Top Banner

of 24

Advances in Design-Installation-Operation Analysis of Offshore Pipelines_Giertsen

Oct 29, 2015

Download

Documents

alkhwarizmi1968

This article describes the state of the art in designing offshore pipelines.
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • 11MARINTEKMARINTEK do Brasil / Opening Seminar 19th April 2007 / Giertsen

    Trondheim

    Marine Technology Centre in Trondheim

    OsloBergen

    Houston

    MARINTEK (USA), Inc.MARINTEKNorwegian Marine Technology Research Institute

    Main office in TrondheimOffices in Oslo and BergenSubsidiary in Houston; MARINTEK (USA), Inc.Office in Rio de Janeiro; MARINTEK do Brasil

    MARINTEK do Brasil - Opening Seminar19th April 2007, Rio de Janeiro

    Advances in Design, Installation and OperationAnalysis of Offshore Pipelines

    Egil Giertsen, MARINTEK

    2MARINTEKMARINTEK do Brasil / Opening Seminar 19th April 2007 / Giertsen

    Presentation Outline Background Offshore pipeline R&D projects The Ormen Lange gas field

    SIMLA development strategy

    SIMLA analysis functionality - highlights Examples from the Ormen Lange project

    Use in the oil and gas industry

    Plans

  • 23MARINTEKMARINTEK do Brasil / Opening Seminar 19th April 2007 / Giertsen

    PIPESTAB JIP (1983-1988) Executive partners: MARINTEK

    Sponsors: ExxonMobil, Statoil

    Objectives: State of the art before PIPESTAB: Dnv 1981 Rules for Submarine

    Pipeline Systems => High concrete coating costs

    Outcome: Reduced concrete coating thickness => Cost savings Computer programs PIPE and PONDUS => CARISIMA/Beta DnV RP E305

    4MARINTEKMARINTEK do Brasil / Opening Seminar 19th April 2007 / Giertsen

    SUPERB JIP (1992-1996) Executive partners: MARINTEK, Snamprogetti and DNV

    Sponsors: ExxonMobil, Conoco, Statoil, EMC, HSE, Agip,Norsk Hydro, NPD, Shell

    Objectives: Reliability based design of Submarine Pipelines State of the art before SUPERB: DnV 1981 Rules for Submarine

    Pipeline Systems High steel costs

    Outcome: Code calibration resulted in increased utilization (0.72 -> 0.80) Reduced wall thickness => Cost savings DnV Offshore Standard F101 (DnV 1996)

  • 35MARINTEKMARINTEK do Brasil / Opening Seminar 19th April 2007 / Giertsen

    DEEPIPE JIP (1996-1999) Executive partners: MARINTEK, JP Kenny and DNV

    Sponsors: NFR, Conoco, Statoil, Phillips, Allseas, ETPM McDermott

    Objectives: Qualify existing Lay vessels for Deep Water Laying allowing

    overbend strains up to 1% DnV 1996 Maximum strain during installation of 0.5%

    Outcome: Increased allowable strain (0.5% -> 1.0%) Possibility of using existing lay vessels also in deeper waters DnV Guideline for Deep Water Pipelines

    6MARINTEKMARINTEK do Brasil / Opening Seminar 19th April 2007 / Giertsen

    CARISIMA JIP (1999-2002) Executive partners: MARINTEK, Statoil Sponsors: Norsk Hydro, Statoil, Conoco, BP, Texaco, ExxonMobil,

    Agip, Petrobras, Halliburton, Technip-Coflexip

    Objectives: Develop a pipe-soil interaction model suitable for detailed analysis

    of TDP effects for catenary risers Verify the numerical model by 2D geotechnical small-scale tests

    (performed at NGI) Validate the model by back-calculation of monitored in-situ full

    scale test data

    Outcome: A numerical pipe-soil interaction model applicable for on-bottom

    pipeline stability and TDP effects for catenary risers More accurate prediction of fatigue life and extreme stresses

  • 47MARINTEKMARINTEK do Brasil / Opening Seminar 19th April 2007 / Giertsen

    INT-STAB JIP (2003-2006) Executive partners: DNV, MARINTEK and DHI

    Sponsors: Statoil, Norsk Hydro, Woodside, PRCI

    Objectives: A Recommended Practice for On-bottom Stability Design

    (replacing DNV RP E305) Up-to-date know-how with respect to sediment transport A new PONDUS database for clay type soil A completely revised version of the PIPE software for on-bottom

    stability analysis

    Outcome: DNV RP F109 (currently on external hearing) New PIPE version v3.02

    8MARINTEKMARINTEK do Brasil / Opening Seminar 19th April 2007 / Giertsen

    DEEPLINE SIP (2003-2006) Executive partners: MARINTEK

    Sponsors: RCN, Norsk Hydro, Statoil

    Objectives: Development of new analysis tools for offshore pipelines

    Outcome: SIMLA a special purpose computer tool for engineering analysis

    of offshore pipelines during design, installation and operation

  • 59MARINTEKMARINTEK do Brasil / Opening Seminar 19th April 2007 / Giertsen

    CORROSION FATIGUE JIP (2001-2008) Executive partners: MARINTEK, SINTEF

    Sponsors: Petrobras, Statoil, ConocoPhillips, Total, Norsk Hydro, Acergy, Technip, NKT, Wellstream

    Objectives: Steel armour layer of a flexible riser/umbilical subjected to

    fatigue loading The environment in the annulus may become corrosive:

    Sea water ingress due to damage of outer sheath Diffusion of CO2 or H2S from bore Diffusion of water vapour from bore

    Fatigue design criteria for these environments are needed

    Outcome: Provide basis for fatigue strength assessment of armour wire in

    annulus environments

    10MARINTEKMARINTEK do Brasil / Opening Seminar 19th April 2007 / Giertsen

    UMBILICAL JIP (2005-2007) Executive partners: MARINTEK

    Sponsors: Petrobras, Norsk Hydro, BP, Shell, Nexans

    Objectives: Development of next-generation software tools for stress and

    fatigue analysis of umbilicals Verification and validation by full-scale testing Case studies

    Outcome: The UFLEX Program System Laboratory test results Case study reports

  • 611MARINTEKMARINTEK do Brasil / Opening Seminar 19th April 2007 / Giertsen

    FLEXIBLE RISER DESIGN FORMAT JIP (2003-2007)

    Executive partners: MARINTEK

    Sponsors: Petrobras, Statoil, BP, Wellstream

    Objectives: Enhanced Fatigue Design Formats for Flexible Risers

    Establish refined statistical models of relevant parameters Perform additional case studies Develop simplified case-based procedure Evaluation and categorization of safety factors

    Outcome: Guideline on case specific fatigue design factors Measurements and analysis results from field test data, full-scale

    laboratory tests and small-scale tests Case study reports

    12MARINTEKMARINTEK do Brasil / Opening Seminar 19th April 2007 / Giertsen

    Ormen Lange location

    StoreggaSlide edge

    StjTrondheim

    KristiansundMolde

    Alesund

    PL208

    Ormen Lange Location

  • 713MARINTEKMARINTEK do Brasil / Opening Seminar 19th April 2007 / Giertsen

    Ormen Lange, concept selected 2002

    Storegga Slide Edge

    Nyhamna

    Langeled to UK

    Template A

    Template B

    Control Umbilicalsand MEG Lines

    -250m

    -850m

    z2 x 30 Import Pipelines (ca. 120 km)z2 x 6 MEG Lines (ca. 120 km)z2 x Umbilicals (ca. 120 km)z1 x 6 Infield MEG Line (ca. 3 km)z1 x Infield Umbilical (ca. 3 km)

    z1 x 42 Export Pipeline (ca. 1 200 km)

    14MARINTEKMARINTEK do Brasil / Opening Seminar 19th April 2007 / Giertsen

    N

    Vertical exaggeration = 2.5X

    KP 98

    KP 121.7

    TEMPLATE B

    TEMPLATE A

    KP 102

    KP 105

    KP 114

    KP 118

    umb umb6 6 30 30

    Ormen Lange the ultimate challenge for offshore pipe laying

    Extreme seabed topography

    Large water depth Strong current Low temperature

    Water depth = 850 m

    Water depth = 250 m

  • 815MARINTEKMARINTEK do Brasil / Opening Seminar 19th April 2007 / Giertsen

    SIMLAa special purpose computer tool for engineering analysis ofoffshore pipelines during design, installation and operation

    Nonlinear 3D FEM static and dynamic analysis

    Simulation of pipe laying Evaluation of laying stability Upheaval buckling and

    snaking analysis Inspection and evaluation of

    free spans Training and familiarization Route planning and

    optimalization Seabed interventions Prediction of vessel position Operator guidance

    16MARINTEKMARINTEK do Brasil / Opening Seminar 19th April 2007 / Giertsen

    Development Strategy

  • 917MARINTEKMARINTEK do Brasil / Opening Seminar 19th April 2007 / Giertsen

    Technology Development PhilosophyZG

    YG

    XG

    1

    2

    X2L

    Z2L

    Y2L

    X1L

    Z1L

    Y1L

    [S1xx, E1xx, ]

    [S2xx, E2xx, ]

    World-class Special PurposeNumerical Methods

    18MARINTEKMARINTEK do Brasil / Opening Seminar 19th April 2007 / Giertsen

    World-class 3D Visualization

    Technology Development Philosophy

  • 10

    19MARINTEKMARINTEK do Brasil / Opening Seminar 19th April 2007 / Giertsen

    Lifecycle Approach

    Field development

    Concept development Technology and

    concept evaluation Environmental issues Risk

    Routing/optimization Seabed intervention Free span evaluation Installation analysis

    Design

    Interventions (rockdumping, trenching,dredging)

    Installation procedures Pipe installation

    Installation

    Monitoring Remaining fatigue life Change in seabed

    topography Change in operational

    conditions

    Operation

    High Level Architecture (HLA) / Run-Time Infrastructure (RTI)High Level Architecture (HLA) / Run-Time Infrastructure (RTI)

    DatabaseStorage

    and retrievalStorage

    and retrieval

    20MARINTEKMARINTEK do Brasil / Opening Seminar 19th April 2007 / Giertsen

    Basic Analysis Functionality

  • 11

    21MARINTEKMARINTEK do Brasil / Opening Seminar 19th April 2007 / Giertsen

    Installing a 42 Export Line (Nearshore)

    22MARINTEKMARINTEK do Brasil / Opening Seminar 19th April 2007 / Giertsen

    Pipe sliding in trench

  • 12

    23MARINTEKMARINTEK do Brasil / Opening Seminar 19th April 2007 / Giertsen

    Dynamic stability

    24MARINTEKMARINTEK do Brasil / Opening Seminar 19th April 2007 / Giertsen

    Expansion Control Analysis

  • 13

    25MARINTEKMARINTEK do Brasil / Opening Seminar 19th April 2007 / Giertsen

    Back-calculation of snake lay design OL PL-A

    -5.0

    -4.0

    -3.0

    -2.0

    -1.0

    0.0

    1.0

    2.0

    3.0

    4.0

    5.0

    91800 92300 92800 93300 93800 94300 94800 95300 95800 96300

    KP (m)

    Dis

    plac

    emen

    t (m

    )

    SIMLAAnsys

    26MARINTEKMARINTEK do Brasil / Opening Seminar 19th April 2007 / Giertsen

    Defining the 3D numerical route corridor (1)

  • 14

    27MARINTEKMARINTEK do Brasil / Opening Seminar 19th April 2007 / Giertsen

    Defining the 3D numerical route corridor (2)

    Z

    Z

    YY

    28MARINTEKMARINTEK do Brasil / Opening Seminar 19th April 2007 / Giertsen

    Use in The Oil and Gas Industry

  • 15

    29MARINTEKMARINTEK do Brasil / Opening Seminar 19th April 2007 / Giertsen

    SIMLA in Ormen Lange

    30MARINTEKMARINTEK do Brasil / Opening Seminar 19th April 2007 / Giertsen

    OLFP - Major Offshore Contractsz Pipeline detail engineering

    Reinertsen

    z EPC Subsea systemFKS

    z Shallow water installation30 & 42Allseas

    z Coating (weight and corrosion)Bredero Shaw

    z SurveyGeoconsult

    z Rock installationVan Oord ACZ

    z MEG installationAcergy

    z Deep water installation30 & tie-inSaipem

    z Umbilical productionNexans

    z Umbilical installationSubsea 7

    z Heavy liftHeerema

    z DredgingNexans

    Contractors using SIMLA Contractors with SIMLA installed

  • 16

    31MARINTEKMARINTEK do Brasil / Opening Seminar 19th April 2007 / Giertsen

    Installation Analysis of Umbilical - Static

    32MARINTEKMARINTEK do Brasil / Opening Seminar 19th April 2007 / Giertsen

    Installation Analysis of Umbilical - Dynamic

  • 17

    33MARINTEKMARINTEK do Brasil / Opening Seminar 19th April 2007 / Giertsen

    Use of the SIMLA Program System in the Ormen Lange field project has been - and is - a success

    Communication Partners Media

    Familarization Project team Contractors

    Design and construction Verification and validation (specialist analysis) Interface meetings with contractors Company representative on board lay vessels

    A 3D visual model of the complete field layout has grown as the project has moved forward, and is now believed to be used also during operation

    34MARINTEKMARINTEK do Brasil / Opening Seminar 19th April 2007 / Giertsen

    The Pluto Field - Overview

    Woodside Energy Ltd

  • 18

    35MARINTEKMARINTEK do Brasil / Opening Seminar 19th April 2007 / Giertsen

    Planned Development Solution

    Woodside Energy Ltd

    36MARINTEKMARINTEK do Brasil / Opening Seminar 19th April 2007 / Giertsen

    The Seabed at The Deepwater Area

  • 19

    37MARINTEKMARINTEK do Brasil / Opening Seminar 19th April 2007 / Giertsen

    The MEDGAZ Project (www.medgaz.com)

    Capacity: 8 billion m3/yearLength: 200 kmDiameter: 24 inchesMaximum WD: 2,160 metersInvestment: 900 millionWorkforce: Over 2,000 people will be involved in the

    construction phase

    38MARINTEKMARINTEK do Brasil / Opening Seminar 19th April 2007 / Giertsen

    What now

    Photo: Geir Endal

  • 20

    39MARINTEKMARINTEK do Brasil / Opening Seminar 19th April 2007 / Giertsen

    SIMLA.INSTALLATION

    On board monitoring, analysis and decisionsupport during offshore pipe lay operation

    Status: DEMO2000 Application (2007-02-21)

    40MARINTEKMARINTEK do Brasil / Opening Seminar 19th April 2007 / Giertsen

    Lifecycle Approach

    Field development

    Concept development Technology and

    concept evaluation Environmental issues Risk

    Routing/optimization Seabed intervention Free span evaluation Installation analysis

    Design

    Interventions (rockdumping, trenching,dredging)

    Installation procedures Pipe installation

    Installation

    Monitoring Remaining fatigue life Change in seabed

    topography Change in operational

    conditions

    Operation

    High Level Architecture (HLA) / Run-Time Infrastructure (RTI)High Level Architecture (HLA) / Run-Time Infrastructure (RTI)

    DatabaseStorage

    and retrievalStorage

    and retrieval

  • 21

    41MARINTEKMARINTEK do Brasil / Opening Seminar 19th April 2007 / Giertsen

    Lifecycle Approach

    Field development

    Concept development Technology and

    concept evaluation Environmental issues Risk

    Routing/optimization Seabed intervention Free span evaluation Installation analysis

    Design

    Interventions (rockdumping, trenching,dredging)

    Installation procedures Pipe installation

    Installation

    Monitoring Remaining fatigue life Change in seabed

    topography Change in operational

    conditions

    Operation

    High Level Architecture (HLA) / Run-Time Infrastructure (RTI)High Level Architecture (HLA) / Run-Time Infrastructure (RTI)

    DatabaseStorage

    and retrievalStorage

    and retrieval

    42MARINTEKMARINTEK do Brasil / Opening Seminar 19th April 2007 / Giertsen

    SIMLA.Installation - Main Objectives1. Generate, collect and store calculated key installation

    parameters from a selected set of design analyses (as designed datasets)

    2. Generate, collect and store an equivalent set of key installation parameters from available on board control and monitoring systems (as installed datasets)

    3. Create an on board decision support system by combining as designed datasets with real-time information

    4. Calculate accumulated fatigue damage due to the installation, from the as designed and/or as installeddatasets, as a function of pipeline route position

    5. Apply as installed information as start-up condition forre-assessment analysis during operation

  • 22

    43MARINTEKMARINTEK do Brasil / Opening Seminar 19th April 2007 / Giertsen

    SIMLA.Installation - Potential On board 3D FEM analysis real-time, to support decisions related to

    specific events or emerging situations (bad weather + curves) Evaluation of laying stability, both for the current position and as

    forecast for the next section of the as-designed pipe route Generation of the As-built deliverable in a direct reusable form, also

    including key parameters from real-time 3D FEM analysis Connect via satellite link from onshore control rooms, and view the

    whole operation, including 3D FEM results, positions of supporting vessels, ROVs, etc

    For familiarization/HAZID/HAZOP, produce a complete 3D scenario (including 3D FEM results, laying stability evaluation, etc) of the installation process prior to the actual offshore operation

    For de-briefing, play back the installation process from the As-built log Based on the As-built log, calculate the accumulated fatigue damage

    due to installation, store it as a function of pipe route position and apply it as startup condition for fatigue assessment of critical areas during operation

    Assessment of on-bottom stability during operation Assessment of upheaval buckling and snaking during operation

    44MARINTEKMARINTEK do Brasil / Opening Seminar 19th April 2007 / Giertsen

    On board monitoring, analysis and decisionsupport during offshore pipe lay operation

  • 23

    45MARINTEKMARINTEK do Brasil / Opening Seminar 19th April 2007 / Giertsen

    Network Link to External Users

    HLA

    NMEA 0183

    Others

    Con

    trol

    Sys

    tem

    Inte

    rfac

    eLa

    yer

    NumericsNumerics

    High Level Architecture (HLA) / RTIHigh Level Architecture (HLA) / RTI

    FEResults

    FEResults

    TerrainTerrain

    Generic Logging System

    DatabaseKERNELSetup

    On board Logging and Analysis

    NumericsNumerics

    High Level Architecture (HLA) / RTIHigh Level Architecture (HLA) / RTI

    FEResults

    FEResults

    TerrainTerrain

    Analysis at Other Locations

    46MARINTEKMARINTEK do Brasil / Opening Seminar 19th April 2007 / Giertsen

    Onshore Monitoring of Electrical Connection on Troll PilotRecorded Online 27. September 2006. Time: 06:30-07:15, Place: Home Office

  • 24

    47MARINTEKMARINTEK do Brasil / Opening Seminar 19th April 2007 / GiertsenPhoto: Geir Endal

    Thank you for your attention!