Page 1
AFRICAN DEVELOPMENT BANK
NIGER
DEVELOPMENT AND IMPLEMENTATION OF THE NATIONAL ACTION
PLAN FOR INTEGRATED WATER RESOURCES MANAGEMENT
(PANGIRE) OF NIGER
PROJECT COMPLETION REPORT
(PCR)
RDGW/AWTF/AHWS
March 2019
Translated document
Pu
blic
Dis
clo
sure
au
tho
rize
d
Pu
blic
Dis
clo
sure
au
tho
rize
d
Page 2
1
A Report data
Report date
Date of report: September 2018
Mission date (if field mission) From: 13/08/18
B Responsible Bank staff
Positions At approval At completion
Regional Director Franck J.M. PERRAULT Marie-Laure AKIN-OLUGBADE
Sector Director Mohamed ELAZIZI Gladys Wambui GICHURI
Sector Manager Akissa BAHRI Jean Michel OSSETE
Task Manager Jean Michel OSSETE Ousseynou GUENE
Alternate Task Manager
PCR Team Leader Ousseynou GUENE
PCR Team Members Francis Daniel BOUGAIRE, Adolphe
TITIKPEU
C Project data
Project name: Development and Implementation of the National Action Plan for Integrated Water Resources
Management (PANGIRE) of Niger
Project code: P-NE-EAZ-004 Grant No.: 5600155003602
Project type: Institutional support Sector : Water
Country : Niger Environmental category (1-3): 3
Processing milestones (grant) Key events (grant) Disbursement and closing dates (grant)
Date approved: 20 December 2013 Cancelled amounts: Nil Date of 1st disbursement: July 2014
Date signed: 16 April 2014 Supplementary financing:
Swiss-Luxembourg Coop:
(CFAF 252 600 000)
DANIDA (CFAF 220 000 000),
OXFAM-GB: (CFAF 60 000 000)
Government of Niger: CFAF 249 919 617
Original closing date: 31 October 2016
Date of entry into force: 12 June 2014 Restructuring (specify date & amount
involved): -
Revised (if applicable) closing
disbursement date: 30 November 2018
Date effective for 1st disbursement:
July 2014
Extensions (last disbursement): 30/11/18 Revised (if applicable) closing date: 30
November 2018
Date of actual 1st disbursement: July
2014
Financing source (Euros):
Committed amount
(Euros):
Percentage
Committed
(%):
Uncommitted
amount (Euros):
Percentage
uncommitted
(%)::
AWF 876 650.77 88 121 349 12
I BASIC DATA
PROJECT COMPLETION REPORT (PCR) FOR PUBLIC SECTOR OPERATIONS
AFRICAN DEVELOPMENT BANK GROUP
DEVELOPPEMENT
Page 3
2
DANIDA 335 388 100 0 0
Swiss-LUX DEV Coop* 385 082 100 0 0
OXFAM* 91469 100 0 0
Government of Niger 381000 100 0 0
TOTAL 2 069 589.77 98 121 349 12
Financing source(UA): Disbursed amount
(amount, Euros ):: Percentage
disbursed (%):
Undisbursed
amount (Euros):
Percentage
undisbursed
(%):
AWF 876 650.77 88 121 349 12
DANIDA-LUX DEV* 335 388 100 0 0
Swiss-Lux DEV Cooperation 385 082 100 0 0
OXFAM* 91 469 100 0 0
Government of Niger 381 000 100 0 0
TOTAL 2 069 589.77 98 121 349 12
Co-financiers and other external partners: DANIDA-Lux Dev and OXFAM
Executing and implementing agency: Ministry of Water and Sanitation through the PANGIRE Management Unit
D Management review and comments
Report reviewed by Name Date reviewed Comments
Peer Review
Division Manager
Sector Director
Resident Representative
Regional Director
Page 4
3
II Project performance assessment
A Relevance
1. Relevance of project development objective
Rating* Narrative assessment (max 250 words)
4 The development objective of the project is to improve the country's socio-economic situation and reduce
the incidence of poverty through sustainable management and rational use of Niger's water resources.
This development objective was defined on the basis of the Government’s vision to reduce the country’s
poverty threshold from 50% in 2012 to 40% by 2025. The project is consistent with Niger’s various
strategy papers and programmes: the Poverty Reduction Strategy Paper (PRSP 2008-2012), particularly
its focus area No.2 relating to the development of productive sectors and job and income creation, the
Water and Sanitation Sector Policy and Strategy Paper (2000), the Rural Development Strategy (SDR
2011-2015), Economic and Social Development Plan (PDES 2012-2015), the National Environmental
Plan for Sustainable Development (PNEDD 1998), and the various instruments of the water and
sanitation sector, namely: the Water Code, the National Water and Sanitation Commission and the
Regional Water and Sanitation Commission (CNEA and CREA 2006), and the 2007 instrument relating
to the establishment of the Ministry of Water and Sanitation (MHA) and the implementation of water
policy in 2013.
The project is aligned with the first Millennium Development Goal (MDG 1) which aims to reduce
extreme poverty and hunger. It is also aligned with the Government’s 3N strategy, and the various
sustainable development goals (SDGs).
The project is fully in line with the shared vision and the Sustainable Development Action Plan (PADD)
of the Niger River Basin adopted in 2007 and updated in 2012, the Water Resources Policy in West
Africa (ECOWAS), developed in collaboration with WAEMU and CILSS (2008), the Regional Strategic
Plan for Concerted Management of Water and Land Resources of the Lake Chad Basin, adopted in 1998
and revised in 2008, the AfDB's 2013-2022 Long-Term Strategy which seeks to achieve inclusive
growth and transition to green growth.
The project is also consistent with the African Water Vision 2025 and the Regional Plan of Action
(PARGIRE/WA, 2000), the World Water Fora, the goals of the World Summit on Sustainable
Development, which was held in Johannesburg in 2002 and focused on the development of integrated
plans for the management and rational use of water resources to accelerate economic and social
development. The project helps to effectively combat poverty stemming from the effects of climate
change and to boost the climate resilience of water sector development operations.
In term of the relevance of its development objective, the project remains fully aligned with the various
strategies outlined above
For all ratings in the PCR use the following scale: 4 (Highly satisfactory), 3 (Satisfactory), 2 (Unsatisfactory), 1 (Highly unsatisfactory)
Page 5
4
2. Relevance of project design
Rating* Narrative assessment (max 250 words)
3 The project consists in developing PANGIRE and its investment programme, as well as the Priority
Investment Programme (PIP). The project contributes to addressing the challenges pertaining to the
sustainable management of the country's water resources. The project prepares investment projects in
the water sector. The technical activities are accompanied by capacity building. All these activities
should lead to sustainable socio-economic development, while enabling the achievement of the
objectives of PANGIRE. The diagnosis led to the development of PANGIRE from which the Priority
Investment Plan (PIP) was drawn. The implementation mechanism, in particular the institutional
framework (the Project Management Unit (PMU), attached to the Directorate of Water Resources (DRE)
of the Directorate General of Hydraulics (DGH) at the Ministry of Water and Sanitation (MHA), as well
as the multi-stakeholder and interinstitutional Steering Committee), the procurement arrangements (in
line with the Bank's current provisions), and the monitoring and evaluation system are relevant.
However, reducing Niger’s poverty threshold by 10 percentage points between 2012 and 2025, as
estimated at project design, was deemed too optimistic.
3. Lessons learned related to relevance
B Effectiveness
1. Progress towards the project’s development objective (project purpose)
Comments
The project's development objective is to help reduce poverty reduction, particularly from a threshold of 50% in 2012
to 40% by 2025. The project will not make it possible to achieve this rate by 2025, given the failure to mobilize financing
for PANGIRE at the round table of the Economic and Social Development Plan (PDES) that was organized in place of
the originally planned PANGIRE donors’ roundtable. This delayed the implementation of PANGIRE activities. Even
though financing was secured and the infrastructure built, this project’s outcomes may not achieve the goal of reducing
the poverty threshold by 10 percentage points, from 50% in 2012 to 40%, by 2025. Other factors and projects may help
achieve this goal.
All the products of components 1 and 2 were achieved. Important project documents, including the document on
PANGIRE and the one on PIP, have been produced and approved. These flagship products of the project are available.
Regarding component 3, the project completion report is yet to be produced, but will be at the end of the project. Only
the financing for PANGIRE projects is still to be mobilised. Once the documents are produced and approved, the
Government can at any time seek financingfinancing from the main development partners.
Key issues (max 5, add rows as needed)
Lessons learned Target audience
1. Project’s alignment with the
country strategy
1. The project is fully aligned with the water and
sanitation sector strategy developed by Niger’s authorities,
the IWRM strategy and its adoption, and addresses the
country's needs with respect to the effects of climate
change. It is an indispensable element for ownership of the
outcomes by the authorities and the donors.
1. The technical
services of the
MHA, the people
of Niger
Page 6
5
2. Outcome reporting
Outcome indicators (as
per RLF; add more rows as
needed)
Baseline
value (2013)
Most recent value
(A)
End target (B)
(expected value at
project completion)
Progress
towards
target (% realized)
[A/B) ]
Narrative assessment (indicative max length: 50 words per outcome)
Core
Sector
Indicator (Yes/No)
Indicator 1:
The sector-based and
cross-cutting
programmes developed
are in line with IWRM
principles.
0
programme
60% 60% of sector-
based and cross-
cutting
programmes at
end-2016
100
Three sector-based programming documents are
adopted by the Government and available at the
PMU: PROSEHA and PANGIRE (09/05/2017) and
SOPHAB 1/07/2014. Preparation of the Water
Development and Management Master Plan
(SDAGE) and installation of IWRM bodies at the
sub-basin level are still to be done.
Yes
Indicator 2:
Rate of mobilization of
financingfinancing for
the implementation of
PANGIRE
0
programme
1% 80% of the
financing
mobilized in
2016
0.01 Priority Investment Plan (PIP) developed, validated
and made available in May 2017 for a total of CFAF
74.36 billion to be mobilized for 40 projects over the
2017-2030 period. The portion of financingfinancing
actually mobilised is very small: Swiss Cooperation:
CFAF 333 million, MCF-PROSEHA CFAF 40
million for 2018; CFAF 150 million for 2019.
Nothing has yet been mobilised from PIDEC /AfDB,
EU, WB, OXFAM, Mercy Corp, and MCC Compact
1. These donors have shown interest in financing the
PANGIRE.
The mobilisation rate is 0.07%, which is very low.
The total PDES budget is CFAF 6,300 billion, while
PANGIRE's share stands at CFAF 74.36 billion or
0.01% of the PDES allocation.
Yes
RATING
All important documents, including the three sector-based programming documents, have been adopted by the Government and are available.
These documents are of great importance and may be used at any time by the Government to seek financingfinancing for activities. Out of a total
of two targets, one has been fully achieved (at 100%), while the other is well below 1%. The financing is not yet secured. With the PIP document,
the Government can at any time seek the necessary financing.
The outcomes are rated at 3.
3
Page 7
6
3. Output reporting
Outcome indicators (as per
RLF; add more rows as needed) Most recent value
(B)
End target (B)
(expected value at project completion Progress
towards
target (% realized)
(A/B)
Narrative assessment (indicative max length: 50 words per outcome)
Core
Sector
Indicator (Yes/No)
Component 1: Development of PANGIRE
Indicator 1:
Number of documents
adopted relating to the
conceptual and
methodological
framework
1 document
developed and
approved
1 document produced in 2014 100%
All documents are developed and approved in a
participatory manner. PANGIRE and PIP,
financingfinancing mobilization strategy,
communication and monitoring and evaluation
system. The monitoring and evaluation system was
adopted at the end and not at the start of the
project.
Yes
Indicator 2:
Number of awareness
meetings held, number
of training
workshops/seminars
3 sharing and
feedback
workshops,
5 awareness meetings in 2014, 6 in
2015, 1 in 2016 (0 in 2013)
- 2 training workshops/seminars in
2014, 1 in 2015 and 1 in 2016 (0 in
2013)
100% Reports of the various workshops available
PANGIRE and PIP, three sharing and feedback
workshops relating to the three strategy papers
(mobilisation of financingfinancing,
communication, monitoring and evaluation)
-One feedback workshop was organized
The PMU grouped awareness meetings into the
sharing and feedback workshops, and the training
seminar on feedback workshops
Yes
Indicator 3: Number of
reports on the status of
water resources, number
of thematic studies
carried out
- 1 report on the
status of water
resources,
-6 thematic studies
carried out
1 report on the status water resources
produced in 2014 (0 in 2013)
- 6 thematic studies carried out in
2014 (0 in 2013)
100% 1 report on the status of water resources is available
-6 thematic reports are available
-a study on the status of water resources was carried
out (started in 2014 and completed in 2016)
Yes
Page 8
7
Indicator 4:
Number of SESA
reports, number of
Environmental and
Social Management
Framework (ESMF)
reports produced;
number of documents
produced relating to
PANGIRE and its
implementation
1
- 1 SESA report produced in 2014 (0
in 2013)
-1 ESMF report produced in 2014 (0
in 2013)
100% The various validated documents are available
1 SESA report accompanied by the Environmental
and Social Management Framework (ESMF)
produced and validated
Yes
Indicator 5
Number of documents
produced relating to
PANGIRE and its
implementation
1 1 document relating to PANGIRE
and its implementation produced in
2015
100% The PANGIRE document and its annexes are
available
The PANGIRE document was approved in a
participatory manner involving all IWRM
stakeholders of Niger in 2017
Yes
Output indicators (as
specified in the RLF; add more rows as needed)
Most recent value
(A)
End target (B)
(expected value at project completion)
Progress
towards target (% realized)
(A/B)
Narrative assessment (indicative max length: 50 words per output)
Core
Sector
Indicator (Yes/No)
Component 2: Development of the investment programme (PANGIRE and PIP)
Indicator 1:
Number of investment
programme document
produced
1 1 investment
programme document
produced in 2015 (0
in 2013
100% Document available
The PIP document is produced and validated in 2017
Yes
Indicator 2:
Number of reports on the
preliminary technical
evaluation of 10
sites/projects prepared
15 1 technical report on
the preliminary
technical evaluation
of 10 sites/projects
produced in 2015 (0
in 2013)
150% Report available
15 reports on evaluated project sites available
Yes
Page 9
8
Indicator 3:
Number of preliminary
design (PD) reports
prepared on priority
infrastructure projects
8 5 PD reports prepared
in 2016 (0 in 2013) 160% PD documents available
Yes
Output indicators (as
specified in the RLF; add more
rows as needed)
Most recent value
(A)
End target (B)
(expected value at project
completion)
Progress
towards target (% realized)
(A/B)
Narrative assessment (indicative max length: 50 words per output)
Core
Sector
Indicator (Yes/No)
Component 3: Project coordination and management
Number of project
structures put in place
1 Steering
Committee (SC),
1 Project
Management Unit
(PMU)
1 multi-stakeholder
and inter-institutional
steering committee set
up at the end of the
first quarter of 2014
100% Two MHA orders concerning the establishment, composition and
operation of PMU and Steering Committee (SC)structures are
available,
- PMU set up and functional since 2014
- SC set up and functional since 2014
Yes
Indicator 2:
Number of progress
reports, number of
completion reports
8, then 0 8 quarterly progress
reports
-1 project completion
report
75% All the documents are available
8 progress and management reports have been produced and are
available
- Completion report not produced (but will be at the end of the
project)
Yes
Indicator 3:
Donors’ roundtable
organised, rate of
mobilisation of financing
required for priority
operations
0 ;
1%
1 donors’ roundtable
in 2016
- Financial resource
mobilisation rate of
100% in 2017
0
0.1%
There was no specific donors' roundtable for the financing
PANGIRE. However, a donors' roundtable for the Economic and
Social Development Plan, of which PANGIRE is a major
component, `was organized in Paris in December 2017. The
document on the PDES financing roundtable is available, but there
is no mention of the amount allotted to PANGIRE. In addition,
MHA is planning to organize a meeting to mobilize financing for
PANGIRE in 2019 in Luxembourg.
Yes
Indicator 4:
Number of capitalization
documents produced
1 document 1 capitalization
documents produced
in 2016
100% The capitalization document with the IWRM Guide is available.
OXFAM has started disseminating the printed Guide in Great
Britain. The Guide has been translated into English
All stakeholders have the document
Yes
RATING
3
Out of a total of 12 targets, 8 targets have been achieved 100%, one target 160%, one to the tune of 150%, one to the tune of 75% and
lastly one to the tune of 0.1%, representing a general output rate of 93%.
The output score is 3
Page 10
9
4. Development Objective (DO) rating
DO rating (derived from
updated IPR)* Narrative assessment (indicative max length: 250 words
3 The operations carried out to achieve the project's development objective are satisfactory (3).
Indeed, one of the project’s objectives was achieved with the adoption of PANGIRE and its
implementation instruments. On the other hand, the mobilization of financial resources for
implementation of the PANGIRE investment programme has not yet been achieved.
5. Beneficiaries (add rows as needed)
Planned (A) Actual (B) Progress towards
target (% realized) (A/B)
% of women Category (eg. farmers,
students)
The people of Niger
The people of Niger
100% 49.4 Not Applicable
The State, through the
administrative services of
ministries (central and
devolved services), Water
Management Units
(WMUs), the National
Water and Sanitation
Commission (CNEA) and
its regional branches
(CREA), public water
supply (SPEN and SEEN)
and sanitation services,
local authorities, the
private sector
(consultants, water works
companies, etc.), the
National Water
Partnership (NEP), NGOs
and water users’
associations.
Public administrative
services and devolved
services, all associations,
the private sector and
NGOs involved in water
management
100%
Not Applicable Not Applicable
Basin agencies (NBA,
LCBC);
- Regional and sub-
regional organizations
(ECOWAS, WAEMU and
CILSS;
Basin agencies (NBA,
LCBC);
- Regional and sub-
regional organizations
(ECOWAS, WAEMU and
CILSS)
100% Not Applicable Not Applicable
Technical and financial
partners
Technical and financial
partners
100% Not Applicable Not Applicable
Page 11
10
6. Unanticipated or additional outcomes (add rows as needed)
Description Type (e.g. gender,
climate change, social,
other)
Positive or
negative
Impact on
project (High,
Medium, Low)
There were no unanticipated outcomes
7. Lessons learned related to effectiveness
Key issues (max 5, add rows as needed) Lessons learned Target audience
1. Proper preparation of the project-specific donor
roundtable
2. Preparation strategy
3. Project coordination
1. Proper preparation and organization of a
roundtable dedicated specifically to the
financing of a project or programme helps
to secure the commitment of the various
donors for the financing of activities
2. The preparedness strategy adopted allowed
the effective participation of all IWRM
actors
3 The establishment of project coordinating
bodies including the PMU and the SC was
effective in enabling the production and
approval of the various documents
Bank and donee
Bank and donee
Bank and donee
C Efficiency
1. Timeliness
Planned project duration – years (A)
(as per PAR) Actual implementation time – years
(B) (from effectiveness for 1st disb.) Ratio of planned and actual
implementation time (A/B)
Rating*
30 months 52 months 0.57 2
Narrative assessment (indicative max length: 250 words)
The total duration of the project initially planned is 30 months, with effect from the date of signature of the Grant
Agreement. It took long for the counterpart financing to be made available because of cash flow issues, and there were
also long delays in the processing of files at the Bank, justifying extension. Prior to the Bank's first disbursement, the
project received significant financing from Swiss and Luxembourg Cooperation, which was not originally planned.
DANIDA also increased its contribution from CFAF 20 million planned to CFAF 219 million. These contributions made
it possible to finance such activities as the situation analysis of water resources prior to the signing of the grant. A
substantial balance was left, in addition to the savings on the procurement process. So the Government of Niger requested
permission from the Bank to use the remaining funds to finance additional activities (PD in other regions). The Bank gave
its consent for the use the funds. This justifies the second extension, given that the activities were not part of the original
project. The grant was initially scheduled to close on 13 October 2016, but this date was extended to 30 November 2018
to allow the completion of all project activities. The turnaround time from the effectiveness of the first disbursement until
the project completion is 52 months. The delays observed at the start of the project and during its implementation are not
related to the design, but to other factors (effectiveness conditions, additional activities undertaken thanks to the savings
made on the procurement process, and the funds contributed by DANIDA at the start of the project).
The rating is 2.
Page 12
11
2. Resource use efficiency
Median % physical implementation of RLF outputs financed by
all financiers (A) (see II.B.3)
Commitment rate (%) (B) (See table 1.C – Total commitment rate
of all financiers)
Ratio of the
median percentage
physical
implementation
and commitment
rate (A/B)
Rating*
Component 1: Development of PANGIRE
(i) All PANGIRE and PIP documents prepared and
approved, financing mobilization and communication
strategy, and the monitoring and evaluation system,
prepared; (ii) Three sharing and feedback workshops were
organized for PANGIRE and PIP, a feedback workshop was
organized for the three strategy papers (mobilization of
financing, communication, monitoring and evaluation); (iii)
a study on the status of water resources was carried out, a
report covering six thematic areas was produced and
approved; (iv) a SESA report complete with the
Environmental and Social Management Framework
(ESMF) was produced and approved; (v) the PANGIRE
document was approved with the participation all IWRM
stakeholders in Niger.
Overall implementation rate: 100%.
Budget at appraisal =
EUR 390,000
Actual expenditure =
EUR 390,000
Disbursement rate = 100 %
100% 3
Component 2: Preparation of the Investment Plan (PIP)
(i) The PIP was prepared on the basis of PANGIRE and
approved; (ii) the technical evaluation of 15 project sites
was conducted; and (iii) feasibility studies on 8 priority
infrastructure projects was carried out (PD level).
Implementation rate for activities: 100%
Budget at appraisal =
EUR 479,000
Actual expenditure =
EUR 479,000
Disbursement rate = 100%
100%
Component 3: Project Coordination and Management:
(i) All project steering, supervision, monitoring,
coordination and management structures have been set up
and are functioning; (ii) progress and management reports
are prepared on a regular basis; (iii) a PDES donors’
roundtable was organized, but the amount allocated to
PANGIRE does not seem to be clearly specified in the final
document; (iv) a capitalization document along with an
IWRM Guide was developed and approved with
dissemination of this Guide. There is also an English
translation of the Guide.
The beneficiary's completion report has not yet been
prepared. No donors' roundtable was organized for
PANGIRE, but a PDES roundtable was held. The financing
of PANGIRE is not complete.
Implementation rate for activities: 50%
Budget at appraisal =
EUR 81 000 Euros
Actual expenditure = EUR
81 000
Disbursement rate =100%
50%
Page 13
12
Narrative assessment (indicative max length: 250 words)
Resource use efficiency is satisfactory. Overall, with the exception of the beneficiary’s completion report that has not yet
been produced, the project has achieved the expected outputs within the limits of the available AWF budget, although the
donnee had to provide additional resources to cover the operation expenses of the PMU and the salaries of its team
members, following the extension of the project's closing deadlines. The disbursement rate stands at 88% and will increase
to 99.8% by the end of the project. A grant of about CFAF 219 million was also provided by DANIDA (Danish
Cooperation), while Swiss Lux-Development Cooperation (Lux-Development) granted approximately CFAF 252,600,000
at commencement. The grant from DANIDA enabled the conduct of the diagnostic study on water resources (CFAF 20
million). The balance of the DANIDA and the Swiss Lux-Development grants and savings on the procurement amounted
to CFAF 383 million. The reallocation of this amount made it possible to finance studies on the preparation of the Water
Development and Management Master Plan (SDAGE) for four sub-basins and studies on the improvement of the new
MHA database. The DANIDA and Swiss Lux Development Coorp grant funds have been disbursed in full.
3. Cost benefit analysis
Economic Rate of Return
(at appraisal)
Updated Economic Rate of Return
(at completion)
Rating*
Not applicable(NA) NA -
Narrative assessment (indicative max length: 250 words)
4. Implementation progress (IP)
IP Rating (derived from
updated IPR) *
Narrative comments (commenting specifically on those IP items that were rated Unsatisfactory or Highly
Unsatisfactory, as per last IPR). (indicative max length: 500 words)
3
Two MHA decrees relating to the establishment, composition and functioning of the Project Management
Unit (PMU) and the Steering Committee (SC) were issued in 2013 and are available. The PMU and the
Steering Committee have been operational since 2014. The actors involved in the PANGIRE
development process took part in sharing, feedback and awareness workshops that were held for the three
strategy documents (mobilization of financing, communication and monitoring and evaluation). The
project start-up workshop was held on 15 January 2015.
The first disbursement of EUR 100,590 from the AWF was made on 13 July 2014. The consultants were
paid directly by the Bank.
The implementation of the project’s three components lasted a total of 52 months instead of the 30 months
initially planned, following a second extension that was made with the agreement of the Bank to allow
the implementation of additional activities. These activities were financed with the contribution from
Swiss and Luxembourg Cooperation – not included in the original project financing - and the contribution
from DANIDA, which increased its grant from CFAF 20 million to CFAF 219 million. There was a delay
in the release of counterpart financing due to cash flow problems and also long delays in the processing
of files at the Bank.
More than 80% of the activities have been completed and the disbursement rate stands at 88%. By the
end of the project, 0.2% of the grant will be left. Still to be finalized are: (i) studies on the preparation of
the Water Development and Management Master Plan (SDAGE) for four sub-basins. The contract, worth
EUR 89,937, was approved by the Bank. AGHECRA consulting firm was told to start work on 15 August
2018 for period of four months; (ii) the remaining part of the balance was used to finance studies on the
improvement of the new MHA database. The contract of the consortium, worth EUR 28,340, was
approved by the Bank. NAZAN-Building Business Practice Group was asked to start work on 15 August
2018, lasting a period of three months. By the financing closing date set for 31/11/2018, only 0.02% of
the financing was to be cancelled. All other financing was disbursed 100%.
Page 14
13
5. Lessons learned on efficiency
Key issues (max 5, add rows as needed) Lessons learned Target audience
1. Setting up of the PMU
2. Provision of counterpart financing
3. Fulfilment of grant conditionalities
6. Processing of files at the Bank
1. The establishment of a PMU with various skills
helped to ensure the success of project activities. It
comprised
Project Coordinator, Water Specialist (hydrogeologist
and IWRM), 1 Monitoring and Evaluation Expert
(hydraulics and IWRM); 1 Socio-economist and
Gender Expert (socio-planner), 1 Environmentalist
(environmental sector executive), 1 Communication
Expert (journalist and MHA press officer), 1 Manager-
Accountant (treasury inspector).
2. The timely provision of counterpart financing helped
to avoid delays in the commencement of the project.
3. The expeditious fulfilment of grant conditionalities
enabled the timely commencement of project activities
4. The expeditious processing of files at the Bank made
it possible to avoid delays in the implementation of
project activities
1. Bank and
Donee
2. Donee
3. Donee
4. Bank
D Sustainability
1. Financial sustainability
Rating * Narrative assessment (indicative max length: 250 words)
2 A Priority Investment Plan (PIP) for 40 projects worth CFAF 74.36 billion has been approved and is available.
The MHA has programmed activities for a six-year period (2019-2024). The PIP is already being used for the
programming of the activities for 2019. However, the mobilisation of financing for the budget, which depends
largely on donors, remains low (less than 1%). The Government of Niger plans to make up for the shortfall by
organizing a PANGIRE financing meeting in 2019 in Luxembourg. A monitoring mechanism for financing the
PANGIRE is also not available. The financial sustainability of the project upon completion does not seem
guaranteed as yet.
2. Institutional sustainability and capacity building
Rating * Narrative assessment (indicative max length: 250 words)
3 The Ministry of Water and Sanitation (MHA) has taken ownership of PANGIRE. All documents relating to the
design and implementation of PANGIRE were prepared and adopted in a participatory manner with the
involvement of all IWRM stakeholders in Niger, who took an active part in exchanges and discussions relating
to the preparation of documents on the situation of water resources, development of the IWRM Action Plan,
priority operations and the implementation arrangements of that plan. The various working sessions with the
authorities at all levels, as well as all available documents, attest to the strong political will and commitment of
Page 15
14
the Government of Niger with regard to the preparation of PANGIRE. The preparation of PANGIRE is founded
on legal and institutional bases. To ensure institutional sustainability, the Government issued two decrees: one
establishing the Ministry of Hydraulics and Sanitation, and the other transforming the PMU into the Permanent
Secretariat (PS) of PANGIRE, headed by a Permanent Secretary appointed by decree of the Council of
Ministers and ranking as Director General at the Ministry. The staff of the Permanent Secretariat (PS) is
appointed by an MHA order. PS/PANGIRE relies on a committee of experts for support in various research
activities (identification, design and validation of research themes or scientific studies). However, the thematic
summary report document notes the lack of technical skills in terms of quantity, especially at the level of
devolved services, even though there are existing and new vacancies created as part of the decentralization
effort. In terms of quality, the regional and central services lack technical skills in such specialised areas as
hydrogeology, hydrology and sanitary engineering. The project also addresses all water-related aspects by
providing a plan that is consistent with national and regional policies and priorities (ECOWAS, WAEMU,
NBA and LCBC). Capacity building was also provided to key players involved in the PANGIRE preparation
process through awareness and training activities. The capitalization document, along with an IWRM Guide,
has been prepared and approved. The Guide has been translated into English, and its distribution has also begun.
Lastly, the IWRM process is steered and partly implemented by national executives with the support of
experienced and competent consultants recruited through a competitive call.
3. Ownership and sustainability of partners
Rating * Narrative assessment (indicative max length: 250 words)
3 The Ministry Water and Sanitation (MHA) has forged and strengthened partnerships with the National Water
and Sanitation Commission (CNEA) and the Regional Water and Sanitation Commission (CREA). The IWRM
is now an instrument on which donors must rely in providing the subsidies needed for the implementation of
sustainable water management operations in Niger. In addition, PANGIRE will promote regional integration
by strengthening cross-border cooperation on shared waters (NBA and LCBC). Different partnerships have
already been established with the partners who made commitments to finance PANGIRE (Swiss Cooperation
and Danish Cooperation). Other partnerships will also be forged with other partners after they must have
fulfilled their commitments (PIDEC/AfDB, EU, BM, OXFAM, Mercy Corp and MCC Compact1). The IWRM
implementation process involves a large number of governmental and non-governmental actors and now relies
on the expertise and know-how of the private sector and national NGOs for the reorganization of the water
sector.
4. Environmental and social sustainability
Rating * Narrative assessment (indicative max length: 250 words)
NA The PANGIRE preparation project is not likely to generate any negative environmental and social impacts, but
environmental and social concerns have not been overlooked. A SESA report accompanied by the ESMF was
produced and validated.
5. Lessons learned related to sustainability
Key issues (max 5, add rows as needed) Lessons learned Target audience
1- Financial sustainability
2- Conduct of the SESA
1- A permanent IWRM financing mechanism
is needed to consolidate the gains of the
project and ensure its continued existence.
2. The production of a SESA complete with
the Environmental and Social Management
Framework (ESMF) is important to ensure
the environmental and social sustainability
of the project.
1. Bank and
Donee
2. Donee
Page 16
15
III Performance of stakeholders
A Relevance
1. Bank Performance
Rating* Narrative assessment by the Borrower on the Bank’s performance, as well as any other aspects of the project
(both quantitative and qualitative). See guidance note on issues to cover. (indicative max length: 250 words)
3 AfDB/AWF has ensured compliance with Bank procurement rules and procedures. It has made arrangements
to facilitate the project’s implementation, particularly by carrying forward the date of project closure in order
to allow the PMU to complete all the activities. The grant beneficiary indicated that the project was
implemented in collaboration and with the support of the AfDB/AWF, but noted that the time taken to process
files at the Bank was rather long. The donee also reported that the AfDB/AWF carried out only one supervision
mission during project implementation, instead of at least one mission per year. So there is a project monitoring
problem. Also, the mission team was limited to one person, and had no financial expert. A mid-term audit of
the project was conducted and approved by the Bank. The final audit has not been performed, but is planned
for the end of the project.
Key issues (related to Bank performance, max 5, add rows as needed) Lessons learned
1. Consistency of supervision missions
2. Processing of files
1. The composition of supervision missions must be
multidisciplinary to address the concerns of the project
team
2. It is imperative to expedite the processing of files at the
Bank to avoid project implementation delays.
2. Borrower performance
Rating* Narrative assessment on the Borrower performance to be inserted by the Bank (both quantitative and qualitative,
depending on available information). See guidance note. (indicative max length: 250 words)
3 The donee set up the Project Management Unit (PMU) to manage the project. The donee took steps to ensure
the involvement of stakeholders in all stages of the project, including in the conduct of studies and in their
approval, but failed to provide the counterpart financing on time because of cash flow difficulties. Also, the
donee took a long time to start the project because it needed to fulfil the grant conditionalities to avoid a repeat
of problems, especially the difficulty of opening the foreign exchange account. The donee failed to approve the
monitoring and evaluation of the project at the beginning but did so at the end of the project. It has taken steps
to ensure the sustainability of the project, including by issuing the decree on PANGIRE and transforming the
PMU of PANGIRE into a Permanent Secretariat responsible for project implementation. The donee has
responded in a timely manner to the requests and implemented the recommendations of the start-up and
supervision missions. It is making every effort to ensure that the last studies are conducted and approved before
the close of the project, scheduled for 30 November 2018. It plans to produce the beneficiary’s project
completion report at the end of the project. Key issues (related to Borrower performance, max 5, add rows as needed) Lessons learned
1. Project counterpart financing
2. Fulfillment of grant conditionalities
1. The provision of counterpart financing at the start of
the project makes it possible to avoid delays in the
implementation of the project
2. Expeditious fulfilment of grant conditionalities
allows for timely commencement of project activities
Page 17
16
3. Performance of other stakeholders
Rating* Narrative assessment on the performance of other stakeholders, including co-financiers, contractors and service
providers. See guidance note on issues to cover. (indicative max length: 250 words)
3 The project’s implementation involved the PMU, DANIDA, Swiss Cooperation/Lux Development,
OXFAM and STUDI, SOFRECO and FGC consulting firms, and the consulting firm group comprising
BERD Burkina and SQUEN Niger. DANIDA and Lux Development have each fully disbursed the initial
and additional financing which was increased to Euro 335,388 following the resource reallocation. OXFAM
also disbursed its financing of Euro 91,469. The performance of STUDI consulting firm, which produced
PANGIRE and PIP documents, was entirely satisfactory. This consulting firm produced good quality
documents within the contractual deadlines. It produced the 3 APS following an amendment to its initial
contract. The SOFRECO and FGC group carried out studies on the status of water resources, and BERD-
Burkina Faso and SQUEN-Niger consulting firms conducted the strategic environmental and social
assessment (SESA). Two studies are still to be carried out: (i) studies on the preparation of the Water
Development and Management Master Plan (SDAGE) for four sub-basins. The contract worth Euro 89,937
(CFAF 58,995,000) won by AGHECRA was approved by the Bank. AGHECRA was requested to start
work by 15 August 2018, for a period of four months; (ii) the remaining portion was used to finance studies
on the improvement of the new MHA database. The contract totalling EUR 28,340 (or CFAF 18,590,000),
won by NAZAN-Building Business Group, was approved by the Bank. NAZAN-Building Business group
was requested to start work on 15 August 2018 for a period of three months. The project's Regional Steering
Committee has met six times since the start of the project.
Key issues (related to performance of
other stakeholders, max 5, add rows as
needed)
Lessons learned (max 5) Target audience (for
lessons learned)
1. Finalisation of studies 1. It is necessary to finalize all the planned studies within the
allotted time so that they may be available for use in establishing
a coherent investment project
1. Donee.
IV Summary of key lessons learned and recommendations
1. Key lessons learned
Key issues (max 5, add rows as needed) Key lessons learned Target audience
1. Financial sustainability
2. Delay in the implementation of project
activities
3. Donor coordination
4. Project monitoring by the Bank
1. A permanent mechanism for monitoring the
commitments of the various donors is
needed to consolidate the project’s gains
2- The processing of files at the Bank needs to
be expedited to save time in the
implementation of project activities
3. The Bank's participation in the donor group
strengthens coordination and prevents the
same project from being financed by several
donors
4. Regular contact with the project team makes
it possible to resolve any difficulties that
may arise during project implementation.
1. Donee
2. Bank
3. Bank
4. Donee/Bank
Page 18
17
3. Key recommendations (with particular emphasis on ensuring sustainability of project benefits)
Key issue (max 10, add rows as needed) Key recommendation Responsibl
e
Deadlines
1. Completion of project activities
1. Complete the last studies required for
preparation of the Water Development and
Management Master Plan (SDAGE) for four
sub-basins, and for improvement of the new
database of MHA
Donee Immediate
2 Maintenance of the project coordination
and management system.
2. The coordination and management system
established during the project
implementation has worked well and been
successful. This system will need to be
maintained in implementing PANGIRE
activities.
Donee Medium
term
3. Permanent mechanism for monitoring
donor commitments
3. Establish a permanent system for
monitoring the commitments of the various
donors for the financing of PANGIRE
activities.
Donee
Immediate
4. Project monitoring and evaluation 4. Adopt the monitoring and evaluation system
at the start of the project
Donee Medium
term
5. Storage of project documents
5. Electronically and physically archive
project documents
Donee Immediate
6. Mobilization of resources for the
financing of PANGIRE
6. Organize the specific meeting in
Luxembourg scheduled for 2019 to mobilize
financing for PANGIRE and inform the
Bank of the outcomes of that meeting.
Donee /
Bank
Short term
V Overall PCR rating
Dimensions and Criteria Rating*
DIMENSION A: RELEVANCE 3.5
Relevance of project development objective (II.A.1) 4
Relevance of project design (II.A.2) 3
DIMENSION B: EFFECTIVENESS 3
Development Objective (DO) (II.B.4) 3
DIMENSION C: EFFICIENCY 2.66
Timeliness (II.C.1) 2
Resource use efficiency (II.C.2) 3
Cost-benefit analysis (II.C.3) -
Implementation Progress (IP) (II.C.4) 3
DIMENSION D: SUSTAINABILITY 2.66
Financial sustainability (II.D.1) 2
Institutional sustainability and capacity building (II.D.2) 3
Ownership and sustainability of partnerships (II.D.3) 3
Environmental and social sustainability (II.D.4) -
OVERALL PROJECT COMPLETION RATING 3
Page 19
18
VI Acronyms and abbreviations
Acronym (add row as
needed)
Description
3N Les Nigériens Nourrissent les Nigériens (Nigeriens Feed Nigeriens)
ADF African Development Fund
AfDB African Development Bank
AWF African Water Facility
CILSS Permanent Inter-State Committee for Drought Control in the Sahel
CNEA National Water and Sanitation Commission
CREA Regional Water and Sanitation Commission
CRP Regional Project Steering Committee
CSP Country Strategy Paper
DANIDA Danish International Development Agency
DGH Directorate General of Hydraulics
DRE Directorate of Water Resources
ECOWAS Economic Commission of West African States
ESMF Environmental and Social Management Framework
IWRM Integrated Water Resources Management
LCBC Lake Chad Basin Commission
LCBC Lake Chad Basin Commission
MDGs Millennium Development Goals
M&E Monitoring and Evaluation
MHA Ministry of Water and Sanitation
NBA Niger Basin Authority
NBA Niger Basin Authority
PADD Sustainable Development Action Plan
PANGIRE National Action Plan for Integrated Water Resource Management
PCR Project Completion Report
PDES Economic and Social Development Plan
PIP Priority Investment Programme
PMU Project Management Unit
PROSEHA Water, Hygiene and Sanitation Sector Programme 2016-2030
PRSF Poverty Reduction Strategy Framework
PRSP Poverty Reduction Strategy Paper
RAT Quarterly Progress Report
SDAGE Water Development and Management Master Plan
SDR Rural Development Strategy
SDRP Accelerated Development and Poverty Reduction Strategy
SESA Strategic Environmental and Social Assessment
SG Secretary General of the Ministry of Water and Sanitation of Niger
SISEAN Integrated Monitoring and Evaluation System for Water and Sanitation in Niger
SOPHAB Operational Strategy for the Promotion of Hygiene and Basic Sanitation
Page 20
19
TFP Technical and Financial Partner
TOR Terms Reference
WAEMU West African Economic and Monetary Union
WR Water Resources
WSS NP Water Supply and Sanitation National Programme
ANNEXES
List of persons interviewed
Full Name Function Contact Number
Atahirou Karbo SG MHA +227 90 07 04 40
Khamada Baye Director in charge of
Studies and
Programming, MHA
+227 96 97 33 26
Dr Sandao Issoufou Coordinator, PMU +227 96 96 77 54
Abdou Sani Expert Monitoring and
Evaluation Expert,
PMU
+227 97 10 08 88
Mahamadou Magé Accountant +227 90 96 06 87
Oher Persons Interviewed
Full Name Function Contact Number
Kané Dia Nouridine AfDB Resident
Representative in Niger
+227 90 11 26 99