 111
The farm comprises three portions:
−−−− Elandskloof 59/9;
−−−− Elandskloof 59/11; and
−−−− Elandskloof 59/4.
This application relates to the farm portions Elandskloof 59/11 and Elandskloof 59/4.
Agrisouth Orchards (SA) (Pty) Ltd (‘Agrisouth’) purchased the ‘Meerlustkloof’ property in 1990.
‘Meerlustkloof’ is a working fruit farm which exports apples and pears. It was established as a
fruit farm in 1970. Orchards occupy about 109 ha or roughly 12% of the 929 ha farm, which spans
the Elandskloof River and a tributary, the Meerlustkloof River. The Elandskloof River joins the
Riviersonderend which also represents the southern boundary of the farm.
The terrain is hilly and rises steeply from the floodplains of the two rivers to the Riviersonderend
Mountains directly to the north. The foothills of the Riviersonderend Mountains are characterised
by deeply incised kloofs. ‘Breëkraal se Rante’ overlook the Elandskloof River from the west. See
Figure 2 for a topo-cadastral map of the property.
The ‘Introduction’ firstly describes the broad physical landscape, and how this shapes the spatial
layout of orchards and associated infrastructure, before summarising the impacts of each flood
episode and, in turn, how the Applicant responded to the ensuing disruption to farming
operations.
The ‘Introduction’ also identifies the listed activities1 for which rectification is sought, describes
the scope of work and records the assumptions and limitations that informed and defined the
environmental assessment.
1 The legal and regulatory context relating to the unauthorised activities in question is presented in detail in
Chapter 2 of this report.
REVISED FINAL EIR FOR ‘MEERLUSTKLOOF’ 59/11, CALEDON
Page 8 of 111
Figure 2: Topography of farm and sites of flood damage, 2008 and 2012
1.1 LAYOUT OF THE FARM IN RELATION TO THE PHYSICAL LANDSCAPE
Topography, the major drainage systems and distribution of arable soils dictate the location of
orchards and infrastructure on the farm. It is necessary to understand the physical opportunities
and constraints within which this farming operation functions in order to understand the
Applicant’s response to the destructive effects of floods. See Figure 2 for a schematic explanation
of the main features referred to here.
1.1.1 Overview of river and floodplain (wetland) systems
Two rivers that drain southwards from the Riviersonderend Mountains converge on the farm
‘Meerlustkloof’ – the Elandskloof River (the larger of the two watercourses) and a tributary that
joins the Elandskloof River from the east, the Meerlustkloof River. These rivers form a typically
dendritic or ‘Y’-shaped pattern, with the Elandskloof River forming the left-hand ‘arm’ and stem
of the ‘Y’. The Elandskloof River joins the eastwards-flowing Riviersonderend about 3 km below
REVISED FINAL EIR FOR ‘MEERLUSTKLOOF’ 59/11, CALEDON
Page 9 of 111
its convergence with the Meerlustkloof River. The floodplains associated with two watercourses
represent the most intensively developed parts of the farm. Chapter 3 describes the natural
environment.
1.1.2 River crossings
The local topography and two rivers effectively divide the cultivated parts of the farm into three
sections which are informally labelled A, B and C for the sake of explanation (see Figure 3). These
sections are separated as follows by the two rivers:
Section of farm Right (W) bank2 Left (E) bank
(A) North of confluence of Meerlustkloof
and Elandskloof rivers (affected reach ± 1.5
km)
Orchards, roads and
employee
accommodation
Orchards, roads
and packing sheds
2 Convention holds that the viewer is facing downstream when referring to the left or right banks of a river
REVISED FINAL EIR FOR ‘MEERLUSTKLOOF’ 59/11, CALEDON
Page 10 of 111
(B) Elandskloof River from Meerlustkloof
River to the DR1313 (± 3 km)
Orchards, roads and
employee
accommodation
Orchards, roads
and pump house
(C) Elandskloof River from the DR1313 to
the Riviersonderend River (± 0.5 km)
Orchards, two
pump houses and
roads
Orchards and roads
The main, tarred, access road to the farm from the DR1313 runs in a northerly direction to the
east of the Elandskloof River. Gravel roads connect the latter road with accommodation,
infrastructure and orchards on the western (right) banks of the two rivers by means of two
crossings (see Figures 2 and 3).
Access to Section A from the main transport axis on the farm is located next to the packing sheds,
on the left bank of the Meerlustkloof River. Before November 2008, a cement bridge spanned the
Meerlustkloof River at this point. Flood damage necessitated the replacement of the bridge with
a temporary pipe culvert, which is described below.
See Appendix C for photographs of the respective sites.
The box on the right provides the co-ordinates for the
respective sites.
Section B of the farm used to be connected to the
remainder of the property by means of a concrete drift
across the Elandskloof River, about 140 m downstream
of the confluence of the two rivers. The drift was also
replaced by a pipe culvert following its destruction by
the November 2008 flood.
Access arrangements to Section C are recorded for the sake of completeness. This part of the
farm is readily accessible from the DR1313, which was severely damaged at its crossing over the
Elandskloof River in October 2012.
Repairs in November 2012 to the damaged pipe culvert over the Elandskloof River were
undertaken by either the Overberg District Council or the Western Cape Department of Transport
and Public Works.
Bridge Meerlustkloof River
34° 2'53.03"S 19°24'56.84"E
Bridge Elandskloof River
34° 3'07.91"S 19°24'56.97"E
Drift Elandskloof River
34° 3'08.12"S 19°24'57.39"E
Sump Elandskloof River
34° 3'15.64"S 19°25'13.70"E
Pipeline Elandskloof River
34° 3'47.46"S 19°26'11.96"E
REVISED FINAL EIR FOR ‘MEERLUSTKLOOF’ 59/11, CALEDON
Page 11 of 111
1.1.3 Irrigation infrastructure
Altogether 109 ha of ‘Meerlustkloof’ are under irrigated orchard. The farm is watered from three
main sources:
− About 37 ha of orchards in the upper reaches of the farm are irrigated from an earth-
walled dam that is replenished via a pipeline from the mountains (centre point of the
dam – approx. 34°02'19.11"S 19°25'11.25"E);
− Another 31 ha of orchards in the lower-lying parts of the farm, i.e. towards the
Riviersonderend, receive water from the Zonderend Water Users Association; and
− The middle parts of the farm – constituting about 41 ha of orchards or a third of the
entire planting – are irrigated by water abstracted directly from the Elandskloof River.
The critical period for irrigation is usually between October and March, over the dry summer
months.
It has been the central portions of the farm, which are irrigated from the Elandskloof River, that
have been most adversely affected by floods episodes over the past seven years, namely in 2006,
2007, 2008 and 2012.
Until 2006, water was taken from a concrete weir about 800 m downstream of the confluence of
the Elandskloof and Meerlustkloof rivers. The pump house, which is still in use, is about 200 m
north-east of the location of the former weir. It is understood that the weir was built at the time
that ‘Meerlustkloof’ had been first developed as a fruit farm, and therefore had been in operation
for at least 20 years by the time ‘Meerlustkloof’ was bought by Agrisouth Orchards (SA) (Pty) Ltd.
The structure was apparently about 1.5 m high and 25 m wide.
The weir was ruptured in a flood in the autumn of 2006 and rendered inoperable by another
flood in November 2007. In order to ensure that irrigation was not interrupted, a pipe was
installed at a bridge upstream of the weir and connected via a gravity feed to the pump station.
This temporary system was destroyed by yet another flood, in November 2008, which swept
away about 5 ha of orchards, the drift and two bridges, and destroyed farm roads along the banks
of both rivers.
The preceding sections described the broad topography and layout of the farm, and the
infrastructural elements – river crossings and abstraction points – that have borne the brunt of
flood damage. The following section provides a more detailed account of damage that resulted
from the floods of November 2008 and October 2012 respectively. It also describes the actions
REVISED FINAL EIR FOR ‘MEERLUSTKLOOF’ 59/11, CALEDON
Page 12 of 111
taken by Agrisouth Orchards (SA) (Pty) Ltd to protect is property and secure the ‘Meerlustkloof’
farming operation against further disruption and, potentially, loss of production.
1.2 FLOOD DAMAGE: NOVEMBER 2008
Cut-off low pressure systems contributed to substantial flooding in the Cape Winelands and
Overberg districts between 11 and 13 November, 2008 (Holloway and Fortune, 2009). Although
meteorologically less significant than a similar event the previous year, the November 2008 cut-
off low contributed significant losses which totalled R943-million in the Winelands and Overberg.
At ‘Meerlustkloof’, 369 mm of rainfall were measured between 11 and 13 November 2008 (Mr
Arrie Grobler, pers comm, 24-01-2013). The swollen rivers and ensuing erosion damaged bridges,
roads, orchards and irrigation systems, and large parts of the farm were left isolated for several
days. The damage to farm infrastructure is described below.
1.2.1 Meerlustkloof River
As indicated previously, a cement bridge used to connect the two banks of the Meerlustkloof
River just upstream from the packing sheds. This bridge was, however, washed away in November
2008. It was replaced by a vented culvert comprising two segmented 1.5 m diameter concrete
pipes overlain with a one-lane deck built from wooden poles and compacted rock. This structure
remained in place until it was breached by the flood in October 2012 (Figures 5 and 6, Appendix
C).
1.2.2 Elandskloof River
The river channel downstream of the former drift over the Elandskloof River had been about 26 m
wide prior to the flood in November 2008. Lateral erosion cut massively into both banks of the
river, increasing the bank width of the channel by some 30 m to 150 m – in other words, a three
to five-fold increase in the width of the incised area. Figure 1, Appendix C, shows the extent of
erosion and deposition of coarse sediments across the width of the flood channel.
The river was ‘opened up’ relatively less at the site of the former weir (~25 m in 2004) but its
width was approximately doubled by the 2008 flood. A rock outcrop that strikes laterally into the
channel appears to have inhibited erosion at the site of the weir (see Figure 4, Appendix C, which
shows the remains of the weir in the bed of the Elandskloof River), although the remains of the
structure appeared to have deflected flow towards the left bank.
REVISED FINAL EIR FOR ‘MEERLUSTKLOOF’ 59/11, CALEDON
Page 13 of 111
The former drift spanning the Elandskloof River was irrevocably damaged in the November 2008
flood. As with the damaged crossing at the packing shed, this reach of the Elandskloof River was
also subsequently spanned by an informal pipe culvert with three segmented 1.5 diameter pipes
and a single-lane deck built from poles and compacted rock. The rebuilt structure was severely
damaged by the flood in October 2012 (Figure 7, Appendix C).
The November 2008 flood also destroyed the relocated abstraction point and, with the weir
entirely inoperable as a result of flood damage, necessitated urgent steps to reinstate a supply of
water to irrigate fruit trees. It bears noting that the 2008 flood coincided with the onset of the
hot, dry summer season, which meant that securing a reliable supply of water in order to irrigate
fruit trees was a pressing concern for the farm.
From a business perspective, the situation amounted to an emergency. If irrigation had not been
resumed timeously, up to R3.8-million’s worth of annual fruit production from the 41 ha of
orchards in question could have been lost. It takes about five years for a newly planted orchard to
start bearing fruit that can be harvested. Had it been necessary to replace water-stressed fruit
trees, the total cost to Agrisouth would have been in the order of R20-million in forfeited income
(pers comm. Mr André van Wyk, 23 April 2013).
At the time, the Western Cape Department of Agriculture was unable to provide advice
immediately on what steps should be taken to reinstate irrigation to the central portions of the
farm. An irrigation firm based in Worcester, Brandwacht Besproeiing, apparently recommended
that a sump be excavated in the reworked bed of the river, upstream of the former weir.
The excavations were undertaken as advised and the water supply to the orchards was re-
established in December 2008. The structure in question entails an excavation of some 2 900 m2
in extent which is surrounded, except at its upstream extremity, by a bulldozed berm. See Figures
1 and 3, Appendix C, for photographs of the sump. It was necessary to raise the level of water to
allow a gravitational feed to the pump station on the northern or left bank of the Elandskloof
River. The excavation was limited in its entirety to the massively scoured and widened channel
that resulted from the flood in November 2008.
The next section describes the impacts of the October 2012 flood on the farm ‘Meerlustkloof’.
REVISED FINAL EIR FOR ‘MEERLUSTKLOOF’ 59/11, CALEDON
Page 14 of 111
1.3 FLOOD DAMAGE: OCTOBER 2012
Heavy rainfall in the catchments of the Elandskloof and Meerlustkloof rivers resulted in the
destruction of two bridges and substantial erosion of roads and orchards on ‘Meerlustkloof’
between 14 and 21 October 2012. Altogether 250 mm of rain was measured in this period.
The damage that required the most urgent attention was:
− The rupturing of two pipe culvert crossings that resulted in about 20 ha of orchards on the
western banks of the Meerlustkloof and Elandskloof rivers (i.e, sections A and B of the farm)
being made inaccessible to vehicles for spraying and eventual harvesting;
− Loss of the water supply, as a result of lateral, westwards migration of the Elandskloof River,
to the emergency sump, and damage to pipes that supplied more than half of the farm’s
irrigation water; and
− Inundation of two pump houses near the Riviersonderend as a result of sediment build-up in
the latter river that has caused flow to back up above the obstruction.
The question of how to deal with sediment build-up at the confluence of the Riviersonderend and
Elandskloof River does not form part of this application. It is clearly, however, a significant
problem that holds adverse consequences for both the farm and the environment. It is also a
problem that needs to be addressed at the appropriate hydro-geomorphological and ecological
scales. This is an issue that should form part of the scope of work for the proposed strategic
management plan for the Elandskloof and Meerlustkloof Rivers (see Chapter 8).
1.3.1 Meerlustkloof River
Although the channel and banks of the highly disturbed Meerlustkloof River remained largely
unscathed as a result of the flood in October 2012, a portion of the bridge at the packing sheds
was washed away, leaving Section A entirely cut off from the rest of the farm. See Figure 6,
Appendix C.
Advice was obtained from the Western Cape Department of Agriculture and a specialist
freshwater ecologist on the best method for effecting emergency repairs to the breached
structure (see Appendices D and E for correspondence and specialist reports relating to the best
approach to implementing the emergency repairs). In summary, it was recommended that:
−−−− Additional pipes be added to the culvert to improve its capacity to accommodate
elevated base flows;
REVISED FINAL EIR FOR ‘MEERLUSTKLOOF’ 59/11, CALEDON
Page 15 of 111
−−−− A temporary berm be constructed to deflect flow into the existing pipes for the duration
of repairs;
−−−− Rehabilitation measures be implemented as a matter of urgency to stabilise the banks by
means of re-shaping and vegetation with appropriate indigenous plants; and
−−−− A long-term solution had to be sought for the crossing, which was vulnerable to damage
by floods and would, unless redesigned, contribute to ongoing degradation and
destabilisation of the river environment.
The severely damaged culvert crossing over the Meerlustkloof River was repaired in November
2012, with the addition of two more segmented, 1.5 m diameter pipes, thereby roughly doubling
the hydraulic capacity of the structure. The deck of the rebuilt log-and-stone structure is about 21
m long and 5 m wide. The spaces between pipes are grouted and protected with stone pitching.
The work has been completed, except for a protective wing wall that needs to be built into the
right-hand bank upstream of the bridge in order to prevent erosion occurring at this point. See
Figure 10, Appendix C.
The four segmented pipes are laid several centimetres above the bed of the channel, but water is
able to percolate below and past the structure through a loosely deposited substrate of cobble
and small boulders. Higher flows would pass through the pipes.
Analysis of satellite imagery indicates that the damaged bridges over the Meerlustkloof River that
were rebuilt after the floods in 2008 and 2012 were both constructed along the same alignment
as the former concrete bridge that was destroyed in 2008. The centre point of the current pipe
culvert crossing over the Meerlustkloof River is: 34o 02’ 53.0”S 19
o 24’ 56.8”E.
1.3.2 Elandskloof River
As was the case with the damaged bridge over the Meerlustkloof River, the western approaches
of the rebuilt structure over the Elandskloof River were washed away in October 2012, isolating
Section B from the rest of the farm. An informal drift was established directly downstream of the
damaged culvert structure as a temporary measure to reinstate contact with Section B. See
Figures 7 and 8, Appendix C, for photographs of the damaged river crossing over the Elandskloof
River and temporary drift respectively.
The drift was about 20 m long and 3.5 m wide. It was constructed from uncemented rocks and
cobbles that had been dislodged from the damaged bridge directly upstream. The drift was
vented by two unanchored pipes. The drift was demolished once the bridge had been repaired
early November 2012 and most vestiges of the drift had disappeared by January 2013. According
REVISED FINAL EIR FOR ‘MEERLUSTKLOOF’ 59/11, CALEDON
Page 16 of 111
to the freshwater ecological assessment (Day, 2013, p 17; Appendix E), the long-term ecological
consequences of the latter drift were “negligible”.
The Applicants, acting on the advice of the Western Cape Department of Agriculture and Dr Liz
Day, the freshwater ecologist, added three additional 1.5 m diameter pipes to the pipe culvert
structure over the Elandskloof River. The structure, which has been built in precisely the same
way as the repaired bridge over the Meerlustkloof River, is currently equipped with six culverts
instead of the previous three (see Figure 11, Appendix C).
The rebuilt bridge over the Elandskloof River appears to be identically aligned to the drift that
spanned the channel until it was destroyed in the flood of November 2008. The centre point of
the repaired bridge is at: 34o 03’ 07.9”S 19
o 24’ 57.0”E
The flood that occurred in October 2012 brought about significant changes to the alignment of
the channel of the Meerlustkloof River in the vicinity of the sump, which was effectively put of
commission owing to changed course of the river.
The channel at the irrigation sump was forced further to the south, and the left bank of the active
channel has been laterally displaced by 15 to 21 m from its previous position. The flood of
October 2012 also precipitated extensive deposits of coarse fluvial material that raised the profile
of the river bed at the intake to the sump which, with down-cutting and lateral migration of the
active channel to the south, left the sump entirely cut off from the channel and its supply of
water.
The channel migration has taken place over a distance of about 200 m. Besides literally stranding
the sump, the realigned river has started under-cutting the farm road that runs along the top of
the southern bank of the Elandskloof River. The active channel has also found its way to the right
of a large, free-standing plinth of sediment whereas it had previously passed this structure to the
left (see Figure 1, Appendix C).
The loss of the sump as an irrigation asset has been effectively off-set by the Applicant’s resort to
two submersible ‘sump pumps’ for taking water for irrigation from the Elandskloof River. These
devices, which operate at water depths of 1 m or more, are portable and each one can be
installed in half a 200 ℓ drum partly sunken into the river bed. This technology, which was not
available when the farm experienced major damage to its irrigation infrastructure in November
2008, has a negligible impact on the riparian environment and does not trigger any requirement
for environmental authorisation. Water is fed to the existing pump station by a ‘quick release’
pipe. Together, the two pumps deliver 60 000 ℓ per hour.
REVISED FINAL EIR FOR ‘MEERLUSTKLOOF’ 59/11, CALEDON
Page 17 of 111
The flood in October 2012 also washed away the irrigation pipe that crossed the Elandskloof River
at the bridge which connected the two banks in Section B as outlined above, as well as a plastic
pipe that conveys water from one of the two pump houses below the DR1313 to the central parts
of the farm. The repairs to the damaged irrigation pipeline did not trigger any activities requiring
environmental authorisation, and are therefore not subject to this section 24G application.
Owing to the vital role of irrigation at ‘Meerlustkloof’, and the challenges of securing irrigation
infrastructure that would not have an adverse environmental impact, or be vulnerable to extreme
events such as floods, the question of the best practicable option for taking water across the
Elandskloof River is simply raised to inform future planning in this regard.
The pipe over the Elandskloof River, which used to be supported on wooden posts secured in
drums dug into the river bed, was replaced provisionally with several ‘quick release ‘aluminium
sections laid across the river bed. Owing to the force of the pump, the pipes had to be reinforced
with wooden poles and steel bindings, which meant that they can no longer be dismantled at
short notice, such as prior to an anticipated flood (Figure 9, Appendix C). The pipe was also liable
to cause erosion under slightly elevated flows and would probably be washed away under flood
conditions. The structure of drums and wooden posts that previously supported the pipe has
since been reinstated (i.e. by March 2013), lifting the pipe about 1 m above the bed of the
channel.
An alternative method for conveying irrigation water across the Elandskloof River at this point has
been identified as a priority action. The freshwater ecologist has recommended two other
alternatives to the system that is currently in place, namely:
− Routing the irrigation pipe via the existing pipe culvert road crossing over the Elandskloof
River (the most ecologically-desirable option); or
− Burying the pipe to a depth of least 0.5 m along its current alignment and securing it to a
gabion mattress (which is viewed as an improvement over the suspension of the pipes as
described above).
Another alternative has since been identified by Mr Hans King of the Western Cape Department
of Agriculture, namely suspending the pipeline from cable strung between two towers.
Any decision about the long-term routing and alignment of the water pipeline will have to be held
in abeyance until after the 2013 harvest as irrigation cannot be interrupted in this crucial period.
Also, if environmental authorisation is needed for either of the additional alternatives outlined
above, this is unlikely to be achieved before the onset of the 2013 winter and ‘flood season’ when
REVISED FINAL EIR FOR ‘MEERLUSTKLOOF’ 59/11, CALEDON
Page 18 of 111
work would in any case not be able to take place in the river. It was for these reasons that the
Applicant opted to temporarily reinstate the suspended pipe alternative (i.e. the status quo
before the 2012 flood).
The following section describes the impact of the most recent damage on the functioning of the
farm and explains why the Applicant could not countenance delays that would propel the farm
towards a worsening emergency. The description is limited to flood-related damage or disruption
which, besides having to be attended to urgently owing to the impact on farming operations,
resulted in the unauthorised activities that are the subject of this application (see Section 1.5 for
a full description of the listed activities that were triggered by emergency repairs in 2008 and
2012).
1.4 GROUNDS FOR EMERGENCY MEASURES – OCTOBER 2012
As indicated previously, ‘Meerlustkloof’ is an export fruit farm that enters the height of its
operational activities with the onset of summer and the annual harvest (which, on average, starts
in the second week of January and proceeds to mid-April each year). Being able to rely on
uninterrupted irrigation in order to ensure effective ripening of high quality fruit is particularly
critical at this time of the year on the deciduous fruit calendar. These considerations applied
directly to the Applicant’s decision to excavate an emergency sump following destruction of
irrigation infrastructure by the flood in November 2008. They were as relevant in October 2012
when it was initially believed necessary, as a stop-gap emergency measure, to dig a channel so
that water could be relayed from the realigned river to the sump, which had been left stranded
by the flood.
The grounds for the Applicant’s decision to proceed with emergency interventions in November
2008 and October 2012, without following the prescribed (and, under the circumstances,
prohibitively time-consuming) procedures for obtaining environmental authorisation, were
essentially identical, namely to reinstate normal agricultural operations which were at a critical
stage in terms of the need to irrigate and spray orchards on the eve of the respective harvest
seasons (see correspondence between the attorneys Smith Ndlovu Summers and the Department
of Environmental Affairs and Development Planning, 9 November 2012; Appendix D). Failure to
act urgently would have exacerbated what, from the Applicant’s perspective, amounted to an
escalating emergency and the prospect of catastrophic crop – and financial—losses.
The dire circumstances precipitated by the two floods are explained below. The expert opinion
provided by Dr JJB Pretorius, a specialist horticulturalist, with respect to the impact of the
REVISED FINAL EIR FOR ‘MEERLUSTKLOOF’ 59/11, CALEDON
Page 19 of 111
October 2012 flood on fruit production can be applied with equal measure to the effects of the
preceding flood, in November 2008.
1.4.1 Impacts on fruit production arising from the interruption of irrigation
With respect to the destruction of irrigation infrastructure, failure to adequately water apple
trees with ripening fruit can have severe consequences for a farming operation (Dr JJB Pretorius,
deciduous fruit specialist – 31 October 2012; Appendix E), some of which are potentially
irreversible: initially trees start losing fruit and fruit that is retained on the tree shrinks in size,
which make it potentially unsuitable to be sold for fresh consumption; complete crop loss can
result.
Apple trees that are severely water-stressed lose leaves and enter a state known as
ektodormancy. If such trees are exposed to rainfall before winter, while temperatures are still
suitable for growth, the tree responds by flowering prematurely, which destroys the next year’s
crop.
Dr Pretorius warned that there was a “very real chance” of trees dying due to a lack of water. He
recommended that the water supply to the affected orchards be restored “as soon as possible”. If
not, crop loss could start to occur “within the next couple of days” – i.e. by the first week of
November 2012. It can be assumed that the urgent situation described here with respect to water
stress and potential crop losses would have been compounded by the 2008 flood, which occurred
about three weeks later into the season than the flood in 2012.
1.4.2 Impacts on production arising from damage to bridges
Besides major inconvenience to the general operation of the farm – such as staff not being able
to get to work at a critical time of the year or, in some cases, being cut off from the outside world
– the destruction of internal river crossings by floods can seriously impede the treatment of fruit
trees against fungal infection as spraying equipment cannot be deployed in the affected orchards.
As explained by Dr Pretorius, the transition from a wet winter to dry summer creates moist and
warm conditions that are highly advantageous for fungal infection of fruit trees. In terms of
integrated pest management protocols, contact fungicides need to be applied to protect crops
during the first 60 to 80 days after full bloom. Fruit not treated in this manner may not be
marketable overseas which, in the case of Agrisouth Orchards (SA) (Pty) Ltd., could be financially
ruinous. Untreated fruit could become reduced in size, making it unsuitable even for processing
which would translate into a 100% loss. It also becomes increasingly difficult to maintain disease-
REVISED FINAL EIR FOR ‘MEERLUSTKLOOF’ 59/11, CALEDON
Page 20 of 111
free crops in orchards that have not been properly treated for fungal infections. The risk of fungal
infection remains unabated throughout the ripening process and is exacerbated by warm, wet
conditions as would have prevailed in both November 2008 and October 2012.
In the case of both floods, physical access to the orchards on the western or right banks of the
Meerlustkloof and Elandskloof Rivers was entirely cut off due to the destruction of the affected
river crossings (see sections 1.1.2, 1.1 and 1.2). Access to the affected orchards was reinstated by
constructing the two pipe culvert crossings in November and December 2008 (replacing inter alia
the destroyed drift over the Elandskloof River) and, in October and November 2012, excavating a
temporary drift over the Elandskloof River and re-equipping the damaged bridges with expanded
flow capacity in the form of additional pipes and repaired decks.
The situation with respect to the farm’s treatment of trees for fungal infections was sufficiently
acute in October 2012 to compel the Applicant to employ the services of a helicopter company to
undertake aerial spraying at a daily cost of R11 000 and an additional R350 per hectare. The
temporary drift over the Elandskloof River proved, owing to its rough surface, to be unsuitable for
transporting fungicides in tanks towed by tractors. Repairing the bridges was, in the
circumstances, an unavoidable and urgently necessary option for the farm.
From the Applicant’s perspective, the flood damage had amounted to an “ongoing emergency
situation” and, in order to protect its property – in the form of the orchards and the current
harvest – Agrisouth Orchards (SA) (Pty) Ltd, had “no alternative but to undertake the flood repair
and/or restorative works as a matter of urgency and necessity...” (Smith Ndlovu Summers,
paragraph 12; Appendix D).
1.5 UNAUTHORISED ACTIVITIES SUBJECT TO THIS APPLICATION
This section highlights those aspects of the emergency repairs (i.e. prescribed ‘activities’ listed in
terms of national environmental impact assessment regulations) that were undertaken without
the requisite environmental authorisations in terms of Chapter 5 of the National Environmental
Management Act 107 of 1998 (NEMA) as amended.
Certain aspects of the actions taken in response to the flood damage in November 2008 would
have required authorisation in terms of the 2006 version of the environmental impact assessment
REVISED FINAL EIR FOR ‘MEERLUSTKLOOF’ 59/11, CALEDON
Page 21 of 111
(EIA) regulations,3 whereas the emergency repairs initiated immediately after the flood in
October 2012 were in contravention of the 2010 EIA regulations.4
The activities relating to the November 2008 flood were concluded in a matter of weeks after the
damage had been incurred.
All of the listed activities arising from the October 2012 flood emergency had commenced before
the end of the year and had, with a few exceptions, been concluded by the end of January 2013.
Incomplete work associated with the 2012 flood includes the addition of a protective wing wall to
the repaired and expanded pipe culvert crossing over the Meerlustkloof River, and finding a more
suitable and secure method for routing an irrigation pipe across the lower reaches of the
Elandskloof River (repairs to the latter pipe in late 2012 and early 2013 did not, however,
constitute listed activities and are therefore do not form part of this section 24G application).
Both of the latter activities formed part of the suite of emergency responses implemented by
Agrisouth Orchards (SA) (Pty) Ltd in the last two months of 2012.
1.5.1 Activities triggered in November 2008 by the 2006 NEMA EIA regulations
The emergency repairs in November and December 2008 entailed excavation of the sump in the
Elandskloof River, and reinstating two vehicle crossings over the Meerlustkloof and Elandskloof
rivers.
The activities that were triggered by these unauthorised operations in 2008 are activities 1(m)
and 4 of Listing Notice, 1 GN R. 386 of the 2006 NEMA EIA regulations, namely:
3 Listing Notice 1, GN R. 386 of 21 April 2006, identified in terms of sections 24 and 24D of the National
Environmental Management Act 107 of 1998. 4 Listing Notice 1, GN R. 544 of 18 June 2010 (as amended) and, potentially, Listing Notice 3, GN R. 546 of 18
June 2010, published in terms of sections 24(2) and 24D of the National Environmental Management Act 107
of 1998.
REVISED FINAL EIR FOR ‘MEERLUSTKLOOF’ 59/11, CALEDON
Page 22 of 111
1(m) The construction of facilities or infrastructure,
including associated structures or infrastructure, for...
any purpose in the one in ten year flood line of a river
or stream, or within 32 metres from the bank of a
river or stream where the flood line is un-known,
excluding purposes associated with existing
residential use... but including (iii) bridges and (iv)
dams...
Construction of two pipe culvert crossings (‘bridges’)
to replace a drift over the Elandskloof River and a
former cement bridge over the Meerlustkloof River,
both of which were destroyed in the flood. The
alignment of the repaired/replacement structures was
identical to what had been there previously.
Excavation of an emergency irrigation sump (i.e. a
‘dam’) in the reworked bed of the Elandskloof River
following destruction of an abstraction point by the
flood. See below.
4 The dredging, excavation, infilling, removal or
moving of soil, sand or rock exceeding 5 cubic metres
from a river, tidal lagoon, tidal river, lake, in-stream
dam, floodplain or wetland
The sump lies roughly along the median line of the
reworked flood channel. There is a gap of 40 to 80 m
between the northern bank of the sump and the river
bank, and a 30 m gap between the sump and the right
(southern) bank of the river. The sump is about 2 900
m2
in extent. It is a kidney-shaped structure, open at
its upstream end, with bulldozed banks increasing to
about three metres in height along its downstream
aspect. The southern bank of the sump is partly
defined by remnants of floodplain soil deposits.
Overall, the sump occupies about one fifth of the
post-2008 river reach within which it is located. Water
was drawn via a 250 mm pipe to an established
pumping station about 280 m due east of the sump.
Excess water was released into the Elandskloof River
about 275 m downstream of the sump. The sump was
in use from late 2008 to October 2012, when changes
in the position of the active channel resulted in the
sump losing its supply of water.
1.5.2 Activities triggered in October 2012 by the 2010 NEMA EIA regulations
Emergency repairs following the flood in October 2012 entailed:
− Excavating a temporary drift across the Elandskloof River; and
− Rebuilding the damaged bridges over the Meerlustkloof and Elandskloof rivers, and
equipping them with additional 1.5 m diameter pipes.
Note that the unauthorised construction (and completion) of the sump had commenced during the
validity of the 2006 NEMA EIA regulations, which means that this set of activities do not require
retrospective authorisation in terms of the 2010 NEMA EIA regulations.
REVISED FINAL EIR FOR ‘MEERLUSTKLOOF’ 59/11, CALEDON
Page 23 of 111
The interventions carried out in October 2012 and directly thereafter triggered various activities in
Listing Notice 1 and, potentially, Listing Notice 3 of the 2010 NEMA EIA regulations (GN R. 544 and
546 respectively, published 18 June 2010), namely in terms of:
− Listing Notice 1, activities 11(iii) and (xi), 18, 39(iii) and 40(iv); and
− Listing Notice 3, activity 16(iv).
These following activities were triggered in terms of Listing Notice 1:
11 The construction of (iii) bridges and (xi)
infrastructure or structures covering 50 square
metres or more where such construction occurs
within a watercourse or within 32 metres of a
watercourse...
Construction of two expanded pipe culvert crossings
to repair two bridges over the Meerlustkloof and
Elandskloof rivers respectively. The alignment of the
repaired/replacement structures was identical to
what had been there previously. The temporary drift
over the Elandskloof River was about 70 m2
in extent.
18 The infilling or depositing of any material of more
than 5 cubic metres into, or the dredging, excavation,
removal or moving of soil, sand, shells, shell grit,
pebbles or rock or more than 5 cubic metres from (i)
a watercourse... (Note that the EMP drafted for this
application is also to be submitted for approval as a
management plan for maintenance purposes as
provided for by Activity 18, LN1).
[Corrected by “Correction Notice 2” of 10 December
2010, GN No. R. 1159]
This activity applies to the construction of a
temporary drift over the Elandskloof River, pending
repairs to the damaged pipe culvert crossing. The
drift had been dismantled by late January 2013.
39 The expansion of (iii) bridges within a watercourse
or within 32 metres of a watercourse....
The hydraulic capacity of the two repaired pipe
culvert crossings was doubled (on the advice of the
Department of Agriculture and a freshwater
ecologist) with the addition of extra 1.5 m diameter
concrete pipes. In the case of the bridge over the
Meerlustkloof River, two extra pipes were added.
Three more pipes were added to the crossing over
the Elandskloof River.
40 The expansion of (iv) infrastructure by more than
50 m2
within a watercourse or within 32 m of a
watercourse....
[Corrected by “Correction Notice 2” of 10 December
2010, GN No. R. 1159]
Each pipe consists of two lengths, totalling 5 m when
laid end-on-end. The total area of expansion was
therefore 75 m2, explained as follows: Before the
repairs, the bridge over the Meerlustkloof River had
two pipes with a surface area of 15 m2 in total which
was doubled to 30 m2. The bridge over the
Elandskloof River initially had three pipes (of 22.5
m2), which were doubled in extent to 45 m
2.
REVISED FINAL EIR FOR ‘MEERLUSTKLOOF’ 59/11, CALEDON
Page 24 of 111
One activity was commenced in terms of Listing Notice 3, namely:
16 The construction of (iv) infrastructure covering 10
square metres or more where such construction
occurs within a watercourse or within 32 metres of a
watercourse (d) in the Western Cape (ii) outside
urban areas (hh) within 5 km of a statutory protected
area that is not a national park....
[Corrected by “Correction Notice 2” of 10 December
2010, GN No. R. 1159]
All the unauthorised activities in question occurred
within 2 km of the Riviersonderend Nature Reserve,
which is a proclaimed protected area in terms of the
National Forests Act 30 of 1998 and the National
Environmental Management: Protected Areas Act 57
of 2003. The reserve is managed by CapeNature
(cf.< http:bgis.sanbi.org>)
The identification of these unauthorised activities is based on communication between the
Applicant’s lawyers and the Department of Environmental Affairs and Development Planning (cf.
Appendix D), interviews with the Applicant and site visits with:
− LandCare representatives from the Western Cape Department of Agriculture on January
26 and February 16, 2012 (i.e. with respect to the activities triggered in response to the
November 2008 flood) ; and
− The Department of Environmental Affairs and Development Planning, Breede-Overberg
Catchment Management Agency, Department of Water Affairs and the Western Cape
Department of Agriculture on 29 October 2012 (following renewed flood damage in
October 2012).
1.6 ADMINISTRATIVE ACTIONS RELATING TO SUBMISSION OF s 24G APPLICATION
This section summarises actions following the issuing of a pre-compliance notice in terms of section
31L of the National Environmental Management Act (NEMA) 107 of 1998 as amended by the
Department of Environmental Affairs and Development Planning (DEADP) on 28 December 2011. It
also outlines the sequence of authority consultations that followed on the flood damage in October
2012.
Pre-compliance
notice issued by
DEADP
28-12-2011
Agrisouth Orchards SA (Pty) Ltd (‘Agrisouth’) notified that a dam
had been constructed in a watercourse without environmental
authorisation. Agrisouth instructed to cease unauthorised
activity, rehabilitate the site to its original condition, and to
rectify the effects of the unlawful activity. Agrisouth afforded
seven days in which to make representations as to why a
compliance notice should not be issued.
Response by DEADP requested to refrain from issuing a compliance notice
REVISED FINAL EIR FOR ‘MEERLUSTKLOOF’ 59/11, CALEDON
Page 25 of 111
Agrisouth’s attorneys
16 January 2012
until attorneys had an opportunity to consult with their client
and make written representations to DEADP.
DEADP to attorneys
17 January 2012
Agrisouth granted an extension until 23-01-2012 to make a
submission to DEADP.
Attorneys to DEADP
24-01-2012
Agrisouth’s attorneys set out circumstances of excavation of
sump, i.e. sump excavated as a response to an emergency
resulting from severe flooding in November 2008. Request that
DEADP refrains from issuing a compliance notice, instead
motivating inter alia that Agrisouth submit a section 24G
application with a view to investigation, among others, whether
rehabilitation of the site (and reinstatement of original
conditions) would constitute the best practicable environmental
option.
Agrisouth appoints
EAP to undertake s
2G environmental
assessment
27-01-2012
EAP undertakes site visits with representatives of Western Cape
Department of Agriculture’s sustainable resource management
programme on 26-01-2012 and 16-03-2012. EAP notifies DEADP
of appointment on 31-01-2012. Freshwater Consulting Group
appointed to undertake specialist aquatic impact assessment (23-
02-2012)
Section 24G
application form
submitted to DEADP
08-02-2012
DEADP acknowledges
receipt of application
27-02-2012
DEA&DP requests correction to activities for which authorisation
is being sought (viz. 2006, not 2010 NEMA EIA regulations).
Public participation process must be undertaken and organs of
state must be consulted. Amended application form accepted by
DEA&DP on 06-03-2012.
Section 24G process –
Submission of Final
EIR to DEA&DP, 06-
09-2012
RENEWED FLOOD
DAMAGE, OCTOBER
2012
Final EIR published by BolandEnviro cc for second, 21-day round
of comment. Comment received from CapeNature and Overberg
District Municipality (see Appendix F). Final EIR submitted to
DEA&DP on 06-09-2012; acknowledgement of receipt issued by
DEA&DP on 17-09-2012.
Agrisouth hosts
authority meeting at
‘Meerlustkloof’ to
discuss emergency
responses to flood
damage, 29-10-2012
Meeting attended by representatives of DEA&DP section 24G
Unit and IEM directorate, BOCMA, Department of Water Affairs
and the Western Cape Department of Agriculture.
− It was agreed to that no decisions on the regulatory
responsibilities of Agrisouth could be taken on site.
− Agrisouth would request EAP to compile a memorandum on
REVISED FINAL EIR FOR ‘MEERLUSTKLOOF’ 59/11, CALEDON
Page 26 of 111
the situation at the farm for consideration by the
Department of Environmental Affairs and Development
Planning and Department of Water Affairs respectively (see
Appendix D).
− It was recommended that a meeting be set up with the
respective departments to consider an authorisation strategy
once the departments had received a formal request in this
regard from Agrisouth.
Meeting between EAP
and DEA&DP on
revised s 24G process,
26-11-2012
In summary, it was agreed that:
− The Final EIR would be amended to reflect the circumstances
that were triggered by the flood in October 2012;
− The Final EIR would be resubmitted to the DEA&DP after a
single, 21-day public participation process;
− The application for rectification would be expanded to
include – in terms of the 2006 NEMA EIA regulations – the
unauthorised construction of the two bridges in response to
the 2008 flood (note that these activities had not been
included in the s 31L pre-compliance notice issued on 28-12-
2011);
− Unauthorised activities that had commenced in response to
the October 2012 flood would be dealt with in terms of the
2010 NEMA EIA regulations. These activities related to the
reconstruction (and expansion) of the two pipe culvert
crossings, and the temporary drift; and
− All reporting and the EMPR/Maintenance Management Plan
would be amended accordingly.
1.7 SCOPE OF THE WORK TO BE UNDERTAKEN
The scope of the study is determined with reference to the requirements of the relevant
legislation namely section 24G of the National Environmental Management Act (Act 107 of 1998)
(NEMA), as amended.
The main responsibilities of the Environmental Assessment Practitioner (EAP) undertaking an
environmental assessment in terms of s 24G would include but not be limited to, the following:
− Submission of the required Application Form to the relevant authority to register the
proposed project;
REVISED FINAL EIR FOR ‘MEERLUSTKLOOF’ 59/11, CALEDON
Page 27 of 111
− Consultation with the relevant authorities and stakeholders, at prescribed intervals
throughout the environmental assessment process, to ensure that relevant issues or
concerns are identified, assessed and reported;
− Ensure the assessment of and response to issues that are raised throughout the public
participation process, and which are relevant to the decision that needs to be taken;
− Compile a report containing —
(i) an assessment of the nature, extent, duration and significance of the impacts of the
activity on the environment, including the cumulative effects;
(ii) a description of mitigation measures undertaken or to be undertaken in respect of
the impacts of the activity on the environment;
(iii) a description of the public participation process followed during the course of
compiling the report, including all comments received from interested and affected
parties and an indication of how issues raised have been addressed; and
(iv) an environmental management programme.
− Provide such other information or undertake such further studies as the relevant
authority may deem necessary;
− Submission of the draft report to the public and commenting authorities for comment,
and
− Submission of the final report to the competent authority, specifically the Department of
Environmental Affairs and Development Planning (DEA&DP), for a decision.
1.8 ASSUMPTIONS AND LIMITATIONS
This environmental assessment is assailed with predictive uncertainty arising from a variety of
inter-related sources. The recommendations that are captured in Chapter 5 and Chapter 8 have
been specifically designed to contend with these uncertainties by means of an incrementally
structured planning process.
The over-riding problem is thus: Owing to extensive, flood-related erosion, destabilisation of the
Elandskloof and Meerlustkloof rivers and the generally degraded condition of the adjacent
floodplains, it will take a comprehensive planning process to identify the most appropriate
strategy for achieving long-term stability of the river in manner that it is consistent with
rehabilitation of ecological function and structure as well securing reasonable levels of
agricultural activity in adjacent areas (cf. Day (2012; 2013); Appendix E).
In this context, the problems arising from historical degradation of the affected catchment,
changing weather patterns, chronic instability of the Elandskloof and Meerlustkloof rivers and the
ensuring vulnerability of critical farming infrastructure to floods represent a sub-set of a larger
REVISED FINAL EIR FOR ‘MEERLUSTKLOOF’ 59/11, CALEDON
Page 28 of 111
management problem that needs to be addressed in a strategic, holistic manner, with the right
specialist expertise, and at a catchment scale if further degradation and instability of the system is
to be halted and rectified.
In the absence of reliable assumptions about how the unauthorised works may be impacting on
the riparian environment, and what effect future floods may have on a highly destabilised system,
a phased process of investigation and management is recommended to deal with these
uncertainties. Given these critical uncertainties, it would be rash to recommend alternative
stream crossing and rehabilitation measures without understanding the dynamics and responses
of the broader system, and what is necessary to achieve its stabilisation and long-term
rehabilitation. These questions are dealt with comprehensively in the environmental impact
report (Chapters 6 and 7).
Assumptions and limitation that apply specifically to the specialist investigations and impact
assessment are recorded in Section 5.1 (‘Uncertainty of predictive methods and assumptions’).
1.9 THE NEED AND DESIRABILITY OF THE PROPOSED DEVELOPMENT
‘Need’ is understood to mean requiring something because it is essential or very important, and
not just desirable. ‘Desirability’, in turn, refers to wanting or wishing for something owing to its
attractiveness, utility or necessity (cf. The New Oxford Dictionary of English, 1998). The DEA&DP
guideline on need and desirability (2010) suggests that ‘need’ refers to the ‘timing’ of a proposed
development, and ‘desirability’ to place. Jointly, the concepts raise critical questions about the
contextual appropriateness of development, and the “wise use of land”.
Here, the ‘need’ for a proposed development would depend on the degree of social or public
harm that would result from the development not going ahead. ‘Desirability’ can reflect both a
private desire that, if not met, will result in disappointment, as well as a more objective aspect –
namely, would a proposed development be strategically and contextually appropriate?
The preferred alternative is discussed in terms of its need and desirability in Chapter 4.
REVISED FINAL EIR FOR ‘MEERLUSTKLOOF’ 59/11, CALEDON
Page 29 of 111
1.10 ALTERNATIVES
The assessment of feasible and reasonable alternatives to development proposals forms a
cornerstone of integrated environmental management. It is also required by law.5 The rationale
underpinning the function of alternatives in project planning, impact assessment and decision
making is dealt with comprehensively in Chapter 4 below.
Alternatives are only addressed with respect to the events that followed the flood in October
2012. The reason for this are set out below.
1.10.1 Assessment of alternatives relating to the unauthorised emergency sump
Firstly, the emergency sump – which was the original trigger for this section 24G application – has
been effectively left stranded and operationally redundant as a result of sediment accumulation
and the southwards migration of the active channel during the 2012 flood (Day, 2013, p 14).
Although it was initially recognised that a long-term and more environmentally-acceptable
alternative had to be found for taking water from the middle reaches of the Elandskloof River (see
the August 2012 version of this Final EIR), changes in the river morphology and, more
importantly, procurement of new pumps by the Applicant have negated the need to investigate
other options for abstracting water for irrigation (see section 1.3.2 above for a description of this
technology, and its application). This environmental impact report confirms the earlier
recommendation that the removal of obstacles in the adjacent channel adjacent to the sump be
treated as a matter of priority. The sump, however, should be left in situ until completion of the
proposed strategic planning process for the stabilisation and rehabilitation of the Meerlustkloof
and Elandskloof rivers (see Chapter 8).
On the basis of the foregoing, alternatives to the sump will not be dealt with any further.
1.10.2 Assessment of alternatives relating to the unauthorised emergency repairs to
the bridges over the Meerlustkloof and Elandskloof rivers in 2008
Secondly, the initial application for retrospective environmental authorisation of unauthorised
activities that had been undertaken in response to flood damage in November 2008 did not
5 Cf. s 24(4)(b) of the National Environmental Management Act 107 of 1998 as amended
REVISED FINAL EIR FOR ‘MEERLUSTKLOOF’ 59/11, CALEDON
Page 30 of 111
include listed activities triggered by the repair of the flood-damaged pipe culvert crossings over
the Meerlustkloof and Elandskloof rivers.
The decision to confine the section 24G application to the unauthorised excavation of the
emergency was informed by the pre-compliance notice (issued by the DEADP on 28 December
2011) that related exclusively to the sump. It was the Applicant’s understanding that the repairs
to the two damaged bridges was confined to the replacement of damaged infrastructure and, on
the basis of the so-called ‘like-for-like’ principle, did not trigger a requirement for prior
environmental authorisation. Hearsay has it that this opinion was communicated verbally to the
Applicants at the time. Whereas this cannot be independently corroborated, it can be confirmed
that that the Department of Environmental Affairs and Development Planning did not raise this as
an issue in response to the section 24G application form that was submitted on 8 February 2012,
or during subsequent communications with the Applicants attorneys.
As a consequence, the initial environmental assessment only dealt with impacts arising from the
unauthorised excavation of the emergency sump. It was only during the site visit at
‘Meerlustkloof’, on 29 October 2012, that the legality of the emergency repairs to the two bridges
in 2008 came into question. It was subsequently agreed at a meeting between the Applicant’s
environmental assessment practitioner and representatives of the Sub-directorate: Section 24G
applications on 26 November 2012 that this Application would be amended to include the
unauthorised emergency repairs to the two bridges following the flood in November 2008, as well
as the urgent but unauthorised works that had been undertaken in the wake of the October 2012
flood.
1.10.3 The need to balance short-term mitigation with long-term rehabilitation of the
two rivers
Under the circumstances, it is not possible to provide a detailed assessment and evaluation of
impacts arising from the unauthorised repairs to the two bridges in 2008 as these did not feature
in the environmental assessment process that commenced early in 2012, and neither were they
included in the terms of reference for the aquatic ecologist, Dr Liz Day. Both bridges have been
rebuilt in the interim, following severe damage in the October 2012 flood, and both have been
equipped with extra hydraulic capacity by doubling the number of 1.5 m pipes that provide
venting through the structures (see Day, 2013, p 23; Appendix E).
The aquatic specialist did (Day 2013, Appendix E), however, note that the repairs to the two
bridges in 2008 would have had adverse environmental effects, including:
REVISED FINAL EIR FOR ‘MEERLUSTKLOOF’ 59/11, CALEDON
Page 31 of 111
− Concentration of flows and increased velocities as a result of river narrowing;
− In-filling of the floodplain and further concentration of flows by berms placed along the
top of the river bank; and
− A significant contribution to negative cumulative impacts on both rivers (such as severe
sedimentation, erosion and ongoing disturbance to downstream riparian habitats).
The latter findings with respect to the freshwater ecological impacts of the repairs to the bridges
in 2008, as well as the updated Present Ecological Status of the Meerlustkloof and Elandskloof
rivers, provides a useful baseline against which to assess the environmental effects of the
additional pipes that were added to the bridges after the flood in October 2012. The latter will be
treated as a design alternative for the purposes of impact assessment and evaluation.
The aquatic ecologist was unable to assess the impacts of the unauthorised drift as it had been
demolished by the time that she visited the farm in January 2013, and most traces of the
structure had disappeared by then. It could, however, be concluded that the drift would have had
a “negligible” long-term impact (See Day, 2013; Appendix E). The lifespan of the drift was, from
the outset, viewed as limited as it constituted a temporary measure to allow farm personnel to
ford the Elandskloof River until such time that adjacent pipe culvert crossing had been repaired.
The only alternatives to the drift would have been the ‘no go’ option, i.e. accepting the status quo
directly after the flood in October 2012 – and do nothing to reinstate contact with the western
parts of the farm – or to rebuild the pipe culvert crossing, which has happened, but with
potentially hugely damaging delays to the farming operation.
Neither of the latter options are considered to be feasible or reasonable. Their need and
desirability would also have to be questioned if considered in the light of the arguments
presented in Chapter 4, ‘Alternatives’.
1.10.4 Strategic, contextual constraints to the identification of alternatives
In general, it must be emphasised that without effective simultaneous rehabilitation of
the river from the overwhelming effects of flood damage, and deliberate steps to curb
pressures that contribute to the degradation of the farming-ecosystem interface, efforts
expended in rehabilitation of the impacts of the sump and other unauthorised
infrastructure will be of little measureable effect in terms of contributing improvements
to the overall ecological state of the affected rivers and wetlands.
Furthermore, insufficient information exists at present to provide a useful guide as to the
best approach to achieve long-term stability of the river system in a manner that is
REVISED FINAL EIR FOR ‘MEERLUSTKLOOF’ 59/11, CALEDON
Page 32 of 111
compatible both with rehabilitation of ecological function and structure, while allowing for
and securing reasonable levels of agricultural activity in adjacent areas. This issue is
particularly true in a context where extreme storms are predicted to become more
frequent with global climate change and, given the present levels of degradation and
instability of the above rivers, seemingly throughout their reaches in developed areas, their
present levels of resilience to ongoing hydrological / climatic disturbance is expected to be
particularly low.
This state of affairs can probably be extended to many other sub-catchments in this part of
the Riviersonderend system.
In light of the above, it is strongly recommended that the detailed design and actual
implementation of mitigation measures needs to be informed by additional critical
information that would only become available by means of a suitably-resourced
investigation at the appropriate hydro-geomorphological and ecological scales.
It is against this background that the identification of alternatives would, for the purposes
of this application and the decision that is sought, be premature and unjustified, and that
the question of alternatives is properly left to the conclusion of the recommended
planning process
REVISED FINAL EIR FOR ‘MEERLUSTKLOOF’ 59/11, CALEDON
Page 33 of 111
2. LEGAL AND POLICY REQUIREMENTS
This Environmental Impact Assessment (EIA) is being undertaken in terms of Section 24G of the
National Environmental Management Act (Act 107 of 1998), which relates to the rectification of
the unlawful commencement of listed activities.
Other legislation and policy may, however, also apply to this application. Other regulatory and
policy instruments may include:
− The National Environmental Management: Biodiversity Act 10 of 2004 (threatened
species);
− The National Water Act 38 of 1998 (water use licensing);
− The National Heritage Resources Act 25 of 1999;
− The Conservation of Agricultural Resources Act 43 of 1983;
− The draft Western Cape Rural Land-use Planning and Management Guidelines (2009);
− CapeNature’s requirements and recommendations with respect to applications for
environmental, mining, agriculture, water, and planning-related authorisations (2009).
Several technical and interpretive guidelines may also apply to aspects of the application. These
include:
− Brownlie S (2005) Guideline for involving biodiversity specialists in EIA processes: Edition
1. CSIR Report No ENV-S-C 2005 053 C. Republic of South Africa, Provincial Government
Western Cape, Department of Environmental Affairs and Development Planning, Cape
Town;
− Holness and Bradshaw (2010) Critical Biodiversity Areas of the Overberg District
Municipality. Park Planning and Development Unit, SANParks, Port Elizabeth; and
− DEA&DP (2010) Guideline on Need and Desirability, EIA Guideline and Information
Document Series. Western Cape Department of Environmental Affairs & Development
Planning (DEA&DP).
The implications of each of these instruments are set out below.
REVISED FINAL EIR FOR ‘MEERLUSTKLOOF’ 59/11, CALEDON
Page 34 of 111
2.1 NATIONAL ENVIRONMENTAL MANAGEMENT ACT (NEMA) AND THE
NEMA EIA REGULATIONS
The interpretation and application of environmental legislation is governed by the Constitution of
the Republic of South Africa Act 108 of 1996.
Chapter 2 of the Constitution constitutes a Bill of Rights that includes an environmental clause.6
Section 24 of the Bill of Rights states that “everyone has the right to have the environment
protected through reasonable laws or other means that prevent pollution and ecological
degradation, promote conservation and secure ecologically sustainable development and use of
natural resources while promoting justifiable economic and social development”.
Constitutional provisions relating to the promotion of administrative justice and promotion of
access to information have a direct bearing on the environmental regulatory dispensation, which
obtain statutory expression through framework legislation in the form of the National
Environmental Management Act 107 of 1998, as amended.
NEMA is enforced by the national Department of Environmental Affairs, but certain powers have
been assigned to the Western Cape Department of Environmental Affairs and Development
Planning (DEA&DP), which in this instance is the recognised competent authority.
2.2 NEMA CHAPTER 1: THE NATIONAL ENVIRONMENTAL MANAGEMENT
PRINCIPLES
Chapter 1 of NEMA (the National Environmental Management Principles) lays down principles7
that apply the actions of all organs of state that may significantly affect the environment. These
principles serve as guidelines by reference to which any organ of state must exercise any function
when taking any decision in terms of any statutory provision concerning the protection of the
environment.8
The National Environmental Management Principles place people and their needs at the forefront
of environmental management, and require that development must be socially, environmentally
6 s 24, The Constitution of RSA
7 Section 2, Act 107 of 1998 as amended
8 Section 2(1)c), Act 107 of 1998 as amended
REVISED FINAL EIR FOR ‘MEERLUSTKLOOF’ 59/11, CALEDON
Page 35 of 111
and economically sustainable.9 They also promote the right of all interested and affected parties
to participate in environmental governance.10
The principles that would have particular relevance to decisions relating to the transformation of
undisturbed habitats and ecosystems are those that require that environmental management
must (in paraphrased format):
− Avoid, minimise or remedy disturbance of ecosystems and loss of biodiversity;
− Avoid degradation of the environment;
− Avoid jeopardising ecosystem integrity;
− Pursue the best practicable environmental option by means of integrated environmental
management; and
− Pay specific attention to management and planning procedures pertaining to sensitive,
vulnerable, highly dynamic or stressed ecosystems.11
2.3 NEMA CHAPTER 7: THE DUTY OF CARE
Chapter 7 of the National Environmental Management Act 107 of 1998 prescribes a general ‘duty
of care’ and requirement to remediate environmental damage. Section 28(1) of NEMA states:
Every person who causes, has caused or may cause significant pollution or degradation of
the environment must take reasonable measures to prevent such pollution or
degradation from occurring, continuing or recurring, or, insofar as such harm to the
environment is authorised by law or cannot reasonably be avoided or stopped, to
minimise and rectify such pollution or degradation of the environment....
The Duty of Care can, inter alia, be enforced through directives issued by the competent
authority.12
9 Section 2(2), Act 107 of 1998 as amended
10 Section 2(4)(f), Act 107 of 1998 as amended
11 Cf. sub-sections 2(4)(a)(i), (ii), (vi); (b); and (r)
12 s 28(4), NEMA
REVISED FINAL EIR FOR ‘MEERLUSTKLOOF’ 59/11, CALEDON
Page 36 of 111
2.4 NEMA CHAPTER 5: INTEGRATED ENVIRONMENTAL MANAGEMENT
One of the primary objectives of integrated environmental management is to promote the
integration of the National Environmental Management Principles into all decision making that
may significantly affect the environment.13
Section 24(4)(a) of NEMA, in turn, lays down minimum, non-discretionary procedures14
that apply
to every application for an ‘environmental authorisation’, i.e. a listed or specified activity.
‘Listed activities’ refer to activities listed or specified in terms of, respectively, NEMA s 24(2)(a) or
(b) that may not be commenced without environmental authorisation issued in terms of section
24(1) of NEMA. Listed activities are defined by Listing Notices that are published with the NEMA
EIA regulations.
2.5 MANDATORY AND DISCRETIONARY PROCEDURES RELATING TO
APPLICATIONS FOR ENVIRONMENTAL AUTHORISATION
The mandatory and discretionary procedures relating to environmental assessment in support of
applications for environmental authorisation are summarised as follows:
NEMA s 24(4)(a)
Minimum, non-discretionary requirements that apply to
every application for environmental authorisation
NEMA s 24(4)(b)
Minimum, discretionary requirements that may apply with
respect to every application for environmental
authorisation
There must be co-ordination and co-operation between
organs of state where an activity may fall under the
jurisdiction of more than one organ of state.
All applications for an environmental authorisation (see
below) must include, where applicable:
−−−− Investigation of the potential consequences or impacts
of alternatives to the activity on the environment; and
−−−− Assessment of the significance of those potential
consequences or impacts, including the option of not
implementing the activity.
Any decision by an organ of state must take into account:
−−−− The findings and recommendations flowing from an
environmental assessment;
−−−− The general objectives of integrated environmental
management as provided for in Chapter 5 of NEMA
−−−− The national environmental management principles
Where applicable, measures must be investigated to
mitigate adverse consequences or impacts to the minimum.
13 s 23(2)(a), NEMA
14 As amended by the National Environmental Management Amendment Act 62 of 2008
REVISED FINAL EIR FOR ‘MEERLUSTKLOOF’ 59/11, CALEDON
Page 37 of 111
NEMA s 24(4)(a)
Minimum, non-discretionary requirements that apply to
every application for environmental authorisation
NEMA s 24(4)(b)
Minimum, discretionary requirements that may apply with
respect to every application for environmental
authorisation
(section 2, NEMA).
An application must contain a description of the
environment likely to be significantly affected by the
proposed activity.
Where applicable, potential impacts on heritage resources
(the ‘national estate’ in terms of section 3(2) of the National
Heritage Resources Act 25 of 1999) must be investigated,
assessed and evaluated.
There must be an investigation of:
−−−− The potential environmental consequences for, or
impacts on, of the activity; and
−−−− The significance of those potential consequences or
impacts.
Where applicable, gaps in knowledge, the adequacy of
predictive methods and underlying assumptions and
uncertainties arising from the compilation of information
must be reported.
The public and all organs of state with jurisdiction over any
aspect of the activity must be given a reasonable
opportunity to participate in public information and
participation procedures.
Where applicable, arrangements for monitoring and
managing environmental consequences and impacts must
be investigated and formulated, as must the effectiveness
of such arrangements.
Where applicable, applications must consider information
and maps that specify the attributes of the environment in
particular geographic areas where such information and
maps have been complied by either the national Minister of
Water and Environmental Affairs or a provincial MEC
2.6 THE NEMA EIA REGULATIONS
NEMA section 24(5) provides for regulations that lay down procedures for applications for
environmental authorisations. These, and their accompanying listing notices of activities that may
not commence without environmental authorisation in terms of NEMA s 24(1), are generally
known as the ‘EIA regulations’.
2.6.1 ‘Listed activities’ requiring environmental authorisation: the 2006 and 2010
NEMA EIA regulations
The activities subject to this application commenced in November/December 2008 and
October/November 2012 respectively, which means that two different sets of listed activities
applied to the respective flood incidents.
The unauthorised excavation of the emergency sump and repairs to the two bridges in 2008
commenced in terms of the 2006 version of the NEMA EIA regulations, whereas the unauthorised
activities that were commenced with in response to flood damage in October 2012 were in
contravention of the 2010 amendments to the NEMA EIA regulations.
REVISED FINAL EIR FOR ‘MEERLUSTKLOOF’ 59/11, CALEDON
Page 38 of 111
Whereas listing notices published with the 200615
and 201016
NEMA EIA regulations identify
activities that require environmental authorisation subject to the respective periods of validity of
the regulations, the EIA regulations17
‘proper’ constitute the substantive rules governing
applications for environmental authorisation. Both sets of regulation have undergone periodic
amendment.
The NEMA EIA regulations have, since 2006, broadly provided two types of application procedure:
− The basic assessment; and
− The more comprehensive scoping and EIA process.
Under the 2006 NEMA EIA regulations, Listing Notice 1 defined activities for which a basic
assessment had to be undertaken, and Listing Notice 2 described activities subject to mandatory
scoping and EIA. Permission could be sought for a basic assessment, for example, to be upgraded
to a full EIA. Similar provisions are currently in force with respect to the 2010 NEMA EIA
regulations, except that there are currently three and not two listing notices: Listing Notices 1
and 3 respectively define activities and geographical areas to which the basic assessment
procedure applies. Scoping and EIA must be undertaken with respect to activities on Listing
Notice 2.
Had the activities subject to this application been contemplated de novo, afresh, they would have
been subject to environmental authorisation and the prescribed basic assessment process as
defined in the 2006 and 2010 editions of the NEMA EIA regulations respectively..
2.6.2 Listed activities ‘triggered’ by emergency excavations and repairs in 2008
The following listed activities on Listing Notice 1 of GN R. 386 of 21 April 2006 were undertaken
without environmental authorisation in 2008:
1(m) The construction of facilities or infrastructure, including associated structures or
infrastructure, for... any purpose in the one in ten year flood line of a river or stream, or within
32 metres from the bank of a river or stream where the flood line is un-known, excluding
15 GN R. 386 of 21 April 2006 (Listing Notice 1)
16 GN R. 544 and 546 of 18 June 2010 (Listing Notices 1 and 3 respectively)
17 Cf. GN R. 385 for the 2006 NEMA EIA regulations, and GN R. 543 for the 2010 NEMA EIA regulations
REVISED FINAL EIR FOR ‘MEERLUSTKLOOF’ 59/11, CALEDON
Page 39 of 111
purposes associated with existing residential use... but including (iii) bridges and (iv) dams...;
and
4 The dredging, excavation, infilling, removal or moving of soil, sand or rock exceeding 5 cubic
metres from a river, tidal lagoon, tidal river, lake, in-stream dam, floodplain or wetland....
2.6.3 Listed activities ‘triggered’ by emergency excavations and repairs in 2012
The following listed activities on Listing Notice 1 (GN R. 544 of 18 June 2010) were undertaken
without environmental authorisation in 2012:
11 The construction of (iii) bridges and (xi) infrastructure or structures covering 50 square metres
or more where such construction occurs within a watercourse or within 32 metres of a
watercourse...
18 The infilling or depositing of any material of more than 5 cubic metres into, or the dredging,
excavation, removal or moving of soil, sand, shells, shell grit, pebbles or rock or more than 5
cubic metres from (i) a watercourse... (Note that the EMP drafted for this application is also
submitted for approval as a management plan for maintenance purposes as provided for
by Activity 18, LN1). [Corrected by “Correction Notice 2” of 10 December 2010, GN No. R. 1159]
39 The expansion of (iii) bridges within a watercourse or within 32 metres of a watercourse....
40 The expansion of (iv) infrastructure by more than 50 m2
within a watercourse or within 32 m
of a watercourse.... [Corrected by “Correction Notice 2” of 10 December 2010, GN No. R. 1159]
The following activity on Listing Notice 3 (GN R. 546 18 June 2010) was undertaken without
environmental authorisation in 2012:
16 The construction of (iv) infrastructure covering 10 square metres or more where such
construction occurs within a watercourse or within 32 metres of a watercourse (d) in the
Western Cape (ii) outside urban areas (hh) within 5 km of a statutory protected area that is
not a national park.... [Corrected by “Correction Notice 2” of 10 December 2010, GN No. R. 1159]
See Section 1.5 above for a full definition and description of the activities in question.
It is an offence to commence a listed activity without environmental authorisation.18
Transgressors can, on conviction, be sentenced to a fine not exceeding R5-million and/or
18 NEMA s 24F(2)
REVISED FINAL EIR FOR ‘MEERLUSTKLOOF’ 59/11, CALEDON
Page 40 of 111
imprisonment to a maximum of 10 years.19
It is a defence to a charge in terms of NEMA s 24F(2)
to show that the activity was commenced or continued in response to an emergency so as to
protect human life, property or the environment.
2.7 APPEALS
In terms of section 43(1) of NEMA, any affected person may appeal to the Minister against a
decision taken by any person acting under a power delegated by the Minister under Act of 107 of
1998.
2.8 NEMA CHAPTER 5: COMPLIANCE NOTICES AND RECTIFICATION
PROCEDURES
2.8.1 Compliance notices
Section 31L of the Act provides that an environmental management inspector may issue a
compliance notice if there are reasonable grounds to believe that a person has not complied with
a provision of the law (such as the NEMA EIA regulations) for which that inspector has been
designated. A compliance notice must inter alia set out the details of the conduct that constitutes
non-compliance and any steps that must be taken with a specified period.20
Failure to comply
with a compliance notice constitutes an offence as defined by s 24F(2) of the Act.
2.8.2 Rectification applications i.t.o. s 24G of NEMA
NEMA, through s 24G, provides a process that can lead to the rectification of unauthorised,
unlawful activities. The ‘rectification process’ entails submission of an environmental impact
assessment to the competent authority that, in turn, can have two potential outcomes:
− An instruction to cease the activity, either wholly or in part, and to rehabilitate the
environment;21
or
− Authorisation, subject to conditions, of the activity/ies that had been commenced
unlawfully (i.e. continuation).22
19 NEMA s 24F(4)
20 Cf. sub-sections 31L(1) and (2)
21 s 24G(2)(a), NEMA
22 s 24G(2(b), NEMA
REVISED FINAL EIR FOR ‘MEERLUSTKLOOF’ 59/11, CALEDON
Page 41 of 111
The prescribed NEMA s 24G process may, depending on what the competent authority requires,
entail:
− An environmental assessment;
− A description of mitigation measures;
− A description of the public participation process, the issues raised by interested and
affected parties, and how these had been addressed; and
− An environmental management programme.23
The findings of any other studies that may be been required by the relevant authorities would
also have to be recorded in the environmental impact report.24
It is understood that an
application for rectification of an unauthorised activity to allow for its legal continuation would be
subject to the NEMA section 24(4) procedures for the investigation, assessment and
communication potential environmental impacts of activities on the environment.25
2.9 NATIONAL ENVIRONMENTAL MANAGEMENT: BIODIVERSITY ACT
The National Environmental Management: Biodiversity Act, 2004 (Act 10 of 2004) (NEMBA)
among others provides for the:
− Management and conservation of South Africa’s biodiversity within the framework of the
National Environmental Management Act, 107 of 1998;
− Protection of species and ecosystems that warrant national protection;
− Sustainable use of indigenous biological resource; and
− Fair and equitable sharing of benefits arising from bio-prospecting involving indigenous
biological resources; and
− Establishment and functions of a South African National Biodiversity Institute.
The NEMBA is part of a suite of legislation falling under NEMA, which includes the Protected
Areas Act, the NEM: Air Quality Act and the NE: Coastal Zone Act.
23 s 24G(1)(a), NEMA
24 s 24G(1)(b), NEMA
25 “An application (or EIA process followed) in terms of section 24G of NEMA is also subject to the minimum requirements
of section 24(4)(a) and (b) of NEMA. As such, the requirement to investigate the impact of alternatives is applicable. The
requirement for public participation is applicable, but the extent thereof is left to the discretion of the competent
authority.” Paul Hardcastle, DEA&DP, by e-mail 01.04.2010.
REVISED FINAL EIR FOR ‘MEERLUSTKLOOF’ 59/11, CALEDON
Page 42 of 111
Chapter 3 of NEMBA provides a framework for integrated and co-ordinated biodiversity planning,
monitoring of conservation status and promote research in biodiversity.
Chapter 4 deals with threatened and protected ecosystems and species and related threatening
processes and restricted activities.
Section 73 deals with Duty of Care relating to invasive species, while Section 76(2) calls for
development of invasive species monitoring, control and eradication plans by all organs of state
in all spheres of government, as part of environmental management plans required in terms of
Section 11 of NEMA.
NEMBA is particularly relevant to the EIA regime with regard to its provision for the listing of
threatened ecosystems26
and threatening processes27
which, in turn, provide the basis for certain
listed activities. However, no threatened ecosystems had been gazetted when the unauthorised
activities in question had commenced. The ecosystem status of affected vegetation is recorded
below, and uses the recently-published ‘National list of ecosystems that are threatened and in
need of protection’ (DEA 2011) as the reference.
NEMBA would appear to apply to this application insofar as mitigation and longer-term
management of the sites and the broader catchment would be aimed at clearing and controlling
invasive alien plants. Most of the subject property would have supported Greyton Shale Fynbos
(FFh7; Mucina and Rutherford, 2006), an Endangered ecosystem gazetted in terms of the 2011 list
of threatened ecosystems (DEA 2011). The threatened status of this ecosystem is attributed to
loss of habitat measured against the biodiversity target for Greyton Shale Fynbos.
However, this vegetation type – if it had at all been present in a palmiet floodplain wetland
associated with braided foothill channels – has been extirpated from the floodplains of the
Meerlustkloof and Elandskloof river by decades of cultivation and associated agricultural
developments and appears to be limited to steeper, shale-based slopes and high-lying foothills
flanking the river.
The unauthorised activities in question were confined exclusively to the severely eroded channels
of the Meerlustkloof and Elandskloof rivers and therefore would not have entailed the
disturbance or removal of Greyton Shale Fynbos.
26 S 52
27 S 53
REVISED FINAL EIR FOR ‘MEERLUSTKLOOF’ 59/11, CALEDON
Page 43 of 111
2.10 NATIONAL WATER ACT
The National Water Act (NWA), Act 36 of 1998 has the purpose to ensure that South Africa’s
water resources are protected, used, developed, conserved, managed and controlled in ways
which inter alia:
− Promote equitable access to water;
− Redress past racial discrimination;
− Facilitate social and economic development;
− Protect aquatic and associated ecosystems and their biological diversity;
− Reduce and prevent pollution and degradation of water resources; and
− Manage floods and droughts.28
Section 4 of the NWA describes the entitlement to water use, whereby a person may continue
with an existing lawful water use and a person may use water in terms of a general authorisation
or license. Section 21 of the Act defines ‘water use’ which is subject to compulsory licensing
unless the water use is exempted from such compulsory licensing in terms of subsections 22(1)(a)
and (c). Two ‘water uses’ as defined by section 21 of the Act would appear to apply to this
application, viz:
− s 21(c) – Impeding or diverting the flow of water in a watercourse (see definitions below);
and
− s 21(i) – Altering the bed, banks, course or characteristics of a watercourse.
Definition of ‘watercourse’29
Definition of ‘wetland’30
“Watercourse” means –
(a) a river or spring;
(b) a natural channel in which water flows
regularly or intermittently;
(c) a wetland, lake or dam into which, or from
which, water flows; and
(d) any collection of water which the Minister
may, by notice in the Gazette, declare to be a
watercourse, and a reference to a water-
course includes, where relevant, its bed and
banks...
“Wetland” means –
land which is transitional between terrestrial and
aquatic systems where the water table is usually at
or near the surface, or the land is periodically
covered with shallow water, and which land in
normal circumstances supports or would support
vegetation typically adapted to life in saturated soil...
28 S 2 National Water Act 36 of 1998
29 S 1(1), NWA 36 of 1998
30 S 1(1), NWA 36 of 1998
REVISED FINAL EIR FOR ‘MEERLUSTKLOOF’ 59/11, CALEDON
Page 44 of 111
Section 39 of the Act provides for General Authorisations, in terms of which specified water uses
do not require a licence. In this instance, the General Authorisation31
that dispenses with the
need to obtain a water use licence for impeding or diverting the flow of water in a watercourse,
or altering the bed, banks, course or characteristics of a watercourse, is not applicable to the
unauthorised activities that are the subject of this application. This is because GN 1199 does not
apply to development within 500 m of a wetland.
It is recommended that the s 24G process be concluded before a final decision is taken on the
obligations of the applicant in terms of the National Water Act 36 of 1998 as water licensing
requirements in terms of the latter Act would be linked to the alternatives that are eventually
authorised retrospectively by the Department of Environmental Affairs and Development
Planning. The ecological assessment that has been undertaken to inform this application is of
direct relevance to the factors that would inform a decision on a water use licence application
(see, for example, subsections 7(1) to 7(10) of GN 1199 of impacts that must not arise from a
water use).
Section 41 of the National Water Act prescribed procedures for applications for water use
licences. Subsection 41(2)(a)(ii) states that a responsible authority may require that the effect of
the proposed licence on water quality be investigated. The responsible authority may direct that
such an impact assessment complies with the EIA regulations published in terms of the former
Environment Conservation Act 73 of 1989.32
Those aspects of the NEMA s 24G application that also may require a water use licence in terms
of Act 36 of 1998 (viz. sections 21(c) and (i)) have been subjected to a comprehensive assessment
by an aquatic specialist (see Chapters 3, 5 and 6 and Appendix E for the ecological assessment).
2.11 NATIONAL HERITAGE RESOURCES ACT 25 OF 1999
The National Heritage Resources Act (NHRA) 25 of 1999 regulates the management of heritage
resources in South Africa. It is enforced by Heritage Western Cape in the Western Cape Province.
The Act applies to propose planning and development processes in two main aspects, viz. through
regulating of activities:
31 GN 1199 of 18 December 2009 – Impeding or diverting the flow of water in a watercourse [Section 21(c)] and
Altering the bed, banks, course or characteristics of a watercourse [Section 21(i)] 32
Section 41(3), NWA
REVISED FINAL EIR FOR ‘MEERLUSTKLOOF’ 59/11, CALEDON
Page 45 of 111
− Affecting the National Estate;33
and/or
− That may exceed prescribed thresholds.34
The ‘National Estate’ is defined as:
(Those) heritage resources of South Africa which are of cultural significance or other
special value for the present community and for future generations...”35
The NHRA provides for a system of grading and recording heritage resources into resources of
national, provincial or local heritage significance. Criteria are laid down by the Act. The Act
prescribes penalties for damaging or otherwise harming heritage resources. Section 38(1) of the
NHRA identifies activities that have to be reported to the provincial heritage authorities for a
decision on whether a heritage impact report is necessary. These activities include construction of
barriers of various types exceeding 300 m in length, construction of bridges or similar structures
in excess of 50 m in length and development or other activity which will change the character of a
site exceeding 5 000 m2.
None of these circumstances apply to the unauthorised activities in question. See Section 1.2
above for a comprehensive description of the sump and its dimensions.
2.12 CONSERVATION OF AGRICULTURAL RESOURCES ACT
The Conservation of Agricultural Resources Act (CARA), Act 43 of 1983 has the objectives of
conserving the natural agricultural resources of South Africa, through the maintenance of the
production potential of the land, by combating and preventing erosion and the weakening of
water sources, the protection of vegetation and the combating of weeds and invader plants.
CARA provides for prescribed Control Measures,36
enforced through regulations37
. A directive also
may be issued in order to compel landowners to comply with a Control Measure.38
Section 6 describes how that the Minister is to achieve the objects of the Act by prescribing
control measures which may relate to (a) cultivation of virgin soil, (b) the utilisation and
33 Section 3, NHRA 25 of 1999
34 Section 38, NHRA
35 Section 3(1), NHRA
36 Section 6 of CARA.
37 Section 29 of CARA.
38 Section 7 of CARA.
REVISED FINAL EIR FOR ‘MEERLUSTKLOOF’ 59/11, CALEDON
Page 46 of 111
protection of land which is cultivated, (c) the irrigation of land, (d) the prevention or control of
water logging or salination of the land, (e) the utilisation and protection of vleis, marshes, water
sponges, water courses and water sources, (f) the regulating of the flow pattern of run-off water,
(g) the utilisation and protection of vegetation ... (l) the control of weeds and invader plants, (m)
the restoration or reclamation of eroded land or land which is otherwise disturbed or denuded, ...
(o) the construction, maintenance, alteration or removal of soil conservation works or other
structures on land.
The CARA regulations give regulatory effect to the Section 6 Control Measures. They inter alia
deal with the cultivation of virgin soil (i.e. soil that has not been mechanically disturbed for 10
years or more), cultivation of land with a slope, protection of cultivated land against erosion
through the action of water and wind, and utilisation and protection of vleis, marshes, water
sponges and water courses. Permits for the cultivation of virgin soil are issued in terms of
Regulation 2, R1048 of 25 May 1984. CARA is enforced by the Department of Agriculture, Forestry
and Fisheries (DAFF).
Comment has been elicited from the Western Cape Department of Agriculture and the national
Department of Agriculture, Forestry and Fisheries on the obligations of the Applicant in terms of
the CARA Section 6 Control Measures.
2.13 LAND USE PLANNING ORDINANCE
The Land Use Planning Ordinance 15 of 1985 (LUPO) provides a framework for strategic spatial
planning as well as land use control.
Chapter 1 of LUPO provides for structure plans that lay down guidance for the future spatial
development of an area, such as a municipality. Structure plans do not confer or take away rights
in land. However, applications for rezoning must be consistent with an applicable structure plan.
Structure plans must give regard to the preservation of the natural and developed environments.
Chapter 2 of LUPO deals with zoning schemes which form the nub of municipal land use
regulation. Zoning schemes determine land-use rights, provide for control over these rights and
the utilisation of land in the area of jurisdiction of a municipality. Scheme regulations give effect
to control over zoning, and scheme regulations may authorise the granting of departures and sub-
divisions by a municipal council.
Land use must be consistent with its zoning, and the province or a municipal council – if
authorised by the provisions of a structure plan – may grant or refuse an application for rezoning.
REVISED FINAL EIR FOR ‘MEERLUSTKLOOF’ 59/11, CALEDON
Page 47 of 111
Rezoning applications are dealt with by municipal councils and must follow prescribed
procedures. Land must first be rezoned before it can be sub-divided.
The unauthorised activities subject to this rectification application do not require a decision in
terms of LUPO.
2.14 THE DEPARTMENT OF ENVIRONMENTAL AFFAIRS AND DEVELOPMENT
PLANNING (DEA&DP) GUIDELINES AND BIODIVERSITY SECTOR PLANS
There are a number of guideline documents and conservation plans that must inform the work of
both the environmental practitioner and specialists. Of direct relevance are:
− The Department of Environmental Affairs and Development Planning Guidelines on Public
Participation (2010);
− DEA&DP guideline on involving biodiversity specialists in EIA (2005);
− The Draft Western Cape Rural Land-use Planning and Management Guidelines (2009);
and, related to this,
− Critical Biodiversity Areas of the Overberg District Municipality (Holness and Bradshaw,
2010).
Salient aspects of each of the guidelines are summarised below.
2.14.1 Public participation
The public participation guideline provides information on the DEA&DP’s interpretation of the
public participation requirements of the EIA regulations (2010). Of direct relevance here are the
guidelines relating to appropriate mechanisms for notifying interested and affected parties of
their right to comment on applications for environmental authorisation and rectification (e.g. use
of notice boards on site, or the placement of notices in local or regional newspapers). Also
applicable are the minimum periods for public comment: 40 days in the case of draft reports, and
21 days for final documents. Interested and affected parties will have 21 days in which to
comment on this Revised Final Environmental Impact Report. See Chapter 9 for full details of the
public participation process.
2.14.2 Biodiversity specialists
The DEA&DP guideline on involving biodiversity specialists in EIA processes (2005) places a very
strong emphasis on pre-empting irreversible loss of biodiversity and ecological functioning
REVISED FINAL EIR FOR ‘MEERLUSTKLOOF’ 59/11, CALEDON
Page 48 of 111
through proactive planning and impact avoidance. These considerations can no longer apply,
however, once transformation has occurred and mitigation through remediation – not avoidance
– is the only alternative strategy.
Key elements of the DEA&DP biodiversity guidelines that do apply to the application in question,
and have been implemented, are:
− Adoption of an ecosystem approach to impact assessment;
− Addressing impacts on biodiversity at the major levels of hierarchical organisation
(species, communities/habitats, and the catchment or riverscape scale); and
− Relating impact significance to ecological management objectives and the thresholds that
underpin Critical Biodiversity Areas (cf. Holness and Bradshaw, 2010) and National
Freshwater Ecosystem Priority Areas (Driver et al., 2011).
2.14.3 CBA maps and National Freshwater Ecosystem Priority Areas
The CBA Map for the Overberg District Municipality (Holness and Bradshaw, 2010) indicates
areas of land as well as aquatic features which must be safeguarded in their natural state if
biodiversity is to persist and ecosystems are to continue functioning.
Maps of ‘Critical Biodiversity Areas’ (CBA maps) are derived from systematic conservation
planning methods (Margules and Pressey, 2000; Pence, 2008) and identify the most spatially-
efficient network of sites that are required to ensure the continued persistence of:
− Biodiversity pattern (e.g. species, habitats, vegetation types and ecosystems);
− The ecological processes and disturbance regimes by which this biodiversity pattern is
maintained (e.g. seasonal migration of sunbirds or fire in fynbos); and
− The services nature provides to society, such as supplying water, pollination in support of
fruit production, and providing protection against floods
With ecological support areas and areas of other natural vegetation, CBAs form the basis for the
system of spatial planning categories that were designed to give effect to the goals and objectives
of the Western Cape Provincial Spatial Development Framework in rural areas (see below).
The desired management objectives for CBAs (manage against further degradation, restore to a
natural or near-natural condition, manage in a natural condition) provide a useful test for
determining the appropriateness of a proposed development – development that is consistent
with a site’s desired management objectives would be appropriate, whereas development that is
REVISED FINAL EIR FOR ‘MEERLUSTKLOOF’ 59/11, CALEDON
Page 49 of 111
not consistent with these objectives would probably not be appropriate, and an alternative
should be explored. Biodiversity sector plans incorporate a CBA map for each municipality, a
profile of biodiversity per municipality, and land use guidelines. CBA maps represent
CapeNature’s primary reference when commenting on development applications.
Maps produced for South Africa’s National Freshwater Ecosystem Priority Areas (NFEPA) project
depict areas that have been prioritised for conserving freshwater ecosystems and supporting
sustainable use of water resources. (Driver et al., 2011; Day, 2012).
As with CBA maps, FEPA maps promote an ecosystem perspective in environmental assessment in
that they introduce a broader scale to impact identification than is often the case with site or
property-specific impact assessment. These maps emphasise the functional attributes of
biodiversity by providing spatial or geographic surrogates for ecological processes that may
otherwise not be readily evident if an assessment were limited to a particular site or property.
FEPAs have been determined for different river and wetland types throughout South Africa.
Criteria for selection as FEPAs include ensuring that there is an adequate extent of conservation
of different river and wetland ecosystem types, that they represent adequate habitats to support
threatened fish species and their migration corridors, and ecological connectivity between
systems is maintained as far as possible. FEPAs are often tributaries or rivers that support ‘hard-
working’ rivers downstream (that is, rivers that are heavily utilised or impacted by agricultural,
industrial or other human activities). They need to stay (or get into) good condition to manage
and conserve freshwater ecosystems and to protect downstream water resources for human use.
FEPAs do not necessarily need to be protected from all human use. Rather, they should be
supported by good planning, decision-making and management to ensure that human use does
not impact on their condition or on the important resources they may protect downstream (cf.
Driver et al., 2011).
The extent of degradation of wetlands and rivers in South Africa means that even systems
considered in the best relative condition for a particular ecosystem type may be highly degraded.
Nevertheless, the recommended condition for all river and wetland FEPAs is an Ecological
Category A (natural) or B (largely natural) indicative of a system that is in an unmodified/natural
to largely natural condition respectively (Driver et al., 2011).
It is important to recognise that although CBA and NFEPA maps represent the best available
mapped information on biodiversity priority areas, they need to be ground-truthed and do not
REVISED FINAL EIR FOR ‘MEERLUSTKLOOF’ 59/11, CALEDON
Page 50 of 111
replace the need for a specialist assessment (Ralston et al., 2009). Ground-truthing is also needed
to identify potential errors in land cover mapping.
Also, impacts on CBAs and NFEPAs need to be related to the criteria that informed the selection
of a piece of land as a CBA or FEPA as these can range from irreplaceable vegetation, habitats or
species – for which no compensatory trade-offs are available – to areas selected in terms of the
‘best design’ principle which promotes ecologically functional landscapes. In the latter instance,
the goal is to secure ecological processes which, depending on circumstances, may allow more
flexibility in planning than would be the case with developments that would result in irreversible
loss of biodiversity and for which no options remain for meetings targets or thresholds.
See Chapter 3 (‘The receiving environment’) for a description of important biodiversity features
and conservation priorities in the study area.
2.15 THE DRAFT WESTERN CAPE RURAL LAND-USE PLANNING AND
MANAGEMENT GUIDELINES
The draft Western Cape Rural Land-use Planning and Management Guidelines (DEA&DP 2009a)39
translate mapped CBA categories into spatial planning policy in areas outside the urban edge in
the Western Cape. The guidelines are based on the Western Cape Provincial Spatial Development
Framework, an approved section 4(6) structure plan in terms of the Land-use Planning Ordinance
15 of 1985. They aim to:
− Promote sustainable development in appropriate rural locations throughout the
Western Cape;
− Safeguard the functionality of the province’s life-supporting ecosystem services;
− Maintain the integrity, authenticity and accessibility of the province’s significant
farming, ecological, cultural and scenic rural landscapes and natural resources;
− Assist Western Cape municipalities to plan and manage their rural areas more
effectively; and
− Provide clarity to the province’s social partners on what kind of development is
appropriate beyond the urban edge, suitable locations where it could take place, and