Advanced Project Management Project Time Management Ghazala Amin
27
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Advanced Project Management Project Time Management Ghazala Amin.

Advanced Project Management

Project Time Management

Ghazala Amin

Page 2: Advanced Project Management Project Time Management Ghazala Amin.

2

Project Time Management

• Reference study materials– A guide to the Project Management Body of

Knowledge (PMBOK Guide), Chapter 6– Study notes– Dr. Kerzner’s book, Chapter 12

Page 3: Advanced Project Management Project Time Management Ghazala Amin.

3

The project life-span can range from very short - for e.g., one week for recataloguing books in a public library - to very long, for e.g., eight years for the construction of a large dam with attached electric power generating station.

As with cost, it is often difficult to determine the life-span of a project with a high level of accuracy, especially in the pro-ject‘s early stages. Schedule overruns are common in pro-jects and, like cost overruns, they too are also considered a manifestation of project failure.

All projects have a life span, namely, the interval between the point in time the project formally commences and the point in time when it is completed or prematurely terminated.

Project Parameters: Time

Page 4: Advanced Project Management Project Time Management Ghazala Amin.

4

Project Parameters: Time(Important Topics in Project Time Management)

Project Activities Dependency Relationships Between Project Activities Project Activity Duration Estimation Project Milestones Project Schedule Baseline Project Gantt Charts Network Diagrammes (Arrow-on-Arrow, Arrow-on-Node) Critical Path Method Programme Evaluation Review Technique “Crashing“ the Project Earned Value Method Time Management Training for Project Staff

Page 5: Advanced Project Management Project Time Management Ghazala Amin.

5

PMBOK Area: Time Management

Project Time Management includes the processes required to ensure the completion of the project within the time-frame which has been allocated for it.

Processes covered under Project Time Management are activity definition, activity resource estimating, activity duration estimating, schedule development, and schedule control.

Page 6: Advanced Project Management Project Time Management Ghazala Amin.

6

Project Time Management• Includes the processes required to ensure timely

completion of the project

• Enables effective management of time and resources assigned to project tasks

Page 7: Advanced Project Management Project Time Management Ghazala Amin.

7

Project Time Management

• Poor time management is caused by–difficulty in saying no– lack of self discipline–bureaucracy– lack of delegation–poor utilization of staff

Page 8: Advanced Project Management Project Time Management Ghazala Amin.

8

Project Time Management - ProcessesProject Time Management processes (per PMBOK)

Define Activities Sequence Activities Estimate Activity Resources

Estimate Activity Duration Develop ScheduleControl Schedule

Process Groups Initiation Planning Execution Control Closing

Knowledge Areas          

Time Management   Define Activities   Schedule Control  

    Sequence Activities      

   Estimate Activity ResourcesEstimate Activity Duration      

    Develop Schedule      

Page 9: Advanced Project Management Project Time Management Ghazala Amin.

9

Activity Definition• Involves identifying and documenting the

specific activities that must be performed in order to produce the deliverables and sub-deliverables identified in the work breakdown structure

Page 10: Advanced Project Management Project Time Management Ghazala Amin.

10

Activity Definition• Work breakdown structure is reviewed.• Any additional Constraints and assumptions are

identified• Expert judgment of staff or SMEs are procured

• Results in;– Finalized Activity list for project delivery– Work breakdown structure updates are made if

needed.

Page 11: Advanced Project Management Project Time Management Ghazala Amin.

11

Activity Sequencing• Involves identifying and documenting

interactivity logical relationships. Activities must be sequenced accurately to support later development of a realistic and achievable schedule

Page 12: Advanced Project Management Project Time Management Ghazala Amin.

12

Activity Sequencing• Activity list is finalized.

• Mandatory dependencies are identified

• Discretionary dependencies are identified

• External dependencies are identified

• Milestones are identified

• Common Tools & Techniques used are;

• Precedence Diagramming Method (PDM)

• Arrow Diagramming Method (ADM)

• Results in;

– Project network diagram – Schematic Display of project activities and logical relationships among them. (Eg. ADM, PDM)

– Activities will get further decomposed and redefined after establishing logical relationships.

Page 13: Advanced Project Management Project Time Management Ghazala Amin.

13

Activity Sequencing

• Precedence Diagramming Method (PDM)– Nodes represent activities– Arrows connect activities and show dependencies– Also referred to as Activity-on-Node (AON)– Uses four type of dependencies:

• Finish-to-start, finish-to-finish, start-to-start, start-to-finish

Activity (A) Activity (B)

Page 14: Advanced Project Management Project Time Management Ghazala Amin.

14

Activity Sequencing

• Arrow Diagramming Method (ADM)– Arrows represent activities– Connected at nodes showing dependencies– Also referred to as Activity-on-Arrow (AOA)– Uses only finish-to-start dependencies– May use dummy activity

Activity

Page 15: Advanced Project Management Project Time Management Ghazala Amin.

15

CUPID Unload

DealerUnload

Dealer (16)

Dealer (18.1 & 18.2)

Contact History (6&7)

Mileage (5,10&15)

Suppression

PMC

DesignTrans. Code

Freeze

PIT Testing

CKS R2Launch

5/22 6/2

6/7 7/27 7/28 9/6

6/7 6/23

6/7

6/7

6/27 6/28 8/8 8/9 8/23

8/1 8/2 8/18

9/79/11 10/27

10/30

PITHandoff

Project Network Diagram – Example

Page 16: Advanced Project Management Project Time Management Ghazala Amin.

16

Resource Planning• Involves determining physical resources and the

quantities required to perform project activities– People– Facilities– Equipment– Material

Page 17: Advanced Project Management Project Time Management Ghazala Amin.

17

Activity Duration Estimating– Involves assessing the number of work

periods likely to be needed to complete each identified activity

Page 18: Advanced Project Management Project Time Management Ghazala Amin.

18

Activity Duration Estimating

• Activity list is further reviewed and finalized• Any additional Constraints and assumptions are identified• Resource requirements/capabilities are defined• All Historical information is retrieved for estimating• Identified Risks with estimation is documented.• Expert judgment is used for time estimation• Reserve time (Contingency) is built in as risk mitigation

• Results in;– Activity duration estimates– Activity list updates

Page 19: Advanced Project Management Project Time Management Ghazala Amin.

19

Schedule Development– Schedule development means determining

start and finish dates for project activities

Page 20: Advanced Project Management Project Time Management Ghazala Amin.

20

Schedule Development

• Project Management Software is most commonly used for schedule development.

• Leads and lags are identified for tasks;– Lead: A modification of a logical relationship

which allows an acceleration of the successor task

– Lag: A modification of a logical relationship which directs a delay in the successor task

• Resource pool description• Calendars and work hours are updated

Page 21: Advanced Project Management Project Time Management Ghazala Amin.

21

Schedule Development

• Mathematical Analysis used commonly;• Critical Path Method (CPM)• Graphical Evaluation and Review Technique (GERT)• Program Evaluation and Review Technique (PERT)

– Duration Compression• Crashing• Fast Tracking

– Simulation• Monte Carlo

Page 22: Advanced Project Management Project Time Management Ghazala Amin.

22

Schedule Development• Critical Path Method (CPM)

– Determines early and late start and finish date for each activity

– Calculate float – Find least flexible activities

Page 23: Advanced Project Management Project Time Management Ghazala Amin.

23

Schedule Development• Program Evaluation and Review Technique (PERT)

– Uses weighted Average duration estimates– PERT uses mean instead of Most Likely estimate

used by CPM• Pert Calculations

– O = Optimistic– P = Pessimistic– M = Most likely– Weighted duration = (O+4M+P)/6

Page 24: Advanced Project Management Project Time Management Ghazala Amin.

24

Schedule Development• Crashing

– Maximum amount of compression for minimum additional cost

• Fast tracking– Overlapping serial activities

Page 25: Advanced Project Management Project Time Management Ghazala Amin.

25

Schedule Control• Schedule control is concerned with

– (a) influencing the factors which create schedule changes to ensure that changes are beneficial,

– (b) determining that the schedule has changed, – (c) managing the actual changes when and as

they occur

Page 26: Advanced Project Management Project Time Management Ghazala Amin.

26

Schedule Control• Project schedule is updated with actual• Change requests are reviewed and added to

schedule• Project Management software is used for updates

• Results in;– Schedule updates– Documentation of Corrective actions and lessons

learned.

Page 27: Advanced Project Management Project Time Management Ghazala Amin.

27

Schedule Management Plan

– Plan for how the schedule changes will be managed– Plan for change control process and procedures,

performance measures– This will be part of Project Plan