AEGIS LIVING 8511 15TH AVE NE EARLY DESIGN GUIDANCE PACKET MAY 11 2015 DPD #3018400
2 A n k r o m M o i s a n A r c h i t e c t s & A e g i s L i v i n g E A R L Y D E S I G N G U I D A N C E
INTRODUCTION
Table of Contents................................................................................................2
General Project Information.............................................................................3
CONTEXT ANALYSIS
Vicinity Map..........................................................................................................4
Context Axonometric.........................................................................................5
SITE ANALYSIS
Photomontages...................................................................................................6
Site Photos and Surrounding Zoning............................................................8
Topography + Structures and Tree Survey..................................................10
Site Access Opportunities ...............................................................................12
Sun/Shadow (Existing).....................................................................................13
MASSING OPTIONS
Proposed Site Plan............................................................................................14
Sun/Shadow (Proposed).................................................................................15
Detailed Zoning Analysis.................................................................................16
Design Guidelines............................................................................................ ..17
Massing Study & Plan Diagrams........................................................................
Massing Study A..............................................................................19
Massing Study B.............................................................................20
Massing Study C - Preferred........................................................21
Summary.............................................................................................22
Preferred Option Design Guideline Response..........................................23
Departures...........................................................................................................29
Ta b l e o f c o n t e n t s
3 A n k r o m M o i s a n A r c h i t e c t s & A e g i s L i v i n g E A R L Y D E S I G N G U I D A N C E
Project Team
ARCHITECT
Ankrom Moisan Architects, Inc.117 South Main Street, Suite 400Seattle, WA 98104206.576.1600
Contact: JP [email protected]
OWNER/APPLICANT
Aegis Living17602 NE Union Hill RoadRedmond, WA 98052425.284.1624
Contact: Michael [email protected]
LANDSCAPE ARCHITECT
LA Studios LLC15200 52nd Ave S, Suite 210Seattle, WA 98188206.204.0717
Contact: Roby [email protected]
CONTRIBUTE TO THE UNIQUE CHARACTER OF THE SITETo the West, our site is located adjacent to the Maple Leaf Reservoir, which is an excellent urban park and a connector feature of the neighborhood. To the East, the so-called “Waldo Woods” is a protected tree easement appreciated by the neighborhood and the applicant. Our community will address and enhance the character of each of these features.
DEVELOP A SUSTAINABLE COMMUNITY; MEET BUILT GREEN 4-STAR STANDARDOur community will be a lasting addition to the neighborhood, sustaining an older generation of residents for decades into the future. In order to ensure this lasting value, our development will meet the Built Green 4-Star standard through a variety of sustainable design features.
Our proposal is to construct a 3-story assisted living commu-nity that will be an exceptional feature of the neighborhood. The basic program includes:
62/18 assisted living units/memory care units
74,646 sfgross square footage
31 underground parking stalls
G E N E R A L I N F O R M A T I O N
Development Goals
Project Goals
site
site
4 A n k r o m M o i s a n A r c h i t e c t s & A e g i s L i v i n g E A R L Y D E S I G N G U I D A N C E
Maple Leaf Reservoir
Maple Leaf Park
MAPLE LEAF RO
OSEV
ELT WA
Y N
E
LAKE CIT
Y WAY N
E
WEDGEWOOD
EN E
VA HT
02
15TH
AV
E N
E
NE 80TH ST
RAVENNA
SITE
RAVENN
A STREET
12TH
AV
E N
E
LAKE CITY WAY N
E
PRINCIPAL ARTERIAL ROADS
MINOR ARTERIAL ROADS
COLLECTOR ARTERIAL ROADS
LEGEND
15TH A
VE N
ENE 80TH ST
20TH
AV
E NE
C O N T E X T - V I C I N I T Y M A P
5 A n k r o m M o i s a n A r c h i t e c t s & A e g i s L i v i n g E A R L Y D E S I G N G U I D A N C E
NE 88th StreetNE 89th Street
NE 84th Street
MAPLE LEAF RESERVOIR
MAPLE LEAF PARK
LEGEND
SITE
BUS STOPS
LOCAL BUSINESSES
SCHOOLS/INSTITUTIONS
N
PHARMACY
GARDEN STORE
CAFE
RESTAURANT
ST. CATHERINE OF SIENA
FAITH LUTHERAN
73
73, 77
73, 373309, 312
68
68
NE 85th Street
NE 86th Street
NE 88th Street
NE 85th StreetNE 86th Street
16th Avenue NE15th Avenue NE
14th Avenue NE
Brooklyn Avenue NE
12th Avenue NE
NE 82nd Street
SITE
C O N T E X T - A D J A C E N T F E A T U R E S
6 A n k r o m M o i s a n A r c h i t e c t s & A e g i s L i v i n g E A R L Y D E S I G N G U I D A N C E
S T R E E T L E V E L P H O T O M O N T A G E
426.4’
411.4
’
424.8’
411.1’
SITE
7 A n k r o m M o i s a n A r c h i t e c t s & A e g i s L i v i n g E A R L Y D E S I G N G U I D A N C E
S T R E E T L E V E L P H O T O M O N T A G E
421.5
’
410.6’
422.3’
410.6’
SITE
8 A n k r o m M o i s a n A r c h i t e c t s & A e g i s L i v i n g E A R L Y D E S I G N G U I D A N C E
S I T E P H O T O S
7
2
6
5
1
4
3
1 SOUTHWEST VIEW OF SITE
5 EAST VIEW OF SITE
2 EAST VIEW OF SITE
4 VIEW OF MAPLE LEAF RESERVOIR
3 VIEW OF MAPLE LEAF RESERVOIR HOUSING
6 VIEW OF HOUSING 7 VIEW OF HOUSING
9 A n k r o m M o i s a n A r c h i t e c t s & A e g i s L i v i n g E A R L Y D E S I G N G U I D A N C E
C1-40
NC2-40LR2
LR2
522 /
LAKE C
ITY W
AY NE
17TH
AV
E N
E
16TH
AV
E N
E
15TH
AV
E N
E
15TH
AV
E N
E
RO
OSE
VEL
T W
AY N
E N
E
17TH
AV
E N
E
17TH
PLA
CE N
E
85TH STREET NE
86TH STREET NE
88TH STREET NE
82TH STREET NE
88TH STREET NE
86TH STREET NE
85TH STREET NE
84TH STREET NE
83TH STREET NE
MAPLE LEAF PARK
RETAIL AND MIXED-USE CORRIDOR
RESIDENTIAL, MULTIFAMILY,
LOWRISE 2
COMMERCIAL CORRIDOR
PROJECT SITE
LR2
S U R R O U N D I N G Z O N I N G
1 0 A n k r o m M o i s a n A r c h i t e c t s & A e g i s L i v i n g E A R L Y D E S I G N G U I D A N C E
EXISTING 2-STORY BUILDING
(TO BE DEMOLISHED)
T O P O G R A P H Y + E X I S T I N G S T R U C T U R E S
1 1 A n k r o m M o i s a n A r c h i t e c t s & A e g i s L i v i n g E A R L Y D E S I G N G U I D A N C E
1
23
45
6
7
August 13, 2014
Michael DerrAegis Retirement Communities17602 NE Union Hill RoadRedmond, WA 98052
Project site: maple Leaf site, 8511 85th Avenue Northeast, Seattle
Dear Michael,
Per your request I visually inspected trees located on the project site 8511 85th Avenue Northeast, Seattle Washington The visual evaluation was performed to determine size, species and overall health of seven on-site trees.
The visual condition of each tree is described in the report below.
Excellent - No defects or signs of natural decline;
Good - Limited, or minor, defects and no signs of natural decline, remove if impacted;
Fair - Significant defects and/or signs of natural decline, remove if impacted;
Poor - Major defects, obvious decline or dead. Remove regardless of impacts.
DBH = Diameter at Breast Height
Tree #
Botanical Name Common name DBH Visual Condition /Comments
1 Pinus monticola Western White Pine
28” Good / pruned to approx. 20’ ht.
2 Acer platanoides Norway Maple 11” Good
3 Betula pendula European White Birch
18.5 Good
4 Betula pendula European White Birch
15” Good
5 Betula pendula European White Birch
13” Good
6 Prunus cerasifera Flowering Plum 9” Good
7 Pinus sp. Pine 18” Poor / Dead
See attached sketch dated August 13, 2014 for corresponding numbers and surveyed locations
of trees.
None of these trees meet the threshold to be considered exceptional as defined in City of Seattle Directors Rule 16-2008.
Information regarding existing trees and potential development can be found at Seattle Municipal Code 25.11, directors rule 16-2008 and Client Assistance Memo 242 and 253.
If I can answer any questions or provide further service please let me know.
Regards
Margarett HarrisonCertified Arborist PN 502
August 13, 2014
Michael DerrAegis Retirement Communities17602 NE Union Hill RoadRedmond, WA 98052
Project site: maple Leaf site, 8511 85th Avenue Northeast, Seattle
Dear Michael,
Per your request I visually inspected trees located on the project site 8511 85th Avenue Northeast, Seattle Washington The visual evaluation was performed to determine size, species and overall health of seven on-site trees.
The visual condition of each tree is described in the report below.
Excellent - No defects or signs of natural decline;
Good - Limited, or minor, defects and no signs of natural decline, remove if impacted;
Fair - Significant defects and/or signs of natural decline, remove if impacted;
Poor - Major defects, obvious decline or dead. Remove regardless of impacts.
DBH = Diameter at Breast Height
Tree #
Botanical Name Common name DBH Visual Condition /Comments
1 Pinus monticola Western White Pine
28” Good / pruned to approx. 20’ ht.
2 Acer platanoides Norway Maple 11” Good
3 Betula pendula European White Birch
18.5 Good
4 Betula pendula European White Birch
15” Good
5 Betula pendula European White Birch
13” Good
6 Prunus cerasifera Flowering Plum 9” Good
7 Pinus sp. Pine 18” Poor / Dead
Dear Michael,
Per your request I visually inspected trees located on the project site 8511 85th Avenue Northeast, Seattle Washington The visual evaluation was performed to determine size, species and overall health of seven on-site trees.
The visual condition of each tree is described in the report below.
Excellent - No defects or signs of natural decline;
Good - Limited, or minor, defects and no signs of natural decline, remove if impacted;
Fair - Significant defects and/or signs of natural decline, remove if impacted;
Poor - Major defects, obvious decline or dead. Remove regardless of impacts.
DBH = Diameter at Breast Height
Tree #
Botanical Name Common name DBH Visual Condition /Comments
1 Pinus monticola Western White Pine
28” Good / pruned to approx. 20’ ht.
2 Acer platanoides Norway Maple 11” Good
3 Betula pendula European White Birch
18.5 Good
4 Betula pendula European White Birch
15” Good
5 Betula pendula European White Birch
13” Good
6 Prunus cerasifera Flowering Plum 9” Good
7 Pinus sp. Pine 18” Poor / Dead
E X I S T I N G T R E E S U R V E Y
1 2 A n k r o m M o i s a n A r c h i t e c t s & A e g i s L i v i n g E A R L Y D E S I G N G U I D A N C E
AC
CES
S FR
OM
WES
T B
LOC
KED
BY
RES
ERV
IOR
ACCESS FROM NORTH BLOCKED BY EXISTING BUILDINGS
AC
CES
S FR
OM
15T
H A
VE
BLO
CK
ED
BY
CO
NSE
RVA
TIO
N E
ASE
MEN
T
DISTANCE FROM PROPERTY LINE ALONG 85TH STREET TO EASEMENT TOO NARROW FOR VEHICULAR ACCESS
AVAILABLE SITE ACCESS AREA
25’-
0”
S I T E A C C E S S O P P O R T U N I T I E S
1 3 A n k r o m M o i s a n A r c h i t e c t s & A e g i s L i v i n g E A R L Y D E S I G N G U I D A N C E
March/September 21 - 10AM March/September 21 - NOON March/September 21 - 2PM
June 21 - 10AM June 21 - NOON June 21 - 2PM December 21 - 10AM December 21 - NOON December 21 - 2PM
S H A D O W S T U D I E S , E X I S T I N G C O N D I T I O N S
1 4 A n k r o m M o i s a n A r c h i t e c t s & A e g i s L i v i n g E A R L Y D E S I G N G U I D A N C E
PROPOSED 3-STORY BUILDING
P R O P O S E D S I T E P L A N1
A
NE 85TH ST
15TH
AVE
NE
L IN
E O
F CO
NSE
RVAT
ION
EAS
EMEN
T (E) TREE, TYP. TREES WITHINCONSERVATION EASEMENT TO REMAIN
(E) TREE, TYP. TREES WITHINCONSERVATION EASEMENT TO REMAIN
LINE OF CONSERVATION EASEMENT
(E) PATHWAY TO REMAIN
(E) CONC WALL TO REMAIN (E) ROCKERY TO REMAIN
6' - 6"
27' -
7" RE
AR S
ETBA
CK
15' -
0"
SIDE SETBACK
5' - 0"
15' -
0"
SIDE SETBACK
5' - 0"
2.1%
[No Slope]
5.0%10.0%
20.0%
10.0%5.0%
413' - 10"
414' - 1"
414' - 7"
424' - 7"
425' - 1"
425' - 4"
426.34
425' - 6"
SIDEWALK
TEMP PARKING
TEMP PARKING
TEMP PARKING
425' - 11"
EGRESS PATH
30' -
0"
17' - 0"
20' - 0"
5' - 0"5' - 0"
50' - 0"
5' - 0"
20' - 8 15/32"
8' -
0"8'
- 0"
8' -
0"
A3.02
2
A3.01 1
A3.01
2
A3.021
1 5 A n k r o m M o i s a n A r c h i t e c t s & A e g i s L i v i n g E A R L Y D E S I G N G U I D A N C E
March/September 21 - 10AM March/September 21 - NOON March/September 21 - 2PM
June 21 - 10AM June 21 - NOON June 21 - 2PM December 21 - 10AM December 21 - NOON December 21 - 2PM
S H A D O W S T U D I E S , P R O P O S E D D E S I G N
1 6 A n k r o m M o i s a n A r c h i t e c t s & A e g i s L i v i n g E A R L Y D E S I G N G U I D A N C E
L A N D U S E C O D E S U M M A R Y
ParcelAPN 510040024556,771 SF
ZoneLR2
FAR 1. Up to 1.3 if following LEED Silver or 4 Star Built Green, under the following: 2008 Multifamily or 2007 New Construction at election of applicant
2. FAR Bonus Standard for Parking: Must be totally enclosed within the structure.
3. Exemptions from FAR: All underground stories Portions of a story which extend no more than 4’ above existing or finish grade, measured to the ceiling, excluding access
Height 1. 30’-0” above average grade.
2. 4’-0” height exception for shed and butterfly roofs
3. See Exhibit A for 23.45.514
4. 10’-0” exception for 20% of roof area for the following Stair penthouses, mech equipment, play equipment, chimneys, communication equip ment.
Setbacks 1. Front 5’-0” 2. Rear 15’-0” (no alley) 3. Side Facades 40’-0 or longer – 5’-0” min, 7’-0” average.
Amenity Area 1. Requirements for amenity areas for apartments do not apply. 2. Amenity area must equal 5% of total unit floor area or 25% of lot area, whichever is less. 3. 400 square foot minimum outdoor area. Minimum dimension of 10 feet.
Maximum Structure Width 1. 90’-0” in any direction. 2. Portions within 15’-0” of any lot line which is not a rear, street, or alley line shall not exceed 65% of the lot length.
Street Facades 1. See Exhibit B for 23.45.529
Parking 1. AL units; 1 space per ea 2 sta� members at peak sta�ng, plus 1 barrier free loading and unloading space. Any tandem spaces provided count as 1.5 spaces. 62 units / 4 = 16 spaces 2. Peak Sta�ng = 30 / 2 = 15 spaces 3. Total Required = 31 spaces
Dwelling 23.42.048 1. Per 23.42.048 there are no ‘dwelling units’ in this development.
1 7 A n k r o m M o i s a n A r c h i t e c t s & A e g i s L i v i n g E A R L Y D E S I G N G U I D A N C E
CS1 Natural Systems and Site Features
Use natural systems and features of the site and its surroundings as a starting point for project design.
PROJECT DESIGN RESPONSES• Project goal to be Built green 4 Star.• Retain existing tree easement to remain with improvements to the existing pathway.
CS2 Urban Pattern and Form
Strengthen the most desirable forms, characteristics, and patterns of the streets, block faces, and open spaces in the surrounding area.
PROJECT DESIGN RESPONSES• Main massing of the structure abuts the adjacent Lowrise 3 lot, pulled away from Single-family lots across the street.• Existing tree easement to bu�er building height from smaller neighboring buildings.• Existing tree easement to frame views of architecture.• Roof forms to match residential character of neighbor hood.
CS3 Architectural Context and Character
Contribute to the architectural character of the neighborhood.
PROJECT DESIGN RESPONSES• Historical tree easement and pathway used to connect to building.• Building to have a ‘residential’ street presence to match neighborhood context.
PL1 Connectivity
Complement and contribute to the network of open spaces around the site and the connections among them.
PROJECT DESIGN RESPONSES• Landscape improvements along NE 85th St public sidewalk lead towards reservoir.• Existing tree easement pathway improved for resident amenities.• Public landscape amenity space along 15th Ave NE.
D E S I G N G U I D E L I N E S
1 8 A n k r o m M o i s a n A r c h i t e c t s & A e g i s L i v i n g E A R L Y D E S I G N G U I D A N C E
-
PL2 Walkability
Create a safe and comfortable walking environment that is easy to navigate and well-connected to existing pedestrian walkways and features.
PROJECT DESIGN RESPONSES• Public sidewalk along NE 85th St connection to site entrance.• Accessibility for people of all abilities provided throughout site and entrance.
DC1 Project Uses and Activities
Optimize the arrangement of uses and activities on site.
PROJECT DESIGN RESPONSES• All parking provided below grade, temporary accessible spaces near entrance.• Exterior ‘sun patio’ and interior uses take advantage of views.• Separate pedestrian sidewalk leading to main entry.
DC2 Architectural Concept
Develop an architectural concept that will result in a unified and functional design that fits well on the site and within its surroundings.
PROJECT DESIGN RESPONSES• Concept reduces perceived mass through window patterning at upper levels and horizontal breaks in the facade materials.
DC3 Open Space Concept
Integrate open space design with the design of the building so that each complements each other.
PROJECT DESIGN RESPONSES• Connect building and residents to retained existing tree easement.• New landscaping along public sidewalks and within site used to blend building design with neighborhood character.• New landscaping used to create areas of interest for residents and bu�er them from the public tra�c.
D E S I G N G U I D E L I N E S
1 9 A n k r o m M o i s a n A r c h i t e c t s & A e g i s L i v i n g E A R L Y D E S I G N G U I D A N C E
Gross Area 69,056 sq. ft.
Number of Units 56/18
Parking Count 24
Stories 3
N
N
SOUTHEAST VIEW
SOUTHWEST VIEW
NSITE PLAN DIAGRAM UPPER LEVEL PLAN
DIAGRAM N
AREA SUMMARY
Exterior Amenity
Parking
Residential
Interior Amenity
COLOR LEGEND
NE 85TH ST
15TH
AV
E N
E
NE 86TH ST
PARKING/LOWER LEVEL PLAN DIAGRAM N
M A S S I N G S T U D Y A
PROS & CONS OF MASSING
Study A demonstrates a code compliant option with no departures. The building is the allowable 90’-0” width at the street and runs the full depth of the lot.
Cons• Massive street facing facade• Very deep residential units• Does not achieve 1.3 FAR• Does not respond to context• Does not follow design guidelines
Pros• No departures
2 0 A n k r o m M o i s a n A r c h i t e c t s & A e g i s L i v i n g E A R L Y D E S I G N G U I D A N C E
N
N
SOUTHEAST VIEW
SOUTHWEST VIEW
NSITE PLAN DIAGRAM UPPER LEVEL PLAN
DIAGRAM N
Gross Area 61,790 sq. ft.
Number of Units 48/18
Parking Count 15
Stories 3
AREA SUMMARY
Exterior Amenity
Parking
Residential
Interior Amenity
COLOR LEGEND
NE 85TH ST
15TH
AV
E N
E
NE 86TH ST
PARKING/LOWER LEVEL PLAN DIAGRAM N
M A S S I N G S T U D Y B
PROS & CONS OF MASSING
Study B creates an internal courtyard and provides a connection to the existing tree easement. It requires a departure for structure width.
Cons• Inefficient for elevators and stairs• Parking ramp faces SE corner of site• Insensitive to view from Reservoir• Large mass on 3 sides of site• Does not achieve 1.3 FAR
Pros• Ideal unit depth• Front of building faces street.
2 1 A n k r o m M o i s a n A r c h i t e c t s & A e g i s L i v i n g E A R L Y D E S I G N G U I D A N C E
N
N
SOUTHEAST VIEW
SOUTHWEST VIEW
NSITE PLAN DIAGRAM UPPER LEVEL PLAN
DIAGRAM N
Gross Area 55,462 sq. ft.
Number of Units 62/18
Parking Count 31
Stories 3
AREA SUMMARY
Exterior Amenity
Parking
Residential
Interior Amenity
COLOR LEGEND
NE 85TH ST
15TH
AV
E N
E
NE 86TH ST
PARKING/LOWER LEVEL PLAN DIAGRAM N
M A S S I N G S T U D Y C - P R E F E R R E D
PROS & CONS OF MASSING
Study C responds to the best features of the site and context. The views from the street and the park are relieved by the L-shaped massing. There is room for a generous entry court and memory care garden in the SW of the building.
Cons• Requires departure for building
width.
Pros• Good unit depth.• Extensive landscaping at street.• Good views from street and park.• Interacts with tree easement.• Best position relative to topography
2 2 A n k r o m M o i s a n A r c h i t e c t s & A e g i s L i v i n g E A R L Y D E S I G N G U I D A N C E
M A S S I N G S T U D Y S U M M A R Y
massing study a massing study b preferred massing
Gross Area 69,056 sq. ft.
Number of Units 56/18
Parking Count 24
Stories 3
AREA SUMMARY
Gross Area 61,790 sq. ft.
Number of Units 48/18
Parking Count 15
Stories 3
AREA SUMMARY
Gross Area 74,646 sq. ft.
Number of Units 62/18
Parking Count 31
Stories 3
AREA SUMMARY
PROS & CONS OF MASSING PROS & CONS OF MASSING PROS & CONS OF MASSING
Study A demonstrates a code compliant option with no departures. The building is the allowable 90’-0” width at the street and runs the full depth of the lot.
Cons• Massive street facing facade• Very deep residential units• Does not achieve 1.3 FAR• Does not respond to context• Does not follow design guidelines
Pros• No departures
Study B creates an internal courtyard and provides a connection to the existing tree easement. It requires a departure for structure width.
Cons• Inefficient for elevators and stairs• Parking ramp faces SE corner of site• Insensitive to view from Reservoir• Large mass on 3 sides of site• Does not achieve 1.3 FAR
Pros• Ideal unit depth• Front of building faces street.
Study C responds to the best features of the site and context. The views from the street and the park are relieved by the L-shaped massing. There is room for a generous entry court and memory care garden in the SW of the building.
Cons• Requires departure for building
width.
Pros• Good unit depth.• Extensive landscaping at street.• Good views from street and park.• Interacts with tree easement.• Best position relative to topography
2 3 A n k r o m M o i s a n A r c h i t e c t s & A e g i s L i v i n g E A R L Y D E S I G N G U I D A N C E
S P E C I F I C R E S P O N S E S T O D E S I G N G U I D E L I N E S
2 4 A n k r o m M o i s a n A r c h i t e c t s & A e g i s L i v i n g E A R L Y D E S I G N G U I D A N C E
S P E C I F I C R E S P O N S E S T O D E S I G N G U I D E L I N E S
COMMONAREA
VIEWS THROUGH
PEDESTRIAN MOVEMENT
RESIDENTIAL
HISTORICAL PATH CONNECTION
PL2 Walkability
Create a safe and comfortable walking environment that is easy to navigate and well-connected to existing pedestrian walkways and features.
Response
DC1 Project Uses and Activities
Optimize the arrangement of uses and activities on site.
Response
2 5 A n k r o m M o i s a n A r c h i t e c t s & A e g i s L i v i n g E A R L Y D E S I G N G U I D A N C E
S P E C I F I C R E S P O N S E S T O D E S I G N G U I D E L I N E S
A B A B A
MASSING
A
B
B
VERTICAL BAYS
HORIZONTAL BAYS CONCEPT DESIGN
DC2 Architectural Concept
Develop an architectural concept that will result in a unified and functional design that fits well on the site and within its surroundings.
Response
CS3 Architectural Context and CharacterDevelop an architectural concept that will result in a unified and functional design that fits well on the site and within its surroundings.
Response
2 6 A n k r o m M o i s a n A r c h i t e c t s & A e g i s L i v i n g E A R L Y D E S I G N G U I D A N C E
S P E C I F I C R E S P O N S E S T O D E S I G N G U I D E L I N E S
PROP
ERTY
15’ 27’ AVG.24’
REQU
IRED
SET
BACK
CS2 Urban Pattern and Form
Develop an architectural concept that will result in a unified and functional design that fits well on the site and within its surroundings.
Response
DC3 Open Space Concept
Integrate open space design with the design of the building so that each complements each other.
Response
2 7 A n k r o m M o i s a n A r c h i t e c t s & A e g i s L i v i n g E A R L Y D E S I G N G U I D A N C E
S P E C I F I C R E S P O N S E S T O D E S I G N G U I D E L I N E S
DC3 Open Space Concept
Integrate open space design with the design of the building so that each complements each other.
Response
CS1 Natural systems and Site Features
Use natural systems and features of the site and its surroundings as a starting point for project design.
Response
PL1 Connectivity
Complement and contribute to the network of open spaces around the site and the connections among them.
Response
2 8 A n k r o m M o i s a n A r c h i t e c t s & A e g i s L i v i n g E A R L Y D E S I G N G U I D A N C E
S P E C I F I C R E S P O N S E S T O D E S I G N G U I D E L I N E S
DC3 Open Space Concept
Integrate open space design with the design of the building so that each complements each other.
Response
CS1 Natural systems and Site Features
Use natural systems and features of the site and its surroundings as a starting point for project design.
Response
PL1 Connectivity
Complement and contribute to the network of open spaces around the site and the connections among them.
ResponseNew landscape planting at the main corner on 15th Ave and along NE 85th will help to draw people along the sidewalk towards the Maple Leaf Reservoir park.
2 9 A n k r o m M o i s a n A r c h i t e c t s & A e g i s L i v i n g E A R L Y D E S I G N G U I D A N C E
D E P A R T U R E S
Maximum Structure Width23.45.527
Apartments in the LR2 Zone may not exceed 90’ in structure width.
89’ 60’15’
62’
126’
PROPOSED BUILDING
AVAILABLE WIDTH NOT USED
DEPARTABLE AREA USED
10’5’
3 0 A n k r o m M o i s a n A r c h i t e c t s & A e g i s L i v i n g E A R L Y D E S I G N G U I D A N C E
D E P A R T U R E S
Setbacks23.45.518
5’ side and 15’ rear setbacks required for apartments in the LR2 Zone. 15’
15’+/-10’
164’ 20’
PROPOSED BUILDING
AVAILABLE AREA NOT USED
DEPARTABLE AREA USED
3 1 A n k r o m M o i s a n A r c h i t e c t s & A e g i s L i v i n g E A R L Y D E S I G N G U I D A N C E
D E P A R T U R E S
89’ 60’15’
62’
126’
PROPOSED BUILDING
AVAILABLE AREA NOT USED
DEPARTABLE AREA USED
15’
15’+/-10’
164’ 20’