AGRICULTURAL LAND DRAINAGE IN BRITISH COLUMBIA: THE RICHARDS CREEK-SOMENOS CREEK EXAMPLE Carla Vander Sluys B.Sc., McGill University, 1983 RESEARCH PROJECT SUBMITTED IN FARTIAL FULFILLMENT OF THE REQUIREMENTS FOR THE DEGREE OF MASTER OF NATURAL RESOURCES MANAGEMENT Natural Resources Management Program Report No. 35 @ Carla Vander Sluys 1986 SIMON FRASER UNIVERSITY December 1986 All rights reserved. This work may not be reproduced in whole or in part, by photocopy or other means, without permission of the author.
104
Embed
AGRICULTURAL LAND DRAINAGE IN BRITISH COLUMBIA: THE ...summit.sfu.ca/system/files/iritems1/6035/b15324138.pdf · Agricultural land drainage is a management practice whereby excess
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
AGRICULTURAL LAND DRAINAGE IN BRITISH COLUMBIA:
THE RICHARDS CREEK-SOMENOS CREEK EXAMPLE
Carla Vander Sluys
B.Sc., McGill University, 1983
RESEARCH PROJECT SUBMITTED IN FARTIAL FULFILLMENT OF
THE REQUIREMENTS FOR THE DEGREE OF
MASTER OF NATURAL RESOURCES MANAGEMENT
Natural Resources Management Program
Report No. 35
@ Carla Vander Sluys 1986
SIMON FRASER UNIVERSITY
December 1986
Al l rights reserved. This work may not be reproduced in whole or in part, by photocopy
or other means, without permission of the author.
APPROVAL
Name: Carla Vander Sluys
Degree: Master o f Natural Resources Management
Tit le of research project:
Agricultural Land Drainage in British Columbia:
The Richards Creek-Somenos Creek Example
Examining Committee:
kenio: ~ u ~ e r v * s o i ' '
Dr. J.C. Day Director MRM Program Simon Fraser University
Committee Member Dr. T-Gunton Professor MRM Program Simon Fraser University
Date Approved: December 6, 1986
i i
PARTIAL COPYRIGHT LICENSE
I hereby g ran t t o Simon Fraser U n i v e r s i t y t h e r i g h t t o lend
my thes is , p r o j e c t o r extended esszy ( t h e t i t l e o f which i s shown below)
t o users of the Simon Fraser U n i v e r s i t y L ib rary , and t o make p a r t i a l o r
s i n g l e cooies on ly f o r such users o r i n response t o a request from t h e
l i b r a r y o f any o+her u n i v e r s i t y , o r o ther educations! i n s t i t u t i o n , on
i t s own behalf o r f o r one o f i t s users. I f u r t h e r agree t h a t permission
f o r m u l t i p l e copying o f t h i s work f o r scho la r l y purposes may be granted
by me o r the Dean o f Graduate Studies. I t i s understood t h a t copying
o r p u b l i c a t i o n o f t h i s work f o r financial ga in s h a l l not be allowed
wi thout my w r i t t e n permission.
T i t l e of Thes i s/Project/Extended Essay
A g r i c u l t u r a l Land Drainage i n B r i t i s h Columbia: The Richards
Creek-Somenos Creek E x a m ~ l e
Carla Vandersluys
(name
1 2 December 1986
(da te )
ABSTRACT
Land drainage, a common management practice whereby farmland is drained to
increase its productivity, is associated with a number of significant economic and
environmental problems.
The major purposes of this study are to: identify major land drainage issues, provide
an analysis of the legislative and institutional arrangements involved, outline the process
involved in making land-drainage decisions, and finally, analyse the effectiveness of this
framework in dealing with some of the more significant land-drainage issues. This w i l l
be done through the use of a case study, the Richards Creek-Somenos Creek Drainage
Improvement Plan. Research is focussed on the economic eff iciency and benefit
distribution o f the project in the study area, the effectiveness of the process in dealing
with resource conflict, and the extent t o which project and policy objectives were
fulfil led.
A post-audit, cost-benefit analysis indicates that even though the project ratio was
positive, over 87.8% of the benefits went t o only one landowner with most farmers
(77.3%) receiving l i t t le or no benefits f rom the project. The federal and provincial
governments provided 75% of the project funding under the ARDSA program. A special
reserve fund established by the municipality of the District o f North Cowichan provided . the additional 25%. Cost to individual landowners was nonexistent. Thus, the project was
entirely funded by the public sector, for the major benefit of one individual. This question
of benefit distribution was not addressed in the project evaluation. Project planning took
over three years, and lack of interagency agreement on mitigatory measures required for
fisheries protection caused a two year delay in project approval.
Appropriate planning on the part o f the controlling agencies, specific policy
objectives including priorization of important habitats, more baseline data, and increased
monitoring o f requested mitigatory measures could reduce confl ict significantly. More
stringent cost-benefit requirements, including a realistic assessment of anticipated
project benefits, as well as an analysis of potential benefit distribution, would aid in
determining which proposed drainage projects best fu l f i l l government policy objectives.
DEDICATION
To my family
ACKNOWLEDGEMENTS
I am indebted to a number of people without whom this project could not have been
completed. Dr. J.C. Day provided constant encouragement and valuable insight
throughout this research project as my senior supervisor. Dr. T. Gunton provided
constructive criticism. Fellow graduate students in the MRM program have always
created a stimulating environment for discussion and interaction, and I thank all o f them.
Special mention goes to the landowners in the study area for contributing their time and
enthusiasm in responding to my inquiries. I would also like to thank R. Sirois for his
moral support throughout my studies. Funding for this research was provided by a Natural
Sciences and Engineering Research Scholarship.
TABLE OF CONTENTS
Approval ........................................................................................................................................ i i
........................................................................................................................................ ABSTRACT i i i
DEDICATION ..................................................................................................................................... i v
ACKNOWLEDGEMENTS ...................................................................................................................... v
List o f Tables .................................................................................................................................. ix
List o f Figures ................................................................................................................................... x
......................................................................................... 2.3.4 Water Quality 9 . ........................................................................ 2.3.5 Vegetation and Wi ld l i fe 9
.................................................................................. Economics o f Land Drainage 11
.......................................... Criterion 2: Administrative and Legislative Simplicity 17
2.9 Criterion 3: Project and Policy Effectiveness ...................................................... 17
........................ 2.10 Criterion 4: Process Adequacy: Dealing with Resource Conflict 17
BRITISH COLUMBIA AGRICULTURAL LAND DRAINAGE LEGISLATION. PLANNING. AND DECISION-MAKING ............................................................................... 19
AN ANALYSIS OF THE RICHARDS CREEK-SOMENOS CREEK DRAINAGE IMPROVEMENT PLAN ......................................................................................................... 37
6 Distr ibution o f Project Benefits Among Landowners .................................................... 55
...................................... . 8 Percent o f Benefits accrued vs Percent o f Benefit t ing Land 56
..................................................................... 8 Breakdown o f Interest Groups at Meetings 61
LIST OF FIGURES
Figure Page
1 Study Area Location .............................................................................................................. 5 ................................................................. 2 The Land Drainage Decision-Making Process 22
ARDA
ARDSA
DFO
M AF
MDNC
MLPH
MOE
WCT
LIST OF ACRONYMS
Agricultural and Rural Development Agreement
Agricultural and Rural Development Subsidiary Agreement
Federal Department o f Fisheries and Oceans
British Columbia Ministry of Agriculture and Food
Municipality o f the District o f North Cowichan
British Columbia Ministry of Lands, Parks, and Housing
British Columbia Ministry of the Environment
Willis, Cunliffe, and Tait, Consulting Enginers
CHAPTER 1
INTRODUCTION
Agricultural land drainage is a management pract ice whereby excess water is
removed f r o m agricultural lands, increasing product iv i ty o f ex ist ing crops as w e l l as
a l lowing changes in land use patterns t o more lucrat ive crops. Prior t o the 1970's, land
drainage was considered t o be a necessi ty i n m o s t poor ly-drained areas, and there was
l i t t le demand f o r detai led studies o f the environmental impacts o f drainage pro jec ts
(Brady 1982, 1). There w a s also l i t t l e emphasis p laced o n benef i ts and costs o f drainage
projects, part icular ly the dist r ibut ional quest ion o f w h o benef i ts and w h o pays f o r the
drainage works . Nor ton and MacMi l lan (1972, I) suggest that th is m a y be due, in part, t o
the fac t that agricultural land drainage i s f requent ly associated w i t h more marginal
agricultural areas, where economic e f f i c i ency i s less important than survival.
Agr icul tura l development po l ic ies at the federal level encourage land drainage
through economic incent ives such as the ARDSA (Agricultural and Rural Development
Subsidiary Agre,ement) grants. This funding i s general ly a result o f lobby ing b y vocal
interest groups w h o support drainage. A s Chambers (Canada 1985, 3) suggests "the
easiest w a y t o improve an individual farmer's s i tuat ion i s t o bui ld bigger and better
drains, part icular ly i f someone else pays the bi l ls." The rat ionale behind these subsidies
i s that the drainage pro jec ts w i l l improve income d is t r ibu t ion b y increasing earnings in '
the lower income rural regions o f the country. I t has o f t e n been argued that these types
o f subsidies encourage the uneconomic development o f marginal farmland that wou ld
otherwise be l e f t i n a natural state. A lso , there i s l i t t l e incent ive fo r cr i t ica l evaluation o f
these programs due t o their concentrated benef i t and d i f f used cost nature. Since projects
are funded b y federal taxes, the cos t t o each taxpayer i s min imal whereas program
benef i ts are h ighly concentrated in the pro jec t area.
Planning f o r drainage pro jec ts is undertaken b y a number o f government agencies
w i t h var ied interests. The mandates o f these agencies are o f ten very speci f ic and
divergent, resul t ing i n conf l i c ts . A s is the case in many resource issues, a single
ob jec t ive approach b y cont ro l l ing agencies is unsat is factory in reso lv ing conf l i c t . A n
integrated decis ion-making process is necessary, one which considers current use and
future potential, as well as the economic costs and benefits of all proposed management
act ions.
In mountainous regions like British Columbia, productive agricultural land subject to
drainage tends to be located in valleys where it must compete with many other potential
land and resource uses. Water management conflicts frequently arise in such areas,
particularly with respect t o wetland destruction and the potential destruction or
impairment o f f ish habitat. Increasing interest by both the federal and provincial
governments towards the protection o f f ish habitat, and the use o f the Fisheries Act as a
powerful legislative tool, have had a major influence in the debate between agriculture
and fisheries. In many cases, strict application of the federal Fisheries Act without due
consideration being given to agricultural interests is seen to be a problem (British
Columbia 1979, 1). The Fisheries Act has been described as a very 'blunt instrument' to
deal with management confl icts (Pearse 1984; presentation at the water resources
conference). Lack of appropriate baseline data in many instances renders conflict
resolution between agriculture and fisheries difficult.
Although there has been extensive research conducted on agricultural land drainage
in other provinces, relatively l i t t le work has been done in British Columbia. There is
recognition that potential problems exist, as was evidenced by the creation o f the Farm
and Stream Committee in 1977. The role of this committee, initiated by the BC Federation L
of Agriculture, was to undertake an enquiry into "the nature o f government restraint
placed upon farmers attempting t o manage water for the benefit o f farm operations
(British Columbia 1979, I)." The committee identified two important needs. The f i rst was
that there should be procedures developed for farmers with water management problems.
These procedures would aid in increasing the farmers' understanding of government
regulations, and identify potential problem areas before they arise. The second was that
there should be a system developed for solving water management problems that would
be satisfactory to both farmers and concerned agencies.
1.1 Studv Purpose
The purpose o f this study is to examine the effectiveness of British Columbia land
drainage policy, and its approach to planning and decision-making. The major objectives
of the study are:
to provide a theoretical perspective of the major issues in land drainage,
t o provide a framework of the financial, legislative, and institutional land
drainage arrangements in British Columbia,
t o outline the process involved in making land drainage decisions as evidenced
in a case study,
t o provide an analysis of the effectiveness of this framework and process in
dealing with some major land drainage issues; and,
t o provide conclusions and recommendations to improve the process of land
drainage evaluation.
1.2 R e ~ o r t Format
This study uses evaluative research techniques, including a literature review,
interviews with landowners, and an analysis o f administrative records. A case study is
presented to illustrate the approach to drainage planning and decision-making in British . Columbia. A series of land-drainage analyses have been undertaken in Ontario, and a
general methodology that can be applied to this type of evaluative research has been
developed (Day et al. 1977). The hindsight evaluation methodology provides a seven-step
evaluative model. These include: (1) project environment, (2) institutional arrangements
and policies, (3) management actions (4) management impacts (5) process and adequacy,
(6) utilization of findings and, (7) recommendations. A modified version o f the model is
used in this study. Chapter two provides a theoretical framework for the study by
outlining past agricultural land drainage research, identifying current issues, and
introducing the evaluative criteria used in the study. In chapter three, the land drainage
planning and decision-making process in British Columbia is presented, including relevant
legislation and institutional arrangements. Chapter four provides a brief history of the
drainage problems in the case study area, and outlines major steps in the planning process
as evidenced in the case study. Chapter f ive presents an analysis of the Richards
creek-Somenos Creek Drainage Improvement Plan, using the criteria outlined in chapter
two. Conclusions and recommendations are presented in the final chapter.
I .3 The Case Study
The Somenos drainage basi :ated north o f the City of Dun can o n Vancouver
Island (fig 1). I t is 65.7 km2 (25.4 mi2) in size; Richards Creek is a major tributary.
Somenos Creek drains into the Cowichan River upstream of the estuary.
The Somenos drainage basin is subject to frequent inundations during high-water
periods. Up to 228 ha of agricultural land are affected by f looding annually. Eighty
percent of this land is in the Richards Creek subbasin (British Columbia 1981). The major
impact of this annual f looding is the inability of the farmers to get on their land early in
the season to plant crops. As a result, the productivity of the area is lower than it could
be.
Historically, f lood control in the area was the responsibility of the Somenos
Drainage Board. The board was unsuccessful in implementing a drainage scheme in the
area in the 1950's, for reasons to be discussed in chapter four. Subsequently, the
Municipality of the District o f North Cowichan (MDNC) applied to the federal-provincial L
program established under the Agricultural and Rural Development Subsidiary Agreement
(ARDSA) for funding to complete drainage works- in the basin. Under the application, an
initial project feasibility study examined four alternatives. In 1983, funding was approved
and the first alternative was undertaken, that o f cleaning both Somenos Creek and
Richards Creek. The case study presented in chapter four analyses actions taken during
the period 1980 to 1983.
CHAPTER 2
THEORETICAL FRAMEWORK AND LITERATURE REVIEW
The purpose of this chapter is t o ident i fy major land drainage issues, and selected
factors signif icant in the success or failure o f drainage projects. The informat ion
provided here is the result o f an extensive literature review as wel l as the examination o f
a number o f drainage case studies undertaken in Ontario.
2.1 Rationale for Public Investment in Drainage
Public investment in water resources, including drainage projects, involves a number
o f goals, including: a more equitable distr ibution o f income, regional development, and
increased economic ef f ic iency o f the system. Gardiner (1973, 2 ) suggests that unti l
recently
. . . economic decision-making criteria, or the importance o f having the benef i ts o f a project outweigh the costs, exceeded any other as the most important cri teria f o r public investment decisions in water resource projects.
Objectives such as income redistr ibution and more recently, a prist ine natural
environment, tended t o be ranked lower, Problems o f creating policies which sat isfy all
criteria are numerous. One must design a po l icy which considers all possible e f fec ts and
impacts, as wel l as determining which objectives w i l l be the most important and should
therefore carry the greatest weight. Unless these objectives are clearly defined, pol icy
evaluation is extremely d i f f icu l t .
2.2 Physical Objectives of Land Drainage
Major benef i ts o f land drainage include increased product iv i ty due t o a lowering of
the water table (Hill 1975, 253). By increasing the depth o f the root zone, more plant
nutrients are made available t o crops (Manitoba 1972, 2). Soi l structure is improved as a
result o f better venti lat ion which al lows f o r increased availabi l i ty o f oxygen around the
root area. Soi l temperatures also tend t o increase fo l low ing a drainage project (Manitoba
1972, 2). These ef fec ts result in increased so i l fer t i l i ty and crop production because o f
earlier germination, improved soil ability to support a wider range of crops and improved
reactions of the soil to different cropping techniques. There is also a marked
improvement in crop quality (British Columbia 1972). Although land drainage is frequently
undertaken in areas o f already high productivity, a major goal of many drainage projects
is to render marginal farming areas more economically viable through improvements in
productivity.
There are various methods whereby land can be drained. These include:
construction o f , or cleaning, a main drainage channel; construction o f outlet or f ield
ditches to carry water from agricultural fields to main channels, and tile drain
construction, or perforated pipes, which underly agricultural fields. Most drainage
schemes are a combination o f these three methods.
2.3 Environmental Impacts of Land Drainage
There is a relatively large body o f literature on the effects of channelization on channel
morphology, turbidity, hydrology, and stream water chemistry. There is, however, a
paucity of information on the effects o f altering hydrological regimes on fish and wi ldl i fe
populations. Most research is site-specific, and extrapolation of results from one
watershed to another is not always possible or desirable. Insufficient data on the direct
effect of land drainage on fish and wi ldl i fe populations make i t di f f icul t for managers to . reach objective decisions regarding land drainage schemes. Recent Ontario work has
attempted to quantify the effects of land drainage on the biological environment (Diebolt
1981; Hill 1975; Irwin and Whitely 1983; Day, Brady, and Straite 1976). Hill (1975, 253)
describes the goal of these studies as fol lows:
. . . the documentation o f these environmental impacts forms a necessary basis for better decisions regarding the design and implementation of drainage schemes. Furthermore, this information is a vital pre-requisite t o development o f legal and institutional frameworks which can cope with the indirect effects of agricultural land drainage on the environment.
Major land drainage impacts can be divided into several categories o f change:
channel morphology, surface and subsurface f l ow characteristics, water quality, and
vegetation and wi ldl i fe as a result o f habitat alterations (Diebolt 1981, 110-142).
2.3.1 Channel Morphology
Channel morphology is altered as a result o f modifications in stream discharge,
sediment loads, or both. The major effect of changes in sediment load or stream
discharge is an alteration in the equilibrium state o f the watercourse. This is defined as
"the state at which the stream gradient, channel form, and all other physical
characteristics are adjusted so as to move the available sediment with as l i t t le energy as
possible"(Hill 1975, 263). The degree of change that occurs depends on the nature of the
disturbance. These changes are often a result of increased sedimentation due to bank
disturbance and erosion during drain construction. I t must be noted, however, that there is
a lack o f quantitative data on the relationship between land drainage and increased
sedimentation in watercourses. Diebolt (1981, 112) noted in a case study of drain
reconstruction in Ontario, that the channel was almost doubled in size and the banks were
excavated at abrupt, unstable angles o f approximately 60 degrees. Suspended sediments
were 600 times greater than prior t o construction (Diebolt 1981, 123). In addition to
potential harm to the f ish population, these results suggest that the potential benefits of
any project could be reduced i f there is substantial erosion, returning the project site to
preproject conditions in a shorter period o f time. In drainage projects, most sediment is
produced during the initial channel clearing and when the banks are exposed immediately
after construction.
2.3.2 Water Temperatures and Light
Drainage projects can also significantly affect water temperature, particularly i f the
project requires the removal of bank vegetation which normally provides shade. Most
average stream temperatures increase slightly with a decrease in the amount of canopy
cover and streamside vegetation. Opinions on the actual effect of this on fish
populations varies (Hartman and Holtby 1982; Canada 1981). Generally, increased water
temperature increases the rate of metabolism and respiration as well as potentially
affecting reproductive and feeding capacity of some species (Hill 1975, 268). Decreased
canopy also affects the amount of light available, and this can affect stream productivity,
increasing i t somewhat (Hartman and Holtby 1982).
2.3.3 F iow Characteristics
In addit ion t o altering sediment load and channel morphology, drainage projects can
also have a signif icant e f fec t on downstream f l o w characteristics. There are t w o
conf l ic t ing opinions concerning land drainage and s t reamf low (Irwin and Whitely 1983,
90). The f i rs t is that drainage improvements speed the movement o f water through a
stream system and w i l l therefore increase downstream f lood ing through an increase o f
peak f lows. The alternate v iew suggests that drainage projects tend t o increase the
natural so i l storage capacity and, as a result, downstream f lood ing is reduced. Results o f
a literature survey b y Whitely (1975) indicate that drainage w i l l usually increase peak
f low. Instal lat ion o f t i le drainage, however, may reduce f lood ing since t i l e drains tend t o
increase the so i l storage capacity t o a depth be low the normal level. Thus, fo l lowing a
dry period, the e f fec ts o f a s torm event may be less signif icant in an area which has t i le
drainage as compared t o an area that has none. Overall, the e f fec t o f drainage on f l o w
characteristics remains unresolved.
2.3.4 Water Quality
Water chemistry i s also af fected b y agricultural land drainage. Hil l (1975, 264)
suggests that land drainage can result in the accelerated movement o f water containing
fert i l izers and pesticides into the aquatic system. Of particular interest is the increased
nitrogen in the system in the f o rm o f nitrates. Although increased nitrates may increase
product iv i ty o f the system in the short run, long-term eutrophication problems may result
(Hartman and Holtby 1982; Hetherington 1976 in Hartman 1982).
2.3.5 Vegetation and Wi ld l i fe
Drainage impacts on vegetation and wi ld l i fe are varied. Langer (British Columbia
1980) Slaney, Halsey, and Tautz (British Columbia 1977) and Hooten and Reid (British
Columbia 1975) studied the ef fec ts o f sedimentation and channelization on f ish
populations. They found that increased sediment loads o f ten result in adverse ef fects on
plant and animal l i fe. Stream sediment plays an important role in determining the type
and amount o f primary producers in a stream and may be a l imi t ing parameter in many
ecosystems. The major e f fec ts o f increased sedimentation include increased stream
tu rb id i ty wh ich l im i t s photosynthet ic ac t iv i ty , and m a y act as a visual barrier t o some
predaceous f ish species, decreasing their feeding efficiency. Increased substrate a lso has
an abrasive e f fec t on the streambed, alter ing channel morpho logy and blanketing certain
streambed areas w i t h f ine deposits. I t m a y f o r m a mob i l e substrate that inhibits algal
growth, c logs the f i l te r feeding apparatus o f benthic invertebrates, and creates a general
reduct ion in f o o d avai labi l i ty . Changes in the subgravel environment as a result o f f ine
sediment deposi ts is perhaps the mos t s igni f icant impact. Destruct ion o f f i s h eggs may
result through sedimentat ion o f spawning grounds. Salmonid a levin are extremely
dependent o n physical and chemical condi t ions o f the gravel environment f o r survival.
Often, there i s a decreased egg t o f r y surv ival rate as a result o f decreased oxygen in the
subgravel environment. Fry surv ival is a lso af fected. Juveni les and adults m a y suf fe r
f r o m abrasion o f g i l l t issues and accumulat ion o f f i ne sediment i n the gi l ls.
Actual physical remova l o f streamside vegetat ion occurs in m o s t drainage projects,
part icularly a long banks where large machinery cuts a path t o comple te the work. I n areas
where spo i l i s deposited, vegetat ion is o f t e n covered and destroyed. Expansion o f the
agricultural land base as a result o f drainage reduces the size and number o f natural plant
communi t ies. Water table changes can a lso cause al terat ions i n the wet land species
composi ton. Marshes, bogs, and other poor ly-drained areas are important i n the l i f e
cycle o f a number o f w a t e r f o w l and w i l d l i f e species. Changes to , or comple te remova l
o f , such areas can have a s igni f icant local, regional, and somet imes even a national
impact o n some w i l d l i f e populat ions (Diebolt 1981 ; Brady 1982; Hi l l 1975).
2.4 Economics o f Land Drainage
2.4.7 Cost-benef i t Analys is
Discussion o f the economic impact o f land drainage focuses pr imar i l y o n
cost-benef i t analysis. Under this procedure, the ant ic ipated benef i ts o f a project ,
speci f ical ly the expected increase in c rop production, or t ransfer t o a more lucrat ive crop,
are total led. This value is then compared t o the cos t o f undertaking the drainage project.
I f the predicted benef i ts outweigh the expected cos ts , a pro jec t is considered t o be
feasible.
There are a number o f p rob iems associated w i t h the use o f cost-benef i t analysis i n
the determinat ion o f drainage project feasib i l i ty . Accurate c rop pr ice forecast ing i s
d i f f i cu l t , as i s predict ing anticipated crop product ion increases. Predict ions o f an
individual farmer's behavior w i t h respect t o cropping pat terns and investment i s a lso
s igni f icant i n the calculat ion o f p ro jec t benefi ts. M o s t drainage cost-benefi t analyses
assume that newly-drained land w i l l eventual ly b e adapted t o the m o s t
revenue-maximizing land use. Al though th is does occur i n some instances, many farmers
do n o t have the f inancia l abi l i ty , economic incentive, o r the in i t ia t ive t o alter their fa rming
methods or product iv i ty . Day, Brady, and Stra i te (1976.20) found that the preconstruct ion
cost-benef i t ra t ios o f some pro jec ts tended t o overest imate the wi l l ingness t o invest b y
individual farmers. The degree o f t i l e drainage insta l led f o l l o w i n g comple t ion o f a
project i s a lso s igni f icant i n the outcome o f drainage cost-benef i t analysis. Percent o f
t i le drainage insta l led has been shown t o s ign i f i cant ly impact t o ta l net project benef i ts .
Research in Ontar io indicates that:
. . . out let drains prov ide l i t t le increase in crop y ie lds w i thou t associated t i l e drains t o remove water f r o m the crops. Therefore, f o r the agricultural benef i ts o f drainage technology t o be reaped, it i s essential that b o t h t i l e drains and out let drains be constructed t o increase agricultural p roduct iv i ty and qual i ty (Topecon Group Ltd. 197 1, 1).
A l s o important i n the calculat ion o f project benef i ts is the degree t o wh ich there i s p o s t
project maintenance. Often, drains are neglected and benef i ts d o n o t accrue as
anticipated due t o the rapid deter iorat ion o f the drains as a resul t o f th is neglect.
The cos ts associated w i t h large-scale drainage pro jec ts are numerous. I n add i t ion
t o mater ia l and labor, there are a number o f indirect expenses such as administ rat ive,
legal, and maintenance costs. The discussion o f environmental impacts in the preceding
section also indicates that there may be a number o f indirect, long-term, environmental
impacts associated w i t h drainage which are extremely di f f icul t , i f not impossible, t o
quantify.
Past research in land drainage economics reveals signif icant variations in the
economic ef f ic iency o f drainage schemes (Brady 1982, 9). The Topecon Group Ltd.
(Brady 1982, 9) undertook a cost-benefit analysis o f ARDA projects in Ontario, and
discovered that f o r a number o f projects, benefits accrued did not warrant project
expense. Found, Hill, and Spense (1974) also completed a study on economic and
environmental implications o f drainage in Ontario. They found that in 11 o f 37 drains,
benefits fa i led t o surpass the expense o f drainage. These studies indicated that seven
factors accounted f o r the decrease o f benefit-cost rat ios in drainage projects. Tnese
factors were:
the init ial product iv i ty o f the land, whether the so i l was fert i le t o begin w i tn or
needed substantial investment in fert i l izer as wel l as drainage t o become
productive
the propensity o f landowners t o instal l f ie ld underdrainage (ti le drains)
special condit ions such as unstable soi l type and hydrology which can af fec t
the cost o f construction
type o f project (large scale versus small scale)
local in i t iat ive t o invest in and maintain the project
quali ty o f engineering, and
weather condit ions since the start o f the project
These factors are frequently ignored in prel iminary drainage economic feasibi l i ty studies.
Found, Hil l , and Spense (1974) suggest that all benefit-cost studies o f drainage projects
should take these seven important factors into account.
2.4.2 Distr ibution o f Benef i ts and Costs
Gardiner (1973, 5) discusses public investment in drainage in terms o f the
distr ibutional objective, suggesting that the goal o f public investment in drainage is t o
cause changes in the way that income is distr ibuted among members o f society. The
distr ibut ional ob jec t ive ra ises a number o f questions w i t h respect t o drainage projects.
Part icularly relevant here are the cost-benef i t aspects: w h o benef i ts f r o m the project and
w h o pays; and w h o should benef i t and who should pay? In the case o f a
federal ly-subsidized project , these quest ions become signi f icant since i t i s national tax
dol lars wh ich pay f o r a local project .
2.5 Land Use Conflicts Resulting From Drainage Proiects
Land drainage projects, wh i le undoubtedly creat ing b enef i ts t o some indiv idu als,
f requent ly con f l i c t w i t h other user groups including f isher ies, environmental ists, and
downstream landowners.
2.5.7 Environmental is ts
Environmental ob jec t ions t o land drainage are m o s t o f t e n associated w i t h the loss
o f wetlands. Wet lands have r ich organic soi ls , and as a result they are the target o f many
drainage works . Draining them converts otherwise unsuitable land f o r crop production.
Wetlands are- a lso drained t o improve adjacent agricultural areas (Ontario 1974, 18).
Wetlands, unl ike some other natural habitats, are no t subject t o intensive recreational
act iv i t ies. The nature o f the habitat is such that boat ing, camping, hiking, and other
t radi t ional recreational ac t iv i t ies are impossib le. Use o f wet lands i s therefore restr ic ted L
t o ve ry spec i f i c user groups such as bird-watchers and hunters. I t i s on l y i n recent years
that groups have begun t o oppose large-scale wet land drainage. In Ontario, and
part icular ly the Uni ted States, these con f l i c t s have escalated t o b i t ter disputes between
environmental is ts and those responsib le f o r land drainage. Conf l i c t resolut ion i s d i f f i cu l t
when there i s inadequate assessment o f project impacts o n alternative land uses.
2.5.2 Downst ream Users
Frequently, approval o f a drainage plan i s dependent upon agreement b y all, or at
least a ma jo r i t y o f , landowners i n a drainage basin. Approva l i s somet imes d i f f i cu l t t o
achieve, however, f o r a number o f reasons. First, as sec t ion 1.3.3 indicates, drainage in
one area m a y increase f l o w s further downstream. Thus, downstream landowners
Occasional ly ob jec t t o proposed drains on the basis that their p roper ty may b e f l ooded
more frequently as a result. Associated w i t h this is the distr ibution o f project-related
benefits. Downstream landowners o f ten believe they w i l l not derive the same amount o f
long-term benefits f r om a project as landowners direct ly af fected (Brady 1982). Indeed,
they o f ten believe that they w i l l suffer as a result.
2.5.3 Fisheries
In Brit ish Columbia, a major land drainage conf l ic t is associated w i t h drainage
impacts on fisheries, an important provincial resource. Metzger (1982) discusses the
fisheries problems at length. He states that associated conf l ic ts are due t o three factors.
The f i rs t is ignorance o f potential negative drainage impacts and legislative requirements
on the part o f the farmers. The second is the relatively confused regulatory role o f the
agencies involved, and the third is the maintenance o f t oo r ig id a stance b y those
agencies, which results in a confrontational rather than a cooperative attitude towards
conf l ic t resolution. An example o f this conf l ic t w i th fisheries is evident in a paper b y
Regts (1983). He estimated that agricultural losses due t o the failure t o obtain approval
for cleaning and maintaining drainage channels in the Distr ict o f Matsqui were
approximately $1,100,000 per annum, although he concedes that part o f this cost is
attributable t o lack o f federal and provincial funding. Regts also states that:
. . . the fisheries ministry has lost the confidence o f the municipal and consult ing engineers. It appears that the [federal] f isheries ministry is unable t o provide the type o f leadership which w i l l lead t o a cooperative approach fo r maintaining desirable streams fo r a mult i tude o f uses including fisheries, b
drainage, irr igation and recreation.
2.5.4 Mit igat ion as a conf l ic t resolution too l
In Brit ish Columbia, fisheries conf l ic ts are o f ten solved through the use o f
mit igatory measures t o reduce negative project impacts on the fisheries resource. There
are a number o f mit igat ive measures commonly used t o reduce land drainage impacts on
fisheries. Streamside vegetation management is one measure o f which the most common
is t o leave a vegetative str ip along the streambank (Canada 1981). Controversy exists
over how wide this str ip should be. Gil l ick and Scott (Washington 1975) provide an
analysis o f the ideal buffer str ip width, suggesting that the actual w id th depends on such
things as the value o f the resource being supplanted, and the income that resource owners
are wi l l ing t o for fe i t t o protect the fisheries resource. Use o f detailed so i l inventories t o
guide construction, the use of certain construction techniques t o minimize gullying and
sheet erosion and control point-source sediments, (British Columbia 1977b; Hartman and
Holtby 1982; Nelson and Salwasser n.d.; Hartman 1982), and t iming construction to avoid
critical fisheries periods are all common mitigation measures (Hartman and Holtby 1982;
British Columbia 1980b). Swanson (1979) identifies six factors leading to effective
mitigation. These include:
a clear understanding of the concept of mitigation by all those involved;
development o f criteria for determining the type o f mitigative measures to be
used. Carlton (1979) points out that mitigation in the forestry industry is more
often than not piecemeal or ad hoc. In the absence o f established objectives,
mitigative measures become something which are simply added on at the end
o f a project. Standard quantitative methodologies to predict and evaluate
impacts and the effectiveness o f mitigative measures are essentially
nonexistent;
early involvement in planning by all interest parties;
effective implementation o f plans. This is often the least successful aspect
of resource planning. British Columbia has some examples o f successfu!
implementation planning, such as the Tsitika Follow-up Committee, but such
committees are rare (Vreeswijk 1985,95);
effective operation and maintenance of mitigative measures; and L
adequate mitigation funding, including the issue of who provides the
mitigation funds;
Determination of the success o f mitigation in terms o f both environmental and
social allocation of resources is an important part of confl ict resolution analysis.
Information on the costs and benefits of such measures in British Columbia is rare
(Dorcey, McPhee, and Sydneysmith 1980).
2.6 Evaluative Criteria
The preceding sect ions indicate that there are a number o f s igni f icant issues that
should be considered be fo re a drainage project proceeds. Once a project i s ini t iated, n e w
issues arise, such as wh ich construct ion techniques t o use, h o w t o maximize benef i ts ,
min imize negat ive impacts, and ensure that everyone a f fec ted w i l l be re la t ive ly sa t is f ied
w i t h the f inal result. Planning, consul tat ion between the publ ic and the min is t r ies
involved, and appropiate legis lat ion and funding agreements are essential i f pro jects are
t o be economica l ly e f f i c i en t and soc ia l ly and environmental ly acceptable. Nor ton and
MacMi l lan (1972) def ine economic we l fa re e f f i c i ency as a pos i t i on that i s equitable and
ye t g ives a d is t r ibu t ion o f benef i ts that is considered t o be fair. The degree t o wh ich any
development achieves th is goal i s a func t ion o f the po l i t i ca l and inst i tut ional
arrangements cont ro l l ing that development. I n order t o evaluate this, the f o l l o w i n g
cri ter ia, der ived f r o m the preceding l i terature rev iew and adapted f r o m a number o f texts
on po l i cy evaluation, w i l l be used as a basis f o r the evaluat ion o f the Richards
Creek-Somenos Creek Drainage lmprovement Plan.
2.7 Criterion 1: Proiect Economic Efficiency
This c r i te r ion w i l l evaluate the economics o f the Richards-Creek Somenos-Creek L
Drainage lmprovement Plan. It can be d iv ided in to three sections. The f i r s t is a cr i t ique
o f the cost-benef i t analysis comple ted as part o f the pro jec t feas ib i l i t y study. Important
po in ts t o be considered are whether a l l expenses, including environmental and mi t iga t ion
costs, and administ rat ive cos ts o f con f l i c t resolut ion, are included. Second, an
independent cost-benef i t analysis o f the project i s presented t o determine pro jec t
e f f i c iency . Data o n benef i ts in 1984, one year af ter p ro jec t implementat ion, are used as
w e l l as updated values in 1986, three years a f te r p ro jec t complet ion. Final ly, the
avai labi l i ty and success o f current legis lat ive and economic incentives i n ensuring
economic e f f i c i ency and equi ty are examined in the th i rd section.
2.8 Criterion 2: Administrative and Legislative Sim~l ic i ty
This cri terion examines legal and insti tut ional aspects o f drainage po l icy t o
determine the extent t o which the insti t i l t ional and legislat ive aspects are clearly
understood b y those who must deal w i th therm. Ease o f po l icy implementation is also
analysed.
2.9 Criterion 3: Proiect and Policv Effectiveness
The goal o f this cr i ter ion is t o determine the success o f the project and po l icy in
achieving i ts stated objectives. A t the project level, analysis concentrates on whether the
stated objectives o f the project were realized. In the po l icy section, the discussion
focuses on whether the project succeeded in fu l f i l l ing government po l icy objectives. A n
important aspect o f effectiveness project equity in terms o f who benefits, who pays, and
whether that distr ibution o f project benef i ts is in accordance w i t h government po l icy
objectives.
2.10 Criterion 4: Process Adeauacv: Dealing with Resource Conflict
This cri terion examines the abi l i ty o f the process t o deal w i t h environmental . objections t o drainage projects. Evaluative informat ion w i l l include:
the project environmental impacts and how they were dealt with,
the existence o f an adequate appeals procedure in the case o f dissatisfaction
b y interested or af fected parties,
success o f exist ing planning mechanisms t o ensure that all present and
potential land uses in the area are adequately considered before the project
proceeds, and
the availabi l i ty o f a forum fo r public part icipation in the planning process.
This cri terion also examines the role o f the federal and provincial fisheries
departments in project planning. Important points reviewed include: the c lar i ty o f both
governments' objectives w i th respect t o fisheries habitat in the study area; the basis f o r
establishing various mit igat ive measures requested b y these departments; the wil l ingness
o f the fisheries departments t o participate in the planning process; and, the availabi l i ty o f
monitor ing programs t o determine the effectiveness o f mit igat ive measures employed.
Finally, comments are made concerning the openness and accountability o f the
decision-making process.
CHAPTER 3
BRITISH COLUMBIA AGRICULTURAL LAND DRAINAGE LEGISLATION, PLANNING, AND
DECISION-MAKING
Primary objectives o f this chapter are to provide:
a review of legislation affecting land drainage;
a framework of the planning and decision-making process concerning drainage
funding and project development; and,
an introduction to the federal and provincial land drainage agencies.
3.1 Legislation
There are two types o f legislation relating to land drainage in British Columbia:
common law and statute law.
3.7.7 Common Law
Most law for water courses is founded on the maxim "Aqua currit et delet currere"
or, "water f lows naturally and should be permitted to f low." Thus, common law imposes
an obligation on landowners to avoid altering natural drainage to the detriment of others.
According to Chessman (1984), the riparian water rights doctrine has created a . presumption that
. . . secure water f lows and consumption must not be transferred within the water basin or beyond it without unanimous consent f rom all riparians and potential riparians.
Use of this presumption in dealing wi th drainage projects where unanimous approval is
virtually impossible to achieve would ensure that hardly any project is constructed. In
response to this, the doctrine o f prior appropriation was developed in the United States.
In Canada, the 1894 Northwest lrriqation Act established the principle of prior
appropriation in the western provinces through the development o f the f irst water
licensing system. Subsequent legislation in all of the western provinces has fol lowed
this principle (Chessman 1984). In the area o f land drainage, statutory powers of the
province used to expand landowners' rights beyond that which is traditionally permitted
through the court's interpretation of the common law (11 A C.E.D. (Western) 2nd. ed).
These statutes are br ie f ly described in the fo l lowing section.
3.1.2 Statute Law
Licensing and approval o f the right t o use water is covered under the Water Ac t
(British Columbia 1979~) . A l l drainage projects require a water licence before they can
proceed. Under section 6 o f the act, the comptrol ler o f water r ights may issue a license
t o a municipali ty, improvement distr ict, or water distr ict f o r land improvement. Land
improvement is defined as:
. . . the diversion or impoundment o f water t o protect property, faci l i tate the development o f a park or fo r the reclamation, drainage or other improvement o f the land.
The Municipal Ac t (British Columbia 1979d) has a number o f sections relating t o land
drainage undertaken b y municipalities. According t o sect ion 585, all drainage provisions
o f that act are subject t o the applicable provisions o f the Water Act. The Municipal Act is
complex and has a number o f st ipulations relating t o the planning process and funding fo r
drainage projects. These points w i l l be dealt w i th in more detai l i n the fo l lowing section.
The Drainaqe, Ditch and Dyke Ac t (British Columbia 1979e) applies to municipalities
proposing drainage projects involv ing construction in rural areas, or smaller projects
where the work is undertaken b y individuals. Any alterations t o existing drainage
systems must f o l l o w the same procedures applied t o the init ial construction. This act has
a number o f sections dealing w i t h project approvals and funding. These points w i l l be
discussed in more detail later. In addit ion t o these three acts, there are a numerous other
pieces o f legislat ions which deal, albeit indirectly, w i t h land drainage. These include tax
exemption regulations under the Taxation Act (British Columbia 1979f) and property
easement regulations. These regulations are signif icant in land drainage because
frequently, r ight-of-ways are requested for maintenance or f o r leave strips in the case o f
fisheries mit igat ion requirements. The Aqricultural and Rural Development Ac t (British
Columbia 19799) stipulates the condit ions f o r federal-provincial funding arrangements f o r
ARDSA grants.
The Federal Fisheries Ac t (Canada 1970) al lows the federal government t o maintain
jurisdict ion over anadromous and inland fisheries resources. In Brit ish Columbia, the
federal fisheries department plays an important role in determining the way in which a
drainage project w i l l be constructed. I ts role has been perceived as being too powerful
by some interests, including MAF (Metzger 1982), who feel that agricultural priorities
come second in projects involving fisheries.
In summary, statute law in British Columbia covers a wide range of land drainage
aspects, including project initiation, planning, and funding.
3.2 Planninn and Decision-Making
The planning and decision-making process for agricultural land drainage in British
Columbia is based primarily on the licensing system in the Water Act, and the petition
procedure for initiating municipal drains as described in the Municipal Act. This section
wi l l outline the planning and decision-making process for drainage projects as outlined in
the relevant legislation. The decision-making process is illustrated in figure 2.
3.2.7 The Petition Process: Initiation of a Project
Sections 588(2), (3), and (4) of the Municipal Act gives municipalities the right to:
. . . purchase, construct, improve, extend, alter, remove, repair, maintain and operate works to maintain proper f l ow o f water in a stream. . .
as defined by the Water Act. To do this, council may L
. . . prevent, divert or improve drainage of surface water, but must f irst prepare a plan t o carry out those works, and prepare a report which includes descriptions of all landowners affected, the cost of the work and the division o f the cost. They must also apply to the minister who may authorize works in terms of compensation and costs to the owners o f land affected.
Drainage projects may be initiated by a municipal council, or through a petition by
individual landowners. Either o f these must identify the area to be affected by the
proposed project, and list the landowners. The petit ion is not valid unless i t has been
signed by two thirds of the owners to be affected by the project, representing greater
than one half o f the total assessed value of the land in question. After a landowner has
petitioned for a drainage project, the municipal council must, within 15 days, order a
preliminary report to be prepared by the municipal engineer. The engineer's role is to
determine whether or not the project is required, whether benefits w i l l exceed estimated
costs, and what lands w i l l be affected. Items in the cost estimates include engineering
Figure 2
THE LAND DRAINAGE DECISION MAKING PROCESS
by landowner or municipality
-- I WATER LICENSE APPROVAL ]
MOE WATER MANAGEMENT BRANCH
REFERRALS TO DFO.
t FUNDING APPROVAL I +
1 ARDSA: MAF and Agriculture
Canada
ECONOMIC ANALYSIS I by independent consultant (
- - I Appeal to comptroller I
Project does not proceed
Project proceeds without subsidy
Project cancelled or proceeds
without subsidy I Project proceeds
with 75% subsidy
expenses, cost o f advertising and mailing, compensation for land taken for the project,
and expenses incurred by the municipality in determining compensation. Council then
decides whether or not to proceed with a more detailed survey including design details,
cost estimates, maintenance costs, all land affected, and assessments of costs to each
landowner.
Ideally, once the petit ion procedure has been initiated, the municipality wi l l
simultaneously submit an application for a water license and, should i t be eligible, funding
for the project under the ARDSA program. In addition, all drainage projects require a
water license under the British Columbia Water Act. The comptroller of water rights has a
great deal o f decision-making power, since he or she has the final word on the approval
or rejection of any license. The comptroller also has the discretionary power to
determine whether or not a public hearing is required (BC Wildl i fe Federation v Nu-West
Development Corporation Ltd. (1976) 1 B.C.L.R. 244. 72 D.L.R. 581).
3.2.2 Appeals
The Water Act sets out procedures for the suspension and cancellation o f licenses
as well as for appeals of the comptroller's decision. The Environmental Appeal Board
was set up under the Environmental Manaqement Act (British Columbia 1981b) to deal
with objections to the comptroller's decision. Engineer's decisions can be appealed to the
comptroller. Objections to the initial granting o f a license may be made by riparian
landowners, other licensees, the deputy attorney general, the deputy minister of lands,
parks and housing, or the deputy minister o f agriculture and food. Remedial measures
exist for failure to comply with an order of the comptroller or engineer, or misstatement
or material misrepresentation in the application furnished with respect to i t (British
Columbia 1981b). Appeals are also possible under the Municipal Act. Once municipal
council has determined that a project w i l l go ahead, the only way to reverse the decision
is i f a majority o f landowners, again, majority meaning those landowners representing
greater than one half o f the total assessed value of the land affected, oppose the project
(British Columbia 1979d). Any landowner may, within 30 days of receiving an assessment
of costs apportioned to his or her land, appeal the decision to the county court on the
grounds that potential benefits are less than the assessed costs to the property, or i f he
or she fee ls that certain parcels o f land should be included or excluded f r o m the analysis.
The Drainaqe. Di tch and Dvke A c t a lso has sect ions re lat ing t o appeals. Sect ion 12
states that there must be agreement between al l landowners af fected as t o the cos t and
maintenance o f the project. I f agreement cannot be reached, landowners requesting the
project can demand that the appointed engineer re-examine the project si te. The engineer
then determines whether or no t everyone was not i f ied, and he or she must a lso decide
whether or n o t any potent ia l l y a f fec ted landowners were neglected. I t is a lso up t o the
engineer t o determine whether land damage i n some instances exceeds the accrued
benef i ts , and the degree o f compensat ion t o be awarded in such cases. I f landowners are
d issat is f ied w i t h the engineer's decision, they can appeal i t w i th in 15 days. The appellant
is permi t ted t o have the s i te inspected b y any other person, such as a b io log is t o r
f isher ies o f f i ce r , t o get a second op in ion o n the engineer's calculat ions and assumptions.
I f any landowner fee ls that the benef i ts a l lo ted t o his o r her land have no t accrued as
ant ic ipated once the pro jec t i s complete, he or she may, af ter t w o years, in i t ia te
proceedings f o r the reconsiderat ion o f agreements o r awards. Accord ing t o the act, a l l
drainage sys tem maintenance is t o b e undertaken b y the benef i t t ing landowners.
3.3 Subsidies and Funding
When a drainage project does not receive federal o r provincia l funding, i t i s pa id f o r
b y landowners benef i t t ing f r o m the project , as determined b y the project engineer. I f an
area is located outs ide a munic ipal i ty , the funds required are suppl ied b y the Min is t ry o f
Finance and co l lec ted as provincia l taxes.
The Aqr icul tura l and Rural Develowment Ac t w a s created t o establ ish the basis f o r
federal-provincial funding arrangements f o r p ro jec ts concerned w i t h the alternate use o f
the land, rural development projects, and so i l and water conservat ion projects. Under th is
act, the Province o f Br i t ish Columbia m a y enter into an agreement w i t h the federal
government t o receive funding fo r such projects. A n identical amount must be suppl ied
b y the province. Sect ion 3 o f the act states that the M in i s t r y o f Agriculture m a y pay
ent i re ly f o r cer ta in pro jec ts i n ant ic ipat ion o f an agreement w i t h the federal government,
where the pro jec t cos ts m o r e than the agreement under the act provides for , or where the
ministry feels that no agreement can be reached under the act, but st i l l desires to fund a
project. The Canada-British Columbia Subsidiary Agreement on Agriculture and Rural
Development outlines the specific goals and objectives of the provincial and federal
governments. The purpose of this agreement is t o enable
. . . Canada and the provinces to jointly participate in initiatives directed towards the attainment of maximum economic and socio-economic benefits from the agricultural and rural resources of the province o f British Columbia, and particularly rural development initiatives to reinforce federal and provincial government policies and programs relating to the development of, or support of , the agricultural sector.
The agreement states that there are at least 2.5-million acres o f marginal farmland
in the provincial land base that can be upgraded through irrigation or drainage to class 1-4
agricultural land. Factors identified as significant in encouraging improved land utilization
included
. . . the quality of land management, the low ratio o f improved land, ownership o f a large percentage of unexploited land by non-farmers such as pensioners, non-residents and small scattered estates, and substantial amounts o f good quality agricultural land which has never been exploited.
Four programs were established to achieve these objectives. Land drainage funding
falls under part three, primary resource development. Under it, federal and provincial
governments each contribute 37.5% of the cost o f the project, with a local contribution o f
25%. Projects under this program would be initiated only in selected areas o f the
province. To aid in implementation, a management committee was established to . coordinate programs, create operational guidelines, and adopt responsibility for project
approvals. In order t o obtain funds, the province must submit a document for each
proposed project detailing the purpose, cost, cash f low, expected benefits, expenses, and
assessments of the economic significance o f each part o f the project, as well as design
and construction standards.
3.4 Governmental Planning
Participation and input f rom different government agencies for a drainage plan is
usually initiated through the informal referral system that exists between ministries to
deal with resource conflicts. Under this system, the Water Management Branch o f the
Ministry of the Environment (MOE), upon receiving an application for a water license,
refers i t t o all other agencies that it considers could be potential ly af fected b y the
license. This would usually include i ts Fish and Wi ld l i fe Branch, the federal Department o f
Fisheries and Oceans, and any other relevant ministry. In the case o f land drainage, the
Ministry o f Agriculture and Food (MAF) handles the init ial project details, including
funding requests. The result is that MOE, MAF, and DFO are the lead agencies in land
drainage discussions.
3.4.1 The Department o f Fisheries and Oceans
In Brit ish Columbia, the federal government has control over both coastal and
anadromous f isheries while the province is responsible f o r resident sports f i sh (Canada
1981). The federal fisheries' management objective is:
. . . t o protect and preserve salmon habitat, the quali ty and product iv i ty o f which is jeopardized b y conf l ic t ing water use, land use and waste disposal practices (Canada 1981).
The DFO habitat management po l icy is currently under review. Although not yet finalized,
the main objective o f this new pol icy has been termed the 'no net loss' objective, whereby
the department w i l l work towards ensuring that net habitat loss is nil. This objective w i l l
be achieved through mit igation, alternative development sites in case of conf l ic t , and
replacement and prohibi t ion o f certain activit ies. The main legislat ion t o enforce DFO
objectives is the Fisheries Act, particularly sections 30(1), 31(1), 33(2), and 33(3). This act
has been amended as the need arose t o ensure that f isheries department objectives are . met. DFO response t o habitat loss, tradit ionally, has been through planning and
enforcement.
. . . many feel that there has been t oo much o f the latter and not enough o f the former (DeBane 1984).
The proposed po l icy would introduce 'habitat management area planning'. Under this
system, a habitat area management plan would be formulated, based on consultation w i th
all water and land users and other interested parties. Other points o f interest in the new
pol icy include the wil l ingness o f the department t o consider habitat replacement f o r any
losses, the recognit ion o f the need fo r public consultation, the legal requirement fo r
proponents t o provide habitat impact studies at their own expense, and the opportunity
for DFO decisions t o be reviewed and reconsidered (Canada 1985~) . The resource
services o f DFO are responsible f o r habitat protect ion and the handling o f interagency
referrals. The fisheries of f icers o f that department are usually the f i rst point o f contact
between DFO and other agencies in any conf l ic t situation (Dorcey et al. 1980). Under the
present referral system, f isheries o f f icers must make quick, site-specif ic, decisions
based on a combination o f available technical and ecological informat ion and value
judgement (Canada 1981; Hartman 1982). A f isheries o f f i ce r in the f ie ld is faced w i th a
variety o f quantitative data requirements such as escapement, migration timing, spawning
and rearing areas, and the overal l signif icance o f a given fisheries resource. Often there
is inadequate ecological informat ion f o r good decision-making.
3.4.2 The Min is t ry o f Environment
MOE recently published a document describing ministry priori t ies and objectives fo r
1985-1990, including a status report on environmental planning in Brit ish Columbia. The
fo l lowing section describes the planning framework and MOE objectives as they relate t o
drainage projects. I t is important t o note that many o f these objectives and procedures
were not in place during the period examined in this report.
The fo l low ing is summarized f r om the MOE status report on environmental planning
and project assessment in August 1985. The goal o f the MOE environmental management
plans is t o speci fy management objectives fo r various resources under the ministry's
mandate, and t o provide a po l icy context w i th in which specif ic project impacts can be
considered and cumulative e f fec ts evaluated. I f proposed projects af fect the
management objectives set out in the ministry plans, mit igat ion is sought through
replacement-in-kind or enhancement in accordance w i t h economic criteria. MOE has four
planning levels. Recent planning process changes have been made in an attempt t o
strengthen the process and provide "a po l i cy context at the f ront end o f project
assessment ". The t op planning level is the ministry or corporate level. This describes the
overal l mandate o f the ministry, outl ining the management philosophy, and di f ferent
program objectives and priori t ies. A t the regional planning level, management objectives
are set fo r specif ic species, based on supply and demand analysis and potential resource
confl icts. Management pr ior i t ies are ident i f ied fo r major program activit ies. I t is hoped
that regional planning w i l l ident i fy management issues that can be further dealt w i t h at
the subregional level. Subregional plans are "integrated statements" which resolve any
internal con f l i c t s between the various branches o f MOE. The goal o f these plans i s t o
"provide a set o f area-specific ob jec t ives" which fu l f i l l the broader object ives ident i f ied
at the upper planning levels. They are comple ted when speci f ic management issues have
been ident i f ied in an area, either through the regional plan, or through the interagency
referra l process in place w i th in the government. MOE has also developed measures t o
ensure that environmental condi t ions such as m i t i ga t i on plans are implemented
e f fec t ive ly . These include a procedures manual t o be f o l l o w e d b y the proponent. The
goal o f th is manual i s t o ident i fy the proponent's intent ions w i t h respect t o project
impacts, m i t i ga to ry measures, as w e l l as out l in ing the regulatory requirements f o r the
project. The l i s t o f commi tmen ts describes the m i t i ga to ry act ions and regulatory
requirements that the proponent agrees t o implement. Contract speci f icat ions prov ide
contractors w i t h an out l ine o f the proponents ' commi tments . The goal o f th is is t o reduce
uncertainty and iden t i f y extra cos ts wh ich may a f fec t p ro jec t bidding. A l l permits and
l icenses required t o comple te the project are a part o f the procedures manual.
The above out l ine o f minister ia l planning indicates that MOE has developed a
f ramework through which resource con f l i c t can be e f fec t i ve l y ident i f ied and dealt w i t h at
an early stage. This a l l ows consul tat ion w i t h interested part ies and resolut ion o f major
issues w i th in a reasonable amount o f t ime, creating a more e f f i c ien t process. O f
part icular relevance t o land drainage, MOE has indicated that more emphasis will be
placed on the management o f cumulat ive impacts and evaluat ion o f mi t iga tory act ions. '
Negot iat ion o f m i t i ga to ry measures w i l l be based o n m in i s t r y surveys ident i fy ing the
recreational values o f f i s h and w i l d l i f e resources. These values w i l l serve as a basis f o r
addressing resource con f l i c t s as well . There i s no fo rma l prov is ion fo r publ ic
consul tat ion i n the MOE planning f ramework (British Columbia 1985).
3.4.3 The M in i s t r y o f Agriculuture and Food
The d is t r ic t agricultural ist o f M A F is usual ly in c lose contact w i t h landowners, is
aware o f government pol ic ies, legislat ions, and programs, and provides advice t o d ist r ic t
residents concerning agricultural issues. M A F also p lays a ro le i n negot iat ing among
landowners, munic ipal i t ies, and government agencies. They are invo lved in mos t land
drainage pro jec ts f r o m the beginning. A s a part o f the ARDSA management commit tee,
which has joint federal-provincial representation, they are responsible for the planning
and implementation o f ARDA programs, project approvals, and related responsibilities.
CHAPTER 4
THE RICHARDS CREEK/SOMENOS CREEK DRAINAGE IMPROVEMENT PLAN
The purpose o f th is chapter is t o out l ine the events o f the Richards Creek-Somenos
Creek Drainage Improvement Plan t o i l lustrate the Br i t ish Columbia approach t o land
drainage planning and decision-making. For the purpose o f analysis, the project is
d iv ided into four planning stages: the preproject , p ro jec t in i t ia t ion and planning,
construct ion, and postproject stages.
4.1 P r e ~ r o iect Stage
The Somenos Creek Drainage Basin i s on southern Vancouver Island, north o f the
c i t y o f Duncan (fig. 1). The drainage basin covers 63.7 km2. The pr inc ip le agricultural
reg ion o f the drainage basin is in the v i c in i t y o f Somenos Lake and the l ower part o f
Richards Creek. Current land use i n the area includes hay, pasture, blueberries, and
potatoes. The land is al l i n the agricultural land reserve. The Somenos Creek-Richards
Creek area has been subject t o f l ood ing o n a regular basis f o r many years. When
questioned, 93% (12; n=22)1 o f the basin landowners c i t ed f l ood ing as the mos t severe
agricultural p rob lem w i t h wh ich they deal. Severe f l o o d s have occurred at least six t imes
in the past 40 years, and l o w l y ing agricultural areas are inundated annually. 6
Planning f o r f l ood ing re l ie f has been ongo ing since 1951, when the Somenos
Drainage Board was established. Board membership consisted o f a l l landowners a f fec ted
b y f lood ing. A $10,000 bond w a s f l oa ted t o prov ide funds fo r the in i t ia l d i tching
contract. Each member contr ibuted a f l a t rate o f $2.75 per acre annually t o service the
debt and p r o v ~ d e maintenance funds. Early work b y the Somenos Drainage Board included
the straightening o f Richards Creek, paid f o r part ia l ly w i t h government funds, and clearing
o f Somenos Creek f r o m Somenos Lake t o the Cowichan River. This in i t ia l wo rk increased
the usable cropland f r o m 60 t o 600 acres. Yearly maintenance kept the area re la t ive ly
f lood- f ree f o r a f e w years. Gradually, maintenance on individual propert ies diminished,
and the creek became overgrown. In 1955, a bot t leneck o f gravel deposi ts o n the ------------------ I In the f o l l o w i n g analysis, the f i r s t number represents the number o f pos i t i ve respondents; n is the to ta l sample size
Cowichan River was cleared at the request of a Somenos Creek farmer. During the late
1950's, the Somenos Drainage Board was dissolved because landowners bordering
Somenos Lake were dissatisfied with the benefits they were receiving relative to the
other landowners. These landowners consistently voted against any type o f drainage
investment. For close to 20 years, drainage remained an unresolved issue.
A comprehensive study on regional drainage problems was undertaken in 1967 by
the Water Investigations Branch, now the Ministry o f Environment, but none of the study
recommendations, including integrated drainage of the Richards Creek-Somenos Creek
basin, were implemented. The 1967 recommendations t o alleviate f looding concentrated
on Somenos Creek diking and improvements to the Cowichan River channel. As early as
1971 i t was recognized that i t would be di f f icul t t o obtain agreement by all concerned
parties for drainage construction, and the municipal engineer recommended that
negotiations to overcome the flooding problems should begin as soon as possible.
4.2 Proiect Initiation and Planning
In 1980, after three seasons o f particularly bad flooding, the Municipality o f the District
o f North Cowichan (MDNC), acting on a MOE recommendation, applied for assistance
under the ARDSA program t o develop a drainage plan for Somenos and Richards Creeks.
Thus, project init iation was due in part to increased flooding, and in part to the substantial 6
drainage subsidies available from the federal and provincial governments. Interviews
with affected landowners indicate that there was strong support for a subsidized drainage
plan. Thirty-two percent (7; n=22) expressed support for the project, while 14% (3; n=22)
were opposed and 14% (3; n=22) were indifferent. When asked whether they would have
supported the project i f i t had not been subsidized, only 9% (2; n=22) said no. Thirty-six
percent (8; n=22) were undecided, indicating that the project benefits would have to
exceed the costs charged to them to warrant support. Once the project was initiated,
meetings w i th affected landowners and government agencies commenced immediately.
These meetings were o f an informal nature and nonaffected parties, including public
interest groups, were not invited to participate. In addition to the Ministry of Agriculture
and Food, the Fish and Wildlife and Water Resources Branches of MOE and DFO were
identified as the lead agencies, and it was agreed that they would be consulted and their
approval required prior to final plan authorization.
Major issues emerged at an early planning stage. These included resource conflict
with downstream users and other resource users, particularly fisheries, institutional
problems associated with the resolution o f these confl icts, and the importance o f
obtaining project funding. Without this funding the project could not be completed. In
order t o ful f i l l ARDSA requirements, MDNC agreed to complete an initial feasibility study.
This included engineering feasibility, environmental impacts, and an economic analysis.
Steps were also undertaken to apply for a water license, as required by the Water
Management Branch (see section 3.2.1). The contract for this study was awarded t o
Willis, Cunliffe, and Tait (WCT), an engineering f i rm with experience in land drainage and
confl ict resolution. Terms o f reference for the feasibil i ty study were set and it was
reemphasized that DFO and BCFW would be contacted by the consultants with regard to
their recommendations concerning the planning and construction o f the project.
Once the feasibility study commenced, initial clearing o f Richards Creek was
undertaken by a local farmer, G. Pastula, in October 1980. Using a backhoe on floats, he
deepened the channel by eight feet and deposited the spoil on the west bank o f the creek.
Fisheries gave their approval for this work. Downstream landowners opposed this action,
fearing that drainage might only be completed in the upper reaches o f the basin, resulting
in increased flooding of their land. The reasons for this initial creek clearing are unclear, L
and are significant since the action only served to aggravate downstream landowners and
impede negotiations for project approval. One important point to note is that the farmer
responsible for the clearing was also the prime potential project beneficiary, since he
owned the greatest amount of property and was the largest agricultural producer.
Commenting on this initial clearing, S.B. Peterson (assistant deputy minister of
agriculture) stated:
. . .this [clearing] presents some conflict with the purpose of a feasibility study. Nonetheless, I feel that we must realistically expect the cost-benefit to be posit ive and certain to justify work (Carne 1980).
By this time, project planning had been ongoing for close t o two years, yet there
was no co-ordination or incorporation of the drainage plans into a regional context. In
May 1981, there was a sudden realization that the Cowichan River Estuary Plan could have
a significant influence on the project outcome. If no dredging occurred on the Cowichan,
the anticipated benef i ts o f draining Somenos and Richards Creeks wou ld be substantially
reduced. This e f fec t had t o be taken into account in the feasibi l i ty study. Input b y the
fisheries departments had also been extremely l imited. Other than having been identif ied
as signif icant agencies, they had, unti l then, played a minor role in project planning.
The init ial feasibi l i ty report was completed in March 1982, at which t ime comments
were invited f r om all agencies. The economic analysis was severely cri t icized b y both
Agriculture Canada and ARDSA. Problems associated w i t h the cost-benefit study are
discussed in detail in chapter 5. Despite this, the ARDSA agreement was signed between
MAF and MDNC on 31 March 1982. A $318,750 subsidy was approved out o f the $425,000
project cost. The municipali ty's share o f the cost, in i t ia l ly estimated at $106,250, is t o be
taken f r om a special municipal reserve fund fo r capital projects. This reserve ensures
that projects not benef i t t ing the municipali ty population major i ty are not funded through
general revenues. The total ARDSA allocation for that year was $1.8 mi l l ion f o r the
complet ion o f 10 projects in Brit ish Columbia. The comptrol ler o f water r ights issued a
'Letter o f Al lowancet which outl ined the requirements t o be met b y MDNC prior t o the
issuance o f a water license. These included:
detailed engineering design and plans,
a detailed fisheries habitat mit igat ion plan t o be developed in co-operation
w i th BCFW and DFO and approved b y the regional water manager,
approval o f plans fo r the relocation o f all l icensed water intakes
signed agreements by all af fected landowners, and
an assessment o f project e f fec ts on water fowl habitat and a mit igat ion plan
submitted t o the regional water manager.
4.2.1 Fisheries Conf l ic ts
Identif ication o f DFO and BCFW as important agencies occurred in 1980. However,
specif ic informat ion regarding the f isheries resource was not provided b y the fisheries
agencies at that t ime. Once funding was approved f o r the project, a meeting was set up
w i th all agencies fo r f inal design plans. Fisheries concerns were identif ied fo r the f i rs t
time. These included: the need t o define rearing habitat on the Richards-Somenos
system, and the need to evaluate project impacts on the fisheries resource. A t that time,
DFO had no idea of the roles of the creeks as habitat, and they emphasized that any
impact assessment was the responsibility of the proponent, in this case, MDNC. MAF was
insistent that mitigative measures be practical t o implement, recognize farmers' rights,
recognize financial limitations of the project, and finally, recognize time constraints for
construction and funding.
The first on-site meeting was held with fisheries to establish the groundwork for a
mitigation plan in June 1982. An analysis o f existing habitat was completed concurrently.
Mitigation plans for fisheries and wi ldl i fe were made b y the same engineering f i rm
responsible for project design. During this period, Ducks Unlimited expressed opposition
to the project for the f irst time, indicating a concern for waterfowl habitat in the area.
They requested $40 000 worth of dike construction to ensure habitat protection. A
variety of measures were proposed to protect the fisheries resource. These included: the
establishment of a greenbelt to provide shade, 7.5-m wide on Somenos Creek and 5.0-m
on Richards Creek, a restrictive covenant t o prevent clearing or cutting o f brush without
written consent f rom BCFW, and shade rafts and pond development in the creeks. On
some properties, only a 2-m greenbelt was possible. Fisheries responded to these plans
by stipulating a minimum acceptable greenbelt o f 54-1, indicating that the average width
o f such strips must be at least 15-m. In addition, they did not support dredging of the
mouth of Somenos Creek. By the end of July 1982, the only outstanding issue in the way
o f project approval was the lack of agreement on the right-of-way for maintenance
purposes as well as the width o f the fisheries leave strip. DFO insisted on a 5-m strip
while the engineering f i rm (WCT) maintained that a 2-m strip was adequate. DFO also
wanted the greenbelt fenced, and a 2 m wide no-farming strip on the bank adjacent the
greenbelt. Anything wider than that, they suggested, was enhancement rather than
mitigation. WCT felt that both provincial and federal fisheries were using their power to
enforce demands in excess of mitigation. They also charged that new demands were
introduced after 6 weeks o f negotiations which could easily have been dealt with earlier.
Two important points should be noted about this dispute. The first was that ARDSA
was only in effect until December 1983, after which the project would no longer be
eligible for funding. Thus, i f the project was to go ahead, agreement had to be reached
before the end of the year. The second important factor was that, in order for benefits t o
accrue as soon as possible, creek clearing had to be completed before the winter, or else
farmlands would be flooded in the spring as usual.
4.2.2 Conflict Resolution
In July 1980, MAF contacted its deputy minister to get help in dealing with both DFO
and BCFW (Metzger 1982b). I t also suggested that MDNC could appeal the water license
decision. Ministerial response to the MAF request was that it should contact senior
management off ic ials in DFO who ". . .may better appreciate the di f f icul ty of the
situation" (Peterson 1982). Finally, in October 1982, DFO identified the upper reaches o f
Richards Creek as the critical rearing area in that drainage basin; all previously
agreed-upon mitigative measures were altered in favor o f protection o f Richards Creek
on the Van Euwan property. I t was too late, however, t o complete the project for the 1983
season.
4.3 Construction
A construction schedule was chosen which coincided with the low-f low season when
there would be the least disturbance to the fisheries resource. Construction continued
f rom June through September 1983. There were some problems with construction, the
most critical of these being a collapse of part of the streambank in late June due to a
shear failure zone which extended at least 12 m beyond the streambank. Spoil taken from
the creek-bed was deposited in a 15-m strip along the west bank of the creeks.
4.4 Postpro iect Stage
Following project completion, a maintenance program was prepared t o be administered by
the municipality. Interviews with landowners were undertaken in the summmer o f 1984 to
determine the effect o f the project on productivity. Only two landowners expressed any
interest in making alterations to their cropping patterns or investing in measures to
increase productivity. None had, at that point, experienced any increase in productivity.
Despite this, all landowners supported the project as being good for 'future generations'.
Monitoring o f the fisheries resource was the resposibility of DFO. There were no
plans to monitor agricultural productivity or other changes to determine the project
effects.
4.5 Summary
Flooding in the case study area has been a problem for many years. The Richards
Creek-Somenos Creek Drainage improvement Plan, initiated to a large extent by the
availability o f government subsidies, had numerous problems during the planning stages.
These included weaknesses in the economic analysis, institutional problems preventing
adequate resolution o f resource conflicts, an inadequate data base for impact assessment
and mitigation, and misconceived perceptions by some landowners of the effects o f the
project. These important issues led to considerable controversy and delays in project
completion.
CHAPTER 5
AN ANALYSIS OF THE RICHARDS CREEK-SOMENOS CREEK DRAINAGE IMPROVEMENT PLAN
The purpose o f this chapter is t o analyse the effectiveness o f Brit ish Columbia
legislation, planning, and decision-making for dealing w i th the major land drainage issues:
as reflected in the case study. The four criteria identif ied in chapter 2 (sections 2.7 t o
2.1 I) provide the f ramework f o r analysis.
5.1 Economic Analvsis
This analysis is divided into t w o sections. The f i r s t examines and critiques the
cost-benefit analysis b y the engineers f o r the Richards Creek-Somenos Creek Drainage
Improvement Plan, and the second section provides a cost-benefit reassessment b y the
author fo r the same project.
5.7.7 The Richards Creek-Somenos Creek Cost-Benefit Analysis
To determine whether or not the project was economically feasible, WCT hired an
economist t o complete a cost-benefit analysis. His results, based on predictions o f
increased crop yields and land use changes over the 25-year project period, concluded
that the project was economic. The cost-benefit rat ios for the various schemes proposed
varied f r om 4.8 t o 15.8. The rat io f o r scheme 1, the recommended option, was 8.4.
Crit icism o f this cost-benefit analysis came f r om both Agriculture Canada and the ARDA
. . . I t is recommended (Handbook f o r Agricultural Project Appraisal, J. Hardie) that increments in benefits and costs gained through staged development be distr ibuted over years 1 through 5, at which t ime ful l project benefits w i l l have been attained. Then i t is but a matter o f projecting the f i f t h year levels through t o year 25. 1 f i nd i t d i f f icu l t to have confidence in a statement to the e f fec t that i n the 15th year an additional 10 acres o f vegetables w i l l be developed. I t is t o o d i f f icu l t to be sure o f any event occurring 15 years f r om now t o base benefit or cost projections on this level o f forecasting. The sooner fu l l benefits the better the project in terms o f our analysis and in terms o f the distr ibution o f those benefits t o producers (Andison 1981).
The Primary Resource Branch o f ARDA also cri t icized the init ial cost-benefit
analysis fo r the fo l low ing reasons (Wallin 1982):
no attempt was made t o determine shadow prices fo r the commodit ies
produced,
production volumes were very high,
no attempt was made t o determine the probabi l i ty o f long-term f lood damage
and i ts e f fec t on agriculture,
repl ication o f the results was impossible,
no sensi t iv i ty analysis was undertaken,
the market analysis made unsatisfactory assumptions and was very optimistic,
and
the study methodology appeared questionable.
The ARDA report on the cost-benefit analysis described i t as "an attempt to just i fy the
pro ject " rather than an object ive analysis. Despite this, project funding was provided by
ARDSA without signif icant changes being made t o the analysis.
5.7.2 Analysis o f the Economic Feasibi l i ty Study
The init ial cost-benefit study had a number o f other discrepancies. I t was based on
a simple questionnaire administered t o basin residents. Wi th the results o f this
questionnaire, estimates were made o f the to ta l land use change in the project area. The
study did not incorporate any sensi t iv i ty analysis o f crop prices or proposed benefits.
The only variable was project cost, depending on which alternative was being considered.
The study fai led t o include the administrative cost o f conf l ic t resolution and i t did not
incorporate environmental costs. Cumulative, long-term impacts such as so i l degradation
and erosion and resultant decreases in product iv i ty were no t considered. Extras such as
contingency fees and material trucking fees were no t included. Benefits were extremely
unrealistic, based on a very simple questionnaire that neglected many important issues,
such as product iv i ty losses due t o land removals fo r the r ight-of-way or the fisheries
leavestrip, a value which could decrease potent ia l increased product iv i ty estimates by up
t o 8 percent. Benefits were not disaggregated b y property owner, making benefit
distr ibution analysis impossible. There was no explanation o f the assumptions made in
calculating project benefits. As indicated in the benef i t calculations, i t was assumed that
all landowners were wi l l ing and able t o develop their land t o attain maximum productivity.
The fact that many landowners were elderly or retired, or s imply not interested in
developing the land, was not addressed.
5.1.3 Independent Cost-Benef i t Ana lys is
A s a result o f the perceived inadequacies o f the consultants' cost-benef i t analysis,
this independent study was undertaken. Since th is w o r k was comple ted the year
f o l l o w i n g pro jec t complet ion, it serves t w o purposes. Fi rst , it provides a basis f o r
compar ison w i t h the consul tants ' cost-benef i t resul ts discussed above, and second, it
provides ver i f i ca t ion as t o whether o r no t benef i ts predicted i n the f i r s t years o f the
pro jec t were realized.
5.1.4 Methodo logy
T o obta in data f o r the economic analysis, a questionnaire was dist r ibuted t o
a f fec ted basin residents. The main purpose o f th is questionnaire was t o determine:
future land use plans,
cos ts incurred on the f a r m as a result o f the project ,
ecological cos ts t o the area,
* benef i ts t o the area i n te rms o f increased crop product iv i ty and crop changes,
and
residents ' at t i tude towards the drainage plan.
Methods used t o calculate cos ts and benef i ts are discussed i n the f o l l o w i n g sections.
5.1.5 Project Costs
There are a number o f cos ts associated w i t h the drain. These can be div ided into:
administ rat ive cos ts o f con f l i c t resolut ion; on-farm expenses as a result o f increased
product iv i ty associated w i t h improved drainage; and, consu l t ing and engineering, legal,
construct ion, maintenance, and environmental cos ts such as loss o f wet land habitat and
downstream ef fec ts . Onfarm costs are n o t included in th is sec t ion as they are subtracted
f r o m on fa rm bene f i t s t o es t imate net project benef i ts i n the f o l l o w i n g section.
Admin is t ra t ive cos ts are est imated t o be the t i m e spent by bureaucrats over and
above what w o u l d normal ly be spent at meet ings t o reso lve major issues pr ior t o pro jec t
approval. It w a s assumed that people f r o m the MOE Water Management Branch w o u l d
normal ly have t o at tend meet ings f o r water l icence approvals. Since i t was impossib le t o
determine h o w much t i m e was no rma l l y spent versus the t i m e spent i n conf l i c t resolut ion,
their t i m e was not included in the es t imate o f administ rat ive costs. The same was true
fo r the Min is t ry o f Agriculture and Food s ta f f . Conversely, f isher ies s ta f f w o u l d no t
normal ly be present at such meet ings; their presence over a two-year per iod was
considered t o be a direct project cost. Transcripts o f meet ing minutes were used t o
calculate f isheries personnel attendance, to ta l number o f meet ings, and average meet ing
length. Using an average annual salary o f $35,000 per year, and an average meet ing t i m e
o f t w o hours, a to ta l o f 40 person hours was est imated t o g ive an administ rat ive cos t o f
$840, less than l % o f the to ta l pro ject cost. This was s ign i f i cant ly lower than anticipated.
Consult ing fees f o r the feas ib i l i t y study were substantial. In i t ia l est imates ranged
under $60,000, but f ina l cos ts exceeded $100,000 (John Blanchet 1983). These costs
include f isher ies and w i l d l i f e m i t i ga t i on plans, a prel iminary cost-benef i t analysis,
engineering plans, and detai led c reek- f low data.
Total contruct ion cos ts in 1982 dol lars are shown in table 1. Costs included
channelizat ion o f the t w o creekbeds, and minor cos ts such as cat t le bridge replacements
and fencing t o prevent animals f r o m walk ing in to the creekbeds. Contingencies and
engineering and superv is ion cos ts a lso fo rmed a s igni f icant po r t i on o f to ta l cost. Gravel
remova l at Somenos Creek, es t imated b y the engineer t~ be approximately $14,000, m a y
actual ly cos t as much as $80,000, depending on the gradient required. This gradient w i l l
have some a f fec t o n the f ina l p ro jec t success. I f Somenos Creek can be kept re la t ive ly
f ree o f debris, i t w i l l be easier t o drain the upper reaches o f ' t h e basin. For the purpose o f
th is cost-benef i t analysis, the lower cos t f igure is used.
Maintenance costs were dist r ibuted over the project l i fe . Some maintenance costs
are incurred annually wh i l e others on l y occur every ten years. These calculat ions were
based on the engineers' assumpt ions as t o the speed w i t h which bank erosion and creek
bed aggradation wou ld occur, and the amount o f gravel remova l required i n the lower
Somenos Creek area near the Cowichan River confluence. I t was est imated that Richards
Creek w o u l d need cleaning w i t h i n f i v e years o f project comple t ion , w i t h subsequent
upkeep every f i ve years. Somenos Creek wou ld on ly need cleaning ten years af ter
project complet ion, w i t h upkeep every f i ve years thereafter. The smal l west t r ibutary
f l o w i n g in to Richards Creek w o u l d need cleaning at ten-year intervals, t o begin ten years
Table 1
Estimated Richards Creek-Somenos Creek Drainage Improvement Plan Construction Costs (1982 dollars)
lmprovements to Richards Creek Cleaning o f Richards Creek at
Somenos Lake Culvert at Richards Trail Fencing on Van Eeuwen property Replacement o f t w o catt le bridges lmprovements t o Somenos Creek Cleaning o f Somenos Creek at
Somenos Lake Gravel removal at lower Somenos Creek Contingencies (1 5%) Engineering and supervision
Total
*may be as high as $80 000
source: Brit ish Columbia 1981.
after project completion. Yearly maintenance costs included right-of-way and inchannel
maintenance, and gravel removal on Somenos Creek (British Columbia 1981). Maintenance
costs are i l lustrated in table 2. To calculate maintenance costs, the net present value o f
costs were calculated using 7, 10, 12, and 15% discount rates. These net present values
were then increased b y 20%, since the engineer stated that the estimated maintenance
costs did not include such factors as trucking o f supplies and contingency fees.
Provision o f a statutory r ight-of-way fo r maintenance as we l l as a restr ict ive
covenant as part o f the f isheries mit igat ion plan cost $27,000 in legal fees. It is not
known i f this amount included payments t o farmers f o r the removal o f their land f r om
productivity, but i t is assumed that such payments were not included. Fencing o f the
fisheries leave str ip fo r the entire length o f both creeks, an estimated total cost o f
$124,000, was not included since the fencing was not constructed, although i t may occur
Table 2
Estimated Stream of maintenance costs at varying discount rates
at some point in the future. Only a small amount of fencing was placed on the Van
Eeuwen property, and these costs were included in the project construction costs.
5.1.6 Project Benef i ts
There are a number o f methods whereby agricultural land drainage benef i ts can be
est imated. The f i r s t i s t o use a cartographical analysis o f the benef i t t ing lands, at tempt
t o est imate the to ta l land area that w i l l be af fected, and predict changing land use
patterns on the n e w l y drained land. This method i s ho l is t ic in nature and addresses the
quest ion o f t o ta l benef i ts rather than deal ing w i t h individual propert ies.
A second method t o est imate benef i ts i s through land resale value. In th is study,
th is method cou ld n o t be adopted because fac tors other than product ion appear t o be
more s igni f icant i n land valuation, and data were imposs ib le obtain.
A f ina l method, used in th is study, was t o quest ion each landowner individual ly. A
questionnaire was devised b y land drainage researchers i n other areas (Brady 1982;
Diebol t 1981). A s imi lar questionnaire was administered t o 22 landowners in the study
area (appendix A). The major goal was t o quant i fy increased product iv i ty o f ex ist ing
croplands, potent ia l land use changes as a result o f the project , and any onfarm costs
incurred b y the landowner, including environmental costs, t o realize the benef i ts made
possib le b y the project. W i t h th is method, benef i ts t o each landowner cou ld be isolated
and their d is t r ibu t ion examined.
T o calculate pro jec t benef i ts , est imates o f the a f fec ted land area were tabulated b y L
proper ty (table 3). Table 3 includes three land base est imates: the f i r s t is the engineer's
original calculat ion, the second i s the author's es t imate based on landowner interviews,
and the th i rd is the same land base minus the land area required f o r the f isheries leave
s t r ip and s ta tu tory r ight-of-way necessary f o r inchannel maintenance. Al though th is area
appears insignif icant, i t i s important t o note, since the to ta l potent ia l p roduct iv i ty o f the
area w i l l decrease b y about 8% as a result o f th is change.
The next step in benef i t calculat ions is t o obta in pr ice and quant i ty est imates o f
agricultural produce g rown in the val ley n o w and under the proposed land use changes, as
w e l l as land clearing and maintenance costs , including fer t i l izers and labor. These values
were obtained f r o m the consultants' cost-benef i t analysis, supplemented b y ver i f i ca t ion
w i t h recent MAF i n fo rmat ion . These values are shown in table 4. No analysis was
landowner
Pastula Robison Bishop Vink Young Kloosterman Doty James Krysler Hayes Comer Woodward Paddle Bradshaw Doman Van Eeuwan lngham L ~ P P King MNC Miller and Horne McDowell & Whittaker
Table 3
Benefitting Area by Property (acres)
198 1 estimate
1984 estimate 2
final estimate (including removals)
total benefitting acreage 562 488 457
estimated reduction from 1981 - 13.2% - 18.7%
Sources: 1 WCT feasibility study 2 Vander Sluys, this study
undertaken to determine what effect different agricultural produce prices would have on
the results; i t was assumed that the real price of agricultural goods would remain
relatively constant over time. The market effect o f having an increased supply of certain
agricultural produce was not considered because most land use change in the basin would
on ly increase po ta to production. The island pota to market i s pr ice inelast ic, especial ly
since other areas o f the island, part icular ly the Saanich Peninsula, are los ing po ta to
acreage (British Columbia 1981).
In a t tempt ing t o quant i fy project benef i ts t o each farmer, i t w a s important t o isolate
h o w much o f the land product iv i ty was due t o the pro jec t as opposed t o normal fa rm
production. T o accompl ish this, f l o o d loss est imates f o r each farmer since 1978 were
made. These est imates were re la t ive ly real is t ic since f l ood ing has increased steadi ly
over th is period, and m o s t f l o o d losses cou ld be at t r ibuted t o the fact that there had been
n o channel maintenance o n Richards o r Somenos Creeks in the past f e w years; many
farmers c la imed that i t was n o t w o r t h their wh i le t o fa rm badly-drained land. On
propert ies where the a f fec ted land base had n o t been used at all, benef i ts were est imated
t o be the to ta l increased product iv i ty as a result o f drainage improvements. Assumpt ions
made are out l ined i n appendix B.
A major prob lem in calculat ing land drainage benef i ts is the d i f f i c u l t y o f forecast ing
land use changes. I n many instances, land use changes occur a f te r a signi f icant delay, and
there tends t o be s l o w incremental land use intensi f icat ion. Mos t land drainage
cost-benefi t analyses assume that land use changes w i l l occur immediate ly, thus
increasing the net present benef i t value and rendering pro jec ts more economical ly
desirable. T o overcome th is problem, th is study examines three d i f fe rent land use '
scenarios. The f i r s t , the highest poss ib le benef i t scenario, assumes that all land use
changes w i l l occur w i th in f i v e years o f project comple t ion , and that m o s t farmers w i l l
invest in t i l e drainage t o further enhance potent ia l benef i ts . This scenario is s imi lar t o
the one adopted b y the pro jec t economic consultant i n the in i t ia l cost-benefi t . I t a lso
assumes that m o s t farmers w i l l take advantage o f the pro jec t t o increase their land
product iv i ty . The second, the op t im is t i c scenario, assumes there w i l l n o substantial
on farm investment. I t i s based on the assumtion that m o s t fa rmers w i l l enhance drainage
benef i ts b y t ransfer ing t o the ideal land use w i th in at least ten years, w i t h n o t i l e
drainage. The f ina l scenario, the m o s t probable, assumes that on l y a f e w farmers (36%,8;
n=22) w i l l take advantage o f the project wh i l e the others w i l l continue t o use the land i n
the exist ing fashion. The set o f assumpt ions associated w i t h th is scenario are those
which, in the author's opinion, re f lec t what is m o s t l i ke ly t o occur in the Richards
Table 4
Onfarm Production Costs and Produce Prices ($)
Hayhay pasture
clearing and breaking costs: hay establishment/harvest costs: annual maintenance/harvest costs: pr ice o f poor hay: pr ice of cereal hay: price o f good hay: expected yields:
o ld stands: f i rs t year: second year: l i f e o f stand:
Vegetables
in i t ia l product ionharvest costs: pr ice of potatoes: expected yields:
f i r s t ten years: af ter ten years: w i t h fert i l izer:
Blueberries:
establishment: annual maintenance: harvesting : pr ice o f blueberries: expected yields:
f i r s t crop second crop: th i rd crop:
subsequent crops:
15 tons /acre 17 tons/acre 28 tons/acre
source: Brit ish Columbia 1981.
Creek-Somenos Creek drainage basin, as i t is based on interview results with landowners.
Project benefits and costs and final cost-benefit ratios are shown in table 5.
5.1.7 Results and Discussion
The highest cost-benefit ratio (7.53) is found under the highest possible scenario at
a discount rate of 7% (table 5). This ratio varies under the different scenarios, ranging
from the maximum mentioned above to a low of 1.62 under the most probable scenario at
a discount rate o f 15%. These values are at least three times lower than those obtained in
the 1982 study. However, the results suggest that from a cost-benefit perspective, the
Richards Creek-Somenos Creek Drainage Improvement Plan is justified. Although the
cost-benefit ratio is positive, there are a number of assumptions inherent in its
calculation, particularly relating to land use. As indicated in chapter two, maximum
drainage benefits are a function o f a number o f factors. The willingness of the
landowners to transfer to more capital-intensive crops and make other important land use
changes and investments, such as installation of t i le drainage, is important. In this study,
87% (19; n=22) o f the basin landowners did not have any intention of transferring to more
lucrative crops;This is reflected in the 'most probable' scenario. and none made any land
use change in the first year. Closely related to this is the availability o f legislative and
economic incentives, information accessibility, and education to encourage farmers to . manage their land effectively. The initial land productivity, and the degree of postproject
maintenance, are other important factors which wi l l be examined below.
Legislative and economic incentives to ensure economic efficiency include
incentives for land development and improvements such as subsidies, low interest loans
to farmers t o enable them to install tile drainage once a drainage project is completed, or
to purchase equipment required to transfer to a more capital-intensive crop, and tax
incentives. British Columbia has some legislative land development incentives. Under the
Agricultural Land Development Program, a farmer may obtain up to $25,000 for land
development. The lending rate is approximately half the current prime interest rate
(Charles 1986). Sections 17 and 18 of the Taxation Act (British Columbia 1979f) provide
some incentive to develop and use improved land as well. These sections state that
improved areas not used for farming shall be taxed at I%, while improved lands in use wi l l
Table 5
Cost-Benefit Ratios
Benefits: scenario
discount rate
Costs:
discount rate
highest possible
optimistic most probable
highest possible
optimistic most probable
Cost /Benef i t Ratio
discount rate highest
possible optimistic most
probable
be taxed at 0.5%. Therefore landowners w h o take advantage o f improved land benef i t b y
a 50% tax saving. Other incent ives include the wr i te -o f f o f up t o $5000 f o r f a r m
purchases re lated t o land improvement (British Columbia 1979d) The act states that:
. . . al l improvements other than dwel l ings and f ix tures, machinery, and similar things erected o n fa rm land and used t o operate the farm, up t o and no t exceeding $5000, shall be exempt f r o m taxation.
I n fo rma t ion accessib i l i ty concerning e f f i c ien t and e f f e c t i v e land management and
maintenance programs t o ensure that p ro jec t benef i ts continue t o accrue beyond the f i r s t
year or t w o are a lso important . This includes making landowners aware o f act ions they
should undertake t o maximize benef i ts , o r i n fo rm ing them about incentives avai lable t o
develop their land. M A F has a number o f smal l publ icat ions re lat ing t o fa rm management
and m in i s t r y programs which are avai lable at d is t r ic t o f f i ces . When questioned regarding
such in format ion , no t a single study-area farmer in terv iewed w a s aware o f any act ion he
could undertake t o increase potent ia l benef i ts .
The degree o f t i l e drainage insta l led pr io r t o project comp le t i on i s perhaps the m o s t
s igni f icant fac tor i n pro jec t economic success. On ly 8% (1; n=13) o f the farmers
demonstrated any interest i n t i l e drainage when asked about it, wh i l e the other 92% (12;
n=13) were either uninterested or considered t i les t o be t o o expensive. No one had any
t i l e drains i n place at the t i m e o f the project construct ion, and 71% (9 ; n=13).were
comple te ly unaware o f t i l e drainage benef i ts . L
Ef fec t i ve maintenance programs are a lso important in ensuring that benef i ts accrue
as anticipated. Maintenance in Br i t ish Columbia is the so le respons ib i l i t y o f the
munic ipal i ty o r d is t r ic t undertaking the project . A s such, the on ly assurance that
necessary w o r k w i l l be done is the in tegr i ty o f the reponsib le organization. Whether th is
is su f f i c ien t is dependent o n the degree o f commi tmen t o f the munic ipal i ty and
landowners t o ensure that the work is kept up. I n the case study, a detai led maintenance
plan was prepared. A n in terv iew w i t h the munic ipal engineer (Berikoff 1986) indicates
that funds were al located t o reclean Richards Creek according t o the prepared
maintenance schedule, and year ly maintenance o f the r ight-of-way, inchannel
maintenance, and gravel remova l at the mou th o f Somenos Creek had been undertaken.
Conversely, maintenance plans b y indiv iduals were a lmost nonexistant. On ly 31% (4;
n=13) had undertaken any maintenance since the pro jec t complet ion, and th is was
restr ic ted t o cleaning exist ing side ditches t o improve their effect iveness. Thus, wh i le
construct ion o f the drains i s subsidized, maintenance is not, and there are n o measures
avai lable t o ensure compl iance t o agreed-upon maintenance plans.
5.7.8 Summary
The WCT s tudy had a number o f problems. These included over ly op t im is t i c benef i t
calculat ions, and a questionable study methodology. This study indicates that three years
f o l l o w i n g project construct ion, i t is economica l ly jus t i f ied i f a l l cos ts are considered.
There are, however, a number of fac tors wh ich should be taken in to account in any
drainage evaluation. These have a st rong inf luence o n cost-benef i t ou tcomes since they
a f fec t the benef i ts s igni f icant ly .
5.2 Administrative and Legislative Sirn~l ic i ty
Legal and inst i tut ional arrangements should be a means whereby a government can
implement i t s po l i cy e f fec t i ve l y . When con f l i c t i ng po l ic ies result i n a var iety o f goals
f o r a speci f ic area, the inst i tut ional arrangements and legis lat ion should enable various
agencies t o reso lve their d i f fe rences e f fec t i ve l y .
A br ief in t roduct ion t o the complex legis lat ion and inst i tut ional bod ies dealing w i t h
land drainage in Br i t ish Columbia was presented in chapter 3. There are at least three
important acts deal ing d i rec t ly w i t h drainage, as w e l l as other legis lat ion wh ich a f fec ts
drainage indi rect ly . Legis lat ion varies depending on whether a project i s in i t ia ted through
a pet i t ion, undertaken o n an individual property, or located in a munic ipal i ty or a d ist r ic t .
For any drainage project , a water l icense i s required. The requirements and condi t ions t o
obtain th is l icense are somewhat nebulous and depend on the demands establ ished b y
various agencies deal ing w i t h land and water resources i n the area. These problems are
discussed at length in f o l l o w i n g sections, but i t should be noted that obtain ing permission
t o undertake a drainage scheme i s a long and arduous process. A l l landowners
interv iewed indicate that the permit sys tem was far t o o complex and made i t very
d i f f i cu l t t o accompl ish anything. Appeals procedures are out l ined i n at least three acts,
depending on who is appealing and the basis for appeal. Indeed, individual landowners
have a great deal o f di f f icul ty in understanding the complexities of the land drainage legal
system.
Although laws, licensing, and appeals are lengthy and complex, channelling of
concerned parties to appropriate information sources can be effective in avoiding delays.
The farmland drainage procedures outlined in a MAF leaflet, 'Farmland Drainage', does this
effectively. This information leaflet summarizes the relevant legislation and briefly
outlines its requirements as well as providing contacts within concerned government
agencies. Interview results with landowners suggest that the role o f MAF in channelling
and dealing with drainage requests is effective. Landowners (5,38%; n=13) who had had
experience in dealing with administrative and legal problems concerning land drainage felt
that MAF was easy to deal with and quite responsive, since they were primarily concerned
with "getting the project done."
The multipl icity o f administrative agencies responsible for drainage results in some
problems such as a lack o f coordination among drainage agencies. Since there is no
agency responsible for comprehensive drainage planning, an integrated, holistic view of
land drainage and associated problems is lacking. Landowners (8,36%; n=22) also
indicated that fisheries agencies made unreasonable demands on them and failed to
adequately consider their views. . 5.2.7 Summary
British Columbia land drainage legislation is confusing. Licensing and approval
procedures are lengthy and complex. However, i f concerned parties are directed to
appropriate agencies effectively, the procedure is simplif ied somewhat.
Varying mandates o f the four agencies responsible for provincial drainage planning
and decision-making, and the lack o f one responsible agency, result in difficulties,
particulary, the absence of coordinated drainage planning. Although the MOE planning
framework described in chapter 3 appears to be an effective means of drainage planning
in conjunction with its other watershed activities, detailed plans are not always
completed. Unless an area is located in an environmentally sensitive or controversial
area, no detailed environmental planning is undertaken. Thus, land drainage and related
conf l ic ts w i l l continue t o be dealt w i th in an ad hoc manner through the referral process.
As such, the present legislat ive and administrative structure is not adequate t o
successfully implement government drainage policy.
5.3 Proiect Effectiveness
The goal o f this cr i ter ion i s t o determine whether or not the objectives o f the
project have been achieved. This includes an analysis at t w o levels: the project level and
the po l icy level.
5.3.1 Project Objectives
The major project objective was t o decrease f lood ing and enable farmers to access
their land early enough each year t o a l low spring planting, thereby increasing productivity.
ARDSA program objectives are (Canada 1977):
To increase the production capabil i ty o f the under-developed land resource, wi th in the framework o f those primary products which show market and production potentials.
To evaluate the success o f the project objectives, landowners were asked a series o f
questions. When requested t o indicate project advantages, only 8% (1; n= 13) said there
had been none. Facil i tat ion o f cul t ivat ion b y 54% (7; n=73) and earlier spring planting b y L
38% (5; n=13) were the most frequent responses. Potential crop increases (4,318; n=13)
and an increase in growing area (323%; n= 13) were the next most common answers. Only
8% (1; n=13) indicated a reduction in the t ime and cost o f working the land, suggesting
that i f the project succeeded as anticipated, the farm would require a greater investment
in both t ime and money. Finally, only one landowner actually experienced an increase in
product iv i ty in the f i rs t year, and since this person had also increased fert i l izer
application it is d i f f icu l t t o determine the real cause of the increase. The other
landowners (12,928; n= 13) did not notice much difference in production levels. On a more
posi t ive note, 54% (7; n=13) indicated that f lood ing was reduced signif icantly. Thus,
although the f i rs t objective, that o f reducing f looding, seems t o have been successful, the
success o f the second, increased productivity, is doubtful. In l984,82% (18; n=22) o f the
basin residents were s t i l l not using the newly-drained land. Since this analysis was done
only one year after the project completion, i t is important t o remember that perhaps the
project objectives w i l l s t i l l be achieved in subsequent years. In order t o determine this,
landowners were questioned concerning their future land use plans. As indicated in
section 5.17, f e w landowners (9,4l%; n=22) had the intention o f undertaking actions t o
enhance the potential success o f the project.
An important factor af fect ing attainment o f project objectives is the existence o f
barriers, either legislative, administrative, or physical, which impede project success.
They also indicated that gravel removal at the mouth o f Somenos Creek was poor ly done.
Lack o f coordination w i t h other regional activit ies was cited as a barrier i n the case study.
Of particular concern was the isolat ion o f the Richards Creek-Somenos Creek Drainage
Improvement Plan f r om other plans in the area, specif ical ly, plans for the Cowichan River.
Residents fe l t that the plans f o r the Cowichan would have a signif icant impact in their
basin and on project benefits, and that this was not adequately addressed in the project.
Other correspondence and minutes sustain this supposit ion (Johanson and Tutty 1982;
Blanchet 1982). This point was also brought up b y DFO. They stated that i f the Cowichan
is aggrading at a rate o f 0.15 f t per year, the proposed Somenos Lake water level
improvements o f 5 in would be el iminated in three years unless dredging occurred. The
project consultants indicated that they had considered this in their init ial feasibi l i ty study
and that improved acreage was calculated on the assumption that no dredging would take
place on the Cowichan. Thus, i f dredging does occur, benef i t t ing area w i l l be higher than '
ini t ia l ly predicted.
5.3.2 Pol icy Objectives
On a broader scale, the success or failure o f the project ref lects, t o a certain extent,
the success or failure o f the ARDSA program t o fu l f i l l government po l icy objectives. The
drainage commit tee responsible fo r f inal decisions concerning drainage funding has
indicated that approval depends largely on whether plans meet the stated objectives o f
the overall drainage program. As stated in the subsidiary agreement (Canada 1977):
. . . a region which exhibits a l o w level o f farm income is subject t o pol icy measures which attempt t o improve the standard o f l iv ing in the region as a whole.
A related po l icy objective states that:
. . . Canada and the province have agreed on a new development opportunity that includes selected agricultural and rural development programs required to increase the economic potential o f rural regions in British columbia.
Chapter 2 also outlined some o f the more theoretical policy goals underlying rural water
projects subsidies. Thus, to evaluate the success of the project in terms of the overriding
policy, one must examine a number of objectives. These include: whether regional
income was increased, whether there was an equitable distribution of that income among
landowners, and, whether the overall regional economic potential was increased. The
first, that o f increasing the income in the region as a whole, has been successful, i f one
considers the cost-benefit analysis results. Total benefits exceeded total costs, and
those benefits wi l l , theoretically, result in increased farm income. However, at the time
this analysis was completed, 70% (9; n= 13) of the farmers had not experienced any change
in income, and did not anticipate any. Thirty percent (4; n= 13) indicated that although they
had not yet experienced any increase in their standard o f living, they did expect one over
the next few years. But the next question, that o f benefit distribution, deserves careful
scrutiny. This study reveals that the project benefit distribution is highly concentrated.
The percentage o f project benefits going to each landowner under the three scenarios is
shown in table 6. Under the most probable scenario, 92% o f the benefits accrue to f ive
properties. Of these five, one is owned and three are rented by the same man. Thus, 92%
o f project benefits accrue t o 23% of landowners, wi th 83% going to one person. Although
benefits are slightly more evenly distributed under the other two scenarios, a large L
proportion st i l l accrue to only a few landowners. Comparison o f the percentage of total
benefits t o each property versus the actual benefitting land owned by each landowner
(table 7 ) indicates l i t t le correlation between the two. Questionnaire results show that 47%
(6; n=13) o f the landowners believed that they benefitted f rom the project, 23% (3; n=13)
did not think they benefitted at all, and 31% (4; n= 13) did not know and indicated that they
were relatively indifferent since they were not paying for the project. The study suggests
a situation of highly diffused costs and concentrated benefits, indicating that the policy
goal o f income redistribution may be more effectively achieved through other means,
such as a user-pay system where benefitting propeties provide at least part of the cost
of drainage.
landowner
Pastula Bishop Doty Kloosterman Kloosterman Robison Vink Young James Krysler Hayes Comer Woodward Paddle Bradshaw Doman
during the planning stage consisted only o f the local fisheries o f f icer (table 8).
Subsequent attendance included regional and provincial representatives.
Date
Table 8
Interest Group Attendence at the Richards Creek-Somenos Creek Drainage Improvement Plan Meetings
MAF
2
2
2
2
0
2
0
0
0
ARDA
0
0
0
1
0
0
0
0
0
DNC
4
0
2
2
2
3
4
3
0
MOE
2
0
1
3
3
4
0
2
1
DFO
2
0
1
1
1
3
0
0
3
WCT
0
2
2
2
2
2
1
1
1
TOTAL
1 Cowichan Indian Band
Involvement by middle and upper management staff f rom DFO only resulted when it
became evident that the confl ict would not be resolved at the f ield level. MAF staff had
requested help f rom their minister in dealing with the fisheries problem, and their minister
had responded that senior fisheries managers were better able to understand the
sensitivity o f these matters. The fisheries confl ict was finally resolved when i t was
established that the critical fisheries habitat was on the Van Eeuwan property and could
be adequately portected.
Once mitigatory measures were agreed upon, they were easy to implement since
they involved only minor construction on the Van Euwan property, in addition to the
dedicated greenbelt and restrictive covenant. Monitoring to ensure compliance and
effectiveness is an important aspect o f mitigation which is frequently ignored. In the
case study, the absence of initial population data made it diff icult to evaluate mitigation
success or failure with any degree of certainty. No monitoring plans were discussed.
5.4.8 Summary
Conflict resolution mechanisms did not function eff iciently during the evaluation
and approval o f the Somenos-Richards Creeks drainage project. The planning and
decision-making process did not adequately consider cumulative, long-term, and indirect
environmental impacts.
Public involvement in drainage was minimal. Although this did not cause serious
problems in the case study, i t may become significant at some point in the future i f a
contentious issue arises with respect to other drains.
Analysis of the fisheries conflict points to a number of difficulties with present
institutional arrangements. Lack of clear f ish habitat objectives, insufficient information
availability for informed discussion, lack o f agreement on the concept of mitigation,
vague criteria for the establishment of mitigative measures, and late fisheries agencies
involvement in the planning process all led to significant delays in project approvals and
the creation o f a confrontational environment between fisheries and other planning!
agencies.
CHAPTER 6
SUMMARY, CONCLUSIONS, AND RECOMMENDATIONS
This chapter summarizes the major conclusions o f the study. Recommendations are
made t o increase the economic e f f i c iency and equi ty , decision-making, and conf l i c t
resolut ion in land drainage in Br i t ish Columbia.
6.1 Criterion I : Pro iect Economic Analvsis
Br i t ish Columbia land drainage economic feas ib i l i t y studies are n o t required t o
incorporate some important factors essential r o e f f e c t i v e and e f f i c i en t decision-making
and resource allocation. These include di rect and indirect environmental costs, and
market and sens i t i v i ty analysis o f certain variables. Benef i t assumpt ions tend t o be
over ly opt imis t ic and they f a i l t o ref lect potent ia l future condi t ions. Assumpt ions are no t
out l ined expl ic i t ly and, as a result, repl icat ion o f resul ts i s impossib le.
Al though the Agricultural and Rural Development Subsidiary Agreement outl ines the
requirements fo r the economic feas ib i l i t y studies o f proposals, cr i ter ia f o r acceptance o r
refusal o f these are unclear. I n the case study, project funding was prov ided despite the
fac t that the cost-benef i t was severely cr i t ic ized b y an ARDSA commi t tee and
Agriculture Canada. Indeed, n o e f f o r t was made t o improve the analysis f o l l o w i n g the '
ident i f i ca t ion o f deficiencies.
This independent study indicates that when fac tors miss ing i n the or ig inal economic
evaluation are incorporated, cost-benef i t rat ios are s ign i f i cant ly lowered. The ra t ios
varied f r o m 1.62 t o 7.53, depending o n assumptions made. The m o s t l i ke ly scenario, at a
discount rate o f lo%, a real is t ic est imate o f the present real cos t o f capital over t ime, had
a cost-benef i t ra t io of 2.49. The resul ts a lso s h o w that the m o r e rap id ly the t ransi t ion t o
revenue-maximizing land use, the greater the potent ia l pro ject benefi ts. I f agricultural
land is devoted t o l o w value uses and land use in tens i f i ca t ion is l ow , the potent ia l
benef i ts w i l l be low. Where in i t ia l p roduct iv i ty i s l o w and the land requires substantial
investment b y individual landowners before max imum benef i ts can accrue, benef i ts w i l l
be even lower.
Certain factors affecting the outcome of cost-benefit analyses have been
identified. These include local incentive for development, legislative and economic
i n ~ e n t i ~ e ~ , installation of t i le drainage, and degree of postproject maintenance. Local
propensity by farmers to manage their land effectively is low, and only 5 or 6 basin
residents were full-time farmers. The remaining were either retired or had other jobs.
This has a significant effect on the initiative to develop land, and should be addressed in
project economic analyses and government funding approval. Legislative and economic
incentives to encourage farmers to develop their land appear to be adequate, although 85%
(6; n=8) landowners indicated that they were unaware o f their existence. The interest and
knowledge o f the study area landowners concerning t i le drainage benefits is also low.
Maintenance programs, although present, are administered by the municipality or
individual landowners. Follow-up provisions are lacking to ensure that maintenance is
carried out and that anticipated benefits are experienced.
6.2 Criterion 2: Administrative and Legislative Simplicity
The present land drainage legislative and administrative structure has some
drawbacks in its ability t o effectively implement government policy objectives.
Legislation is complex, and due to the multipl icity o f government agencies responsible
for different aspects o f drainage planning and decision-making, there is l i t t le opportunity
for coordinated action. Under the present system, the major regulating body is the MOE
Water Management Branch. As such, final project approval or rejection depends on the
comptroller's decision. Considering the complexity o f land drainage economic and
environmental issues, this may be an ineffective method of determining whether or not a
project should be permitted to proceed, with too much emphasis placed on a single
agency. Approval processes are lengthy .and may result in substantial agricultural
productivity losses.
6.3 Criterion 3: Proiect and Policv Effectiveness
Interviews with landowners in 1984 indicated that the objective of decreased
flooding was partially successful; seven landowners (37%; n=22) experienced a significant
reduction in flooding after two years. However, productivity did not increase
substantially fol lowing project completion. Ninety-one percent of respondents (20;
n=22) did not experience increased production levels and 82% (18; n=22) of the farmers
were not using the newly-drained land. Indeed, only 41% (9; n=22) of landowners
intended to take advantage o f the improved agricultural conditions sometime in the
future. Three years fol lowing project completion, only one landowner had done so.
Policy objectives for the ARDSA program include increasing the standard o f living
in certain regions through economic development, and increasing the economic potential
of rural regions. Implicit policy goals include income redistribution. This study suggests
that overall project benefits exceed costs, achieving the goal of pareto-optimality or
economic efficiency. Society has been made better o f f as a whole by the project and no
one is worse of f . However, t o evaluate the real success o f the subsidy of over $425 000,
i t is important t o consider the number o f people directly benefitting f rom the expenditure.
This study points to an extremely high concentration of benefits. Under the most
probable scenario, 92% of the benefits w i l l accrue to only f ive properties. Of these five,
one is owned and three are rented by the same person. In effect, one landowner captured
834 of project benefits. Interview results also indicate that two years after project
completion, 9 landowners (70%; n=13) had not experienced any increase in income.
Research also points t o the fact that extensive land drainage subsidization and
establishment of agriculture on wetlands may contradict other federa! policies,
particularly the federal land use policy. There is no provision for cumulative drainage
impact assessment and no legislated impact assessment procedure for small-scale
projects other than the provincial government referrals process. Drainage programs
apparently proceed in relative isolation of other governmental policies.
6.4 Criterion 4: Resolving Resource Conflict
Although the environmental impacts appear to have been relatively small-scale and
localized, lack o f research and data at the t ime of project implementation make i t diff icult
to discuss these impacts with any degree of accuracy. The only significant environmental
concern was the potential detrimental effect on fish. Environmental impacts could have
been more adequately dealt with in the case study. Potential cumulative impacts were
totally disregarded. There was no attempt to evaluate impacts in a systematic fashion
through pre and postproject data collection, although there was adequate lead time
available prior t o project construction, had this been desired.
Because most land drainage projects are relatively small-scale, there is l i t t le
demand for public involvement. In the case study, the only people to be consulted during
project planning were the landowners. A t present, i t is not necessary to involve the
public extensively in land drainage since most projects are local and small-scale. But
public interest groups should be permitted to participate in the process. Under the
present system, this is not possible.
At the time o f project planning, DFO and the provincial fisheries ministry did not
have specific habitat objectives in the study area, and had no idea o f the importance of
the creeks for either habitat or spawning grounds. There are insufficient data available to . determine project impacts, making i t diff icult for informed discussion to take place.
Fisheries mitigation plans concentrated on controlling stream temperatures and ensuring
adequate shade. A major di f f icul ty in resolving the fisheries conflict was the
disagreement among the various agencies as to the role o f mitigation. The consulting
engineers and MAF off ic ials felt that mitigative requirements identified by DFO amounted
to enhancement rather than mitigation. It was felt that the federal and provincial fisheries
agencies were attempting to enforce demands in excess o f mitigation. Because active
fisheries involvement did not occur until two years after project planning began, their
input was l imited to commenting on and approving proposals, relegating them to a
reactionary rather than an anticipatory or strategic planning role.
6.5 Recommendations
This study suggests that a number of changes could be made to existing legislation
and institutional arrangements to ensure that major land drainage issues are adequately
addressed In the future. The fol lowing recommendations concentrate on incremental
pol icy change, suggesting alterations to the existing legislative and institutional structure
to improve the degree to which governmental goals and objectives are met. The crux o f
this alternative is that the policies do not change but the methods whereby these policies
are implemented are altered so that there is a closer link between policy statements and
actions undertaken. Under existing circumstances this is the most desirable alternative
for a number o f reasons. Successful implementation o f policy change requires sufficient
technical knowledge and a clear understanding o f those groups who w i l l be most affected
by the change. This includes an understanding o f how a decision w i l l affect market
conditions as well as an understanding o f the costs and benefits and a strategy for
compensating those who lose. In the land drainage example, funding policy has resulted
in a situation of concentrated benefits and extremely diffused costs, and any proposed
change to this system is not likely t o be acceptable to the present beneficiaries. As well,
there is l i t t le incentive for change since policy costs are diffused and not felt by any
specific user group.
Cost-benefit feasibil i ty studies should incorporate all environmental costs
associated with a proposed development. Indirect, long-term impacts, where
impossible to quantify, should be identified and their significance established.
This could be done through changes to the Municipal Act.
* An accepted cost-benefit analysis methodology should be adopted. This
would ensure replicability of results as wel l as consistency in project t o
project evaluation. The methodology should be included in ARDSA and
controlled by the ARDSA drainage committee.
Funding criteria should be outlined to ensure that marginal projects are not
approved. These could also be incorporated in ARDSA. Specific cost-benefit
requirements should be identified that must be ful f i l led before funding is
approved.
Benefit calculations should be based on realistic assumptions o f long-term
intended land use changes by affected landowners. This could be
accomplished through the use of a questionnaire similar t o the one on which
this study was based.
Most of the above changes could be incorporated into the subsidiary agreement section
dealing with program implementation procedures. They would ensure that economic
feasibility study requirements are more specific.
To ensure that project benefits accrue as anticipated:
There should be ample encouragement for farmers to transfer from preproject
t o postproject land uses as quickly as possible. More effort is needed t o
inform farmers o f the availabilty of various programs and incentives.
Initial land productivity is important in evaluating possible benefits. This is a
serious consideration and should be reflected in ARDSA funding policy. In the
case study, productivity was so poor t o begin with that the probability o f
increased productivity without substantial investment on the part o f
landowners was minimal. The ARDSA program should target those areas o f
the province where there is a high probability of project success, based on soil
quality evaluated according to its present and future potential.
Farmers should be informed as to effective land management techniques to
decrease flooding or increase productivity by other than capital-intensive
methods such as land drainage. Seymour (Blanchet 1982b) observed:
Farmers often bring about their own flooding problems by overmanaging the land to the point o f clearing all vegetation to the stream edge and thus allowing aggressive species like wi l low, alder, hardtack, and various sedges, rushes, and grasses to dominate
/ stream margins and reduce the flooding capability of low gradient streams.
Farmers should be encouraged to invest in t i le drainage whenever feasible to
ensure that the potential benefits associated with stream channelization are
realized. Although the significance o f t i le drainage has not yet been
established in British Columbia, other studies indicate that this is probably the
single most important factor in determining project benefits (Topecon Group
Ltd. 1971, 1). Thus, landowners should be made aware o f the significance and
potential benefits to be gained f rom tiling.
Maintenance programs, now controlled by the municipality or district initiating
the project, should be required on a contractual basis to ensure that they are
undertaken. Regular monitoring is essential t o ensure that maintenance is
carried out and that the project does not revert to preproject conditions. This
could also be done by the ARDSA committee, after minor legislative changes.
Stream gravel removal operations and dredging should be governed in the
same manner as maintenance programs, particulary i f they are essential to
realize anticipated project benefits.
Analysis o f drainage benefit distributions, and factors affecting these distributions,
could be valuable in determining in what way policies should be altered to more
effectively achieve their objectives. Some methods to ensure that benefit distributions
are more equitable are summarized as fol lows:
As the situation stands, a project could sti l l be subsidized even i f only one
landowner's benefits exceed project cost. I t is recommended that this be
altered so that a project proceeds only i f i t can be shown that the majority of
landowners w i l l benefit.
Landowners' occupation and age profiles should be considered in project
approval. Information concerning such characteristics could be acquired in the
same questionnaire used to determine project benefits. If a significant L
percentage of landowners are hobby farmers, or retired and no longer working
the land, the social desirability of drainage subsidies should be questioned.
To ensure that projects do not confl ict with other land use policies, cumulative
drainage impacts should be considered in project analysis. This might include
/ an analysis of how much each project contributes to total wetland loss in the
region and how much has previously been destroyed. Additional legislation
within the existing framework requiring the completion of environmental
impact assessments for small drainage projects is one way of dealing with
this question. Another method would be the development of class impact
assessments as was suggested in the Ontario case. The benefits o f a class
environmental assessment procedure are numerous. Avoidance of a number
o f small costly impact assessment reports is made possible. As well, this
proposal is more economically eff icient than individual assessments in terms
of time and financing.
Establishment of quantitative data collection techniques to determine drainage
impacts is essential i f provisions are to be made for environmental impacts in
planning. I f this were done, guidelines could be established which describe
actions to be taken during land drainage planning and construction to minimize
impacts.
Pooling of data on indirect, long-term impacts is needed to aid in
decision-making.
Fisheries agencies, both provincial and federal, should clarify their objectives
with respect t o habitat management. Priorization of habitat areas as to their
importance would be valuable in reducing time spent negotiating with different
resource agencies.
Before any discussion of mitigation occurs, the involved agencies should
identify what they perceive the role of mitigation to be and what they hope to
accomplish in demanding certain measures.
Mitigation criteria should be clarified.
A l l affected agencies should be involved early in the planning process to
facilitate confl ict resolution.
Informed discussion is often di f f icul t when the referral process is used to . identify resource values such as f ish or wi ldl i fe habitat. By the time the other
agencies are aware of a proposed project, it is often too late to adequately
assess potential impacts on their area of interest. This was particularly true in
the case of fisheries where there was l i t t le information on the project area
prior t o the proposal. I f the agencies affected were involved at an earlier
stage in the planning process, some confl icts may be easier to resolve.
6.6 Final Conclusion
As discussed earlier, incremental change appears to be the appropriate tool to deal
with land drainage policy in British Columbia. The most feasible solutions center on
legislative and institutional changes at the regional and provincial levels. Further
. --
evaluation, particularly post-audit cost-benefit assessments of a number o f completed
drainage projects would aid in determining whether or not the highly concentrated
benefits observed in the case study are characteristic o f other drainage schemes in the
Province. Should this prove to be the case, a second policy alternative, that of abolishing
federal-provincial subsidies and reinstating the user-pay system similar t o that which
existed under the Somenos Drainage Board, would be a more acceptable alternative to
ensure equity.
6.7 Postscript
In order to test the predictions o f the independent cost-benefit predictions in this
study, updated productivity values were obtained f rom landowners in October 1986, two
years after the initial estimates were made and three years after project completion. The
results reemphasize the conclusions arrived at in the study. First, although the project
was economically efficient, benefits tended to be extremely concentrated. Updated
values indicate that one landowner controls close t o 30% of the land in the valley. This is
the only land on which agricultural use has intensified in the past three years. Although
there have been no major investments on the land, reduction in f looding has increased the
production of potatoes, the most significant crop in the valley, by 40%, to 12-14 tons
annually. The potato farmer is the only landowner t o have benefitted substantially from C
the project. This question o f benefit distribution was not addressed in the project
evaluation. A l l other landowners are either st i l l not using the land or are no longer using
it. Thus, 88% of the benefits st i l l accrue to one person. Predictions o f the overall project
benefits dropped f rom $1,451,793 to $1,353,852 for a cost-benefit ratio of 2.32 at a 1
discount rate of 10% as opposed to 2.49 in the initial prediction.
APPENDIX A
Questionnaire fo r residents in the Richards Creek/Somenos Creek Area
I am a student f r om Simon Fraser University. I am undertaking a study o f the Richards Creek-Somenos Creek Drainage Improvement Plan, and I have would like t o ask you a f ew questions.
Name o f property owner Lot and concession
How long have you l ived here?
Do you own the farm? rent the farm? have another leasing arrangement? other (specify)
What is the total acreage o f your farm?
Is this your permanent residence? Y e s "0-
I f no, where is your permanent residence?
What is primari ly produced on your land?
What were the main agricultural problems you faced prior t o the construction o f the project?
93% required drainage 7% had no agricultural problems-were not af fected
What have been the major advantages o f the drainage improvement plan on your land? .
8% none 8% crop y ie ld increase 31% potential crop y ie ld increase 23% growing area increased 8% reduced t ime and cost t o work land 38% earlier spring planting 54% faci l i tat ion o f cul t ivat ion
What have been the major disadvantages o f the drainage improvement plan on your land? # 75% none
8% decreased water supply 16% increased downstream f looding
Did you have t i le drains on your property prior t o the construction o f the project? 100% no
Did they operate efficiently? Y e s no-
Did the project improve the efficiency o f your tile drains? Y e s no-
Do you plan to install more ti le drains on your property as a result of the project? Y e s "0-
I f you didn't have any ti le drainage on your property prior to the completion o f the project, wi l l you install some now? If so, why and if not, why not?
8% maybe 92% no, stating that t i le drains were too expensive or not necessary
What wi l l your investment be for this work?
Will you, or did you get financial aid for this work? 8% no, the rest were unaware of possible funding
I f yes, from whom and how much?
16. Were you advised of any action required by you as part of the project? Yes- specify no-
17. Have you performed any maintenance on your property adjacent to the creek since the project was completed?
31% yes, new bridges, dug out side ditches 69% no
L
I f yes, what kind and how much did i t cost?
18. Was any spoil deposited on your property? Y e s no-
19. How do you determine whether the productivity of the land has improved?
20. 'mdicate the approximate number of acres of improved agricultural land as a result of the project
acres poorly drained before project acres improved acres poorly drained after project completion Could you point out the area affected on the map?
Do you think that you benefited f rom the drainage improvement plan? 47% yes 23% no 31 % indifferent
Do you plan, or have you made, any alterations to your cropping pattern since the completion o f the project?
13% yes 87% no
I f so, what k ind o f changes and how much did they cost?
Have you made any other land use changes? 100% no
If so, what kind and h o w much did they cost?
24. Have these changes increased the benef i ts o f the project? Y e s no-
Explain
25. Did crop yields change as a result o f the project? 8% es 20$lno 13% no longer farming 59% couldn t te l l
26. Indicate crops and yields prior t o and fo l lowing the project before ~ r o i e - c t
C ~ O D acreage yield $ va luehear
fo l l ow inq the ~ r o i e c t C ~ O D acreaqe vield $ va luehear
l f y o u have any other specif ic figures, please mention.
I f you have experienced any crop yield changes, could this be attributable to factors other than the drainage project?
of the 8% who believed in a real or potential crop increase, all felt that tnis was a direct result of the project although one landowner indicated that he had increased his use of fertilizer
Have you altered the application o f fertilizers or pesticides? 8% yes 92% no
Can you seed earlier in the spring now? 47% yes 53% no
Have you altered our crop rotation? 10016 no
I f yes, describe the change and why.
Do you have a well on your property? Y e s "0-
What is the depth o f the well? The average water level?
Did the water fal l after the project? Yes- How much? "0-
I f yes, w i l l it cost you anything to improve water availability as a result o f this change?
Yes- How much? "0-
L
Does the creek dry up during the summer? Yes- For how long? no-
Does it f lood in the spring? Yes- Where? no-
Did you have any swamp or marshland on your property that has disappeared as a result of the project?
33% yes - 13% no
53% not sure(meaning they are not certain whether it i s gone permanently
36. Are there any drained areas that you are not using? 80% yes 20% no
I f yes, why?
37. Did you lose acreage as a result o f the project? 73% ves
Explain
38. Were the reasons f o r losing the land justi f ied? 13% yes 13% no 74% unsure
Explain
39. Do you feel that the loss was just i f ied in v iew o f the increased benefits o f having wel l drained land?
18% yes 82% no/unsure/indifferent
40. Have there been any w i ld l i f e changes in the area since complet ion of the project? 100% yes beavers have disappeared
41. Was there any hunting in the area before the project? 54% yes 29% no 14% unsure
Is there any hunting now? 43% yes 43% no 14% unsure
42. Were there any f i sh in the creek before the project?
- 72% yes 14% no 14% unsure
43. Are there any f ish in the creek now? 72% no 14% no 14% unsure
44. Did fishermen use the creek? 29% yes 71%no
45. Did any beaver live along the creek? 100% yes
I f so, are they sti l l there now? 100% no
46. Did they cause flooding problems? 100% yes
47. Are there any man-made barriers which adversely affect drainage or prevent you from draining your land?
100% yes 1) all fel t that government approvals took too long 2 ) one said there was a lack of coordination among farmers, in that unless all agreed to dig deeper side ditches, the neglect of one or two could have a negative impact on the others 3) one felt that the engineering was not properly done and the stream silted up too quckly 4 drainage would never be successful until the Cowichan was dredged 5 1 two suggested that gravel clearing at the mouth of Somenos Creek had not been properly done
Will you have to buy or build any new equipment (buildings, pumps or fences, etc) as a result of the project?
item cost reasons for purchase
Have you had or w i l l you have any other expenses as a result o f the project? .
Y e s "0- I f so. how much?
Do you spend more or less time working on the farm as a result of the project? more no change less
Do you have an off- farm job? 19% yes 81% no, but of these, only 38% were farming full t ime
How much do you feel that your farm income has changed as a result of the drainage project?
7 1 % no change 28% not yet, but potentially
53. Did you sign the approval forms for the project? 100% yes
I f you did support the project, would you have supported i t i f it had not been subsidized?
55% yes 9% no 36% undecided
What benefits did you expect f rom the project? increased crop productivity and reduced flooding were the reasons cited b y all landowners
Did all these benefits occur? 37% yes, speaking only o f the f looding
Do you think that all o f the benefits w i l l pay for the project? 42% yes 58% no
Do you think that your benefits w i l l be equal to, or greater than, the value of what you are paying?
19% greater than 25% less than 56% unsure /undecided
What is your share o f the cost o f the project? 100% said that taxes was the only cost
At the time of the project appr'oval were you 32% supportive 14% opposed 14% indifferent
In retrospect, are you 69% supportive 12% opposed 19% indifferent
A series of statements will be read. Indicate i f you SA strongly agree A agree U undecided D disagree SD strongly disagree
The project was initiated because of local interest in ensuring adequate drainage for agriculture.
14% strongly agree 86% agree
The project was initiated because o f the availability of public funding. 29% strongly agree 57% agree
The project w i l l be beneficial t o the community. 43% strongly agree 57% agree
The project should not have gone through. 8% strongly agree 8% agree 46% undecided 8% disagree 30% strongly disagree
The project occurred only because a few o f the basin residents considered i t desirable.
57% agree 43% disagree
Unless t i le drainage is installed, the area influenced by the project is restricted t o acreage close t o the new drains.
29% agree 7 1 % undecided
The project w i l l pay for itself in terms o f increased agricultural , productivity.
14% agree 43% undecided 29% disagree
Acreage near the project should pay more of the cost o f the project because of i ts favored position.
43% agree 57% undecided
The project would not have taken place i f government funding had not been available.
14% strongly agree 57% agree 29% undecided
j. The project had a negative environmental impact on the local area. 29% agree 7 1 % undecided
k. Everyone wou ld have been better o f f i f the project had not gone through. 29% undecided 71% strongly disagree
I. The project w i l l alleviate spring f looding. 57% strongly agree 43% agree
m. The project w i l l increase downstream f lood ing problems.
17% agree 33% undecided 17% disagree
63. Do you feel that there were any unnecessary delays, setbacks or other problems w i t h the project?
100% yes al l landowners fe l t that the f isheries demands signif icantly delayed the project.
64. Do you feel that there is adequate technical and legal informat ion or advice concerning farmland drainage or other construction assistance available t o farmers?
25% fe l t that there was but they were unsure as they had never required it, 75% did not know.
65. What do you think could be done t o make i t easier fo r farmers t o deal w i th all . levels o f government?
100% said that the permit system was complex and made i t d i f f icul t t o get things done 75% fe l t that DFO made unreasonable demands 12.5% mentioned the inef f ic iency in government and the fact that agencies could never agree on anything
66. Do you think that a guideline o f steps t o f o l l o w when undertaking drainage or construction on your property would be helpful in avoiding delays?
one landowner said this was no really applicable in large drainage projects since construction is undertaken b y outside agencies, not - the landowners
67. Which government agency was easiest t o deal w i th? all landowners fe l t that MAF was easiest t o deal w i th
68. Which government agency was the most diff icult to deal with? 75% said fisheries was the most diff icult t o deal with because their demands were unreasonable
69. Additional comments or opinions would be appreciated. one landowner commented on the low productivity in the valley and the fact that the land requires lots of investment to increase crop quality in addition to drainage
HIGHEST POSSIBLE SCENARIO
landowner
Pastula:
Bishop:
APPENDIX B
ASSUMPTIONS FOR BENEFIT CALCULATIONS
year On-farm costs and production
1-2: potatoes 15 tons/acre 3: 30 acres t i le drained 4: 27 acres t i le drained
4.5 acres blueberries 1-5: production 6000 Ibs/acre
6-25: production 8000 Ibs/acre
15 acres-same as Kloosterman's 15 acres
1-4: nothing 5: landclearing
6-10: poor hay 11-25: cereal hay
APPENDIX C
Landowners in the Richards Creek-Somenos Creek Drainage Basin
Bishop, David E.
Bradshaw, C.E.
Comer, J.
Doman Industries
Doty
Hayes, Donald
Ingham, J.H.
James, E.
King, V.
Kloosterman, S.
Krysler, S.
Lipp, H. and C.
McDowell G.T. and Whittaker, J.R.
Miller and Horne
MDC
Paddle, W.H.
Pastula, G.
Robison, J.
Van Eeuwan, H.W.
Vink, A.
Woodward, E.D.
Young, E. A.
329 Sabina Place, Victoria, B.C.
6803 Norcross Road, Duncan, B.C.
6992 Tom Windsor Road, Duncan, B.C.
2739 James, Duncan B.C.
Mays Road, Duncan, B.C.
7004 Mays Road, Duncan, B.C.
7658 Richards Trail, Duncan, B.C.
7087 Mays Road, Duncan, B.C.
2035 Herd Road, Duncan, B.C.
7071 Mays Road, Duncan B.C.
7156 Tom Windsor Road, Duncan, B.C.
P.O. Box I 7 1, Victoria, B.C.
Box 1243, Squamish, B.C.
Norcross Road, Duncan, B.C.
7030 Trans-Canada Highway, Duncan, B.C. L
Norcross Road, Duncan, B.C.
7303 Richards Road, Duncan, B.C.
7619 Richards Trail, Duncan, B.C.
7219 Richards Trail, Duncan, B.C.
7321 Mays Road, Duncan, B.C.
2442 Herd Road, Duncan, B.C.
Mays Road, Duncan, B.C.
REFERENCES
Andison, A. 1981. Memorandum t o J. Metzger, senior agricultural engineer, f r o m Al len Andison, Agriculture Canada. Victoria, B.C.
Ber ikof f , J.N. 22 September 1986. Personal communication w i t h J.N. Ber ikof f , municipal engineer. Duncan, B.C.
Blanchet, J. 19 July 1982. Minutes o f meet ing held at MOE o f f i ce b y John Blanchet, project engineer, WCT. Nanaimo, B.C.
Blanchet, J. 28 May 19821. Memo t o George Reid, b io logist , BC Fish and Wi ld l i fe, f r o m John Blanchet, project engineer, WCT. Victoria, B.C.
Blanchet, J. 24 August 1 9 8 2 ~ . Letter t o Brian Tutty, b io logy DFO, f rom John Blanchet, project engineer. Victoria, B.C.
Blanchet, J. 20 August1983. Personal communication. Victoria, B.C.
Brady, Richard F. 1982. "An Evaluation o f Agricultural Land Drainage in Ontario in the Drain 36 Example." M A Thesis, Department o f Geography, University o f Waterloo, Waterloo, Ontario. N.p.
Br i t ish Columbia. Min is t ry o f Environment. 1972. Drainaqe Guidelines. Victoria, B.C. N.p.
Br i t ish Columbia. Min is t ry o f Environment. Fisheries and Marine Services. Fisheries Operations Directorate. 1973. Brief t o the Select Standins Commit tee o n Forestrv and Fisheries: B.C. Forest Service quidelines fo r clearcut l o w i n s , streamline, shoreline and water auali tv protection. Victoria, B.C. N.p.
Br i t ish Columbia. Min is t ry o f Environment. Fish and Wi ld l i f e Branch. Habitat Protection Services. 1975. lmoacts o f Stream Channelization on Fish and Wi ld l i fe Habitat, b y R.S. Hooten and D.S. Reid. Victoria, B.C. N.p.
Brit ish Columbia. Min is t ry o f Environment. Fish and Wi ld l i f e Branch. 1977. Minimum Acceptable Stream Flows in B.C.: A review, b y H.R. Neuman and C.P. Newcombe. Fisheries Management Report #70. Victoria, B.C. N.p.
Brit ish Columbia. Min is t ry o f Recreation and Conservation. 1977b. Ef fects o f Forest Harvestinq Practises on Soawnins Habitat o f Stream Salmonids in the Centennial Creek watershed. B.C., b y P.A. Slaney, T.G. Halsey, and A.F. Tautz. Fisheries Management Report #73. Victoria, B.C. N.p.
Brit ish Columbia. Min is t ry o f Environment. Federation o f Agriculture. 1979. Farm and Stream: Water Use, Farm Management and the Protection o f the Aauatic Environment, b y C.D. Gram. Victoria, B.C. N.p.
Brit ish Columbia. Min is t ry o f Environment. 1979b. Fisheries i n Greater Victoria: A Resource Guide f o r Local Lakes and Streams. Victoria, B.C. N.p.
- Brit ish Columbia. Min is t ry o f Environment. Environmental Protection Service. 1980. Ef fec ts o f Sedimentation on Stream Li fe, b y Ot to E. Langer. Victoria, B.C. N.p.
Brit ish Columbia. Revised Statutes. 1979 c. The Water Act . c. 429. Victoria, B.C.
Br i t ish Columbia. Revised Statutes. 1979d. The Municipal Act. c. 290. Victoria, B.C.
Br i t ish Columbia. Revised Statutes. 1979 e. The Drainage. Ditch and Dvke Act. c. 78. Victoria, B.C.
Brit ish Columbia. Revised Statutes. 1979f. The Taxation Act. c. . Victoria, B.C.
British Columbia. Revised Statutes. 19799. The Aqricultural and Rural Deve lo~ment Act, c. 7. Victoria, B.C.
British Columbia. Revised Statutes. 1979h. The ~q r i cu l t u ra l and Rural Develo~ment Act. c. 7. Victoria, B.C.
British Columbia. Ministry of Forests. 1980b. Streamside Manaqement: A Decision-Makinq Process for South Coastal B.C., by Keith Moore. Land Management Handbook #l. Vict0ria.B.C. N.p.
British Columbia. Ministry of Agriculture and Food. 1981. Aqricultural Drainaqe Feasibility Study: Somenos Creek and Richards Creek Area by Willis, Cunliffe, and Tait Ltd. Victoria, B.C. N.p.
British Columbia. Revised Statutes. 1981 b. The Environmental Manaqement Act. c. 14. Victoria, B.C.
British Columbia. Ministry of Environment. Surveys and Resource Mapping Branch. 1984. Vancouver Island Capability for Agriculture. Map #94-G 108. Victoria, B.C. 1:50 000. N.p.
British Columbia. Ministry of Environment. 1985. A Status Report on Environmental Planninq and Proiect Assessment in the British Columbia Ministry o f Environment. Victoria, B.C. N.p.
Canada. Revised Statutes of Canada. 1970 The Federal Fisheries Act. c. F-14. Ottawa, Ontario.
Canada. Regional Economic Expansion. 1977. Canada-British Columbia Subsidiary Agreement on Agriculture and Rural Development. Ottawa, Ontario. N.p.
Canada. Canadian Environmental Advisory Council. 1978. Manaqement of Estuarine Resources in Canada. by Irving K. Fox and J.P. Nowlan. Report #6. Ottawa, Ontario. N.p.
Canada. Department o f Fisheries and Oceans. 1981. A Handbook for Fish Habitat Protection on Forest Lands in B.C., by D.A.A. Toews and M.J. Brownlee. Vancouver, BC. N.p.
L
Canada. 1972. The Aqricultural Economists' Contribution to Policy Formation. Proceedinas of the 1972 workshop of the Canadian Agricultural Economics Society. grandon, Manitoba. N.p. '
Canada. Department of Fisheries and Oceans. 1983. Toward a f ish habitat manaqement pol icy for the Department of Fisheries and Oceans. Discussion paper. Ottawa, Ontario. N.p.
Canada. Department o f Fisheries and Oceans. BC Ministry of Forests. BC Ministry of Environment.1983b. Queen Charlotte Islands Stream Rehabilitation Proqram: A Review o f Potential Techniaues. Fish Forestry lnteraction Program Working Paper
I 88, by D.R. Bustard. Victoria, B.C. N.p.
Canada. Department of Fisheries and Oceans. BC Ministry o f Forests. BC Ministry of Environment. 1983c. A Research Approach to Solvinq Fishfiorestrv Interactions in Relation to Mass Wastinq on the Queen Charlotte Islands. Fish and Forestry lnteraction Program Working Paper #I. Victoria, B.C. N.p.
Canada. Ministry of Environment. Lands Directorate. 1985. "A Farmer's Viewpoint of Land Drainage." Paper presented to the Western Provincial Conference on Rationalization o f Water and Soil Research and Management. Land 6(1).
Canada. Ministry of the Environment. Lands Directorate 1985b. The Eastern Ontario ubsidiarv Aqreement Drainaqe Proaram: l m ~ a c t s on the Land Resource: An
fnitial Evaluation. Working paper #40. Ottawa, Ontario. N.P.
Canada. Ministry o f Environment. Lands Directorate. 1985c. "Fisheries' new policy, round two." 6(3).
Carlton, Robert L. 1979. "Mitigation and the Forestry industry", In: Gustaf A. Swanson, tech. coordinator. 19%. The Mitisation s v m ~ o s i u m : A National Workshop on Mitiqatinq Losses of Fish and Wildlife Habitat. Technical Report RM-65., Fort Colins, CO. N.p.
Carne, I.C. 1980. Letter t o J. Metzger, senior agricultural engineer, f rom I.C. Carne, assistant deputy minister, financial assistance program, MAF. Victoria, BC.
Chessman, David R. 1984. "Memorandum on Riparian Rights" in Water Law in Canada: Report on a Workshop for the lnauirv on Federal Water Policy. N.p., n.p..
Day, J.C., and Kettle, A.G. 1974. "Outlet drainage in Ontario: A methodologival exploration." Journal o f Environmental Manasement 2: 331-349.
Day, J.C., Brady, R.F. and Straite, M.J. 1976. Outlet Drainaqe: An Assessment of Environmental I m ~ a c t s . American Society of Civil Engineers, New York. N.p.
Day, J.C., Brady, R.F., Bridger, K.C., Friesen, B.F., and Peet, S.E. 1977. A Stratesv for
Debane, P. 16 May 1984. Presentation by the federal minister of DFO at the Canadian Water Resources Conference. Vancouver, B.C.
Diebolt, Phyllis A. 1981. "Environmental Impact Assessment of Outlet Drain Construction: A Case Study of the Woodisse Drain, Ontario." MA Thesis, Department of Geography, University o f Waterloo. Waterloo, Ontario. N.p.
Dorcey, H.J., M.W. McPhee and S. Sydneysmith. 1980. Salmon Protection and the BC Coastal Forest Industry: Environmental Requlation as a Barqainins Process. Vancouver, B.C: University o f British Columbia, Westwater Research Centre. .
Found, W.C., A.R. Hill, and E.S. Spence. 1975. Economic and Environmental l m ~ a c t of Land Drainaqe in Ontario . Toronto, Ontario: York University. 173pp.
Gardiner, Elizabeth A. 1973. Public Investment Criteria: Application to a Proiect in the Souris River Basin. Report #8. Winnipeg, Manitoba: University of Manitoba, Agassiz Center for Water Studies.
Harr, Dennis and F.M. McCorison. 1978. "Initial Effects of Clearcut Logging on Size and Timing of Peak Flows in a Small Watershed in Western Oregon. ' Water Resource Research l5( l) .
Hartman, G.F. ed. 1982. Proceedinos of the Carnation Creek Workshop: A 10 vear review. Held at Malaspina College, Nanaimo, B.C. N.p.
Hartman, G.F. and L.B. Holtby. 1982. "An Overview of Some Biophysical Determinants of Fish Production and Fish Population Responses to Logging in Carnation Creek, BC." In: Proceedinqs of the Carnation Creek Workshop: A 10 Year Review, by G.F. Hartman. Held at Malaspina College, Nanaimo, B.C. N.p.
Hill, A.R. 1975. "The Environmental Impacts of Agricultural Land Drainage." Journal of Environmental Manasement 4: 251-274.
Irwin, R.W. and H.R. Whitely. 1983. "Effects of Land Drainage on Stream Flow." Canadian Water Resources Journal 8(2).
Manitoba. 1977. The Manitoba Water Commission. Winnipeg, Man. N.p. Johanson, K. and B. Tutty. 1982. Letter to John Blanchet, project engineer, WCT., from K. Johanson, DFO, and B. Tutty, biologist, habitat management, DFO. July 16. Vancouver, B.C.
Metzger, J.F. 1982. "Farmland Drainage Involving Fishbearing Streams in British Columbia." Paper presented to the Canadian Society of Agricultural Engineering. Vancouver, B.C. N.p.
Metzger, J. 1982b. Letter t o S.B. Peterson, deputy minister, MAF, from John Metzger, senior agricultural engineer, MAF. Victoria, B.C.
Nelson, R.D. and H. Salwasser. nd. The Forest Service Wildl ife and Fish Habitat Relationships Proqram. Transactions of the 47th North American Wildlife and Natural Resources Conference. Wildl i fe Management Institute. Washington, D.C. N.p.
Norton, G.A. and J.A. MacMillan. 1972. A Framework for Economic Planninq of Watershed Drainaqe. Research Report #6. Winnipeg, Manitoba: Agassiz Center for Water Studies.
Ontario. Select Committee on Land Drainage. 1974. Aqricultural Land Drainage in Ontario. Final Report. N.p., n.p.
Pearse, P. 16 May 1984. Presentation by the commissioner of the federal inquiry on water policy at the Canadian Water Resources Conference. Vancouver, B.C. N.p.
Peterson, S.B. 1982. Letter t o J.F. Metzger, senior agricultural engineer, MAF, from S.B. Peterson, deputy minister, MAF. Victoria, B.C.
Regts, A. 1983. Cost to Municipalities o f Maintaininq Fish Habitat. Paper presented to the Department of Fisheries and Oceans annual meeting. Parksville, B.C. N.p.
Stokey, E. and R. Zeckhauser. 1978. A Primer for Policy Analysis. New York: Norton.
Suchman, E.A. 1967. Evaluative Research: Pr inc i~ les and Practice in Public Service and. Social Action Proqrams. New York: Russell Sage Foundation.
Swanson, Gustaf A. technical coordinator. 1979. The Mitiqation Symposium: A National Workshop on Mitigatins Losses o f Fish and Wildlife Habitat. General Technical Report RM-65. Fort Collins. CO. N.p.
Sydnevsmith, S. and associates. 1979. A Preliminary Economic Analysis of the Interaction Between Fish and Forest Sectors in B.C. Vancouver, B.C. N.p.
Thomson, P. 1981. Drainaqe Impact Assessment in Ontario: An Evaluation and Review of the State of the Art. Department of Geography, University of Waterloo. Waterloo, Ontario.
Topecon Group Ltd.. 1971. A Studv of the Agricultural Drainaqe Outlet Assistance Program in Eastern Ontario, by S.E. Brooks for the ARDA Branch of the Ontario Department of Agriculture and Food. Ottawa, Ontario. 150 pp. N.p.
Vreeswijk, Wilma J. 1985. "Integrated Resource Management Plan Implementation: The Tsitika Watershed Example, B.C." MRM Research Report no.25, Masters of Natural Resources Management Program. Simon Fraser University. Vancouver, B.C. N.p.
Wallin, P. 11 March 1982. Memo to members of part 1 1 1 technical subcommittee of ARDSA from Peter Wallin, acting head, primary resource development, ARDA branch. Victoria, B.C.
Washington. Department o f Natural Resources. 1975. Buffer Strips and the Protection of Fisheries Resources: An Economic Analysis, by 1. Gillick and B.D. Scott. Olympia, Washington. N.p.
Whitely, H.R. 1975. Does Drainaqe Add t o Flood Peaks? PP. 126-132, 40-46. In: Proceedings of the Drainage Engineers' Conference. Engineering Technical Publication. Guelph, Ontario: University of Guelph.
Williss, Cunliffe and Tait, Consulting Engineers. 1982. Site Plan and Location Plan D 3 1- 1 12 1A- 1. Richards Creek-Somenos Creek Drainaqe Im~rovements. Vancouver, B.C. N.p.