Top Banner
Translated Document AFRICAN DEVELOPMENT BANK GROUP MULTINATIONAL RUZIZI III REGIONAL HYDROPOWER PLANT APPRAISAL REPORT ONEC DEPARTMENT December 2015 Public Disclosure Authorized Public Disclosure Authorized
40

AFRICAN DEVELOPMENT BANK GROUP · AFRICAN DEVELOPMENT BANK GROUP ... 2.7 Bank's Experience and Lessons Reflected in Project Design ... The Ruzizi III Hydropower Plant …

May 27, 2018

Download

Documents

vutu
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: AFRICAN DEVELOPMENT BANK GROUP · AFRICAN DEVELOPMENT BANK GROUP ... 2.7 Bank's Experience and Lessons Reflected in Project Design ... The Ruzizi III Hydropower Plant …

Translated Document

AFRICAN DEVELOPMENT BANK GROUP

MULTINATIONAL

RUZIZI III REGIONAL HYDROPOWER PLANT

APPRAISAL REPORT

ONEC DEPARTMENT December 2015

Publi

c D

iscl

osu

re A

uth

ori

zed

P

ubli

c D

iscl

osu

re A

uth

ori

zed

Page 2: AFRICAN DEVELOPMENT BANK GROUP · AFRICAN DEVELOPMENT BANK GROUP ... 2.7 Bank's Experience and Lessons Reflected in Project Design ... The Ruzizi III Hydropower Plant …

TABLE OF CONTENTS

Currency Equivalents

Acronyms and Abbreviations

Project Information Sheet,

Executive Summa

Results-Based Logical Framework and Implementation Schedule i to v

1 STRATEGIC THRUST AND RATIONALE ............................................................... 1

1.1 Project Linkages with Countries' Strategies and Objectives ......................................... 1

1.2 Rationale for Bank's Involvement ................................................................................. 1

1.3 Aid Coordination ........................................................................................................... 2

2 PROJECT DESCRIPTION ............................................................................................ 3

2.1 Project Description and Components ............................................................................ 3

2.2 Technical Solutions Retained and Alternatives Explored ............................................. 3

2.3 Project Type ................................................................................................................... 4

2.4 Project Cost and Financing Arrangements .................................................................... 4

2.5 Project Target Areas and Beneficiaries ......................................................................... 7

2.6 Participatory Process...................................................................................................... 8

2.7 Bank's Experience and Lessons Reflected in Project Design ........................................ 8

2.8 Key Performance Indicators .......................................................................................... 8

3 PROJECT FEASIBILITY .............................................................................................. 9

3.1 Economic and Financial Performance ........................................................................... 9

3.2 Environmental and Social Impacts ................................................................................ 9

4 PROJECT IMPLEMENTATION ............................................................................... 12

4.1 Implementation Arrangements .................................................................................... 12

4.2 Project Monitoring ....................................................................................................... 14

4.3 Governance .................................................................................................................. 15

4.4 Sustainability ............................................................................................................... 15

4.5 Risk Management ........................................................................................................ 15

4.6 Knowledge Building .................................................................................................... 16

5 LEGAL FRAMEWORK ............................................................................................... 16

5.1 Legal Instrument .......................................................................................................... 16

5.2 Conditions for Bank's Involvement ............................................................................. 16

5.3 Compliance with Bank Policies ................................................................................... 18

6 RECOMMENDATION ................................................................................................. 18

ANNEX 1: Countries' Comparative Socioeconomic Indicators…………………………….……………..I

ANNEX 2: Tables of AfDB Portfolio in the Countries………………………………….………………...IV

ANNEX 3: Development Partners' Operations in the Electricity Sub-Sector in the Great Lakes

Countries………………………………………………………………………………………IX

ANNEX 4: Map of Project Area………………………………………………………………………..….X

ANNEX 5: On-lending of ADF Resources…………………………………………………………..…….XI

ANNEX 6: Factors of Fragility Addressed by the Project…………………………………………..……..XII

Page 3: AFRICAN DEVELOPMENT BANK GROUP · AFRICAN DEVELOPMENT BANK GROUP ... 2.7 Bank's Experience and Lessons Reflected in Project Design ... The Ruzizi III Hydropower Plant …

TABLES

No. Title Page No. Title Page

2.1 Project Components and Cost 3 2.5 Project Cost by Expenditure Category 6

2.2 Project Alternatives and Reasons for

their Rejection

4 2.6 Expenditure Schedule by Component 6

2.3 Estimated Cost by Component 5 3.1 Key Financial and Economic Indicators 9

2.4 Project Sources of Financing 5 4.1 Main Project Implementation Stages 15

2.4bis Project Sources of Financing by

Component

6 6

Currency Equivalents

October 2015 1 Unit of Account (UA) = USD 1.41

1 Unit of Account = EUR 1.25

1 Unit of Account = BIF 2,222.38

1 Unit of Account = CDF 1,300.59

1 Unit of Account = RWF 1,019.60

Fiscal Year

1 January - 31 December

Weights, Units and Measures T Tonne = 1000 kg kW kilowatt = 1000 Watt

GW Gigawatt = 1 000 000 kW or 1 000

MW kWh kilowatt-hour = 1000 Wh

GWh Gigawatt-hour = 1 000 MWh MVA Megawatt-ampere = 1 000 kVA or 1 000 000

VA

Toe Tonne of oil equivalent MW Megawatt = 1 000 000 W or 1 000 kW

kV kilovolt = 1 000 Volt MWh Megawatt-hour = 1 000 kWh

kVA Kilovolt-ampere = 1 000 VA tCO2 Tonne CO2 = 1000 kg of carbon gas

Page 4: AFRICAN DEVELOPMENT BANK GROUP · AFRICAN DEVELOPMENT BANK GROUP ... 2.7 Bank's Experience and Lessons Reflected in Project Design ... The Ruzizi III Hydropower Plant …

i

Acronyms and Abbreviations

ABAKIR Lake Kivu and Ruzizi River Basin

Authority PC Project Company

ADF African Development Fund PCR Project Completion Report AfDB African Development Bank PCU Project Coordination Unit

AFD French Development Agency PIB Gross Domestic Product

CPIA Country Policy and Institutional

Assessment PIDA Programme for Infrastructure Development in

Africa CSP Country Strategy Paper PIU Project Implementation Unit

DRC Democratic Republic of Congo PPP Public-Private Partnership

ECCAS Economic Community of Central

African States PRSP

II Poverty Reduction Strategy Paper

RE Regional Envelop

ECGLC Economic Community of the Great

Lakes Countries RMC Regional Member Countries

EGL Great Lakes Electricity Utility RIPS Regional Integration Policy and Strategy

(RIPS) EIB European Investment Bank RISP East Africa Regional Integration Strategy

Paper EPC Engineering, Procurement and

Construction

EU European Union RO Regional Operation GPRSP Growth and Poverty Reduction

Strategy Paper SME Small-and-Medium-Sized Enterprises

KfW Kreditanstalt für Wiederaufbau tCO2 Tonne of carbon dioxide

NELSAP

Nile Equatorial Lakes Subsidiary

Action Programme - Project to

Strengthen Power Grid Inter-

connection of Nile Equatorial Lakes

Countries

TFP Technical and Financial Partners TSF Transition Support Facility (formerly Fragile

States Facility-FSF) UA Unit of Account

PBA Performance-Based Allocation WB World Bank

Page 5: AFRICAN DEVELOPMENT BANK GROUP · AFRICAN DEVELOPMENT BANK GROUP ... 2.7 Bank's Experience and Lessons Reflected in Project Design ... The Ruzizi III Hydropower Plant …

ii

PROJECT INFORMATION SHEET

CLIENT INFORMATION

Donees:

Borrowers:

Burundi and Democratic Republic of Congo

Democratic Republic of Congo and Rwanda

Executing Agency Electricité des Grands Lacs (EGL)

FINANCING PLAN

SOURCES Amount (UA million) INSTRUMENT

BURUNDI DRC RWANDA TOTAL

COUNTRY TOTAL 21 60 17.5 98.5

ADF (PBA) 7 7 Grant

7 7 Loan

ADF (RE) 14 30 44 Grant

10 10.5 20.5 Loan

TSF (Pillar I) 15 15 Grant

5 5 Loan

AfDB (private sector) 35.62 Loan

Other Donors (AFD, EIB, WB,

KfW, EU) 238.05

Private Partnership 71.24

TOTAL PROJECT COST 443.40

BURUNDI DRC RWANDA

Type of Financing ADF Grant ADF/TSF

Grant ADF/TAF Loan ADF Loan

Currency UA UA UA UA

Interest Rate Type NA(*) NA NA NA

Interest Rate Spread NA NA NA NA

Service Charge NA NA 0.75% / yr. 0.75% /yr.

Commitment Fee NA NA 0.50% / an 0.50% / yr.

Other Charges NA NA NA NA

Maturity NA NA

10-year grace period

and 30 years of

reimbursement

10-year grace period

and 30 years of

reimbursement

(*)NA: Not applicable

Page 6: AFRICAN DEVELOPMENT BANK GROUP · AFRICAN DEVELOPMENT BANK GROUP ... 2.7 Bank's Experience and Lessons Reflected in Project Design ... The Ruzizi III Hydropower Plant …

iii

FIRR 7.84%

FNPV USD 63.13 million

EIRR 13.35%

ENPV USD 36.13 million

TIMEFRAME AND MAIN MILESTONES

Concept Note Approval 3 September 2015

Project Approval 16 December 2015

Effectiveness 30 April 2016

Closing Date 31 December 2022

Completion 31 December 2023

Last Reimbursement 31 December 2056

Page 7: AFRICAN DEVELOPMENT BANK GROUP · AFRICAN DEVELOPMENT BANK GROUP ... 2.7 Bank's Experience and Lessons Reflected in Project Design ... The Ruzizi III Hydropower Plant …

iv

EXECUTIVE SUMMARY

1. Project overview: The Ruzizi III Hydropower Plant Project which is part of the Programme for

the Development of Infrastructure in Africa (PIDA) concerns Burundi, the Democratic Republic of

Congo (DRC) and Rwanda. It entails the construction of a run-of-river dam (on the Ruzizi River

between DRC and Rwanda downstream from the Ruzizi II hydropower dam), a 147 MW power plant

and a distribution station. Burundi’s current total capacity will double, while Rwanda’s will increase by

half. DRC’s share will contribute to raising supply in the Eastern region currently not connected to the

interconnected network, while also significantly reducing the percentage of energy of thermal origin.

The project will help to meet the needs of the population and of the economy, in general, in accordance

with the national development strategies of the countries concerned, which underscore the importance of

ensuring reliable and affordable electric power supply to achieve sustainable economic transformation.

The specific objectives of this operation are to: (i) contribute to the development of Ruzizi III for

hydropower generation; and (ii) strengthen regional economic integration through the creation of an

electricity market. The plan is to implement a project at a total cost of UA 443.40 million (of which UA

98.5 million financed by the Bank’s public sector window and UA 35.62 million expected from the

private window) over a period of six (6) years, one year of which constitutes the development phase.

This is the first regional project designed as a public-private partnership (PPP) aimed at optimizing the

hydropower potential of the Ruzizi cascade. For its implementation, a private partner, acting in the

capacity of investor/developer, will be recruited and awarded a concession. This partner will be required

to develop the project, be a majority partner in a project company (PC) with the three countries

concerned and secure the necessary financing.

2. Needs assessment: The project feasibility study was assessed based on several previous studies

concerning electricity demand, in particular the PIDA study. The three countries are experiencing

enormous problems in meeting demand for electricity due to the lack of major investments for over a

decade in a context of population growth and multiplication of socio-economic development efforts.

Existing infrastructure allows coverage of less than 35% of demand in the project area, estimated at

about 3800 GWh by 2025. All the studies concur that this estimate is below potential demand.

3. Bank's value added: The Bank is providing assistance to the three countries concerned to

develop the energy sector. It became involved at a very early stage by financing transaction advisory

services. The Bank is helping to structure the project and facilitate dialogue among stakeholders. By

being the first to approve the project, the Bank is playing a key catalytic role in leveraging the required

concessional financing to significantly reduce the cost of energy (from USD 0.19 to USD 0.11/kWh) and

initiate the development phase. The Bank is strengthening the project's credibility and sustainability, and

is participating in the creation of an electricity market. It is also asserting its leadership role in the

African energy sector. Its intervention will help to build resilience and address the situations of fragility

that characterize the Great Lakes Region. Close attention will be given to gender issues by putting a

specialist at countries’ disposal during the project’s final design and throughout the implementation

phase.

4. Knowledge management: Using several Bank windows, this is an innovative project that

supports large-scale clean energy generation initiatives with a transformational impact on the economies

of the beneficiary regional member countries. The experience that will be acquired in managing this type

of multinational project structured as a PPP will contribute to the implementation of the Bank's green

growth strategy. Such experience will create opportunities for replication, particularly for Ruzizi IV.

Therefore, the project is in keeping with the Bank's strategic vision for the development of the African

energy sector through the promotion of universal access to modern energy on a low-carbon, inclusive

growth path.

Page 8: AFRICAN DEVELOPMENT BANK GROUP · AFRICAN DEVELOPMENT BANK GROUP ... 2.7 Bank's Experience and Lessons Reflected in Project Design ... The Ruzizi III Hydropower Plant …

v

RESULTS-BASED LOGICAL FRAMEWORK

Country and Name of Project: Multinational (Burundi, DRC and Rwanda) - Ruzizi III Regional Hydropower Plant

Project Goal : Increase renewable energy generation for the sustainable socio-economic development of ECGLC countries

RESULTS CHAIN

PERFORMANCE INDICATORS MEANS OF

VERIFICATION

RISKS/

MITIGATION MEASURES Indicator

(including CSI)

Baseline Situation

(2015) 2023 Target

IMPACT

Increase in electricity trading between ECGLC

countries through the supply of sustainable energy to

achieve economic growth and poverty reduction

Volume of energy trade

Electricity access rate

36 MW and 125

GWh (Ruzizi II)

Burundi: 7%

Eastern DRC: 18%

Rwanda: 22%

Over 247 MW or 1030 GWh

Burundi: 20%

Eastern DRC: 42%

Rwanda: 90%

Annual electricity company

and PS reports

National statistics;

Bank country

reports/economic data;

UNDP reports

1: Regional electricity trade does not materialize;

Mitigation Measure: Support institutional capacity

building for energy trading in ECGLC countries

2: Collapse of shareholding agreement which

supports the Project Company;

Mitigation Measure: maintain close supervision

during operation and establish a strong dispute

resolution forum.

3. Other Risks: political stemming from the fragility

of the peace process and political instability in

Burundi and in the Ruzizi Plain, institutional

structure, financing (counterparty risk, co-financing

risk), trade, technical, implementation including

fiduciary and coordination risks.

Mitigation Measures

Commitment of the three countries that signed a

communiqué on 8 March 2013; undertaking by

governments to include counterpart funding in their

budgets. A donor coordination mechanism is

established; ongoing energy distribution networks;

establishment of ABAKIR, water resource

management and incorporation of lessons learnt from

Ruzizi II development.

OUTCOMES

Improved reliability of energy supply and cost of the

countries' energy mix

Average cost of electricity (USD/kWh) Burundi: 0.10

DRC: 0.05

Rwanda: ≥0.20

Burundi: 0.12

DRC: 0.05

Rwanda: < 0.15

AfDB supervision mission

reports;

Quarterly Activity Reports;

Project Completion Report;

Trade Ministry Reports;

Ministry of Energy, Economy

and Finance Reports

Demand satisfaction rate Burundi: 1/3,

Rwanda: 85%,

DRC: 1/3 coverage

Demand coverage at peak period of 100%

in the participating countries (for East

DRC)

Creation of new jobs Number of jobs created

NA Creation of 800 to 1,000 direct and

indirect jobs during implementation, 100

of which for women and 450 permanent

jobs in the operational phase

Reduction of greenhouse gas emissions Carbon dioxide emission avoidance -- 151,000 tCO2 per year

OUTPUTS

1. The Ruzizi III plant is constructed

2. The Ruzizi III power distribution system is

constructed

3. Institutional support is provide to ECGLC

countries to increase regional electricity trading

4. Audit reports and quarterly status reports are

prepared

1. Installed capacity

2. Length of high voltage line and number

of sub-stations constructed

3. Training programme implemented

4. Number of women trained

5. Report of study on optimization of

power trading opportunities and

maximization of project benefits

6. Audit reports and quarterly reports

--

--

--

--

--

--

147 MW (in 2023)

8.3 km by 2023 &

01 in 2023

Training programme fully implemented by

2020

45 (15 per country)

01

5 and 20

AfDB Supervision Mission

Reports

Executing Agency Reports

Project Completion Report

KEY

ACTIVITIES BY

COMPONENT

1. Component 1: Support for Ruzizi III Implementation - (i) provide States with their equity participations; (ii) provide States with resources to be on-lent to the Project Company;

2. Component 2: Support for Regional Cooperation and Integration – Contribute to the conduct of different studies; and

3. Component 3: Project Management – (i) institutional support to EGL; (ii) monitor works implementation; (iii) establish a panel of independent experts; (iv) prepare a procedures manual; (v)

audit project accounts; and (vi) monitor ESMP implementation.

Inputs: AfDB Group: UA133.5 million including

public sector (UA 98.5 million) and private sector

(UA 35 million); Utilisation: Component 1: UA

90.50 million; Component 2: UA 4.06 million;

Component 3: UA 3.94 million

Co-financing: EIB (USD 120 million + USD 50

million private sector window); WB (USD 150

million); AFD (USD 15 million + USD 30 million

private sector window); KfW (USD 30 million); EU

(USD 11+35 million); Commercial debt (to be

confirmed following assessments)

Page 9: AFRICAN DEVELOPMENT BANK GROUP · AFRICAN DEVELOPMENT BANK GROUP ... 2.7 Bank's Experience and Lessons Reflected in Project Design ... The Ruzizi III Hydropower Plant …

vi

S O N D J F MA MJ J A S O N D J F MA MJ J A S O N D J F MA MJ J A S O N D J F MA MJ J A S O N D J F MA M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M

Project Preparation Phase

Finalization of negotiations with investor/developer

(I/D)

Preparation and signing of Project Agreements

Finalization of project preparation by financial

partners

EGL capacity building

Establishment of project company (PC)

Mobilization of commercial debt by PC

Training Activities (EGL,Steering Committee and

representatives of States)

Project Development Phase

Establishment of the Steering Committee

Recruitment of advisors

Preparation of general project implementation

schedule

Finalization of geotechnical studies

Updates of ESIA and FRP

Implementation of ESMP, FRP and compensation

of PAPs

Preparation of BDs and launching of bidding for

EPC contract

Bid preparation

Establishment of the Steering Committee

Establishment of Water Management Agency

(ABAKIR)

Construction Phase

Detailed designs for civil works and hydroelectric

structures

Civil works and hydroelectric structures

Detailed designs for equipment

Detailed designs for transmission line and sub-

stationMaufacturing of transmission line and substation

equipment

Manufacturing of electromechanical equipment

Installation of transmission line and substation

equipment

Installation of electromechanical equipment

Commissioning of transmission line and

substation

Filling of dam

Commissioning of dam

Operational phase

Industrial commissioning (for 12 months)

Environmental and social monitoring

IMPLEMENTATION SCHEDULE OF RUZIZI III REGIONAL HYDROPOWER PROJECT

2018

Yr3/M

2019

Yr4/M

2020

Yr5/MYr0/M

20232015 2016

Yr2/M

2021

Yr6/M

2022

Yr7/MYr1/M

2017

Page 10: AFRICAN DEVELOPMENT BANK GROUP · AFRICAN DEVELOPMENT BANK GROUP ... 2.7 Bank's Experience and Lessons Reflected in Project Design ... The Ruzizi III Hydropower Plant …

1

MANAGEMENT’S REPORT AND RECOMMENDATIONS TO THE BOARD OF DIRECTORS

CONCERNING THE PROPOSAL TO PROVIDE FINANCING TO THE DEMOCRATIC

REPUBLIC OF CONGO AND RWANDA FOR THE RUZIZI III REGIONAL HYDROPOWER

PLANT PROJECT

Management hereby submits the following report and recommendation concerning a proposal to award

(i) a UA 21 million grant to Burundi; (ii) a UA 45 million TSF grant (Pillar I) to DRC; and grant (iii) a

UA 15 million TSF loan (Pillar I) to DRC; and (iv) a UA 17.5 million ADF loan to Rwanda, to finance

the Ruzizi III Regional Hydropower Plant Project.

1 STRATEGIC THRUST AND RATIONALE

1.1 Project Linkages with Countries' Strategies and Objectives

1.1.1 Due to the dominance of fossil fuels in electricity generation, the ECGLC countries are

experiencing serious electricity supply problems that impede their economic activities. Moreover,

despite their relative socio-political stability, these countries continue to suffer from the effects of over a

decade of wars, marked by acute socioeconomic problems, vulnerable economies and, consequently,

difficulty in attracting investments. The project is a regional solution entailing the implementation of an

integration project in three countries of Central and Eastern Africa, and involves the construction of a

regional hydropower plant in collaboration with the private sector. It supplements ongoing ECCAS

initiatives. The project is in keeping with Pillar I of the Bank's Regional Integration Strategy Papers

(RISP) for Central and Eastern Africa, which are anchored on regional infrastructure.

1.1.2 At country level, the ongoing national development strategies of the three countries underscore

the need to increase electricity generation. For Burundi, developing the electricity sector is one of PRSP

II's main objectives. Pillar II of the Bank's 2012-2016 Country Strategy Paper prioritizes the

development of national and regional energy projects in order to significantly increase supply of reliable

and affordable electricity, and improve countrywide access to electricity. For DRC, the project is in

keeping with the 2011-2015 GPRSP, the main reference framework for all development operations.

GPRSP is focused on 4 pillars, including Pillar (iii) on improving access to basic social services and

strengthening human capital, and Pillar (iv) on environmental protection and climate change adaptation.

The project's objectives are consistent with Pillars 1 and 2 of the 2013-2017 CSP. In the case of Rwanda,

one of the pillars of the Economic Development and Poverty Reduction Strategy 2013-2018 aims to

support growth and economic transformation by improving the connectivity of Rwanda's economy. This

strategy aims to increase electricity generation and access. The project is in line with Pillar I of CSP

2012-2016 on infrastructure development.

1.1.3 The project, which also aims to set up a public-private partnership for the generation of abundant

supplies of electric power is in keeping with the Bank's energy policy and Ten-Year Strategy targeting

inclusive and green growth through the promotion of non-polluting energy. Furthermore, the project

aligns with the Bank's “Strategy for Addressing Fragility and Building Resilience in Africa, 2014-2019”,

whose Focus Area 2 (Promote Resilient Societies Through Inclusive and Equitable Access to

Employment, Basic Services and Shared Benefits from Natural Resource Endowments) considers

equitable access to electricity as a factor likely to strengthen the legitimacy of governments, establish

trust between States and citizens and consolidate peace dividends in post-crisis contexts.

1.2 Rationale for Bank's Involvement

1.2.1 This projects targets the objectives of the Bank's Ten-Year Strategy (2013-2022) and its Energy

Sector Policy. It takes into account the need to increase the population's access to electricity by

strengthening green energy generation, with a view to sustainable development. It is in keeping with the

operational priorities defined by the Bank in terms of regional integration infrastructure and private

sector development. It also aims to build the capacity of two States in transition (Burundi and DRC) as

Page 11: AFRICAN DEVELOPMENT BANK GROUP · AFRICAN DEVELOPMENT BANK GROUP ... 2.7 Bank's Experience and Lessons Reflected in Project Design ... The Ruzizi III Hydropower Plant …

2

well as Rwanda's resilience by providing basic services through inclusive development as recommended

in the Great Lakes Regional Fragility Assessment Report, which identified the following factors of

fragility (reflected in the project design) (see Annex 6): (i) volatility of the security situation and

political instability; (ii) the different forms of exclusion and social inequalities, including those based on

gender; and (iii) extreme poverty and unemployment, especially youth unemployment. By helping to

improve the region's socio-economic situation, the project could serve as a major instrument of dialogue

in the political and security stabilization process.

1.2.2 With annual generation of about 710 GWh, evenly distributed among the three countries, it will

help to avoid greenhouse gas emissions equivalent to 151,000 tonnes of CO2 per year. The Ruzizi III

project will significantly transform the electricity sectors in the countries concerned. Its implementation

will contribute to: (i) optimal exploitation of the Ruzizi River's energy potential to improve security of

supplies and access to electricity; and (ii) the strengthening of regional economic integration by creating

a market for electricity.

1.2.3 At continental and regional level, the project is in keeping with the PIDA Priority Action Plan

and is among the priorities defined in the Bank's Regional Integration Policy and Strategy (RIPoS, 2014-

2023). RUZIZI III is a developmental project, given the role it will play in the electric power system of

the Great Lakes Region. Because of its geographic location - between DRC and Rwanda - it will

contribute to the activities of three of the five African Power Pools: CAPP (Central Africa); EAPP

(Eastern Africa); and SAPP (Southern Africa). The PIDA study also proposes an optimal date for the

commissioning of Ruzizi III between 2015 and 2017, since this plant is part of the plan for the more

cost-effective, long-term development of the Great Lakes Region.

1.2.4 The three countries concerned have made implementation of Ruzizi III one of their

development priorities. They have contacted different partners, including the Bank, regarding the

optimal development of the Ruzizi River’s hydropower potential. They have initiated an innovative

approach consisting of developing a regional project in the form of a public-private partnership.

1.2.5 The Bank Group provides real value added to the development of the Ruzizi III project in that it

is a continuation of its previous actions and provides support to two fragile States to set up a complex

project. The Bank has sound knowledge of the sector's context and actors since its intervention is based

on its recent experience in the region, including the provision of transaction advisory services with

support from NEPAD/IPPF and the construction of a transmission line to supply Burundi. This value

added is reflected in the Bank's involvement, through its public and private sector windows, in the form

of guidance to the countries concerned but also as facilitator between the different actors participating in

the project, in particular, the future private sector partner and the different donors. The Bank's level of

commitment, particularly reflected in the advanced stage of project appraisal and the volume of

concessional resources mobilized by the leverage effect mechanism of regional operations, now

enhances the project's credibility by strengthening its feasibility, with a significant reduction in the cost

of electricity generation.

1.2.6 The Bank's leadership in the development of Africa's energy sector must be maintained,

especially in the Great Lakes Region, confronted by socio-political upheaval, until the implementation

of the Ruzizi III project.

1.3 Aid Coordination

1.3.1 In the three countries, aid is coordinated through groups established for consultation between

the public sector, civil society and technical and financial partners (TFP). These groups meet regularly to

monitor and evaluate the implementation of the sector's different development activities. In the case of

Ruzizi III, TFP coordination will be mainly carried out by Electricité des Grands Lacs (EGL), an

ECGLC specialized institution with a specific mandate for the project's implementation. Since the

launching of project development activities, several TFPs have made various contributions channelled

Page 12: AFRICAN DEVELOPMENT BANK GROUP · AFRICAN DEVELOPMENT BANK GROUP ... 2.7 Bank's Experience and Lessons Reflected in Project Design ... The Ruzizi III Hydropower Plant …

3

through EGL, which makes every effort to improve operations harmonization. At EGL's initiative,

several meetings have been held, including one at ministerial level in Abidjan in May 2015 on the

sidelines of the ADB Annual Meetings in which the French Development Agency (AFD), the African

Development Bank (AfDB), the European Investment Bank (EIB), the World Bank (WB), Kreditanstalt

für Wiederaufbau (KfW) and the European Union (EU) participated. At the request of the States and

following consultation, the TFPs selected the EIB as leader for the overall coordination of mobilization

for project financing. Since then, frequent consultations have been held between the different donors

concerned at each project preparation stage.

1.3.2 This project was prepared by the different donors with a high degree of synergy. This led to the

retention of the co-financing option that allows each donor to make the best possible contribution to the

project.

2 PROJECT DESCRIPTION

2.1 Project Description and Components

The project's sector goal is to tap the energy potential of the Ruzizi cascade to meet demand from the

population and the economy in general, in accordance with ECGLC national development strategies,

which stress the importance of reliable power supply for sustainable socio-economic transformation. The

specific objectives are to: (i) contribute to the development of the Ruzizi III scheme; and (ii) strengthen

regional economic integration by creating a market for electricity.

Table 2.1 Project Components and Cost (UA)

Component Estimated Cost Component Description

1. Support for Ruzizi III

Implementation 435,403,085

Construction of the Ruzizi III hydropower plant with an installed capacity

of 147 MW in DRC and Rwanda; and implementation of the

Environmental and Social Management Plan

2. Support for Regional

Cooperation and Integration in the

Energy Sector

4,060,581

Development of national energy markets and their access to the regional

energy market; institutional framework for the development of regional

energy projects; and support for the development of regional integration.

3. Project Management Support 3,936,626

EGL capacity building, PIU operating costs, preparation of a procedures

and training manual, training actions, project audit, and panel of

independent experts.

Total Project Cost 443,400,292

2.2 Technical Solutions Retained and Alternatives Explored

2.2.1 The technical solution retained consists in the construction of a run-of-river dam located on the

Ruzizi River between DRC and Rwanda downstream from the Ruzizi II hydropower plant, a 147 MW

power plant and a distribution station. This facility will supplement the existing cascade by tripling

installed capacity on the river. Power will be transmitted to the three countries from the Kamanyola

substation by 220 kV transmission lines. It will then be distributed equitably between Burundi's Water

and Electricity Generation and Distribution Company (REGIDESO), DRC's National Electricity

Company (SNEL) and the Rwanda Energy Group Ltd. (REG) (collectively called the “Buyers”), in

accordance with each buyer's long-term power-purchase agreement. The solution is based on the

findings of the feasibility study which confirms those of various previous studies. Under the aegis of

NELSAP, a comparative study1 was launched in 2005 covering an area encompassing Burundi, Kenya,

Uganda, DRC, Rwanda and Tanzania, to assess the economic merit of different sites. The study report

concludes that Ruzizi III is one of “the best development options” along with Rusumo Falls or Kabu 16.

1 Strategic/Sectoral, Social and Environmental Assessment of Power Development Options in the Nile Equatorial Lakes Region, Stage II, Synopsis of the

Final Report, carried out for NELSAP (November 2005).

Page 13: AFRICAN DEVELOPMENT BANK GROUP · AFRICAN DEVELOPMENT BANK GROUP ... 2.7 Bank's Experience and Lessons Reflected in Project Design ... The Ruzizi III Hydropower Plant …

4

Another study conducted for the 2013-2038 period and covering all countries of the Eastern Africa

Power Pool, and the PIDA (2011-2040 period) study focused on regional integration prospects conclude

that Ruzizi III forms part of the most cost-effective development plan for the energy sector in the Great

Lakes Region.

2.2.2 To confirm the selection of Ruzizi III as the adopted technical solution, Table 2.2 below shows

the alternatives explored and reasons for their rejection.

Table 2.2: Project Alternatives and Reasons for their Rejection

Options Description and Characteristics Reasons for Rejection

Diesel Thermal - Installation of diesel generators

- Relevant solution

- High operating costs

- Negative environmental impacts

Methane Thermal

- Option consisting of installing gas turbines fired by

methane gas from Lake Kivu

- Relevant solution

- Slightly higher costs than Ruzizi III

- Impacts being assessed

- Little feedback on such technology

- Option could be envisaged in the

medium-to-long-term

Solar Photovoltaic

- Option consisting of installing solar panels for

electricity generation

- Non-relevant solution

- High costs

- Unable to supply grid with

guaranteed power

Wind

- Option consisting of installing wind generators for

electricity generation

- Non-relevant solution

- Unable to supply guaranteed power

to meet peak demand

Geothermal

- Option consisting of producing electricity from

geothermal resources

- Non-relevant solution

- Costs slightly higher than Ruzizi III

- Option could be envisaged in the

medium-to-long-term

Small-scale

hydropower

- Option consisting of generating electricity from

several smaller hydropower plants

- Relevant solution

- Costs higher than for Ruzizi III

- High connection costs

- Fewer impacts

- Not sufficient to cover all needs

2.3 Project Type

The project is an investment operation designed as a public-private partnership (PPP) aimed at

optimizing the hydropower potential of the Ruzizi Cascade. For its implementation, a private partner

recruited as an investor/developer has been awarded a twenty-five (25) year concession. This partner

will be required to develop the project, be a majority partner in a project company (PC) with the three

countries concerned, and secure the necessary financing. To cover the risks involved and with a view to

reducing the cost of energy, the countries concerned will provide the PC with concessional financing.

2.4 Project Cost and Financing Arrangements

2.4.1 The total project cost, net of taxes and customs duties, is estimated at UA 443.40 million,

comprising approximately UA 358.86 million in foreign exchange and UA 84.55 million in local

currency. The cost includes a 10% provision for physical contingencies and price escalation. The cost by

component is presented in Table 2.3 below.

Page 14: AFRICAN DEVELOPMENT BANK GROUP · AFRICAN DEVELOPMENT BANK GROUP ... 2.7 Bank's Experience and Lessons Reflected in Project Design ... The Ruzizi III Hydropower Plant …

5

Table 2.3 Estimated Cost by Component (in UA million)

COMPONENTS Foreign

Exchange

Local

Currency Total Cost F.E. %

1. Support for Ruzizi III Implementation

Construction cost 291.83 66.65 358.47 81%

Development cost 13.75 0.00 13.75 100%

Environmental and social cost 5.54 5.54 11.08 50%

Reserve account 2.65 0.66 3.31 80%

Revolving fund requirements 6.66 1.66 8.32 80%

Component 1 Total 320.41 74.51 394.92 81%

2. Support for Regional Cooperation and Integration in the Energy Sector

Development of national energy markets and their access to the

regional energy market 1.49 - 1.49 100%

Institutional framework for the development of regional projects 1.70 - 1.70 100%

Support for regional integration development 0.68 - 0.68 100%

Component 2 Total 3.87 - 3.87 100%

3. Support for Project Management

EGL capacity building 1.14 1.14 2.28 50%

PIU operating cost - 0.96 0.96 0%

Preparation of a procedures and training manual 0.03 - 0.03 100%

Training activities 0.15 0.04 0.19 80%

Project audit - 0.12 0.12 0%

Panel of independent experts 0.16 - 0.16 100%

Component 3 Total 1.49 2.26 3.75 40%

Total Project Base Cost 325.77 76.77 402.54 81%

Provision for physical contingencies (5%) 16.02 3.73 19.75 81%

Provision for price escalation (5%) 17.09 4.02 21.11 81%

Total Project Cost 358.88 84.52 443.40 81%

2.4.2 Project Financing Arrangements: The project will be co-financed by different donors2. The

Bank's public sector window contribution is 22%. This contribution comprises grants and loans to the

three States concerned which are participating directly in the project through a shareholding in the PC,

and the award of concessional loans to the company as provided for under the Bank's on-lending policy

(see Annex 5). Therefore, all the project costs are covered by the PC. In addition to this participation, the

States concerned will contribute in kind to the operating costs of the national teams. They will cover the

acquisition of land located in the project right-of-way, which will be reimbursed by the PC. The

financing plan is presented in Table 2.4:

2 For information, the contributions of the other donors (in USD million) to the concessional/commercial debt are as follows: WB (150/0); EIB

(120/50); AFD (15/30); KfW (30/0); and EU (46/0)

Page 15: AFRICAN DEVELOPMENT BANK GROUP · AFRICAN DEVELOPMENT BANK GROUP ... 2.7 Bank's Experience and Lessons Reflected in Project Design ... The Ruzizi III Hydropower Plant …

6

Table 2.4: Sources of Financing (in UA million)

Sources of Financing Cost in Foreign

Exchange

Cost in Local

Currency Total Cost % Total

Component 1

Private Investor 71.24 - 71.24 16%

AfDB Group 73.43 17.07 90.50 21%

Other Donors 208.59 65.07 273.66 63%

Component 1 Total Cost 353.26 82.15 435.40 100%

Component 2

AfDB Group 4.06 - 4.06 100%

Component 2 Total Cost 4.06 - 4.06 100%

Component 3

AfDB Group 1.54 2.40 3.94 100%

Component 3 Total Cost 1.54 2.40 3.94 100%

Project Total Cost 358.86 84.55 443.40

Table 2.4bis below presents the sources of financing by component. The project cost by expenditure

category and expenditure category by component are presented in Tables 2.5 and 2.6.

Table 2.4bis: Sources of Financing by Component (in UA million)

Equity Capital Concessional Debt Commercial

Debt Total

Rwanda Burundi DRC Private

Investor Rwanda Burundi DRC

Component 1

Private Investor 0 0 0 71.24 - - - - 71.24

Bank Group - - - 0 - - - - -

ADF - - - 0 16.08 19.29 - - 35.37

TSF - - 11.70 0 - - 43.43 - 55.13

AfDB - - - 0 - - - 35.62 35.62

Other Donors 11.70 11.70 - 0 61.80 61.80 61.80 29.26 238.04

Total 11.70 11.70 11.70 71.24 77.88 81.09 105.23 64.88 435.40

Component 2

Bank Group - - - - - - - - -

ADF - - - - 0.72 0.87 - - 1.59

TSF - - - - - - 2.47 - 2.47

Total - - - - 0.72 0.87 2.47 - 4.06

Component 3

Bank Group - - - - - - - -

ADF - - - - 0.70 0.84 - 1.54

TSF - - - - - - 2.40 2.40

Total - - - - 0.70 0.84 2.40 - 3.94

TOTAL 1.70 11.70 11.70 71.24 79.30 82.80 110.10 64.88 443.40

Page 16: AFRICAN DEVELOPMENT BANK GROUP · AFRICAN DEVELOPMENT BANK GROUP ... 2.7 Bank's Experience and Lessons Reflected in Project Design ... The Ruzizi III Hydropower Plant …

7

Table 2.5: Project Cost by Expenditure Category (in UA million)

Expenditure Categories Cost in Foreign Exchange Cost in Local

Currency Total Cost % F.E.

Works 320.41 74.51 394.92 81%

Goods - 0.15 0.15 0%

Services 5.36 1.30 6.65 81%

Operation - 0.81 0.81 0%

Total base cost 325.77 76.77 402.54 81%

Provision for contingencies (5%) 16.02 3.73 19.75 81%

Provision for price escalation (5%) 17.09 4.02 21.11 81%

Total Project Cost 358.88 84.52 443.40 81%

Table 2.6 : Expenditure Schedule by Component (in UA million)

Components 2016 2017 2018 2019 2020 2021 2022

1. Support for Ruzizi III Implementation

Component 1 Total 14.50 113.60 72.42 106.73 57.18 19.06 11.44

2. Support for Regional Cooperation and Integration in the Energy Sector

Component 2 Total - 0.16 0.90 1.31 0.63 0.63 0.23

3. Support for Project Management

Component 3 Total 0.58 0.94 0.79 0.58 0.36 0.36 0.14

Total Project Base Cost 15.08 114.70 74.12 108.62 58.17 20.05 11.81

2.5 Project Target Areas and Beneficiaries

2.5.1 The project area lies in South-West Rwanda and Eastern DRC between Lake Kivu and Lake

Tanganyika. The Ruzizi III hydropower facility is on the Ruzizi River between DRC and Rwanda. The

Ruzizi valley is very narrow with steep sides and a difference in level of about 500 metres between the

plateaux and the valley bottom. The dam is about 10 km upstream from Bugarama/Kamanyola while the

power plant is 5 and 6.5 km from these two localities, respectively. The project area lies in South Kivu

Province in DRC, Ruzizi District in Rwanda and Cibitoke Province in Burundi. Agricultural activity in

the project area focuses mainly on food crops. Population pressure, which is very strong in the area, is

one of the main reasons for the small size of farms (less than 1 hectare per family). The estimated

population of the project area is 615,000.

2.5.2 The project will generate many benefits, including: (i) increased supply of electricity in the

region and consequently access to electricity at an affordable cost, the direct beneficiaries of which will

be the population, electricity companies and businesses in the countries concerned; (ii) the creation of

direct and indirect jobs during works and permanent jobs during the operational phase; (iii) a reduction

in subsidies on fossil fuels and development of the industrial fabric for Governments, (iv) the creation

of income-generating activities for women and youth; and (iv) improvement of population's living

conditions. Regarding climate change adaptation, the project will ensure the annual avoidance of about

151,000 tCO2. Since the river flow is highly dependent on climatic variability and the Ruzizi I and II

facilities, a supplementary study and climatic and hydrological parameter monitoring mechanism are

planned. The adequate building of EGL’s capacity will ensure that the new structures on the cascade are

rapidly put in place. Financially, the different governments will benefit from income generated by their

participation in the PC and by the debt on-lent to the PC. This income could be recycled in the sector.

The private partner will also be remunerated for its majority participation in the PC.

Page 17: AFRICAN DEVELOPMENT BANK GROUP · AFRICAN DEVELOPMENT BANK GROUP ... 2.7 Bank's Experience and Lessons Reflected in Project Design ... The Ruzizi III Hydropower Plant …

8

2.6 Participatory Process

The different Governments concerned have adopted a participatory process fully involving the

communities in identifying needs, monitoring activities and assessing them in a spirit of citizen control,

knowledge and know-how sharing, and social efficiency. Thus, the preparation of the Environmental and

Social Impact Assessment (ESIA) and Resettlement Action Plan (RAP) in 2012 was carried out using a

participatory process. Different consultations were held in the main localities of the project area. They

involved the competent government authorities, local authorities, the population including women and

youths, project affected persons and non-governmental organizations (NGO). Project Affected

Smallholder Committees (CPAP) were established in the localities concerned for consultations with

those inhabitants directly concerned by the project. The establishment of CPAPs took into account

representativeness, in particular, gender balance with women's participation. Exchanges with project

affected persons (PAPs) and neighbouring communities highlighted their concerns and/or wishes, some

of which have been taken into account in this project. Furthermore, the project communication strategy

will focus on information, sensitization, education, social mobilization and capitalization.

2.7 Bank's Experience and Lessons Reflected in Project Design

2.7.1 The Bank intervenes in the development of the energy sector in Burundi, DRC and Rwanda,

where the bulk of the projects are being implemented. At community level, it has intervened since 2008

in the Great Lakes region through the NELSAP project, which concerns the three ECGLC countries plus

Kenya and Uganda. This project will contribute to the interconnection between the different countries to

facilitate access to the EAPP regional electricity market. No completion report has yet been prepared for

the NELSAP project, which is ongoing. However, the main lessons to learn from it to-date are: (i) the

need for effective coordination between the different actors; and (ii) the importance of the project

implementation structure. NELSAP is implemented by national entities responsible for structures

located on their territory. The NELSAP Project Coordination Unit (PCU) only carries out regional

coordination to harmonize the different schedules and ensure compatibility of the standards used on the

interconnected grid, which is the reason for the lack of works synchronization. Furthermore, the “public”

management method retained for the Ruzizi II community power plant has incurred losses. DRC and

Burundi's situations as States in transition, confirmed by their weak capacity, and lessons learned in

implementing the NELSAP and Ruzizi II projects explain the decision of States involved to entrust the

execution of the Ruzizi III project to EGL which has experience of working with the TFPs. It is also the

reason for selecting a private operator which will set up a PC for the construction and subsequent

operation of the structures.

2.7.2 These experiences are enriched by lessons drawn by the Bank from the portfolio review of the

countries concerned and its participation in PPPs (like the Ouarzazate Solar Plant) or multinational

projects. The main problems identified relate to: (i) major overruns on the estimated costs; (ii) delays in

establishing adequate financial management systems; (iii) the lack of an efficient monitoring/evaluation

system; (iv) weakness of project implementation structures; and (v) ineffectiveness of project steering

committees. The project addresses these problems by focusing on EGL capacity building and quality at

entry of activities through Component 2.

2.8 Key Performance Indicators

2.8.1 The project's key performance indicators are presented in the Results-Based Logical

Framework. They concern the construction of structures and conduct of studies planned under the

project, but also the facilitation of access to electricity in the Great Lakes Region.

2.8.2 As the project executing agency, EGL will be responsible for establishing a baseline situation

for the performance indicators as well as monitoring and analysing their trends by comparing them with

the logical framework estimates. At the level of the different countries concerned, the project

performance indicators will be integrated into the different periodic activity reports. The indicators will

be analysed in relation to the project's target values or any other benchmark considered relevant, in

particular, during supervision missions fielded by the Bank and other technical and financial partners.

Page 18: AFRICAN DEVELOPMENT BANK GROUP · AFRICAN DEVELOPMENT BANK GROUP ... 2.7 Bank's Experience and Lessons Reflected in Project Design ... The Ruzizi III Hydropower Plant …

9

3 PROJECT FEASIBILITY

3.1 Economic and Financial Performance

3.1.1 Burundi, Rwanda and DRC are experiencing significant power deficits. This justifies major

investments to increase generation capacity and develop the transmission and distribution grids.

Implementation of Ruzizi III falls within this context and constitutes the next stage3 in realizing the

optimal hydropower potential of the Ruzizi cascade, reducing the current supply and demand imbalance

which ranges from 20 to 65%, and meeting future demand.

3.1.2 Ruzizi III was retained following a preliminary review of the costs and benefits of exploitable

sites in the region. Despite the outdated basic figures, the results remain valid given the costs and

technical constraints concerning alternative generation methods. The project financial and economic

evaluation is carried out from 2016 over a thirty-year period (5 years of construction and 25-years of

operation).

3.1.3 The findings of the analysis show that the project is financially and economically viable. Based

on a weighted average price of USD 0.124/kWh and an energy sales volume of GWH 663.4 per year, the

project's estimated financial internal rate of return will be 7.84% and its financial net present value

(calculated on the basis of a weighted average cost of capital of 6.55%) USD 63.13 million. In addition

to the fact that it is part of a long-term development plan for the region at an affordable cost, the

economic justification of the Ruzizi III project may be proved by calculating the economic costs avoided

in the event of no project implementation. Economic agents who are not supplied with electricity from

the grids use individual generators or kerosene lamps. The cost per kWh of these different alternative

energies may be considered as an indicator of consumers’ willingness to pay (WTP) for access to

electricity supply services. Based on an average WTP of USD 0.22, USD 0.29 and USD 0.23 per kWh in

Burundi, Rwanda and DRC respectively, the project shows an economic internal rate of return (EIRR) of

13.35% and an economic net present value (ENPV) estimated at USD 36.13 million. The table below

summarizes the main economic and financial results. The detailed calculations and assumptions are

presented in Annex B7.

Table 3.1: Key Financial and Economic Indicators

PARAMETERS VALUES

FIRR 7.84%

FNPV USD 63.13 million

EIRR 13.35%

ENPV USD 36.13 million

3.2 Environmental and Social Impacts

3.2.1 Environment

3.2.1.1 In accordance with the Bank's Integrated Safeguards System, the project was classified in

Category 1 because of the scale of the works and negative environmental and social impacts identified.

The comprehensive ESIA and Full Resettlement Plan (FRP) were prepared in 2012. The ESIA and FRP

summaries were posted on the Bank's website on 14 August 2015. In view of the project's restructuring

as a PPP, the existing studies will be updated in accordance with the Environmental and Social Action

Plan (ESAP) following the establishment of the PC. These updates constitute conditions precedent to

disbursement.

3 The Ruzizi I (constructed in 1959 with installed capacity of 29.8 MW) and Ruzizi II (commissioned in 1989 with installed capacity of 43.8 MW) plants

are already operational in the Ruzizi valley.

Page 19: AFRICAN DEVELOPMENT BANK GROUP · AFRICAN DEVELOPMENT BANK GROUP ... 2.7 Bank's Experience and Lessons Reflected in Project Design ... The Ruzizi III Hydropower Plant …

10

3.2.1.2 During the works, the main negative impacts will concern: (i) the quantitative and qualitative

degradation of the river's water resources downstream from the works area; (ii) the destruction of

property affecting 4,300 people in DRC and Rwanda; (iii) the destruction of plant species and wildlife

habitat on the right-of-way planned for the reservoir and different facilities; and (iv) other risks related to

health, hygiene and security of employment for employees. In the operational phase, the reservoir is

likely to cause: (a) a proliferation of water-borne diseases; (b) accidents and drownings; and (c)

landslides up to the equilibrium period. The most significant cumulative negative impacts relate to: (1)

successive dam failures (Ruzizi I, II and III); (2) erosion and sedimentation created by various activities

in the catchment area; and (3) those relating to the hydro-ecological continuity of the water course

mainly for barbels (Barbus altianalis).

3.2.1.3 TO mitigate these negative impacts, the contractors selected will be required to prepare, on the

basis of the Project ESMP and PC, environmental and social management system, detailed and specific

environmental and social plans, in particular: (i) Hygiene, Health, Safety and Environment Plans

(HHSEP); (ii) erosion and sedimentation control; (iii) site replanting and rehabilitation; (iv) quarry and

borrow site management; (v) management of fortuitous discoveries; (vi) initial filling of the reservoir;

(vii) monitoring of water quality; (viii) environmental and social training of personnel; and (ix) site

dismantling. Project affected persons will be compensated and assisted in compliance with the

resettlement plan. During the operational phase, an operations and maintenance plan as well as an

emergency preparedness plan will be implemented to manage the impacts during this phase. The

estimated cost of the ESMP measures is USD 17.14 million. Hence, an appropriation of USD 17.14

million was made for updating the ESIA/ESMP and FRP. The project will also generate many positive

impacts. Specifically, through complementary actions under the aegis of ABAKIR, it will contribute to

the implementation of lasting solutions to the basin-wide problems of erosion and sedimentation as well

as to those relating to hydro-ecological continuity, including for Ruzizi I and II.

3.2.2 Climate Change

3.2.2.1 The project was classified in Category 1 with respect to climate change. The impact assessment

indicates that the Ruzizi flow rate depends mainly on the level of Lake Kivu. This level has been falling

for several years due to a downward trend in rainfall, expansion of its catchment area and anthropic

activities which are accelerating erosion and sedimentation in the river. The analyses indicate average

temperature increases of 1.9°C and 2.5°C by 2050 and 2060, respectively. Climate variability will have

an impact on the cascade's energy production and the choice of flow control equipment for Ruzizi III.

Adaptation measures will be integrated in the project's design.

3.2.2.2 It is also recommended to update the hydrological study and monitor the climatic and

hydrological parameters, in order to ensure the smooth operation of the plant. The monitoring indicators

will be updated in the quarterly ESMP implementation reports. Based on the AFD methodological

approach, GHG emissions during works are estimated at 39,000 tCO2 for the dam's construction.

Methane gas emissions from the reservoir during the operational phase will be significantly reduced due

to the fact that: (i) very little vegetation will be submerged; and (ii) the water retention time in the

reservoir will be very short. These emissions particularly concern the first two years. They will be

mitigated by: (a) a reduction in the amount of plant cover submerged by the reservoir; and (b) the

planting of 3,000 trees/ ha over 15 ha, which will serve as protection of the catchment area. Therefore,

the implementation of Ruzizi III would help prevent the emission of over 7.5 million tCO2 over 50

years.

3.2.3 Gender

3.2.3.1 Women, girls and children are still paying a heavy price for the different crises that have

affected the region. Despite the existence of favourable legislation, women's rights are not evenly

enforced in the three countries. The project's implementation will have the following positive impacts on

Page 20: AFRICAN DEVELOPMENT BANK GROUP · AFRICAN DEVELOPMENT BANK GROUP ... 2.7 Bank's Experience and Lessons Reflected in Project Design ... The Ruzizi III Hydropower Plant …

11

women, girls and children: (i) strengthen women's income-generating activities (IGA), in particular,

through the development of small businesses during the construction phase; (ii) at least 20% of unskilled

direct and indirect jobs will benefit women and girls; (iii) promote agricultural produce artisanal

processing activities mainly carried out by women; and (iv) access to electricity and the use of lighting

will improve the well-being of women and girls especially, in terms of education. The likely negative

impacts on women are: (s) increase in water-related health problems (accidents and drownings); (b)

impact on sexually transmitted infections-HIV/AIDS; and (c) changing vectors of disease due to

modifications of the habitat.

3.2.3.2 To mitigate the negative impacts, the project will pursue the following actions: (i) sensitization

campaigns on different themes (STI-HIV/AIDS) for workers and communities settled in the project area,

in particular women and children; (ii) support for the promotion of IGAs will be factored into the local

development plans and the Plan to Restore and Improve Living Conditions financed and implemented by

the PC; and (iii) support for the promotion of well-being through the rehabilitation and equipping of

schools, health centres and women's promotion centres planned in the local development plan. The

financing of women's promotion activities is included in the project costs and their implementation

entrusted to the PC. The Bank's contribution will be used to provide EGL with a specialized expert on

social and gender issues responsible for preparing and implementing the different plans.

3.2.4 Social

3.2.4.1 The Great Lakes Region is one of Africa's fragile areas. The main factors associated with

fragility and analysed in relation to the Ruzizi III project are: (i) the volatility of the security situation

and political instability; (ii) the different forms of social exclusion: identity crisis, ethnic divides and

land tenure conflicts; (iii) the weak water resource governance capacity; (iv) gender-based violence; and

(v) extreme poverty and unemployment, especially among young people. This situation of fragility,

mainly perceived at the social level, poses risks for the project's implementation, which are to be found

among the potential negative impacts referred to in paragraph 3.2.1.2. However, the experience of

existing infrastructure shows that this risk is relative and that the project could serve as an instrument of

dialogue to encourage peace consolidation and stabilization activities in the region. The availability of

energy in this region could help to restore peace by developing highly remunerative economic activities.

3.2.4.2 The project's implementation will have the following positive social impacts: (i) improved

access of households to electricity; (ii) economic diversification; and (iii) creation of 800 to 1000 direct

and indirect permanent and temporary jobs in favour of local but unskilled labour, with a proportion of

20% for women. To optimize its social impact, the project will help affected households to rediscover or

sustainably create satisfactory living conditions. In this regard, a Plan to Restore and Improve Living

Conditions (PRRV) and a local development plan (PDLC) will be rolled out. These two plans will be

finalized by the PC in close collaboration with the competent local authorities. The estimated cost of

implementing these two plans is USD 7 million.

3.2.5 Involuntary Resettlement

Clearing of the works right-of-way, estimated at 115 hectares by the technical studies, will a priori affect

no fewer than 636 households in Rwanda and in RDC, i.e. about 4500 people, 64% of whom are living

in DRC and 36% in Rwanda. Affected property mainly comprises unbuilt land, crops (food and market

garden), fruit trees and various other plants. The Resettlement Action Plan prepared in 2012, a summary

of which will be published on the Bank's website, will be updated by the PC prior to the launching of

invitations to bid for EPC contracts, in accordance with the Bank's requirements.

Page 21: AFRICAN DEVELOPMENT BANK GROUP · AFRICAN DEVELOPMENT BANK GROUP ... 2.7 Bank's Experience and Lessons Reflected in Project Design ... The Ruzizi III Hydropower Plant …

12

4 PROJECT IMPLEMENTATION

4.1 Implementation Arrangements

4.1.1 Through a Panel of Experts, Burundi, DRC and Rwanda shall establish the project steering

body. This committee will comprise, for each country, representatives of the ministries responsible for

energy, environment, finance and electric power utilities. Project implementation is entrusted to EGL -

an ECGLC specialized institution with a specific mandate to implement the Ruzizi III project as a

public-private partnership (cf. special delegation of powers conferred upon EGL to implement Ruzizi

III, on 12 November 2010, by the three States). It is planned that infrastructure construction will be

awarded to a project company and that the implementation of related activities will be awarded to EGL.

4.1.2 The three countries and the private partner, investor/developer have jointly and severally agreed

to establish a project company to finance the construction and operation of the Ruzizi III plant. One third

(1/3) of the PC's share capital will be held in equal parts by the three countries and two thirds (2/3, i.e.

USD 100 million) of the share capital will be held by an investor/developer. Pending the signing of the

project agreement for the establishment of the PC expected by end-2015, preliminary procurement

operations will be carried out by EGL, supported by the Steering Committee established in 2013 and

comprising two experts/representatives per country. The treaty, internal rules and shareholders'

agreement were established by the three governments assisted by international lawyers. Establishment of

the PC will be a condition precedent to first disbursement of the Bank's financing.

4.1.3 Since the related “capacity building/project management” and “regional integration” activities

transcend the individual States, they will be implemented by EGL. The three countries have agreed to on-

lend the related financial resources to EGL. In light of the mandate assigned to EGL and to ensure the

quality of its investments, there is a real need to build its capacity in order to enhance the performance of the

executing agency. Thus, in addition to the international consultants recruited to assist EGL, the key

personnel will include technical, legal, economic and financial experts. The additional human resources

will be recruited through a competitive process and will comprise at least a financial expert, a procurement

expert and electromechanical/electrical engineer, a civil engineer, a legal counsel, a computer specialist, an

environmental expert and expert on social and gender issues. A monitoring/evaluation expert will be

recruited for EGL to monitor project activities. From an institutional standpoint and in view of the project's

scope, EGL will work closely with the other regional entities operating in the river basin's management

(Regional Dispatching Centre (CDR) and the Ruzizi River Cascade Coordination Centre (CC)).

4.1.4 Procurement

4.1.4.1 The procurement process for the selection of the developer/investor was launched in 2012. It

was approved by the Bank as well as the choice of the future developer.

4.1.4.2 However, the future developer and EGL agreed to adopt a competitive selection procedure for a

turnkey contract for engineering, supplies and construction of the Plant (EPC contract) [Component 1:

Support for the implementation of Ruzizi III]. To that end, this contract was awarded in compliance with

the relevant WB Guidelines subject to a waiver by the Bank's Board of Directors. Joint financing was

chosen because: (i) to date, the fiduciary safeguard policies of both the Bank and WB are almost

identical; and (ii) the Bank's Procurement Rules and Procedures and WB Guidelines as well as their

standard bidding documents (SBDs) are closely harmonized. It should be noted that, like other donors,

AfDB will carry out a prior review of procurement documents during the selection process (pre-

qualification, bidding, bid evaluation and contract negotiation phases, etc.). Thus, for the EPC contract,

the procurement of goods, works and services (other than consulting services) will be carried out in

compliance with the WB's “Guidelines for the Procurement of Goods, Works and Non-Consulting

Services” using the WB's relevant SBDs as well as with the provisions stipulated in the Financing

Agreement.

Page 22: AFRICAN DEVELOPMENT BANK GROUP · AFRICAN DEVELOPMENT BANK GROUP ... 2.7 Bank's Experience and Lessons Reflected in Project Design ... The Ruzizi III Hydropower Plant …

13

4.1.4.3 All procurement of goods, works and consulting services for project Components 2 and 3 which

are fully financed by the Bank will be made in accordance with “Bank Rules and Procedures for the

Procurement of Goods and Works”, May 2008 Edition, revised in July 2012, and “Bank Rules and

Procedures for the Use of Consultants”, May 2008 Edition, revised in July 2012, using the Bank's

standard bidding documents (SBDs) as well as with the provisions stipulated in the Financing

Agreement.

4.1.4.4 EGL will be responsible for the award of all contracts for project activities, in particular

monitoring the selection of the EPC (Component 1) and implementation of the procurement activities

planned under Components 2 and 3. The assessment of EGL's capacity indicates a need for capacity

building by a procurement expert, whose qualifications and experience are deemed satisfactory by the

Bank. A draft procurement plan prepared by EGL will be submitted to the Bank for review and approval

prior to negotiations. The procurement details are set out in Annex B5.

4.1.5 Financial Management and Audit Arrangements

4.1.5.1 Based on the review carried out, the project's overall financial management risk at entry was

considered substantial. Mitigation measures proposed in the financial management action plan (Annex

B4 and B6) aim to support EGL for the rapid establishment of a project financial management

mechanism. The recruitment of a financial expert and accountant to strengthen the Administrative and

Financial Department, the updating of EGL's accounting procedures manuals, the preparation of an

accounting procedures manual for the PC prior to first disbursement and speedy implementation of

actions agreed in the action plan will help to lower the residual risk to a moderate level and at EGL, to

meet the Bank's minimum project financial management requirements. It will also be necessary to

acquire software configured to meet the project's accounting needs no later than six (6) months

following project effectiveness.

4.1.5.2 Thus, in accordance with the implementation arrangements, responsibility for project financial

management will fall within the remit of EGL, which will also use the PC’s financial statements. In this

regard, EGL will establish an adequate financial management system which meets international

standards, with qualified and experienced financial staff, to maintain general, cost and budgetary

accounting with adequate software. The project's financial management will be based on the entire

financial management system to be established at EGL, especially the following systems: (i) budgetary

management; (ii) accounting and reporting; (iii) internal control and external audit; and (iv) cash and

funds flow management system. Compliance by EGL with the arrangements agreed upon in the financial

management action plan will ensure that the funds provided to the project are used for project purposes.

In addition, recruitment of the external auditor six months after project effectiveness and all other

measures contained in the financial management action plan constitute other financing conditions. EGL

accounts will be maintained separately from the project accounts. EGL has undertaken to produce and

regularly submit to the Bank quarterly financial monitoring reports as well as annual financial statements

on the due dates agreed upon, in a format to be determined during negotiations. Furthermore, the PC will

be responsible for the establishment and operation of infrastructure, including its own financial

management following signature of the term sheets of the project agreement establishing the PC. The

Bank will ensure the adequacy of the PC's financial management capacity during the project launching

mission.

4.1.5.3 The PC will put in place appropriate and well-documented internal control procedures, in

particular relating to accounting entries, financial transactions, commitment and justification of

expenditure, safeguarding of financial data and project assets. Internal auditing will be carried out by an

internal auditor or an audit committee as required. A detailed reporting system will enable EGL to report

on financial management to the Bank.

Page 23: AFRICAN DEVELOPMENT BANK GROUP · AFRICAN DEVELOPMENT BANK GROUP ... 2.7 Bank's Experience and Lessons Reflected in Project Design ... The Ruzizi III Hydropower Plant …

14

The annual financial statements will be produced for EGL on time in accordance with International

Public Sector Accounting Standards (IPSAS). The PC will produce the agreed upon periodical financial

statements in compliance with International Financial Reporting Standards (IFRS). These reports will

include a balance sheet, income statement, a statement of equity, a cash flow table as well as accounting

principles and notes to the financial statements.

4.1.5.4 The project and EGL financial statements prepared separately will be audited annually by an

external auditor. The auditing of the project and EGL's accounts will be performed in compliance with

International Auditing Standards (IFAC). EGL will publish a request for proposals and will appoint

international external auditors no later than six (6) months after project effectiveness to conduct the

annual audit based on the Terms of Reference agreed upon with the Bank during the negotiations. The

audit report will be submitted to the Bank latest six months after the end of the fiscal year concerned.

The PC will recruit auditors for the project's financial and technical audit.

4.1.6 Disbursement Mechanism and Modalities

Within the project implementation framework, the special account and direct payment disbursement

methods have been retained. EGL will open a special account in a bank deemed acceptable by the Bank,

for financing all eligible expenditure under Components 2 (“Support cooperation and regional

integration in the energy field”) and 3 (“Project management”). The special account will be managed in

compliance with the provisions of the procedures manual and those of the grant protocols of agreement

and loan agreements. The direct payment method will be used for payments related to: (i) resources on-

lent to the PC under Component 1 (“Support for Ruzizi III implementation”); and (ii) Components 2 and

3 expenditures ineligible for special account financing. In accordance with the provisions of the

financing agreements and its Disbursement Rules and Procedures, the Bank will disburse resources to

cover expenditure. Disbursements to the PC shall comply with the Bank’s on-lending policy for

concessional loans.

4.2 Project Monitoring

The main project stages are presented in Table 4.1 below. The activities will be implemented as set out

on the project implementation schedule. EGL will use the services of a monitoring/evaluation expert to

monitor the status.

Table 4.1: Main Project Implementation Stages

Duration Stages Monitoring Activities/Feedback Loop

3 months Approval and

effectiveness

Approval of loans and grants

General Procurement Notice

Signature of financing agreements and effectiveness

AfDB launching mission

8 months Procurement

Review and approval of bidding documents

Bidding and award of contracts

Signature of project agreements

PC's establishment

Signature of EPC contract

72 months Project's physical

implementation

Contract execution

Preparation of periodic project status reports

Supervision missions by the Bank and other partners

Project social and environmental monitoring

Bank's mid-term review

6 months Auditing of Project

Accounts

Recruitment of the auditor to conduct annual audits

Conduct of annual audits

3 months Project Completion

Borrower's and Donees' Project Completion Report

Preparation of the Bank’s Project Completion Report

Page 24: AFRICAN DEVELOPMENT BANK GROUP · AFRICAN DEVELOPMENT BANK GROUP ... 2.7 Bank's Experience and Lessons Reflected in Project Design ... The Ruzizi III Hydropower Plant …

15

4.3 Governance

Governance risk for this project is low and could occur in the course of implementing activities entrusted

to EGL. EGL has already implemented this type of operation with other partners as well as the Bank,

through NEPAD/IPPF. The risk is mitigated by the involvement of donors. The same will apply to the

recruitment of personnel where the Bank's opinion will be required prior to appointments. Procurement-

related risks are minimal since an agreement was reached to award the largest contract in accordance

with WB procedures. Moreover, the Bank's supervision and technical and financial audits will ensure

conformity between the specifications, outputs, disbursements and financing agreements. The

involvement of the countries concerned in the project's management will also strengthen governance.

4.4 Sustainability

4.4.1 Project sustainability will depend principally on the commitment of the three governments

through the specific mandate entrusted to EGL. Furthermore, since the launching of the feasibility study,

the three countries have established a monitoring and dialogue mechanism with a view to achieving

optimal and sustainable development of the Ruzizi Cascade. Thus, in terms of ownership, other actions

such as the institutional study on the cascade management or on the rehabilitation of the Ruzizi I and II

structures are ongoing. These actions should contribute to optimal integrated water resource

management.

4.4.2 The adoption of a PPP project stems from the determination of the countries to avoid the

management problems encountered with Ruzizi II, reason for which the facility now needs

rehabilitation.

4.5 Risk Management

4.5.1 Risk management: EGL undoubtedly has experience of Ruzizi II but has no previous history of

monitoring and implementing a PPP project of Ruzizi III's complexity. This risk will be mitigated by

building EGL's capacity, support from high-calibre consultants, analyses and opinions of the Bank and

other donors on the project implementation process. The project costs include provisions for

contingencies and price escalation.

4.5.2 Fiduciary risk: The project's initial fiduciary risk was deemed high. EGL, which will

implement the project, is not yet sufficiently operational to ensure effective project financial

management at this stage. The project has also become somewhat complex as a result of the need to find

a joint management mechanism for the resources mobilized from different donors - a further risk factor

for the Bank. Fulfilment of conditions precedent related to the financing will help to mitigate this risk to

a moderate and acceptable level. In addition to the operationalization of EGL, it will be necessary for

the Bank to confirm or obtain evidence of the establishment of a satisfactory financial management

mechanism for project implementation. Another aspect of fiduciary risk lies in the confirmation of the

investor/developer since the IPS/Sithe Global Consortium retained in 2012 does not offer all the

guarantees of its determination to pursue the process towards establishment of the PC. The withdrawal

of this consortium or of one of the firms could delay the project by requiring a new bidding process.

4.5.3 Co-financing risk: This risk is real despite the coordination efforts. Slippage or default on

implementation of part of its commitments could undermine the smooth execution of the entire project.

This risk will be mitigated by the collaborative attitude of all the co-financiers but also by the

communication efforts made and which will continue.

4.5.4 Political risk: This risk is the result of the fragility of the ongoing peace process and political

instability in the region, which could impede the implementation of project activities. This risk will be

mitigated by the ongoing political developments, in particular, the consultative process and regional and

Page 25: AFRICAN DEVELOPMENT BANK GROUP · AFRICAN DEVELOPMENT BANK GROUP ... 2.7 Bank's Experience and Lessons Reflected in Project Design ... The Ruzizi III Hydropower Plant …

16

internal mediation. The dialogue pursued by the technical and financial partners to encourage

governments in their efforts to restore State authority over their respective national territories is another

contributory factor, as is the presence of MONUSCO in Eastern DRC.

4.5.5 Technical risk: this risk concerns the availability of distribution networks for energy or water

from Lake Kivu through upstream facilities. These risks will be mitigated by the works being prepared

or implemented, which are expected to be commissioned in 2017 as well as the establishment of

ABAKIR which will work in concert with the Kamanyola Coordination Centre. Ruzizi I and II

rehabilitation and restructuring studies are also being finalized.

4.6 Knowledge Building

4.6.1 The project provides an opportunity to disseminate new knowledge for the Bank and for the

ECGLC through EGL. For the Bank, it is an illustration of support to a sub-regional organization for the

preparation of a complex project. Implementation of this project will build the Bank's capacity to prepare

and support PPP projects. It is also an example of cooperation among technical and financial partners.

4.6.2 New knowledge will be mainly acquired through interaction between partners and also with the

beneficiaries. The documentation stemming from these meetings and supervision reports, periodic status

reports as well as the reports following the different controls will provide the basis for knowledge

building.

4.6.3 Ruzizi III will build EGL's capacity and is expected to facilitate the development of the Ruzizi

IV project on a much larger scale than Ruzizi III.

5 LEGAL FRAMEWORK

5.1 Legal Instrument

The Bank will use the following instruments: (i) for Burundi: a grant of UA 21 million from ADF-13

resources (of which UA 7 million PBA and UA 14 million RE); (ii) for DRC: a grant of UA 45 million

(of which UA 15 million TSF allocation (Pillar 1) and UA 30 million RE) and a loan of UA 15 million

(of which UA 5 million TSF allocation (Pillar 1) and UA 10 million RE); and (iii) for Rwanda: a loan

of UA 17.5 million from ADF-13 resources (of which UA 7 million PBA and UA 10.5 million RE) to

co-finance the project.

5.2 Conditions for Bank's Intervention

A. Conditions Precedent to Grant/Loan Effectiveness:

Effectiveness of the ADF and TAF grant protocols of agreement is subject to their signature by the

Donee, the ADF and the Bank. Effectiveness of the ADF and TSF loan agreements is subject to

fulfilment by the Borrower of the conditions stipulated in Section 12.01 of the General Conditions

Applicable to Loan Agreements and to Guarantee Agreements of the African Development Fund, to the

Fund’s satisfaction.

B. Conditions Precedent to First Disbursement of the Grants/Loans:

Conditions Precedent to First Disbursement of Component 1

In addition to effectiveness of the grant protocols of agreement and the loan agreements, the first

disbursement of each grant or loan for financing Component 1 shall be subject to fulfilment of the

following conditions by the Donee/Borrower, to the full satisfaction of the ADF/TSF:

Page 26: AFRICAN DEVELOPMENT BANK GROUP · AFRICAN DEVELOPMENT BANK GROUP ... 2.7 Bank's Experience and Lessons Reflected in Project Design ... The Ruzizi III Hydropower Plant …

17

(i) Provide the Bank (or the Fund) with evidence of completing project financing

arrangements by showing proof of approval of project financing by other donors;

(ii) For each loan/grant, present to the Bank the original or certified true copy of the

attestation for an account opened by the PC through which the resources of each

loan/grant shall transit, and comprising the full bank account references and indication of

persons authorized to make disbursements therefrom; and

(iii) Provide the Bank to its satisfaction, with a certified true copy of: (a) the signed and

registered Articles of Association of the PC; (b) the Certificate of Registration of the PC;

(c) the power purchase contract between Buyers and the PC; and (d) the agreement on-

lending all or part of grant and loan resources allocated to project Component 1 to the PC,

stating inter alia that: (1) the PC shall forward financial and accounting information to

EGL on a half-yearly basis; and (2) the PC’s annual financial statements shall be audited

by its external auditors in accordance with applicable norms and taking into consideration

the Bank’s terms of reference.

Conditions Precedent to First Disbursement of Components 2 and 3

Apart from effectiveness of the grant protocols of agreement and the loan agreements, the first

disbursement of each grant or loan for financing Components 2 and 3 shall be subject to fulfilment of the

following conditions by the Donee/Borrower, to the full satisfaction of the ADF/TSF:

(i) For each loan/grant, provide the Bank with the original or certified copy of the certificate

proving the opening by EGL of a special account in the name of the project in a Bank

acceptable to the Fund for payment of the ADF and TSF grants and loans (paragraph

4.1.6.1), and containing full banking details of the account and the names of persons

authorized to make disbursements;

(ii) Provide the Bank with a certified true copy of the agreement on-lending to EGL the

ADF/TSF grant and loan resources allocated for financing project Components 2 and 3.

C. Other Conditions:

In addition, the Donees/Borrowers shall, to the Fund’s satisfaction:

(i) Provide, as works advance and in any event prior to the start of works on a given zone,

evidence of compensating project-affected persons in the said zone, in accordance with

the Comprehensive Resettlement Plan (CRP) and the relevant Fund rules and procedures,

especially the Fund’s Involuntary Resettlement Policy and Integrated Safeguards System;

and

(ii) Provide, no later than six months after the financial closure, all the documents relating to

environmental and social aspects (ESIA, FRP, PRRV, PDLC, etc.) (Paragraphs 3.2.1.1).

D. Undertakings:

To the satisfaction of the Fund/TSF, each Borrower or Donee shall undertake to:

(i) Provide the Fund/TSF with all documents reasonably required for the project's

implementation;

(ii) Have prepared by EGL the project implementation and administrative and financial

management procedures manuals (Paragraph 4.1.5.1) ;

Page 27: AFRICAN DEVELOPMENT BANK GROUP · AFRICAN DEVELOPMENT BANK GROUP ... 2.7 Bank's Experience and Lessons Reflected in Project Design ... The Ruzizi III Hydropower Plant …

18

(iii) Implement the Project and ESMP as revised and have them implemented by the PC and

its contractors in compliance with national laws, the recommendations, requirements and

procedures contained in the ESMP as well as with the related Fund/TSF rules and

procedures (Paragraph 3.2.1.2); and

(iv) Provide the Fund/TAF with quarterly reports on the implementation of the revised ESMP

including, as required, weaknesses and remedial action taken or to be taken.

5.3 Compliance with Bank Policies

The Ruzizi III Regional Hydropower Plant Project complies with all applicable Bank rules and

regulations.

6 RECOMMENDATION

Management recommends that the Boards of Directors: (i) waive, on an exceptional basis, the

application of the Bank's rules and procedures in favour of those of the World Bank for the procurement

of goods, works and services for the EPC contracts; and (ii) approve: (a) for Burundi: a grant of UA 21

million from ADF-13 resources; (b) for DRC: a grant and loan from TSF resources (Pillar I), of UA 45

million and UA 15 million; and (c) for Rwanda: a loan of UA 17.50 million from ADF-13 resources to

finance the Ruzizi III Regional Hydropower Plant.

Page 28: AFRICAN DEVELOPMENT BANK GROUP · AFRICAN DEVELOPMENT BANK GROUP ... 2.7 Bank's Experience and Lessons Reflected in Project Design ... The Ruzizi III Hydropower Plant …

I

Annex 1(a)

Comparative Socio-Economic Indicators for Burundi

Year Burundi Africa

Develo-

ping

Countries

Develo-

ped

Countries

Basic Indicators

Area ( '000 Km²) 2014 28 30 067 80 386 53 939Total Population (millions) 2014 10,5 1 136,9 6,0 1,3Urban Population (% of Total) 2014 11,8 39,9 47,6 78,7Population Density (per Km²) 2014 376,7 37,8 73,3 24,3GNI per Capita (US $) 2013 260 2 310 4 168 39 812Labor Force Participation - Total (%) 2014 82,7 66,1 67,7 72,3Labor Force Participation - Female (%) 2014 51,4 42,8 52,9 65,1Gender -Related Dev elopment Index Value 2007-2013 0,904 0,801 0,506 0,792Human Dev elop. Index (Rank among 187 countries) 2013 180 ... ... ...Popul. Liv ing Below $ 1.25 a Day (% of Population)2008-2013 81,3 39,6 17,0 ...

Demographic Indicators

Population Grow th Rate - Total (%) 2014 3,1 2,5 1,3 0,4Population Grow th Rate - Urban (%) 2014 5,6 3,4 2,5 0,7Population < 15 y ears (%) 2014 44,8 40,8 28,2 17,0Population >= 65 y ears (%) 2014 2,4 3,5 6,3 16,3Dependency Ratio (%) 2014 66,8 62,4 54,3 50,4Sex Ratio (per 100 female) 2014 97,6 100,4 107,7 105,4Female Population 15-49 y ears (% of total population) 2014 23,7 24,0 26,0 23,0Life Ex pectancy at Birth - Total (y ears) 2014 54,5 59,6 69,2 79,3Life Ex pectancy at Birth - Female (y ears) 2014 56,6 60,7 71,2 82,3Crude Birth Rate (per 1,000) 2014 44,3 34,4 20,9 11,4Crude Death Rate (per 1,000) 2014 12,5 10,2 7,7 9,2Infant Mortality Rate (per 1,000) 2013 54,8 56,7 36,8 5,1Child Mortality Rate (per 1,000) 2013 82,9 84,0 50,2 6,1Total Fertility Rate (per w oman) 2014 5,9 4,6 2,6 1,7Maternal Mortality Rate (per 100,000) 2013 740,0 411,5 230,0 17,0Women Using Contraception (%) 2014 26,5 34,9 62,0 ...

Health & Nutrition Indicators

Phy sicians (per 100,000 people) 2004-2012 2,8 46,9 118,1 308,0Nurses (per 100,000 people)* 2004-2012 19,1 133,4 202,9 857,4Births attended by Trained Health Personnel (%) 2009-2012 60,3 50,6 67,7 ...Access to Safe Water (% of Population) 2012 75,3 67,2 87,2 99,2Healthy life ex pectancy at birth (y ears) 2012 48,0 51,3 57 69Access to Sanitation (% of Population) 2012 47,5 38,8 56,9 96,2Percent. of Adults (aged 15-49) Liv ing w ith HIV/AIDS 2013 1,0 3,7 1,2 ...Incidence of Tuberculosis (per 100,000) 2013 128,0 246,0 149,0 22,0Child Immunization Against Tuberculosis (%) 2013 95,0 84,3 90,0 ...Child Immunization Against Measles (%) 2013 98,0 76,0 82,7 93,9Underw eight Children (% of children under 5 y ears) 2005-2013 29,1 20,9 17,0 0,9Daily Calorie Supply per Capita 2011 1 604 2 618 2 335 3 503Public Ex penditure on Health (as % of GDP) 2013 4,4 2,7 3,1 7,3

Education Indicators

Gross Enrolment Ratio (%)

Primary School - Total 2011-2014 134,1 106,3 109,4 101,3 Primary School - Female 2011-2014 134,5 102,6 107,6 101,1 Secondary School - Total 2011-2014 33,1 54,3 69,0 100,2 Secondary School - Female 2011-2014 29,2 51,4 67,7 99,9Primary School Female Teaching Staff (% of Total) 2012-2014 52,8 45,1 58,1 81,6Adult literacy Rate - Total (%) 2006-2012 86,9 61,9 80,4 99,2Adult literacy Rate - Male (%) 2006-2012 88,8 70,2 85,9 99,3Adult literacy Rate - Female (%) 2006-2012 84,6 53,5 75,2 99,0Percentage of GDP Spent on Education 2009-2012 5,8 5,3 4,3 5,5

Environmental Indicators

Land Use (Arable Land as % of Total Land Area) 2012 42,8 8,8 11,8 9,2Agricultural Land (as % of land area) 2012 0,8 43,4 43,4 28,9Forest (As % of Land Area) 2012 6,6 22,1 28,3 34,9Per Capita CO2 Emissions (metric tons) 2012 0,0 1,1 3,0 11,6

Sources : AfDB Statistics Department Databases; World Bank: World Development Indicators; last update :

UNAIDS; UNSD; WHO, UNICEF, UNDP; Country Reports.

Note : n.a. : Not Applicable ; … : Data Not Available.

BurundiCOMPARATIVE SOCIO-ECONOMIC INDICATORS

novembre 2015

0

10

20

30

40

50

60

70

80

90

100

20

00

20

05

20

08

20

09

20

10

20

11

20

12

20

13

Infant Mortality Rate( Per 1000 )

Burun di Africa

0

500

1000

1500

2000

2500

20

00

20

05

20

07

20

08

20

09

20

10

20

11

20

12

20

13

GNI Per Capita US $

Burun di Africa

0,0

0,5

1,0

1,5

2,0

2,5

3,0

3,5

4,0

20

00

20

05

20

08

20

09

20

10

20

11

20

12

20

13

20

14

Population Growth Rate (%)

Burundi Africa

01020304050607080

20

00

20

05

20

08

20

09

20

10

20

11

20

12

20

13

20

14

Life Expectancy at Birth (years)

Burun di Africa

Page 29: AFRICAN DEVELOPMENT BANK GROUP · AFRICAN DEVELOPMENT BANK GROUP ... 2.7 Bank's Experience and Lessons Reflected in Project Design ... The Ruzizi III Hydropower Plant …

II

Annex 1(b)

Comparative Socio-Economic Indicators for DRC

Year

Congo,

Dem.

Republic

Africa

Develo-

ping

Countries

Develo-

ped

Countries

Basic Indicators

Area ( '000 Km²) 2014 2 345 30 067 80 386 53 939Total Population (millions) 2014 69,4 1 136,9 6,0 1,3Urban Population (% of Total) 2014 35,9 39,9 47,6 78,7Population Density (per Km²) 2014 29,6 37,8 73,3 24,3GNI per Capita (US $) 2013 430 2 310 4 168 39 812Labor Force Participation - Total (%) 2014 72,0 66,1 67,7 72,3Labor Force Participation - Female (%) 2014 49,8 42,8 52,9 65,1Gender -Related Dev elopment Index Value 2007-2013 0,822 0,801 0,506 0,792Human Dev elop. Index (Rank among 187 countries) 2013 186 ... ... ...Popul. Liv ing Below $ 1.25 a Day (% of Population)2008-2013 87,7 39,6 17,0 ...

Demographic Indicators

Population Grow th Rate - Total (%) 2014 2,7 2,5 1,3 0,4Population Grow th Rate - Urban (%) 2014 4,3 3,4 2,5 0,7Population < 15 y ears (%) 2014 44,8 40,8 28,2 17,0Population >= 65 y ears (%) 2014 2,9 3,5 6,3 16,3Dependency Ratio (%) 2014 91,6 62,4 54,3 50,4Sex Ratio (per 100 female) 2014 98,7 100,4 107,7 105,4Female Population 15-49 y ears (% of total population) 2014 23,0 24,0 26,0 23,0Life Ex pectancy at Birth - Total (y ears) 2014 50,3 59,6 69,2 79,3Life Ex pectancy at Birth - Female (y ears) 2014 52,0 60,7 71,2 82,3Crude Birth Rate (per 1,000) 2014 42,3 34,4 20,9 11,4Crude Death Rate (per 1,000) 2014 15,2 10,2 7,7 9,2Infant Mortality Rate (per 1,000) 2013 86,1 56,7 36,8 5,1Child Mortality Rate (per 1,000) 2013 118,5 84,0 50,2 6,1Total Fertility Rate (per w oman) 2014 5,8 4,6 2,6 1,7Maternal Mortality Rate (per 100,000) 2013 730,0 411,5 230,0 17,0Women Using Contraception (%) 2014 23,0 34,9 62,0 ...

Health & Nutrition Indicators

Phy sicians (per 100,000 people) 2004-2012 10,7 46,9 118,1 308,0Nurses (per 100,000 people)* 2004-2012 52,9 133,4 202,9 857,4Births attended by Trained Health Personnel (%) 2009-2012 80,4 50,6 67,7 ...Access to Safe Water (% of Population) 2012 46,5 67,2 87,2 99,2Healthy life ex pectancy at birth (y ears) 2012 44,0 51,3 57 69Access to Sanitation (% of Population) 2012 31,4 38,8 56,9 96,2Percent. of Adults (aged 15-49) Liv ing w ith HIV/AIDS 2013 1,1 3,7 1,2 ...Incidence of Tuberculosis (per 100,000) 2013 326,0 246,0 149,0 22,0Child Immunization Against Tuberculosis (%) 2013 78,0 84,3 90,0 ...Child Immunization Against Measles (%) 2013 73,0 76,0 82,7 93,9Underw eight Children (% of children under 5 y ears) 2005-2013 24,2 20,9 17,0 0,9Daily Calorie Supply per Capita 2011 ... 2 618 2 335 3 503Public Ex penditure on Health (as % of GDP) 2013 1,9 2,7 3,1 7,3

Education Indicators

Gross Enrolment Ratio (%)

Primary School - Total 2011-2014 110,9 106,3 109,4 101,3 Primary School - Female 2011-2014 103,6 102,6 107,6 101,1 Secondary School - Total 2011-2014 43,3 54,3 69,0 100,2 Secondary School - Female 2011-2014 32,2 51,4 67,7 99,9Primary School Female Teaching Staff (% of Total) 2012-2014 25,5 45,1 58,1 81,6Adult literacy Rate - Total (%) 2006-2012 61,2 61,9 80,4 99,2Adult literacy Rate - Male (%) 2006-2012 76,9 70,2 85,9 99,3Adult literacy Rate - Female (%) 2006-2012 46,1 53,5 75,2 99,0Percentage of GDP Spent on Education 2009-2012 1,6 5,3 4,3 5,5

Environmental Indicators

Land Use (Arable Land as % of Total Land Area) 2012 3,1 8,8 11,8 9,2Agricultural Land (as % of land area) 2012 0,1 43,4 43,4 28,9Forest (As % of Land Area) 2012 67,7 22,1 28,3 34,9Per Capita CO2 Emissions (metric tons) 2012 0,0 1,1 3,0 11,6

Sources : AfDB Statistics Department Databases; World Bank: World Development Indicators; last update :

UNAIDS; UNSD; WHO, UNICEF, UNDP; Country Reports.

Note : n.a. : Not Applicable ; … : Data Not Available.

Congo, Dem. RepublicCOMPARATIVE SOCIO-ECONOMIC INDICATORS

novembre 2015

0

20

40

60

80

100

120

140

20

00

20

05

20

08

20

09

20

10

20

11

20

12

20

13

Infant Mortality Rate( Per 1000 )

Cong o, Dem. Republic Africa

0

500

1000

1500

2000

2500

20

00

20

05

20

07

20

08

20

09

20

10

20

11

20

12

20

13

GNI Per Capita US $

Cong o, Dem. Republic

0,0

0,5

1,0

1,5

2,0

2,5

3,0

3,5

20

00

20

05

20

08

20

09

20

10

20

11

20

12

20

13

20

14

Population Growth Rate (%)

Congo, Dem. Republic

Africa

01020304050607080

20

00

20

05

20

08

20

09

20

10

20

11

20

12

20

13

20

14

Life Expectancy at Birth (years)

Cong o, Dem. Republic

Africa

Page 30: AFRICAN DEVELOPMENT BANK GROUP · AFRICAN DEVELOPMENT BANK GROUP ... 2.7 Bank's Experience and Lessons Reflected in Project Design ... The Ruzizi III Hydropower Plant …

III

Annex 1(c)

Comparative Socio-Economic Indicators for Rwanda

Year Rwanda Africa

Develo-

ping

Countries

Develo-

ped

Countries

Basic Indicators

Area ( '000 Km²) 2014 26 30 067 80 386 53 939Total Population (millions) 2014 12,1 1 136,9 6,0 1,3Urban Population (% of Total) 2014 20,0 39,9 47,6 78,7Population Density (per Km²) 2014 459,4 37,8 73,3 24,3GNI per Capita (US $) 2013 630 2 310 4 168 39 812Labor Force Participation - Total (%) 2014 85,7 66,1 67,7 72,3Labor Force Participation - Female (%) 2014 52,3 42,8 52,9 65,1Gender -Related Dev elopment Index Value 2007-2013 0,950 0,801 0,506 0,792Human Dev elop. Index (Rank among 187 countries) 2013 151 ... ... ...Popul. Liv ing Below $ 1.25 a Day (% of Population)2008-2013 63,0 39,6 17,0 ...

Demographic Indicators

Population Grow th Rate - Total (%) 2014 2,7 2,5 1,3 0,4Population Grow th Rate - Urban (%) 2014 4,3 3,4 2,5 0,7Population < 15 y ears (%) 2014 42,1 40,8 28,2 17,0Population >= 65 y ears (%) 2014 2,4 3,5 6,3 16,3Dependency Ratio (%) 2014 84,7 62,4 54,3 50,4Sex Ratio (per 100 female) 2014 95,5 100,4 107,7 105,4Female Population 15-49 y ears (% of total population) 2014 25,2 24,0 26,0 23,0Life Ex pectancy at Birth - Total (y ears) 2014 64,5 59,6 69,2 79,3Life Ex pectancy at Birth - Female (y ears) 2014 66,2 60,7 71,2 82,3Crude Birth Rate (per 1,000) 2014 34,5 34,4 20,9 11,4Crude Death Rate (per 1,000) 2014 6,9 10,2 7,7 9,2Infant Mortality Rate (per 1,000) 2013 37,1 56,7 36,8 5,1Child Mortality Rate (per 1,000) 2013 52,0 84,0 50,2 6,1Total Fertility Rate (per w oman) 2014 4,4 4,6 2,6 1,7Maternal Mortality Rate (per 100,000) 2013 320,0 411,5 230,0 17,0Women Using Contraception (%) 2014 52,5 34,9 62,0 ...

Health & Nutrition Indicators

Phy sicians (per 100,000 people) 2004-2012 5,6 46,9 118,1 308,0Nurses (per 100,000 people)* 2004-2012 68,9 133,4 202,9 857,4Births attended by Trained Health Personnel (%) 2009-2012 69,0 50,6 67,7 ...Access to Safe Water (% of Population) 2012 70,7 67,2 87,2 99,2Healthy life ex pectancy at birth (y ears) 2012 55,0 51,3 57 69Access to Sanitation (% of Population) 2012 63,8 38,8 56,9 96,2Percent. of Adults (aged 15-49) Liv ing w ith HIV/AIDS 2013 2,9 3,7 1,2 ...Incidence of Tuberculosis (per 100,000) 2013 69,0 246,0 149,0 22,0Child Immunization Against Tuberculosis (%) 2013 99,0 84,3 90,0 ...Child Immunization Against Measles (%) 2013 97,0 76,0 82,7 93,9Underw eight Children (% of children under 5 y ears) 2005-2013 11,7 20,9 17,0 0,9Daily Calorie Supply per Capita 2011 2 148 2 618 2 335 3 503Public Ex penditure on Health (as % of GDP) 2013 6,5 2,7 3,1 7,3

Education Indicators

Gross Enrolment Ratio (%)

Primary School - Total 2011-2014 133,8 106,3 109,4 101,3 Primary School - Female 2011-2014 135,3 102,6 107,6 101,1 Secondary School - Total 2011-2014 32,6 54,3 69,0 100,2 Secondary School - Female 2011-2014 33,7 51,4 67,7 99,9Primary School Female Teaching Staff (% of Total) 2012-2014 53,1 45,1 58,1 81,6Adult literacy Rate - Total (%) 2006-2012 65,9 61,9 80,4 99,2Adult literacy Rate - Male (%) 2006-2012 71,1 70,2 85,9 99,3Adult literacy Rate - Female (%) 2006-2012 61,5 53,5 75,2 99,0Percentage of GDP Spent on Education 2009-2012 4,8 5,3 4,3 5,5

Environmental Indicators

Land Use (Arable Land as % of Total Land Area) 2012 47,9 8,8 11,8 9,2Agricultural Land (as % of land area) 2012 0,8 43,4 43,4 28,9Forest (As % of Land Area) 2012 18,4 22,1 28,3 34,9Per Capita CO2 Emissions (metric tons) 2012 0,1 1,1 3,0 11,6

Sources : AfDB Statistics Department Databases; World Bank: World Development Indicators; last update :

UNAIDS; UNSD; WHO, UNICEF, UNDP; Country Reports.

Note : n.a. : Not Applicable ; … : Data Not Available.

RwandaCOMPARATIVE SOCIO-ECONOMIC INDICATORS

novembre 2015

0

20

40

60

80

100

120

2000

2005

2008

2009

2010

2011

2012

2013

Infant Mortality Rate( Per 1000 )

Rwanda Africa

0

500

1000

1500

2000

2500

2000

2005

2007

2008

2009

2010

2011

2012

2013

GNI Per Capita US $

Rwanda Africa

0,0

1,0

2,0

3,0

4,0

5,0

6,0

7,0

8,0

2000

20

05

20

08

2009

20

10

20

11

2012

20

13

20

14

Population Growth Rate (%)

Rwanda Africa

01020304050607080

2000

20

05

20

08

2009

2010

20

11

20

12

20

13

2014

Life Expectancy at Birth (years)

Rwanda Africa

Page 31: AFRICAN DEVELOPMENT BANK GROUP · AFRICAN DEVELOPMENT BANK GROUP ... 2.7 Bank's Experience and Lessons Reflected in Project Design ... The Ruzizi III Hydropower Plant …

IV

Annex 2a: Status of Bank Group's Active Portfolio in Burundi as at 26 October 2015 National Project

Division Full Name Sector Name Window Approval

Date

Signature

Date

Net Loan Amount

Disbursed

Disb. Ratio Age

OITC2 THE NYAKARARO -MWARO-GITEGA ROAD (RN18)

IMPROVEMENT AND ASPHALTING PROJECT

Transport [ ADF ] 24Sep14 19Nov14 19,420,000 1,640,990 8.5% 1.1

OITC2 THE GITEGA-NYANG ROAD IMPROVEMENT AND

ASPHALTING PROJECT

Transport [ ADF ] 29Jun11 16Mar12 10,000,000 2,172,000 21.7% 4.3

OITC2 THE GITEGA-NYANG ROAD IMPROVEMENT AND ASPHALTING PROJECT

Transport [ ADF ] 29Jun11 16Mar12 32,000,000 26,832,000 83.9% 4.3

OITC2 MAKEBUKO RUYIGI ROAD PROJECT Transport [ ADF ] 18Dec13 18Feb14 8,940,000 787,614 8.8% 1.9

ONEC2 JIJI AND MULEMBWE HYDROPOWER PLANTS

DEVELOPMENT PROJECT

Power [ ADF ] 23Jun14 31Jul14 14,340,000 - 0.0% 1.4

ONEC2 MASTER PLAN STUDY OF ELECTRICITY

GENERATION, TRANSMISSION AND DISTRIBUTION

IN BURUNDI

Power [ ADF ] 30Apr14 14Aug14 414,000 - 0.0% 1.5

OSAN3 WATERSHED MANAGEMENT AND CLIMATE

RESILIENCE IMPROVEMENT PROJECT

Environment [OTHERS] 22Apr13 28May13 2,191,126 929,257 42.4% 2.5

Environment [ ADF ] 22Apr13 28May13 6,230,000 3,939,229 63.2% 2.5

OSGE2 PRIVATE SECTOR DEVELOPMENT SUPPORT

PROJECT (PADSP)

Multi-Sector [ ADF ] 09Nov12 01Mar13 884,730 393,801 44.5% 3.0

OSGE2 PUBLIC FINANCE MANAGEMENT CAPACITY

BUILDING PROJECT

Multi-Sector [ ADF ] 09Nov12 01Mar13 1,244,681 472,841 38.0% 3.0

OSHD1 CAPACITY BUILDING FOR COLLECTION OF DATA

ON LABOUR AND SOCIAL PROTECTION

Multi-Sector [ ADF ] 09Nov12 01Mar13 400,920 399,995 99.8% 3.0

OSHD1 INSTITUTION CAPACITY BUILIDING -EMPLOYMENT

AND ENTREPRENEURSHIP

Multi-Sector [ ADF ] 12Nov12 01Mar13 1,347,796 1,162,045 86.2% 3.0

97,413,253 38,729,771 40% 2.6

Regional Projects

Division Full Name Sector Name Window Approval

Date

Signature

Date

Net loan Amount

Disbursed

Disb. Ratio Age

OITC2 NYAMITANGA-RUHWA-NTENDEZI-MWITYAZO

ROAD PROJECT

Transport [ ADF ] 16Dec08 16Mar09 49,380,000 45,878,958 93% 6.9

OITC2 ISAKA-KIGA/KEZA-MUSONGATI RAILWAY PROJECT-PHASE 2

Transport [ ADF ] 17Nov09 12Feb10 1,670,000 1,240,977 74% 6.0

OITC2 BURUNDI- MUGI ROADS IMPROVEMENT AND

ASPHALTING PROJECT

Transport [ ADF ] 27Jun12 23Jul12 27,500,000 5,731,000 21% 3.3

OITC2 PROJECT PREPARATORY STUDY FOR

DEVELOPMENT OF BUJUMBURA PORT

Transport [OTHERS] 14Oct13 13Dec13 826,652 233,860 28% 2.0

ONEC2 NELSAP INTERCONNECTION PROJECT - BURUNDI Power [ ADF ] 27Nov08 16Mar09 15,150,000 1,818,000 12% 6.9

ONEC2 REGIONAL RUSUMO HYDROPOWER - BURUNDI Power [ ADF ] 27Nov13 18Feb14 16,700,000 93,520 1% 1.9

[OTHERS] 21Nov13 23Sep14 10,196,085 - 0% 1.9

OSAN1 BUGESERA INTEGRATED REGIONAL

DEVELOPMENT PROJECT

Agriculture [ ADF ] 25Sep09 04Nov09 15,020,000 8,062,736 54% 6.1

OWAS2 LAKE VICTORIA WATER AND SANITATION

PROGRAM

Water

Supply/Sanitation

[ ADF ] 17Dec10 04Apr11 14,000,000 700,000 5% 4.9

OSHD1 TECHNICAL ASSISTANCE AND CAPACITY BUILDING TO ICGLR (REGIONAL)

Multisector [ TSF] 15Jul13 08Nov13 1,485,048 579,428 39% 2.3

151,927,785 64,338,479 42% 4.2

Page 32: AFRICAN DEVELOPMENT BANK GROUP · AFRICAN DEVELOPMENT BANK GROUP ... 2.7 Bank's Experience and Lessons Reflected in Project Design ... The Ruzizi III Hydropower Plant …

V

Annex 2b Status of Bank Group's Active Portfolio in DRC as at 30 September 2015

Project Name SAP Code

Source of Financing.

Approval Date

Signature Date

Effectiveness Date

Closing Date

Approved

Amount in

MUA

Total

Disbursed

in MUA

%

Disburse

d.

% sect. Status

AGRICULTURE SECTOR 49.46 10.39 21.00% 7.06%

1 RURAL INFRASTRUCTURE DEVELOPMENT SUPPORT

P-CD-AB0-001 ADF grant 10/11/2011 20.01.2012 20.01.2012 31.12.2017 49.46 10.39 21.00% NPP/NPP

P

TRANSPORT AND ICT SECTOR 285.63 75.96 26.59% 40.75

%

2 PRIORITY AIR SAFETY PROJECT

P-CD-DA0-001 ADF grant 29/09/2010 02.11.2010 02.11.2010 31.12.2015 88.60 60.77 68.59% NPP/NPP

P

3 BATSHAMBA-TSHIKAPA ROAD REHABILITATION PROJECT

P-CD-DB0-002 ADF grant 13/06/2012 07.08.2012 07.08.2012 31.12.2017 53.55 15.19 28.36% NPP/NPP

P

4 BATSHAMBA ROAD- LOVUA SECTION- IMPROVEMENT PROJECT

P-CD-DB0-008 ADF grant 10/12/2013 07.01.2014 07.01.2014 31.12.2019 13.26 0.00 0.00% NPP/NPP

P

ADF loan 10/12/2013 07.01.2014

31.12.2019 0.66 0.00 0.00%

ADF grant 22/10/2014 26.03.2015 26.03.2015 31.12.2019 55.56 0.00 0.00%

5 PROJECT TO IMPROVE THE TSHIKAPA-MBUJI MAYI ROAD (TSHIKAPA-KAMUESHA SECTION) AND REHABILITATE RELATED

RURAL AND AGRICULTURAL INFRASTRUCTURE.

P-CD-DB0-009 ADF grant 17/12/2014 26.03.2015 26.03.2015 31/12/2019 74.00 0.00 0.00% NPP/NPP

P

WATER AND SANITATION SECTOR 106.26 1.26 1.19% 15.16

%

6

REINFORCEMENT OF SOCIO-ECONOMIC INFRASTRUCTURE IN THE

CENTRAL

REGION

P-CD-E00-002 ADF grant 27/11/2013 26.03.2015 26.03.2015 31.12.2019 43.53 0.98 2.26%

ADF loan 27/11/2013 26.03.2015

31.12.2019 1.47 0.00 0.00%

TSF Grant 27/11/2013 26.03.2015 26.03.2015 31.12.2019 55.00 0.21 0.39%

RWSSI 27/11/2013 26.03.2015 26.03.2015 31.12.2019 4.76 0.06 1.32%

7 FEASIBILITY STUDY ON THE EXPANSION OF DRINKING WATER SUPPLY SERVICES

TO WEST KINSHASA AWF 25/06/2015

31.12.2017 1,50 0.00 0.00%

PRIVATE SECTOR 42.72 17.72 41.48% 6.10%

8 NYUMBA CEMENT PLANT PROJECT

P-CD-B00-001 ADB loan 12/02/2014 27.11.2014

42.72 17.72 41.48% NPP/NPP

P

ENERGY SECTOR 105.39 36.09 34.2% 15.04

%

9 INGA HYDROPOWER REHAB. PROJECT-PMEDE P-CD-FA0-001 ADF grant 18/12/2007 10.04.2008 10.04.2008 30.06.2016 35.70 16.42 46.00% PPP

10 RURAL & PERIURBAN ELECTRIFICATION PROJECT

P-CD-FA0-003 TSF Grant 15/12/2010 10.03.2011 10.03.2011 31.12.2017 60.00 15.78 26.30% NPP/NPP

P

RURAL & PERIURBAN ELECTRIFICATION PROJECT P-CD-FA0-003 ADF grant 15/12/2010 10.03.2011 10.03.2011 31.05.2017 9.69 3.89 40.14%

11 ESTABLISHMENT OF INGA SITE DEVELOPMENT AND PROMOTION AUTHORITY

P-CD-FA0-005 TAS 17/04/2013 31.05.2013 31.05.2013 30.11.2016 1.99 0.00 0.00% NPP/NPP

P

Page 33: AFRICAN DEVELOPMENT BANK GROUP · AFRICAN DEVELOPMENT BANK GROUP ... 2.7 Bank's Experience and Lessons Reflected in Project Design ... The Ruzizi III Hydropower Plant …

VI

12 INGA3 DEVELOPMENT PROJECT -INGA/PATCD

P-CD-FA0-009 TAS 13/05/2013 31.05.2013 31.05.2013 30.11.2016 1.5 1.39 92.46% NPP/NPP

P

MULTISECTOR (GOVERNANCE) 80.50 21.13 26.2% 11.49

%

13 PUBLIC FINANCE MODERNIZATION SUPPORT PROJECT

P-CD-KF0-002 ADF grant 25/04/2010 29.05.2012 29.05.2012 31.12.2015 10.00 5.80 58.03% NPP/NPP

P

14 MOBILIZATION OF PUBLIC ADMINISTRATION HUMAN RESOURCES

P-CD-KZ0-004 ADF grant 21/01/2011 04.05.2011 05.05.2011 31.12.2015 20.00 13.83 69.14% NPP/NPP

P

15 STATISTICS AND PUBLIC FINANCE INSTITUTIONAL SUPPORT

P-CD-K00-009 ADF grant 23/10/2013 26.03.2015 26.03.2015 31.12.2016 10.96 1.23 11.26% NPP/NPP

P

16 BUILDING CAPACITY TO STEER REFORMS

P-CD-KF0-008 TAS grant 18/07/2013 06.11.2013 06.11.2013 30.06.2016 1.54 0.26 16.95% NPP/NPP

P

17 PRIVATE SECTOR DEVELOPMENT AND JOB CREATION SUPPORT PROJECT

P-CD-KB0-001 ADF grant 03/06/2015 05/08/2015 05/08/2015 30.06.2019 38.00 0.00 0.00%

SOCIAL 16.25 0.00 0.0% 2.32%

18 GENERAL POPULATION CENSUS AND SOCIAL DATABASES

CONSOLIDATION SUPPORT PROJECT P-CD-KF0-007 ADF grant 26/11/2014 28/05/2015 28/05/2015 31/12/2017 15.00 0.00 0.00%

19 SUPPORT FOR PREPARATION OF CWIQ SURVEY

P-CD-IZ0-005 TAS grant 22/06/2015 09/09/2015 09/09/2015 31/12/2015 1.25 0.00 0.00%

ENVIRONMENT 14.67 0.36 2.5%

20 REDD- KIS INTEGRATED PROJECT

P-CD-AAD-003 FIP 11/09/2013 15.08.2014 15.08.2014 31.07.2018 14.67 0.36 2.46% NPP/NPP

P

National Operations 700.87 162.90 23.24%

EMERGENCY ASSISTANCE 1.34 1.34 100.0% 0.19%

1 EMERGENCY ASSISTANCE TO DISPLACED PEOPLE IN KATANGA

PROVINCE P-CD-AA0-005 SRF 20/02/2014 20/08/2014 20/08/2014 30.06.2015 0.67 0.67 100.0%

2 EMERGENCY ASSISTANCE FOR THE FIGHT AGAINST EBOLA P-CD-IBE-001 SRF 22/09/2014

30/09/2015 0.67 0.67 100.0%

CONGO BASIN FOREST FUND (CBFF) 23.31 13.92 59.7%

1 SANKURU FAIR TRADE CARBON INITIATIVE P-Z1-C00-021 CBFF 07/04/2010 14.02.2011 10.03.2011 31.12.2015 1.05 0.95 90.14% PPP

2 CONSERVATION INTERNATIONALE FOUNDATION P-Z1-C00-025 CBFF 09/06/2010 26.07.2001 10.11.2011 30.09.2015 1.07 0.45 42.36% PPP

3 ECOMAKALA

P-Z1-C00-026 CBFF 12/07/2011 31.08.2011 31.08.2011 30.06.2016 1.98 1.05 53.01% NPP/NPP

P

4 SOUTH KWAMOUTH REDD AGROFORESTRY PILOT PROJECT

P-Z1-C00-027 CBFF 12/07/2011 31.08.2011 31.08.2011 30.09.2016 1.98 1.77 89.40% NPP/NPP

P

5 ISANGI REDD PILOT PROJECT

P-Z1-C00-028 CBFF 19/05/2011 08.06.2011 17.08.2011 30.06.2016 1.83 1.57 85.91% NPP/NPP

P

6 CIVIL SOCIETY AND GOVERNANCE CAPACITY BUILDING

P-Z1-C00-029 CBFF 13/07/2011 31.08.2011 15.10.2011 30.09.2016 2.54 0.94 37.04% NPP/NPP

P

7 LUKI REDD PROJECT

P-Z1-C00-031 CBFF 22/07/2011 31.08.2011 31.08.2011 31.12.2016 1.86 1.05 56.70% NPP/NPP

P

Page 34: AFRICAN DEVELOPMENT BANK GROUP · AFRICAN DEVELOPMENT BANK GROUP ... 2.7 Bank's Experience and Lessons Reflected in Project Design ... The Ruzizi III Hydropower Plant …

VII

8 MAMBASA REDD PROJECT

P-Z1-C00-032 CBFF 27/04/2011 08.06.2011 17.08.2011 30.06.2016 2.35 1.89 80.60% NPP/NPP

P

9 VAMPEEN VALORIZATION OF AFRICAN MEDICINE

P-Z1-C00-043 CBFF 16/11/2011 09.12.2011 30.12.2011 30.06.2016 1.25 0.99 78.50% NPP/NPP

P

10 AGROFORESTRY DEVELOPMENT SUPPORT P-CD-C00-035 CBFF 02/04/2012 12.06.2012 30.08.2012 31.12.2015 5.30 3.25 61.29% PPP

11 PROJECT TO REDUCE DEFORESTATION AND ALLEVIATE POVERTY

IN THE VIRUNGA-HOYO REGION P-CD-C00-037 CBFF 28/11/2014 17.04.2015

31.12.2017 2.10 0.00 0.00%

NPP/NPP

P

MULTINATIONAL 89.56 8.70 9.7%

1

STUDY ON THE ROAD-RAIL BRIDGE BETWEEN KINSHASA (DRC)

AND BRAZZAVILLE (CONGO) P-Z1-D00-016

ADF grant 03/12/2008 13.05.2009 13.05.2009 31.12.2015 3.59 1.86 51.77% NPP/NPP

P

2 STUDY ON THE EXTENSION OF THE KINSHASA-ILEBO RAILWAY P-Z1-DC0-014 IPPF grant 15/07/2012 13.08.2012 13.08.2012 30.06.2015 0.71 0.30 42.61%

3

STUDY ON THE OUSSO-BANGUI-NDJAMENA ROAD AND RIVER

NAVIGATION P-Z1-D00-066

ADF grant 01/12/2010 29.04.2011 29.04.2011 30.11.2016 0.44 0.06 12.79% NPP/NPP

P

4 NELSAP INTERCONNECTION PROJECT - DRC P-Z1-FA0-035 ADF grant 27/11/2008 28.05.2010 28.05.2010 31.12.2016 27.62 2.16 7.81% PPP

5 INTERCONNECTION OF BOALI ELECTRIC POWER GRIDS P-Z1-FA0-047 ADF grant 19/09/2012 20.02.2013 20.02.2013 31.12.2017 5.55 0.08 1.39%

6

INGA SITE DEVELOPMENT AND ELECTRICITY ACCESS SUPPORT PROJECT

P-Z1-FA0-045 ADF grant 20/11/2013 07.01.2014 07.01.2014 31.12.2019 39.40 2.14 5.44%

TAS grant

5.00 2.11 42.17%

7

STUDY ON EXTENSION OF NORTH KIVU 220KV TRANSMISSION

LINES P-Z1-FAD-005

IPPF grant 07/06/2013 20.10.2014 20.10.2014 30.06.2015 1.25 0.00 0.00%

8 LAKE EDWARD AND ALBERT INTEGRATED FISHERIES AND WATER RESOURCES MANAGEMENT (LEAF II)*

P-Z1-AF0-006 ADF grant 20/06/2015

31.12.2019 6.00 0.00 0.00%

GRAND TOTAL 815.08 186.87 22.93%

Page 35: AFRICAN DEVELOPMENT BANK GROUP · AFRICAN DEVELOPMENT BANK GROUP ... 2.7 Bank's Experience and Lessons Reflected in Project Design ... The Ruzizi III Hydropower Plant …

VIII

Annex 2c Status of Bank Group's Active Portfolio in Rwanda as at 03 September 2013

PROJECT Window Total approved Date Approved Closing Date Amt. disb. Disb.

rate

Undisbursed

amount

AGRICULTURE

1 Livestock Infrastructure Support Programme-LISP (SBS) ADF loan 21,810,000 29-Jun-11 31-Dec-15 21,810,000 100.0% 0

WATER

2 Rural Water and Sanitation-Phase II (AEPA) ADF Grant (UA10 M) 10,000,000 1-Jul-09 31-Aug-15 9,955,960 99.6% 44,040

Rural Water and Sanitation-Phase II (AEPA) RWSSI ( EURO 6.960 M ) 6,127,084 1-Jul-09 31-Aug-15 6,127,080 100.0% 4

Sub-total Water 16,127,084 16,083,040 99.7% 44,044

TRANSPORT

3 Base Nyagatare 49,000,000

Sub Total Transport

ENERGY

3 Scaling Up Energy Access Project ADF Grant 11,871,000 596,293 5.0%

Scaling Up Energy Access Project ADF Loan 15,494,000 0 0.0%

SUB-TOTAL INFRASTRUCTURE 92,492,084 16,083,040 17.4% 76,409,044

HUMAN DEVELOPMENT

4 Support to Skills Dev in Science & Tech ADF loan 6,000,000 11-Nov-08 31-Dec-13 2,596,832 43.3% 3,403,168

5 Regional ICT Centre of Excellence 8,600,000 14-Dec-10 30-Jun-16 589,874 6.9% 8,010,126

SUB-TOTAL HUMAN DEV 14,600,000 3,186,706 21.8% 11,413,294

6 Support to EICV-4 ADF Grant 820,000 18-Sep-09 30-Sep-13 590,194 72.0% 229,806

EAC-CoE 12,000,000

7 SEEP II ADF Loan 34,000,000 34,000,000 100.0% 0

8 Support to the Energy Sector (FAPA) FAPA Grant 800,000 30-Nov-13 16-Dec-15 168,571 21.1% 631,429

SUB-TOTAL MULTI-SECTOR 47,620,000 34,758,765 73.0% 12,861,235

Total National Operations - Public 176,522,084 75,838,511 43.0% 100,683,573

PRIVATE SECTOR

9 KivuWatt ADB loan (UA5.3M& FAPA Grant UA 491,834) 15,892,693 3-Feb-11 NA 15,892,693 100.0% 0

10 BRD (LOC & FAPA) ADB loan (UA7.6& FAPA Grant UA 246,799) 7,600,000 19-Nov-10 NA 7,600,000 100.0% 0

11 BRD FAPA) FAPA Grant 480,789 1-Nov-11 31-03-2016 82,237 17.1% 398,553

12 BK (ADF) ADF Loan 12,000,000 19-Nov-10 NA 12,000,000 100.0% 0

BK (FAPA) FAPA Grant 547,200 1-Nov-11 NA 220,296 40.3% 326,904

Sub-TOTAL PRIVATE SECTOR 36,520,682 35,574,930 97.4% 725,457

Total National Operations - Public + Private 213,042,766 111,413,440 52.3% 101,629,326

MULTINATIONAL

13 Isaka-Kigali Railway Study (Phase 2) ADF grant 1,670,000 17-Nov-09 31-Dec-15 1,250,927 74.9% 419,073

14 Rwanda-(Nyamitanga-Ruhwa-Ntendezi-Mwityazo Rd) ADF grant 50,620,000 16-Dec-08 30-Jun-16 34,521,036 68.2% 16,098,964

15 Regional Rusumo Falls 25,384,000 0.0%

NELSAP NBI ADF grant 1,210,000 27-Nov-08 31-Dec-16 1,191,536 98.5%

16 NELSAP Interconnection ADF grant 30,470,000 27-Nov-08 31-Dec-16 21,264,666 69.8% 9,205,334

17 Bugesera Multinational Project ADF loan 14,980,000 25-Sep-09 31-Dec-17 9,010,492 60.2% 5,969,508

18 Rubavu-Gisiza Road Project ADF loan (UA40.525) & ADF grant (UA4.525) 40,050,000 25-Jul-12 31-Dec-17 5,932,906 14.8% 34,117,094

Rubavu-Gisiza Road Project 4,525,000 25-Jul-12 31-Dec-17 312,320 6.9% 4,212,680

19 Sustainable management of woodlands and restoration of natural forests

of Rwanda ADF grant 4,015,424 29-Nov-11 31-May-14 1,590,083 39.6% 2,425,341

20 Lake Victoria Water and Sanitation Programme ADF grant 15,110,000 17-Feb-10 31-Dec-15 8,316,224 55.0% 6,793,776

21 Payment and Settlement Systems Integration Project ADF grant 3,690,000 5-Dec-12 1-Jun-17 - 0.0% 3,690,000

SUB-TOTAL MULTINATIONAL 191,724,424 92,400,682 48.2% 82,931,770

GRAND TOTAL 404,767,190 203,814,123 50.4% 184,561,096

Page 36: AFRICAN DEVELOPMENT BANK GROUP · AFRICAN DEVELOPMENT BANK GROUP ... 2.7 Bank's Experience and Lessons Reflected in Project Design ... The Ruzizi III Hydropower Plant …

IX

Annex 3 - Development Partners' Operations in the Electricity Sub-Sector in the Great

Lakes Countries

DONORS PROGRAMME OR PROJECT AMOUNT

ADB Kamanyola (RDC) – Bujumbura 220KV

Interconnection Line UA 15.15 million

ADB/WB/EU Master Plan for the Transmission and

Distribution of Affordable Electrical Energy in

Burundi (Burundi)

UA 2 million

EU/WB/ADB/EIB Jiji Mulembwe Hydropower Plant (Burundi) UA 172.22 million

CHINA Ruzibazi Hydropower Plant in Burundi (17MW) USD 60 million

EXIM INDIA Kabu 16 Hydropower Plant in Burundi (20 MW) USD 80 million

EU/KFW Ruzizi II Rehabilitation- Regional Project EUR 76 million

EU/WB/ADB Rusumo Falls Hydropower Plant UA 305.5 million

EU/KFW Rwanda, DRC, Burundi Interconnection –

Regional Project EUR 15.8 million

ADB, KFW, EU,

JICA

NELSAP Interconnection Project connecting

Burundi, DRC, Kenya, Rwanda and Uganda

(Bank contribution is 30.47MUA

EUR 317.6 million

ADB Scaling-up Energy Access Project UA 30 million

ADB KIVUWATT (Bank contribution is 25MUSD) UA 184 million

WB Regional and Domestic Power Markets

Development Project (PMEDE)

Southern African Power Market Project

(SAPMP)

USD 937,000,000

KfW - Project for the Rehabilitation and

Strengthening of the Inga Hydropower

Stations and Kinshasa Distribution Grid (Inga II

generator 27)

- Kamanyola Substation Project under the

Ruzizi III Project

Financing being

prepared

EIB - Southern African Power Market Project

(SAPMP)

- Project for the Rehabilitation of the Inga

Hydropower Plants and Kinshasa Distribution

Grid (PMEDE)

EUR 110,000,000

Belgian Technical

Cooperation - Rehabilitation of the Tshopo Hydropower

Plant and Kisangani Distribution Grid EUR 13,500,000

Chinese

Cooperation - Construction of Zongo II Hydropower Plant

(150 MW) EUR 360,000,000

Netherlands

Cooperation

- Project for Consolidating the Interconnection of

the Electric Grids of Nile Equatorial Lakes

Countries

10,000,000

Page 37: AFRICAN DEVELOPMENT BANK GROUP · AFRICAN DEVELOPMENT BANK GROUP ... 2.7 Bank's Experience and Lessons Reflected in Project Design ... The Ruzizi III Hydropower Plant …

X

Annex 4

Map of Project Area

This map has been provided by the staff of the African Development Bank exclusively for the

use of the readers of the report to which it is attached. The names used and the borders shown

do not imply on the part of the Bank Group and its members any judgment concerning the

legal status of a territory nor any approval or acceptance of these borders.

Page 38: AFRICAN DEVELOPMENT BANK GROUP · AFRICAN DEVELOPMENT BANK GROUP ... 2.7 Bank's Experience and Lessons Reflected in Project Design ... The Ruzizi III Hydropower Plant …

XI

ANNEX 5

On-lending of ADF Resources to the Project Company and Impact on the Project

The Bank's existing policy on the on-lending of loans:

1) The basic principle relating to the on-lending of resources allocated by the Bank is to meet

market conditions as closely as possible (paragraph 21);

2) In particular, in the case of ADF resources, which will be on-lent under this project,

paragraphs 29 and 30 of the Policy stipulate that ADF concessional resources may be on-

lent to take into account certain factors or specific situations;

3) The on-lending policy completes these provisions by point (viii) on page 12, which raises

the specific case of companies operating in the basic infrastructure sector.

This Ruzizi III project concerns basic infrastructure and has a strong social dimension due to the

transformational nature of energy on the population's living conditions. The availability of energy in the

Great Lakes Region confronted by armed conflict for over a decade, may contribute to the restoration of

peace through the development of highly remunerative activities. It is also necessary to facilitate access

to this energy from both technically and in terms of price. The issue of pricing has been raised by all the

national electricity companies which, as signatories of the future power purchase contracts, are seriously

concerned about the sustainability of the operation for them. The simulations carried out by EGL and the

future private partner have confirmed the significant impact of on-lending concessional resources to the

Project Company (PC). As an illustration, the on-lending of concessional resources to the PC at a rate of

2% could reduce the cost of energy from USD/kWh 0.19 to USD/kWh 0.11. These cost levels are

sustainable for electricity companies given their energy mix, and should lead to the emergence of more

affordable prices for households and the economy in general.

Therefore, this project comes under the category of projects for which the on-lending of ADF resources

to a non-State entity directly benefits the population and national economies, especially for two

countries in transition.

Financing Plan:

Page 39: AFRICAN DEVELOPMENT BANK GROUP · AFRICAN DEVELOPMENT BANK GROUP ... 2.7 Bank's Experience and Lessons Reflected in Project Design ... The Ruzizi III Hydropower Plant …

XII

ANNEX 6: Factors of Fragility Addressed by the Project

The matrix below, which provides a summary of the fragility assessment presented in the technical

annexes, shows how the project takes into consideration the following factors of fragility identified at

appraisal: (i) the volatility of the security situation and political instability; (ii) the different forms of

social exclusion: identity crisis, ethnic divides and land tenure conflicts; (iii) weak water resource

governance capacity; (iv) gender-based violence; (v) extreme poverty and unemployment especially

among young people; and (vi) EGL's weak institutional capacity.

Factors of

Fragility

Situations of Fragility Measures Project's Planned Activities

Volatility of

the security

situation and

political

instability

Because of the

regionalization of the

conflicts in Great Lakes, the

political context of the

2015-2017 period marked

by tension due to the

electoral process does not

preclude further implosions

in the short-to-medium

term, which could affect the

project.

Obtain information

regularly on the political

situations and include

political risk in the

project's monitoring and

evaluation system.

The project is an important instrument for

dialogue in the political and security

stabilization process in the Great Lakes region.

This aspect is strengthened by the strategic

nature of the sector covered by the project

(Energy) and also by its multi-donor nature.

The project has made provision for a

monitoring/evaluation expert who will

establish a mechanism that takes into account

the monitoring of security and political risks.

The different

forms of social

exclusion:

identity crisis,

ethnic divides

and land

tenure

conflicts

The Great Lakes region in

general, and the zone

covered by Burundi,

Rwanda and DRC, in

particular, is characterized

by different forms of social

exclusion and inequalities

marked by ethnic divides,

identity crises and land

tenure conflicts that

represent real sources of

recurring tension.

Develop a resettlement

plan which does not

exacerbate existing social

exclusions but helps to

reduce them.

A resettlement action plan was prepared in

2012. It will be updated by the Project

Company (PC) before the launching of bidding

for the EPC contracts in compliance with the

Bank's requirements. The update will take into

account the analysis on the different forms of

social exclusion, and will implement measures

not to exacerbate them but instead reduce

them.

Weak water

resource

governance

capacity

Construction of the project

dam could create conflicts

between the use of water

for energy and for

agricultural purposes. The

hydropower release

schedule is not necessarily

the same as that for water

for agricultural purposes.

Such competition between

users could occur within

each country or at regional

level in the three countries.

Prepare a water resource

governance strategy which

factors in the need to

develop the agriculture

sector in the project area.

To mitigate the negative impacts of the

project, including those concerning water

management, contractors will be required to

submit comprehensive specific environmental

and social management plans based on the

Project ESMP and the PC Environmental and

Social Management System.

Gender-based

violence

The Great Lakes region is

one of the areas with the

highest cases of gender-

based violence or

discrimination.

In the project, include

related activities

concerning women's

empowerment and the

combat against gender-

based violence and

discrimination.

The project includes activities with positive

impacts on women, girls and children: (i) the

emergence or strengthening of income-

generating activities (IGA) for women; (ii) the

creation of works-related direct and indirect

jobs with at least 20% of the unskilled jobs for

women and girls; and (iii) promotion of

artisanal agricultural produce processing

activities mainly carried out by women.

Page 40: AFRICAN DEVELOPMENT BANK GROUP · AFRICAN DEVELOPMENT BANK GROUP ... 2.7 Bank's Experience and Lessons Reflected in Project Design ... The Ruzizi III Hydropower Plant …

XIII

Extreme

poverty and

unemployment

especially

among young

people

Extreme poverty and youth

unemployment are

generally considered to be

the key factors of structural

violence and conflict in the

region, and specifically in

the border zone shared by

DRC, Rwanda and Burundi.

Develop an electricity

price-fixing policy that

will maintain social

balances and reduce

exclusion in access to

energy. Also ensure that

the project will contribute

to job creation especially

for young people.

The project makes provision for a Plan to

Restore and Strengthen Living Conditions

(PRRV) as well as a Local Development Plan

(PDLC). The project also aims to improve

household access rate to electricity and to

create 800 to 1000 permanent and temporary

direct and indirect jobs in favour of local

labour.

EGL's weak

institutional

capacity

EGL, which will be

responsible for the project's

implementation, is

experiencing serious

operational difficulties

which prevent it from

securing adequate human

resources.

Provide for specific

support to EGL to build its

project implementation

capacity.

The institutional capacity building activities

planned under the project concern the

recruitment of international consultants for

technical assistance to EGL but also an

adequate skills mix among EGL key staff

members.