Top Banner
Loss of Mains Protection Dr. Adam Dyśko University of Strathclyde Glasgow, UK e-mail: [email protected]
59

[email protected] - National Grid ESO

Feb 24, 2023

Download

Documents

Khang Minh
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: a.dysko@strath.ac.uk - National Grid ESO

Loss of Mains Protection

Dr. Adam Dyśko

University of Strathclyde

Glasgow, UK

e-mail: [email protected]

Page 2: a.dysko@strath.ac.uk - National Grid ESO

Outline

Background

LOM methods and practices in different countries

Existing research work LOM relay performance assessment – ETR 139

Risk assessment study performed for NVD WG

ROCOF relay performance during 28 Sept. event

Dynamic modelling of the UK transmission system

Proposed changes of settings

Possible ROCOF alternatives

Future research work

Page 3: a.dysko@strath.ac.uk - National Grid ESO

Background

System inertia is lowering due to growing penetration of non-synchronous generation

Recent experience in Ireland has demonstrated short time wind penetration of 50% of the demand.

It is anticipated that up to 100% penetration level is achievable by 2020.

In UK n-1 contingency will increase from 1300MW to 1800MW in April 2014.

UK recommended ROCOF setting is 0.125Hz/s (G59/2), in Ireland the recommended setting is 0.4..0.55Hz/s (G10) but the increase to 2Hz/s is proposed.

Continually increasing the ROCOF setting my lead to poor ROCOF dependability.

Page 4: a.dysko@strath.ac.uk - National Grid ESO

OPEN

G

Interconnected

system

Pgen

Qgen

Psys

Qsys

Pload

Qload

Loss-Of-Mains – LOM

Loss of Mains (or islanding) occurs when part of the

public utility network (incorporating generation) loses

connection with the rest of the system.

If LOM is not detected the generator could remain connected, causing a safety hazard within the islanded part of the network.

Passive LOM detection is difficult when the local load closely matches the generator output.

Stability under remote faults and system wide events is also an issue.

Generator

network

Utility network

Page 5: a.dysko@strath.ac.uk - National Grid ESO

Do we really need a dedicated LOM

protection?

Safety hazard probability tree

Loss-Of-Grid

connection (e.g. fault

on the connecting

circuit)

Load/Generation in

close balance (both P

and Q)

Non-detection zone

duration longer than

the acceptable limit,

e.g. 5s

AND

AND

AND

Personnel in

the vicinity

Safety

hazard

AND

AND

Probability (?)

Page 6: a.dysko@strath.ac.uk - National Grid ESO

Health and Safety at Work Act 1974

Do we really need a dedicated LOM

protection?

Individual risk from

inadvertent sustained

power island

Page 7: a.dysko@strath.ac.uk - National Grid ESO

Health and Safety at Work Act 1974

Do we really need a dedicated LOM

protection?

Individual risk from

inadvertent sustained

power island

Page 8: a.dysko@strath.ac.uk - National Grid ESO

Evidence of unintentional islanding

It was reported at CIGRE 2010 session that two

unintended

islanded operations were experienced in 2009 in

Brazil with small hydro generation.

Synchrophasor measurements for LOM applications was

proposed

Islanded operation with PV generation was

experienced in Spain during maintenance

disconnection (up to 40 min.)

Safety of maintenance staff was compromised

Introduce the requirement for the telecontrol systems to

manually disconnect all PV generation

Page 9: a.dysko@strath.ac.uk - National Grid ESO

LOM performance requirements –

sensitivity/dependability

LOM should be sensitive under all possible load and generation scenarios.

The most challenging scenario is when the local load closely follows the generator output both in terms of active and reactive power.

} non-detection zone

Time [h] 24

P [MW]

10

20

30

load profile

generation

profile

Risk of undetected island

t1 t2 t3 t4 G

feeder

Interconnected

system

Pgen

Qgen

Pload

Qload

LOM

~

Page 10: a.dysko@strath.ac.uk - National Grid ESO

G

feeder

Interconnected

system

Pgen

Qgen

Pload

Qload

LOM

~

LOM performance requirements –

stability/security

LOM should be stable under remote faults cleared by the utility system as well as under system dynamic events.

It is undesirable to issue a false trip as it leads to the unnecessary disconnection of the generator.

Page 11: a.dysko@strath.ac.uk - National Grid ESO

Current Practice in dedicated LOM protection

Rate of Change of Frequency (ROCOF)

Good sensitivity but prone to spurious tripping

Voltage Vector Shift (VS)

Fast but poor sensitivity to genuine LOM events and prone to spurious

tripping

Reverse VAR protection

Can fail if the load power factor is close to unity and/or the island

contains long cables

Intertripping

Best performance but cost is high and can become overcomplicated in

some parts of the system.

There is still a need for a reliable passive LOM method.

Page 12: a.dysko@strath.ac.uk - National Grid ESO

Rate-Of-Change-Of-Frequency (ROCOF) Method

The ROCOF method is based on the local measurement of the generator voltage and estimation of the rate of change of frequency.

The measured rate of change of frequency is compared with a preset threshold.

Additional time delay can also be applied.

The rate of change of frequency following an LOM event is directly proportional to the amount of active power imbalance between local load and the generator output.

HS

fPROCOF

n

2

ROCOF – estimated rate of change of frequency [Hz/s]

ΔP – change in active output power during LOM event [MW]

Sn – nominal generator rating [MVA]

f – generator rated frequency [Hz]

H – inertia constant of the generator [s]

Page 13: a.dysko@strath.ac.uk - National Grid ESO

Voltage Vector Shift (VS) LOM Method

The relay measures voltage phase changes in consecutive cycles (or half cycles) and compares the value with the preset threshold.

Zero crossing technique is often used as method of angle measurement

VS is very fast in comparison to other methods such as ROCOF

VS is sensitive to network faults (both resulting in islanding situation and remote faults cleared by the utility)

VS is not sensitive to rate of change of frequency

Low sensitivity to genuine LOM events. The setting of 6requires imbalance of more than 30%Sn to cause operation.

Page 14: a.dysko@strath.ac.uk - National Grid ESO

0 0.01 0.02 0.03 0.04 0.05 0.06 0.07 0.08

-100

-50

0

50

100

t [s]

V [

V]

VT1

VT2

θ

Before LOM After LOM

Voltage Vector Shift (VS) LOM Method

Page 15: a.dysko@strath.ac.uk - National Grid ESO

Vector Shift is used to protect an Embedded Generator.

Calculate the voltage angle change if the generator output

increased from 15MW to 25MW as a result of an LOM event. Before

and islanding the generator operated at unity power factor pf1=1.

Assume that at the time of islanding the generator terminal voltage was

VT1 = 1/0°pu.

Generator: Sn = 30 MVA Vn = 33 kV

Xd” = 0.23 pu Ra = 0.05 pu

Xd

IL

VTEd

R

Xd’

Xd”

Ed’ Ed”

Example – Vector Shift Relay Operation

The resulting angle shift would be = 6.23

This is way below the recommended setting of 12.

Page 16: a.dysko@strath.ac.uk - National Grid ESO

DG protection in different countries

Italy

New directive 84/2012/R/EEL (8 March 2012) was issued by the Italian Regulatory Authority for Electricity and Gas (Aeeg), with the aim of integrate the CEI 0-16 (Reference technical rules for the connection of active and passive consumers to the HV and MV electrical networks of distribution) with a technical document from TERNA (the Italian TSO) defining the system requirements of the DG.

f<47.5

f>51.5

f<49.7

f<50.3

V0>thr.

V2>thr.

V1<thr.

OR

AND

OR

Tripping after 4s

Tripping after 1s

Tripping after 0.1s

f

V

Page 17: a.dysko@strath.ac.uk - National Grid ESO

Systematic LOM relay testing

ETR 139

Page 18: a.dysko@strath.ac.uk - National Grid ESO

Systematic LOM relay testing – ETR 139

Main objectives To establish the behaviour, under various scenarios, of different Loss

of Mains (LOM) protection relays that are typically applied to the

protection of distributed generation installations

Produce a matrix of recommended settings for LOM

Propose standard test scenarios for LOM relays

Case studies Scenario 1: Generator of 30MVA connected

to 33kV network

Scenario 2: Generator of less than 5MVA

connected to a section of 11kV network

It was assumed that maximum system 𝑑𝑓

𝑑𝑡< 0.16Hz/s

Page 19: a.dysko@strath.ac.uk - National Grid ESO

Systematic LOM relay testing – ETR 139

Type of studies Genuine loss of mains events – sensitivity

Cleared system faults (where there is no actual loss of mains) on

adjacent circuits – stability

Generator types Gas turbine with synchronous machine

Wind turbine driven DFIG generator

Induction machine driven generator

(11kV scenario only)

DC/AC inverter connected source

(11kV scenario only)

Page 20: a.dysko@strath.ac.uk - National Grid ESO

Fault Position A (20%

Retained Gen Voltage)

Fault Position B (50%

Retained Gen Voltage)

Fault Position C (80%

Retained Gen Voltage)

Systematic LOM relay testing – ETR 139

Network model

Page 21: a.dysko@strath.ac.uk - National Grid ESO

Systematic LOM relay testing – ETR 139

Typical results – sensitivity (SM based generator)

0

0.1

0.2

0.3

0.4

0.5

0.6

0.7

0.8

0.9

1

-10 -5 -2.5 0 2.5 5 10

RO

CO

F s

ett

ing

[H

z/s

]

Generation - local load balance [%Sn]

Maximum settings to ensure sensitivity under genuine LOM event

Page 22: a.dysko@strath.ac.uk - National Grid ESO

Systematic LOM relay testing – ETR 139

Typical results – stability (SM based generator)

0

1

2

3

4

5

6

7

8

9

10

f1a f1ab f1abc f2a f2ab f2abc f3a f3ab f3abc

RO

CO

F s

ett

ing

[H

z/s

]

Fault scenario

Minimum settings to ensure stability

Page 23: a.dysko@strath.ac.uk - National Grid ESO

Systematic LOM relay testing – ETR 139

Main findings The LOM performance is affected primarily by the generation

technology – the most challenging is a synchronous generator

Stability causes more problems than sensitivity

Improvement in stability can be achieved by providing additional

time delay which does not significantly compromise the sensitivity

Significant difference in

performance between

different relay manufac-

turers was noted, mainly

in terms of stability

Example ROCOF Stability

results for as synchronous

generator

Page 24: a.dysko@strath.ac.uk - National Grid ESO

Risk assessment of NVD

protection requirement

Page 25: a.dysko@strath.ac.uk - National Grid ESO

Safety hazard probability tree

11kV line single

phase-to- earth

fault during NDZ

Local

Load/Generation

P&Q Balance

(LOM non-

detection zone)

Non-detection

zone duration

longer than the

acceptable limit,

e.g. 5s

AND

AND

AND

NVD operation required(i)

(ii)

(iii)

Personnel in

the vicinity

Safety

hazard

AND

AND

Page 26: a.dysko@strath.ac.uk - National Grid ESO

0 1 2 3 4 5 6 7 8

x 104

0

0.1

0.2

0.3

0.4

0.5

0.6

0.7

P[M

W],

Q[M

VA

R]

time [s]

Pload

Qload

Example NVD Requirement probability calculation

(ENW 11kV data – Circuit 1)

Assumptions

o ENW 11kV data – Circuit 1

o 5km of 95mm2 (5MVA)

cable is present

o Non-detection zone 8% (due to

presence of phase-to-earth fault

a value less than 10% is assumed)

o Generator at 0.98pf (lead)

o Generator sizes are spread evenly between

PDG,min=100kW and PDG,max=5MW

o Maximum acceptable non-detection zone duration

TNDZ,max = 5s

o Number of affected generators in 2020 is nDG=18,000x0.75

(75% LV connected).

Page 27: a.dysko@strath.ac.uk - National Grid ESO

Example NVD Requirement probability calculation

(ENW 11kV data – Circuit 1)

Average time of non-detection zone:

Number of expected incidents in a single scheme:

National number of expected incidents:

Total annual time of expected incidents:

Annual probability of existence of hazardous islanded system

condition resulting from the relaxation of the NVD protection

requirement is:

s972.54, avrNDZT

p/a incidents 0.0000745100

76.6000220.0

10023, l

nPN OHE

1DGNVD

p/a incidents 003.175.018000000074.0, DG1DGNVDNVD nNN

s 50.105 54.9721.03,, maxNDZavrNDZNVDNVD TTNT

61059.160608760

10.50

a

NVD

NVDT

TP

Page 28: a.dysko@strath.ac.uk - National Grid ESO

System event

28 September 2012

Page 29: a.dysko@strath.ac.uk - National Grid ESO

PMU Frequency Record

49.65

49.7

49.75

49.8

49.85

49.9

49.95

50

50.05

50.1

50.15

50.2

01:48:00.00 01:49:26.40 01:50:52.80 01:52:19.20 01:53:45.60 01:55:12.00

Fre

qu

en

cy (

Hz)

GPS Time

Strathclyde

Manchester

Imperial

Page 30: a.dysko@strath.ac.uk - National Grid ESO

PMU Frequency Record

512 513 514 515 516 517 518 519 52049.7

49.75

49.8

49.85

49.9

49.95

50

50.05

50.1

t [s]

f [H

z]

PMU Frequency

London

Manchester

Glasgow

Page 31: a.dysko@strath.ac.uk - National Grid ESO

PMU Phase Angle Difference

512 513 514 515 516 517 518 519 52020

25

30

35

40

45

t [s]

angle

[deg]

PMU Phase Difference

PMUPhaseGla

- PMUPhaseLon

PMUPhaseGla

- PMUPhaseMan

Page 32: a.dysko@strath.ac.uk - National Grid ESO

PMU df/dt Record

-2

-1.5

-1

-0.5

0

0.5

1

1.5

01:48:31.97 01:48:32.83 01:48:33.70 01:48:34.56 01:48:35.42 01:48:36.29

df/

dt

(Hz/

s)

GPS Time

StrathclydeManchesterImperial

Page 33: a.dysko@strath.ac.uk - National Grid ESO

df/dt calculated from PMU frequency

as 0.5s average

-2

-1.5

-1

-0.5

0

0.5

1

1.5

01:48:31.97 01:48:32.83 01:48:33.70 01:48:34.56 01:48:35.42 01:48:36.29

df/

dt

(Hz/

s)

GPS Time

StrathclydeManchesterImperial

Page 34: a.dysko@strath.ac.uk - National Grid ESO

df/dt calculated from PMU frequency

as 0.5s average

-0.25

-0.2

-0.15

-0.1

-0.05

0

0.05

01:48:31.97 01:48:32.83 01:48:33.70 01:48:34.56 01:48:35.42 01:48:36.29

df/

dt

(Hz/

s)

GPS Time

StrathclydeManchesterImperial

Page 35: a.dysko@strath.ac.uk - National Grid ESO

ROCOF relay testing

RecordDelay

(s)

Trip setting

(Hz/s)*

Tripping time

(s)**

No trip setting

(Hz/s)***

Glasgow

0 0.16 0.96 0.18

0.25 0.15 1.15 0.17

0.50 0.12 1.32 0.14

Manchester

0 0.11 0.80 0.12

0.25 0.10 1.14 0.12

0.50 0.10 (2/5 times) 1.27 0.11

London

0 0.16 0.31 0.18

0.25 0.10 0.50 0.13

0.50 0.10 (2/5 times) 1.72 0.11

* 5/5 injections result in a trip unless otherwise stated

** This is the average of 5 (or less) injections' tripping times recorded at the trip setting

*** 0/5 injections result in a trip

Three COMTRADE waveform records have been synthesised on a cycle by cycle basis from the available PMU frequency profiles and subsequently injected into the MiCOM P341 relay.

Page 36: a.dysko@strath.ac.uk - National Grid ESO

Observations

df/dt seen by the DG depends on the position in the

network and position in relation to the initiating event

df/df seen by the relay depends on the frequency and

ROCOF calculation method (i.e. mainly the averaging

period)

Applying additional time delay increases relay stability

Applying additional frequency dead band (e.g. 49.5Hz to

50.5Hz) will block ROCOF operation during the majority

of system wide events.

Page 37: a.dysko@strath.ac.uk - National Grid ESO

Equivalent dynamic model of

the UK transmission system

Page 38: a.dysko@strath.ac.uk - National Grid ESO

21 bus equivalent transmission network model is proposed

7YS was used to obtain the load and generation data in each zone.

Available PSS/E full load flow model was used to obtain the circuit equivalent impedances.

PMU data was used to verify the dynamic performance.

UK Transmission System model

France

12

3

4

Page 39: a.dysko@strath.ac.uk - National Grid ESO

Dynamic Validation: PMU Data

PMU data captured during a major event in the UK transmission system – 28 September 2012

65

Phase difference Frequency

The analysis of the voltage angle shift from different parts of the system, prior to, and after the event can assist the load flow solution validation.

The frequency response can be used to validate the inertia and system dynamics, potentially revealing power flow oscillations.

0

10

20

30

40

50

60

70

14:03:22 14:03:23 14:03:25 14:03:26 14:03:28 14:03:29 14:03:31

GL-MN

GL-LN

49.5

49.55

49.6

49.65

49.7

49.75

49.8

49.85

49.9

49.95

50

50.05

03:22.003:22.603:23.203:23.903:24.503:25.203:25.803:26.4

GL

MN

LN

Page 40: a.dysko@strath.ac.uk - National Grid ESO

Simulation of the 28 September event

66

0

10

20

30

40

50

60

70

0.0 1.4 2.9 4.3 5.8 7.2 8.6 10.111.512.914.415.817.318.7

GL-MN

GL-LN

49.55

49.6

49.65

49.7

49.75

49.8

49.85

49.9

49.95

50

50.05

0.0 0.7 1.4 2.1 2.9 3.6 4.3 5.0 5.8 6.5 7.2 7.9 8.6 9.4

GL

MN

LN

Phase difference Frequency

No PSSs included

Page 41: a.dysko@strath.ac.uk - National Grid ESO

Adding stabilisers

STAB1 provided by PSS/E

is used in following buses:

1,2,3,8,9,10,13,19,20 STAB1 transfer function

-0.2 0 0.2 0.4 0.6 0.8 1

-0.1

-0.05

0

0.05

0.1

0.15

1

2

3

4

5

67

8910

11121314

15161718

19

20

Eigenvectors and

participation factors of

each lightly damped

oscillation mode indicate

the need for a stabiliser.

Eigenvectors of one lightly

damped oscillation mode

Page 42: a.dysko@strath.ac.uk - National Grid ESO

Dynamic performance after adding PSSs into the system

68

0

10

20

30

40

50

60

70

0.0 0.6 1.2 1.9 2.5 3.1 3.8 4.4 5.0 5.7 6.3 6.9 7.6 8.2 8.8 9.4

GL-MN

GL-LN

49.55

49.6

49.65

49.7

49.75

49.8

49.85

49.9

49.95

50

50.05

0.00.20.50.70.91.11.41.61.82.12.32.52.73.03.23.43.73.94.14.44.64.8

GL

MN

LN

Phase difference Frequency

Simulation of the 28 September event

Page 43: a.dysko@strath.ac.uk - National Grid ESO

PMU Data - 28 September

Original PMU record

Phase difference Frequency

0

10

20

30

40

50

60

70

14:03:22 14:03:23 14:03:25 14:03:26 14:03:28 14:03:29 14:03:31

GL-MN

GL-LN

49.5

49.55

49.6

49.65

49.7

49.75

49.8

49.85

49.9

49.95

50

50.05

03:22.003:22.603:23.203:23.903:24.503:25.203:25.803:26.4

GL

MN

LN

Page 44: a.dysko@strath.ac.uk - National Grid ESO

ROCOF settings adjustment

Page 45: a.dysko@strath.ac.uk - National Grid ESO

Initial Thoughts on Minimising System Risks

New plant connecting in and beyond Apr 2014 must not have LoM protection sensitive to RoCoF; or

the RoCoF setting must be at or above 1Hz/s and with a

minimum timer setting of 0.5 s

New plant connecting after Apr 2013 but before Apr 2014 must not have LoM protection sensitive to RoCoF; or

the RoCoF setting must be at or above 0.5Hz/s with a minimum

timer setting of 0.5 s with a provision of changing to 1 Hz by Apr

2014

Existing plant If LoM protection is sensitive to RoCoF, its setting is required to

be changed to 0.5Hz/s or above and with a minimum timer setting

of 0.5s as soon as practically possible

Provision should be made to change to 1 Hz by Apr 2014

… this may be an ideal solution from system security perspective, but…

Page 46: a.dysko@strath.ac.uk - National Grid ESO

Issues to consider

Can the setting of 1Hz/s and 0.5s delay provide

acceptable LOM sensitivity?

Are there any time coordination issues with the

delayed LOM operation (in excess of 500ms)?

Can the ROCOF setting recommendation be

made dependent on the generating technology?

Should ROCOF be removed from the acceptable

LOM methods?

What LOM methods (if any) should be adopted in

the future?

Page 47: a.dysko@strath.ac.uk - National Grid ESO

Other LOM methods

Page 48: a.dysko@strath.ac.uk - National Grid ESO

Phase Angle Drift (PAD) LOM Protection

H.T. Yip, G. Lloyd, A. Dysko, G.M. Burt, R.M. Tumilty, “Islanding Detection Using an Accumulated Phase Angle Drift Measurement”, 10th

International Conference on Developments in Power System Protection, Manchester – UK, 2010.

Local frequency is measured by the relay

Grid frequency is estimated using linear extrapolation of recorded

historical data

The PAD algorithm is based on a threshold comparison of an

accumulated voltage phase angle derived from the difference

between the current measured frequency and estimated frequency

fn

fnest

fn-Dfn-D-W

n

f[n]

TW TD

Page 49: a.dysko@strath.ac.uk - National Grid ESO

DG

~

LOM

Protection

trip

Transmission System

GPS stamped frequency signal

Satellite based LOM protection

The LOM protection algorithm

uses the difference between

the received signal and the

locally measured frequency to

estimate the voltage angle

shift according to the following

formula:

tff ref

nnnn )(21

n – calculated angle

fn – frequency measured locally

fnref – reference frequency received from the satellite

t – angle calculation time step

A tripping signal is sent when n exceeds the preset threshold.

Satellite channel latency can be easily compensated using GPS

A. Dyśko, G.M. Burt, P.J. Moore, I.A. Glover, J.R. McDonald, “Satellite Communication Based Loss-of-Mains Protection”, 9th International

Conference on Developments in Power System Protection, Glasgow – UK, vol. 1, pp. 687-692, March 2008.

𝑓𝑟𝑒𝑓𝑓

Page 50: a.dysko@strath.ac.uk - National Grid ESO

Satellite based LOM protection

Relay response to 28 September event

Manchester and London PMU record as a reference frequency

Glasgow PMU record as a DG local frequency

Accumulated phase angle difference contained within 7deg.

Accumulated angle resets if df<0.002Hz for more than 2s.500 550 600 650

-1

0

1

2

3

4

5

6

7

t [s]

an

gle

[d

eg

]

Phase Angle Difference calculated from frequency difference

PAD from (fGla

- fLon

)

PAD from (fGla

- fMan

)

Page 51: a.dysko@strath.ac.uk - National Grid ESO

Satellite based LOM protection

Relay response to 28 September event

Artificial time delay

of 100ms has been

introduced.

Angle difference still

contained within

reasonable margin

(16deg), i.e. GPS

accuracy in time

synchronisation is

not essential.

500 550 600 650-4

-2

0

2

4

6

8

10

12

14

16

t [s]

an

gle

[d

eg

]

Phase Angle Difference calculated from frequency difference

PAD from (fGla

- fLon

)

PAD from (fGla

- fMan

)

Page 52: a.dysko@strath.ac.uk - National Grid ESO

Internet based LOM protection

General WAM system for LOM

Instantaneous phase difference

less hourly “steady-state” average

oscillation of phase angle

difference rarely exceeded

±5°

Laverty, D.M.; Morrow, D.J.; Best, R.J.; Crossley, P.A.; , "Differential ROCOF relay for Loss-of-Mains protection of Renewable Generation

using phasor measurement over Internet Protocol," Integration of Wide-Scale Renewable Resources Into the Power Delivery System, 2009

Page 53: a.dysko@strath.ac.uk - National Grid ESO

Reverse VAR Method

Reverse VAR relay measures the generator reactive

power flow Qgen and operates when it exceeds a fixed

threshold.

G

Interconnected

system

Qgen»0

Qload

LOM

Pgen

PloadQsys

Psys

G

Interconnected

system

Qload

LOM

Pgen

PloadQsys=0

Psys=0

QgenConnected Islanded

Trip if Qgen > Qs

Page 54: a.dysko@strath.ac.uk - National Grid ESO

Centralised LOM protection using IEC-61850

The technique is based on communication of CB status

to the central controller.

Can be combined with conventional passive LOM method with

adaptive settings as a backup.A B

C

D

E

F G

CB1 CB3CB2CB1 CB3CB2

CB1

CB3

CB2

CB1 CB3

CB2

CB4

CB5CB1

CB3

CB2

CB1

CB3

CB2

CB4

CB1 CB3CB2

CB4 CB5

MAINS

CENTRAL

CONTROLLER

Coffele, F.; Moore, P.; Booth, C.; Dysko, A.; Burt, G.; Spearing, T.; Dolan, P., “Centralised Loss of Mains protection using IEC-61850”,

Developments in Power System Protection (DPSP 2010).

Page 55: a.dysko@strath.ac.uk - National Grid ESO

Reverse VAR Method

The amount of reactive power from the generator Qgen may

become insufficient to activate the relay if the total capacitance of the

connecting cables is high delivering reactive power to the loads.

Islanded

G

Interconnected

system

Qload

LOM

Pgen

PloadQsys=0

Psys=0

Qgen

Qc

Qc

Qc

Page 56: a.dysko@strath.ac.uk - National Grid ESO

GG

Signal send

Signal block

Signal block

Signal send

Signal receive

G

Signal receive

Signal receive

Intertripping of Open Ring Feeders

Intertripping for open ring feeders can be facilitated using

Power Line Carrier (PLC) technique.

Intertripping signal is always delivered to the correct

generators regardless of the position of the open point.

Open point

Page 57: a.dysko@strath.ac.uk - National Grid ESO

Intertripping for open ring feeders can be facilitated using

Power Line Carrier (PLC) technique.

Intertripping signal is always delivered to the correct

generators regardless of the position of the open point.

Open point

GG

Signal send

Signal block

Signal block

Signal send

Signal receive

G

Signal receive

Signal receive

Intertripping of Open Ring Feeders

Page 58: a.dysko@strath.ac.uk - National Grid ESO

Active methods

Active methods are more reliable but may be

slower and loose performance in larger groups of

generators

The use of active frequency shift method was suggested

such as Sandia Frequency Shift.

This could also be combined with ROCOF to achieve the

best performance (combined use of active and passive

methods).

The Grid Connection Code in Japan mandates the

combined use of the passive and the active methods.

Page 59: a.dysko@strath.ac.uk - National Grid ESO

Future research

One Year Satellite Applications Catapult funded

LOM demonstrator project has been awarded and will

commence in March 2013.

A research team has been set up at Strathclyde to look

into equivalent modelling of the UK transmission system.

Hardware LOM relay testing under recorded and simulated

system wide disturbances (?).

Risk assessment of the LOM protection under new

proposed setting guidelines (?).