1 Aggregate and Workforce Planning (Huvudplanering) Production and Inventory Control (MPS) MIO030 The main reference for this material is the book Factory Physics by W. Hopp and M.L Spearman, McGraw-Hill, 2001.
21

Aggregate and Workforce Planning (Huvudplanering) · Aggregate and Workforce Planning (Huvudplanering) Production and Inventory Control (MPS) MIO030. The main reference for this material

May 17, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Aggregate and Workforce Planning (Huvudplanering) · Aggregate and Workforce Planning (Huvudplanering) Production and Inventory Control (MPS) MIO030. The main reference for this material

1

Aggregate and Workforce Planning (Huvudplanering)

Production and Inventory Control (MPS)MIO030

The main reference for this material is the book Factory Physics by W. Hopp and M.L Spearman, McGraw-Hill, 2001.

Page 2: Aggregate and Workforce Planning (Huvudplanering) · Aggregate and Workforce Planning (Huvudplanering) Production and Inventory Control (MPS) MIO030. The main reference for this material

2

What is the Role of Aggregate Planning?

• Role of Aggregate Planning– Long-term planning function– Strategic preparation for tactical actions

• Aggregate Planning Issues– Production Smoothing: inventory build-ahead– Product Mix Planning: best use of resources– Staffing: hiring, firing, training– Procurement: supplier contracts for materials, components– Sub-Contracting: capacity vendoring– Marketing: promotional activities

Page 3: Aggregate and Workforce Planning (Huvudplanering) · Aggregate and Workforce Planning (Huvudplanering) Production and Inventory Control (MPS) MIO030. The main reference for this material

3

Aggregate Planning is Long Term

PersonnelPlan

FORECASTING

CAPACITY/FACILITYPLANNING

WORKFORCE PLANNING

MarketingParameters

Product/ProcessParameters

LaborPolicies

CapacityPlan

AGGREGATEPLANNING

AggregatePlan Strategy

WorkSchedule

WIP/QUOTASETTING

DEMANDMANAGEMENT

SEQUENCING & SCHEDULING

CustomerDemands

MasterProductionSchedule

SHOP FLOORCONTROL

WIPPosition Tactics

REAL-TIMESIMULATION

PRODUCTIONTRACKING

WorkForecast

Control

Page 4: Aggregate and Workforce Planning (Huvudplanering) · Aggregate and Workforce Planning (Huvudplanering) Production and Inventory Control (MPS) MIO030. The main reference for this material

4

Basic Aggregate Planning Situation

• Problem: plan production of single product over planning horizon.

• Motivation for Study:– mechanics and value of Linear Programming (LP) as a tool– intuition of production smoothing

• Inputs:– demand forecast (over planning horizon)– capacity constraints– unit profit– inventory carrying cost rate

Page 5: Aggregate and Workforce Planning (Huvudplanering) · Aggregate and Workforce Planning (Huvudplanering) Production and Inventory Control (MPS) MIO030. The main reference for this material

5

A Simple Aggregate Planning Model (I)

Notation:

. period of end at theinventory . period during soldquantity

. period during producedquantity period. onefor inventory ofunit one hold cost to

cost) holding including(not profit unit . periodin capacity . periodin demand

.,.......,1 periods,timetheofindex an

tItS

tXhr

tctd

ttt

t

t

t

t

t

=======

==

Page 6: Aggregate and Workforce Planning (Huvudplanering) · Aggregate and Workforce Planning (Huvudplanering) Production and Inventory Control (MPS) MIO030. The main reference for this material

6

Formulation

ttISXttSXIIttcXttdS

hIrS

ttt

tttt

tt

tt

tttt

,.....10,,,.....1,,.....1,.....1

subject to

max

1

1

=≥=−+==≤=≤

=∑

demandcapacityinventory balancenon-negativity

sales revenue - holding cost

summed over planning horizon

A Simple Aggregate Planning Model (II)

Page 7: Aggregate and Workforce Planning (Huvudplanering) · Aggregate and Workforce Planning (Huvudplanering) Production and Inventory Control (MPS) MIO030. The main reference for this material

7

Product Mix Planning (I)

• Problem: determine most profitable mix over planning horizon

• Motivation for Study:– linking marketing/promotion to logistics.– Bottleneck identification.

• Inputs:– demand forecast by product (family?); may be ranges– unit hour data– capacity constraints– unit profit by product– holding cost

Page 8: Aggregate and Workforce Planning (Huvudplanering) · Aggregate and Workforce Planning (Huvudplanering) Production and Inventory Control (MPS) MIO030. The main reference for this material

8

Product Mix Planning (II)

maximize profit

subject to:

production ≤ capacity, at all workstationsin all periods

sales ≤ demand, for all productsin all periods

Note: we will need some technical constraintsto ensure that variables represent reality.

Verbal Formulation

Page 9: Aggregate and Workforce Planning (Huvudplanering) · Aggregate and Workforce Planning (Huvudplanering) Production and Inventory Control (MPS) MIO030. The main reference for this material

9

Product Mix Planning (III)

. of endat product ofinventory . periodin soldproduct ofamount

periodin produced product ofamount . period onefor ofunit one hold cost to

product ofunit one fromprofit net

. periodin on workstatiofcapacity

.product ofunit one produce totion on worksta required time periodin product of allowed sales minimum

. periodin product for demand maximum

1 period, ofindex an ,1 on, workstatiofindex an

,.....,1 product, ofindex an

tiItiS

tiXtih

ir

tjc

ijatid

tid

t,......,ttn,.....jj

mii

it

it

it

i

i

jt

ij

it

it

==

===

=

=

==

====

==

Notation

Page 10: Aggregate and Workforce Planning (Huvudplanering) · Aggregate and Workforce Planning (Huvudplanering) Production and Inventory Control (MPS) MIO030. The main reference for this material

10

Product Mix Planning (IV)

tiISX

tiSXII

tjcXa

tidSd

IhSr

ititit

tiittiit

jtmi itij

ititit

itiitimi

tt

, allfor 0,,

, allfor ,

, allfor

, allfor subject to

max

1

1

11

−+=

≤≤

=

==

∑∑

(demand)

(capacity)

(inventory balance)

(non-negativity)

(sales revenue - holding cost)

Mathematical Formulation

Page 11: Aggregate and Workforce Planning (Huvudplanering) · Aggregate and Workforce Planning (Huvudplanering) Production and Inventory Control (MPS) MIO030. The main reference for this material

11

A Product Mix Example (I)

Assumptions:

Data:

• two products, P and Q• constant weekly demand, cost, capacity, etc.• Objective: maximize weekly profit

Product P Q Selling price $90 $100Raw Material Cost $45 $40Max Weekly Sales 100 50Minutes per unit on Workcenter A 15 10Minutes per unit on Workcenter B 15 35Minutes per unit on Workcenter C 15 5Minutes per unit on Workcenter D 25 14

Page 12: Aggregate and Workforce Planning (Huvudplanering) · Aggregate and Workforce Planning (Huvudplanering) Production and Inventory Control (MPS) MIO030. The main reference for this material

12

A Product Mix Example (II)

Formulation:

24001425240051524003515

24001015 :subject to

50006045max

≤+≤+≤+≤+

−+

QP

QP

QP

QP

QP

XXXXXX

XX

XX

Solution:

09.36

79.75 $557.94 Objective Optimal

*

*

=

=

=

Q

P

X

X

Net Weekly Profit : Round solution down (still feasible) to:

36

75*

*

=

=

Q

P

X

X

To get $45 ×75 + $60 ×36 - $5,000 = $535.

A Linear Programming (LP) Approach:

Page 13: Aggregate and Workforce Planning (Huvudplanering) · Aggregate and Workforce Planning (Huvudplanering) Production and Inventory Control (MPS) MIO030. The main reference for this material

13

Extensions to the Basic Product Mix Model (I)

Other Resource Constraints:

Utilization Matching: Let q represent fraction of rated capacity we are willing to run on resource j.

∑=

≤m

ijtitij tjqcXa

1, allfor

Notation:

Constraint for Shared Resource j: ∑=

≤m

ijtitij kXb

1

tiX

tjk

ijb

it

jt

ij

periodin produced product ofamount

periodin available resource of units ofnumber

product ofunit per required resource of units

=

=

=

Page 14: Aggregate and Workforce Planning (Huvudplanering) · Aggregate and Workforce Planning (Huvudplanering) Production and Inventory Control (MPS) MIO030. The main reference for this material

14

Backorders:

Overtime:

• Substitute • Allow to become positive or negative• Penalize differently in objective if desired

−+ −= ititit IIIitI

−+itit II ,

• Define Ojt as hours of OT used on resource j in period t and βj the cost of one overtime hour in workstation j

• Add Ojt to cjt in capacity constraint.

• Penalize Ojt in objective if desired

Extensions to the Basic Product Mix Model (II)

∑=

+≤m

1ijtjtitij tj, all forOcXa

{ }−+== −−∑∑ itiitiiti

m1i

t1t IIhSrmax π

{ }∑∑∑ =−+

== −−− n1j jtjitiitiiti

m1i

t1t OIIhSrmax βπ

Page 15: Aggregate and Workforce Planning (Huvudplanering) · Aggregate and Workforce Planning (Huvudplanering) Production and Inventory Control (MPS) MIO030. The main reference for this material

15

Workforce Planning

• Problem: determine most profitable production and hiring/firing policy over planning horizon.

• Motivation for Study:– hiring/firing vs. overtime vs. Inventory Build tradeoff– iterative nature of optimization modeling.

• Inputs:– demand forecast (assume single product for simplicity)– unit hour data– labor content data– capacity constraints – hiring/ firing costs– overtime costs– holding costs– unit profit

Page 16: Aggregate and Workforce Planning (Huvudplanering) · Aggregate and Workforce Planning (Huvudplanering) Production and Inventory Control (MPS) MIO030. The main reference for this material

16hour-man oneby workforcedecrease cost tohour-man oneby workforceincrease cost to

hour-man/dollarsin overtime ofcost hour-man / dollarsin meregular ti ofcost . period onefor unit one hold cost to

.unit one fromprofit net

. periodin center work ofcapacity unit. one produce torequired hoursman ofnumber

tion on worksta hoursunit periodin allowed sales minimum

. periodin demand maximum

1 period, ofindex an ,1 ion, workstatofindex an

=′==′===

==

=

==

====

eell

thr

tjcb

jatd

td

t,......,ttn,.....jj

jt

j

t

t

A Workforce Planning Model (I)

Notation

Page 17: Aggregate and Workforce Planning (Huvudplanering) · Aggregate and Workforce Planning (Huvudplanering) Production and Inventory Control (MPS) MIO030. The main reference for this material

17

hoursin t periodin overtimeOhours.-man

in t to1 tperiod from cein workfor (fires) decreaseFhours.-man

in t to1t period from cein workfor (hires) increaseHmeregular ti of hours-manin t period workforceW

t of endat inventory It periodin soldamount S

t periodin producedamount X

t

t

t

t

t

t

t

=

−=

−=

=

=

=

=

Notation (cont.)

A Workforce Planning Model (II)

Note, this model only considers a single product. Generalizations to m products are straightforward!

Page 18: Aggregate and Workforce Planning (Huvudplanering) · Aggregate and Workforce Planning (Huvudplanering) Production and Inventory Control (MPS) MIO030. The main reference for this material

18

{ }

tFHWOISXtOWbX

tFHWW

tSXII

tcXatdSd

FeeHOllWIhSr

ttttttt

ttt

tttt

tttt

jttj

ttt

ttttttt

t

allfor 0,,,,,, allfor

allfor

allfor ,

allfor allfor

subject to

max

1

1

1

≥+≤

−+=

−+=

≤≤≤

′−−′−−−

=∑

A Workforce Planning Model (III)

Formulation

Page 19: Aggregate and Workforce Planning (Huvudplanering) · Aggregate and Workforce Planning (Huvudplanering) Production and Inventory Control (MPS) MIO030. The main reference for this material

19

Problem Description• 12 month planning horizon• 168 hours per month• 15 workers currently in system• regular time labor at $35 per hour• overtime labor at $52.50 per hour• $2,500 to hire and train new worker

$2,500/168=$14.88 ≈ $15/hour• $1,500 to lay off worker

$1,500/168=$8.93 ≈ $9/hour• 12 hours labor per unit• demand assumed met (St=dt, so St variables are unnecessary)

A Workforce Planning Example (I)

Page 20: Aggregate and Workforce Planning (Huvudplanering) · Aggregate and Workforce Planning (Huvudplanering) Production and Inventory Control (MPS) MIO030. The main reference for this material

20

• Solution:– LP optimal Solution: layoff 9.5 workers– Add constraint: Ft=0

• results in 48 hours/worker/week of overtime– Add constraint: Ot ≤ 0.2Wt

• Reasonable solution?

A Workforce Planning Example (II)

Page 21: Aggregate and Workforce Planning (Huvudplanering) · Aggregate and Workforce Planning (Huvudplanering) Production and Inventory Control (MPS) MIO030. The main reference for this material

21

Aggregate Planning Conclusions

• No single AP model is right for every situation• Simplicity promotes understanding• Linear programming is a useful AP tool• Robustness matters more than precision• Formulation and Solution are not separate activities.