Al Fareed Engineering Services & Consultants Major Achievements & Performance Report (MES-PMCL Project) Al-fareen Engeneering & Consultants (Pvt) LTD
Al-fareen Engeneering & Consultants (Pvt) LTD
Al Fareed Engineering Services & Consultants
Major Achievements & Performance Report(MES-PMCL Project)
Al-fareen Engeneering & Consultants (Pvt) LTD
Major Achievements
Zero Outage count (Karachi) S1Less repeated Outage (cable
installation)Prolonged T-prime/DC issues
rectified
Al-fareen Engeneering & Consultants (Pvt) LTD
Organizational Policy
Being Quality Solution provider AFES strives for cost effective and consistent rectification, Keeping above policy Below mentioned Sites may be lead as a role model ,since some of them were running prime fro, 3 yrs.
Al-fareen Engeneering & Consultants (Pvt) LTD
Optimization Initiatives Timely Ho-ToSwift SLA obedience under given
conditions Additional
recommendations/ProposalsCost effective ,Consistent
rectification Certified electrical Staff for PMT
(Wapda)24/7 NOC availability Transparency in reporting &
client Comfort Level
Al-fareen Engeneering & Consultants (Pvt) LTD
Team Build Up Karachi Region 618 sites
SummeryCable Installation Team-3 PersonsKorangi – 1 personMalir , Shahfaisal – 3 personOrangi– 1 personBaldia -1 personLyari – 1 personDefence – 1 personGarden – 2 personLaandhi ,Gulsha e hadeed – 2 personsBahadurabad ,Nazimabad - 2Total = Logistics DetailsNo Of Bikes – No Of Utility van – 03
Cable installation - 3person
Korangi – 1 person
Malir , Shahfaisal – 3 person
Orangi -1 Baldia-1,Lyari1,Defence1,Garden2Laandhi ,Gulsha e hadeed – 2 persons
Bahadurabad-Nazimabad -2
Al-fareen Engeneering & Consultants (Pvt) LTD
Team Build Up Karachi Region 618 sites
Cable Instal-la-tion; 3
Korangi; 1Laandhi; 1
Orangi; 1
Baldia; 1
Gulshan-e-Hadeed; 1Bahadurabad; 1Nazimabad; 1
Lyari; 1
Defence; 1
Garden; 2
Malir-Shahfaisal; 3
Al-fareen Engeneering & Consultants (Pvt) LTD
Monthly Escalation trend
May; 80June; 210
July; 181
August; 177
September; 334October; 219
November; 183
December; 204
Al-fareen Engeneering & Consultants (Pvt) LTD
Major Site Rectifications Plz double click
Cable Installation Jobs @-KHI5013__S_Near_Korangi_Crossing -
50 meters 16mm 4 core-KHI0665__P_KDA_Employees_Krngi -
190 meter 16mm 4 core-KHI0656__H_Korangi_5_Township -
115 meter 16mm4core-KHI0910__S_BhainsColonyMor - 120
meter 16 mm4core-KHI5437__S_KgiRes10Sector50B -35
meter 16 mm4core-KHI5328__s_future_colony_blocke -
15 meter LT-Meter
Microsoft Office PowerPoint Presentation
Microsoft Office PowerPoint Presentation
Microsoft Office PowerPoint Presentation
Microsoft Office PowerPoint Presentation
Al-fareen Engeneering & Consultants (Pvt) LTD
Major Site Rectifications Plz double click
Site Rectification @
Al-fareen Engeneering & Consultants (Pvt) LTD
Current Karachi trend
Zero Count Record In KHI for AFES End
Summary KarachiTotal Under process = 05Cases Pending PMCL end = 02Pending at MES End including approvals = 01KESC issues = 02
T-Prime Count Karachi
Day 2-Jan-13 3-Jan-13 4-Jan-13 5-Jan-13 6-Jan-13 7-Jan-13 8-Jan-13 9-Jan-13 10-Jan-13 11-Jan-13 12-Jan-13 13-Jan-13 14-Jan-13 15-Jan-13 16-Jan-13 17-Jan-13
Count 2 4 4 4 4 7 6 6 6 6 4 4 4 4 4 5
2-Ja
n-13
3-Ja
n-13
4-Ja
n-13
5-Ja
n-13
6-Ja
n-13
7-Ja
n-13
8-Ja
n-13
9-Ja
n-13
10-Ja
n-13
11-Ja
n-13
12-Ja
n-13
13-Ja
n-13
14-Ja
n-13
15-Ja
n-13
16-Ja
n-13
17-Ja
n-13
012345678
2
4 4 4 4
76 6 6 6
4 4 4 4 45
T-Prime Trend Karachi (MES)
Al-fareen Engeneering & Consultants (Pvt) LTD
Current Hyderabad trend
Zero Count Record In HYD for AFES End
Summary HyderabadTotal Under process = 16CP DC cases Pending at PMCL end = 06Pending at myson End including approvals = 07Contactor Faulty Sites = 02
T-Prime Count HYDDay 5-Aug-12 6-Aug-12 7-Aug-12 8-Aug-12 9-Aug-12 10-Aug-12 11-Aug-12 12-Aug-12 13-Aug-12
Count 14 15 16 16 15 14 14 14 16
5-Au
g-12
6-Au
g-12
7-Au
g-12
8-Au
g-12
9-Au
g-12
10-A
ug-1
2
11-A
ug-1
2
12-A
ug-1
2
13-A
ug-1
21313.5
1414.5
1515.5
1616.5
14
15
16 16
15
14 14 14
16T-Prime Trend HYD (MES)
Al-fareen Engeneering & Consultants (Pvt) LTD
Current MPK trend
Zero Count Record In HYD for AFES End
T-Prime Count MPKDay 5-Aug-12 6-Aug-12 7-Aug-12 8-Aug-12 9-Aug-12 10-Aug-12 11-Aug-12 12-Aug-12 13-Aug-12
Count 2 1 2 1 1 2 3 3 3
5-Au
g-12
6-Au
g-12
7-Au
g-12
8-Au
g-12
9-Au
g-12
10-A
ug-1
2
11-A
ug-1
2
12-A
ug-1
2
13-A
ug-1
200.5
11.5
22.5
33.5
2
1
2
1 1
2
3 3 3T-Prime Trend MPK(MES)
Summary Mirpur khasTotal Under process = 03CP DC cases pending at PMCL end = 02Pending at myson End including approvals = 01
Al-fareen Engeneering & Consultants (Pvt) LTD
Snag Indication & Achievements HYD Plz double click
S.No Site name Site Code
Status Generic Reason with Remarks (OSV) CP Restored - Restored / Pending
CP Meter Reading DG Reading
1 DAO7071__S_Dando 7071 T-Prime CP Restored Restored N/A N/A2 HYD5334__S_Hyderabad_1 5334 T Prime CP Restored Restored 19179 62783 HGW6108__H_TMK_HYD_Highway_PW6108 T-Prime CP Restored by replacing of PMT Bush & tapping Restored 311797 3396.254 NRP6362__H_nasarpur_Matiari_Rd6362 T-Prime Access Issue Pending N/A N/A5 MTL5888__H_Digri_Rd_Matli 5888 Stand By (One Phase) No CP issue found - All phases OK Restored 157075 13813.116 HGW6311__H_Khandu_Hala_MRI6311 T-Prime CP Restored Restored 8368 / 3032 1047.687 BUL6168__S_MirpurBathoro 6168 T-Prime CP restored by installing 16 mm 4 core 5 meters cable Restored N/A 2457.568 TBG6377__H_Talhar_Tando_Bagho6377 T Prime CP restored by sagging of HT jumpers Restored 2425 / 1085 2920.79 HYD5856__S_Suzuki 5856 T Prime CP restored by LT Service Restored N/A N/A10 BSC_Auto_Bhan_Repeater 6407 T Prime CP DC due to billing Pending N/A N/A11 HGW7090__S_Palijani_Station7090 T-Prime CP DC due to billing Pending N/A N/A12 RJK7062__S_Rajo_Khanani 7062 T-Prime CP DC due to billing Pending 2741 / 3287 1167.1613 HYD5335__S_Hyderabad2 5335 T-Prime CP restored by sagging of HT jumpers Restored N/A N/A14 BER6132__H_Bherani_DTE 6132 T-Prime CP Restored Restored N/A 490515 PHK0073__S_Falkara 73 T-Prime CP DC due to billing Pending 3200 / 383 N/A16 HYD5666__S_Bilal_Complex 5666 T-Prime Approval req - Neutral grounding 300 ft cable Pending 0 017 HYD6494__S_Ghumanabad 6494 T-Prime CP Restored Restored 1041 1100418 NRP6361__S_Akbari_Masjid 6361 T-Prime CP Restored Restored N/A 258.3219 MRI7070__S_SarhandiMohallah7070 T-Prime CP restored - Structural & Civil work required at site Restored N/A N/A20 HYD5853__S_Unit_5_Latifabad5853 T-Prime CP Restored Restored N/A N/A
Al-fareen Engeneering & Consultants (Pvt) LTD
Snag Indication Prior To Ho-To
Individual visit to all Sites within region Highlighting and recommendation of
proposals such as Contactor replacements ,DG auto issue , Meter Burnt ,Cable Requirements
Initiation of approvals Rectification of snags in view of go ahead
Microsoft Office Excel Worksheet
Al-fareen Engeneering & Consultants (Pvt) LTD