Equipment Advisory
Adv. No. 2015-012 R1
Supersedes: Adv. No. 2015-012 R0
Issue Date: April 21, 2015
File: 1649.10
This Advisory is for the information of personnel working on BC Hydro’s distribution equipment, and is not for public distribution.
Page 1 of 6
Information Bulletin: Backfill
Revision Note Revised text since R0 edition is shown with a vertical bar in the margin, changed or added text is underlined, and deleted text is crossed-out.
1.0 Items Covered Class of Work Specification 1322 R9.1 Construction of Underground Electrical Distribution
Structures by a BC Hydro Contractor Class of Work Specification 1323 R8.2 Construction of Underground Electrical Distribution
Structures by a Customer
2.0 Overview The backfill materials in the above Class of Work Specifications were updated to align with the Authorities Having Jurisdiction requirements for backfill. Materials surrounding direct buried ducts and concrete duct banks were changed from sand to granular material to prevent migration of the material away from the area surrounding the ducts and duct bank due to high water tables.
The backfill materials for traffic areas aligns with materials from the Master Municipal Specifications from the Master Municipal Construction Documents Association and the Ministry of Transportation and Infrastructure.
In boulevard areas, the Class of Work Specifications allow selected native material for backfilling the trench based on consideration that such areas may have limited access and hauling an imported material may not be feasible. However, it is expected that the selected native material meets the Class of Work Specification compaction and gradations specified for Bedding material, and BC Hydro reserves the right to review and reject the proposed native material if not appropriate.
3.0 Action Effective August 10 20, 2015, projects must use the appropriate fill materials as per the Class of Work Specifications. Note that the ES54 civil standards, which are presently under revision and will be issued in fall of 2015, will contain further alternatives to the materials specified in the Class of Work specifications and are included in the appendix as a reference. These materials
Use only for doing work with or for BC Hydro. Complete Legal Acknowledgement is at www.bchydro.com/distributionstandards.
Adv. No. 2015-012 R1
This Advisory is for the information of personnel working on BC Hydro’s distribution equipment, and is not for public distribution
Page 2 of 6
are also acceptable and provide greater flexibility than those specified in the Class of Work Specifications.
4.0 Figures
Figure 1: Trench Cross Sections
Boulevard and Non-Traffic Areas Traffic Areas (Roadways, access lanes,
sidewalks)
Backfill Materials
Surface layer is aligned to Authority Having Jurisdiction where applicable
and Material below the surface layer is Bedding Material
or Selected native fill subject to the note below
Compaction must be 85% Modified Procter density
Top layers are aligned to Authority Having Jurisdiction where applicable
and Material below the top layers is Bedding material Compaction must be 95% Modified Procter density
Cover Materials
Pit run placed 150mm under direct buried ducts, and to extend around ducts and 300mm above highest duct
Approved aggregate, pit run or bedding material placed 150mm under concrete encased duct bank, and to extend 300mm above highest duct
Note: Selected Native Material shall be approved excavated material, free from frozen lumps, ashes, refuse, vegetable organic or foreign matter, granular material over 100 mm in any dimension, or other deleterious materials, and shall be accepted by BC Hydro. Native material is not acceptable if it is impracticable to control its water or compact to the specified density. Contractor to provide test results of gradation, compaction, and thermal resistivity if applicable, to BC Hydro’s representative for acceptance.
Table 1: Acceptable Materials
Use only for doing work with or for BC Hydro. Complete Legal Acknowledgement is at www.bchydro.com/distributionstandards.
Use only for doing work with or for BC Hydro. Complete Legal Acknowledgement is at www.bchydro.com/distributionstandards.
Adv. No. 2015-012 R1
This Advisory is for the information of personnel working on BC Hydro’s distribution equipment, and is not for public distribution
Page 4 of 6
Appendix Further clarification is provided with the upcoming revisions to the ES54 Underground Civil Standards, section W. These DRAFT materials are included here for clarification on acceptable materials, testing and compaction.
Fill Materials Fill material shall be selected native or material imported from a source acceptable to BC Hydro’s Representative. Fill placed around and above feeder duct banks (typically 5 inch ducts) shall not exceed a maximum thermal resistivity of 0.9 mm x C / W at 2% moisture content, and at constructed compaction Proctor Density.
Cover
Cover is an approved fill material placed at the bottom of the excavation to the elevation 300 mm above direct buried ducts and duct banks, and around vaults and boxes. Cover placed around direct buried duct banks shall be Pit Run material. Cover placed around concrete encased duct banks shall be any of the Aggregate materials, except for Coarse Drain Rock, which can be placed at the base below the concrete structure only.
Backfill
Backfill is an approved fill material placed below the finished grade or top layers to the bottom of excavations for concrete encased cut banks, and to the top of the Cover for direct buried ducts. Backfill material shall be Aggregate except Course Drain Rock, Selected Native Material or Consolidated Density Fill. Coarse Drain Rock may be used as a base for concrete encased duct banks.
Aggregate
Aggregate shall compose of inert, clean, tough, durable, highly angular, 100 percent mechanically crushed fragments, with two or more fractured faces having a rough surface texture and capable of withstanding the deleterious effects of exposure to water, freeze-thaw, handling, spreading and compacting. It shall be uniform in quality, and free from an excess of flat or elongated particles, wood, shells, coatings of clay or any other deleterious material.
Aggregate gradation shall be determined in accordance with the ASTM C 136 (Dry Sieve Test) and, for the material passing the 0.075 mm sieve, ASTM C 117 (Wash Sieve Test). Gradations shall fall within the limits for the specified classification, as shown in the following table.
Use only for doing work with or for BC Hydro. Complete Legal Acknowledgement is at www.bchydro.com/distributionstandards.
Adv. No. 2015-012 R1
This Advisory is for the information of personnel working on BC Hydro’s distribution equipment, and is not for public distribution
Page 5 of 6
Aggregate Gradation
Notes:
1) MOTI OGB, Granular Base Type 1, Type 2 and Pipe Bedding are high strength and quality crushed aggregate.
2) Pit Run is clean graded or crushed aggregate.
3) Course Drain Rock is highly permeable, clean, round graded or crushed aggregate.
Aggregate Acceptance
Test Description
Test Methodology
Minimum Test Frequency
Acceptance Criteria
Sieve Analysis ASTM C136 and ASTM C117 for 0.075 mm sieve
One (1) per 1,000 cubic metres for each
type of backfill material
Generally uniform gradations within the limits shown in
Table
Sand Equivalent ASTM D2419 Same as above Equal to or more than 40 Laboratory
Compaction ASTM D1557 Same as above Meets the gradation
requirements
Micro Deval Loss Factor
ASTM D6928 Same as above Equal to or less than 25%
Soundness ASTM C88 Same as above Loss after 5 cycles is less than 20% (25% for 4.75 mm)
Rut Resistance Rolled with a fully loaded tandem
axle truck
Same as above Shall not rut
Sieve Opening
Size (mm)
Present Passing by Weight (%)
MOTI OGB
Granular Base
Type 1
Granular Base
Type 2
Pipe Bedding
Pit Run
Coarse Drain Rock
25.0 19.0 12.5 9.50 4.75 2.36 1.18
0.600 0.300 0.150 0.075
100 75-100
- 30-65 5-30 0-10
- -
0-8 -
0-5
- 100
75-100 60-90 40-70 27-55 16-42 8-30 5-20
- 2-8
100 80-100 50-85 35-70 25-50 15-35 5-20
- -
0-5
100 90-100 65-85 50-75 25-50 10-35 6-26 3-17
- -
0-5
- -
100 -
35-100 20-70 13-50 8-35 5-25 2-15 0-6
100 0-100
- 0-5
- - - - - - -
Use only for doing work with or for BC Hydro. Complete Legal Acknowledgement is at www.bchydro.com/distributionstandards.
Adv. No. 2015-012 R1
This Advisory is for the information of personnel working on BC Hydro’s distribution equipment, and is not for public distribution
Page 6 of 6
Selected Native Material
Selected native material is the material which has been removed from an excavation and accepted by the BC Hydro Representative for return to the same excavation as fill material. Such material shall be separated from unsuitable excavated material.
Selected native material shall be granular material free from frozen lumps, ashes, refuse, vegetable, organic or foreign matter, granular material over 100 mm in any dimension, or other deleterious materials. Native material is not acceptable if it is impracticable to control its water content, or to compact to the specified density.
Controlled Density Fill
Controlled Density Fill (CDF) shall be designed by the EOR and accepted by BC Hydro’s Representative. CDF mix design shall be the sole responsibility of the Contractor. All materials and methods of control density fill shall conform to CAN/CSA-A23.1 and CAN/CSA-A23-2.
Lightweight Fills
Lightweight Fills include, but are not limited to, Expanded Polystyrene (EPS, also known as Extruded Polystyrene, STYROFOAM™, GeoFoam™, etc.); pumice; cellular lightweight concrete (e.g. Cell-Crete™); lightweight expanded clay aggregate, and wood waste (hog fuel). Lightweight fills restrict heat dissipation and are not permitted to be placed in the area adjacent to and above the duct banks.
Fill Construction Fill materials shall be placed uniformly and compacted, in lifts not exceeding 200 mm loose thickness. Frozen material shall not be used as fill material, and fill material shall not be placed on frozen ground, and it shall be compacted in dry conditions.
Fill shall extend a minimum 150 mm below the base of the structure and duct bank. All irregularities and cavities in the base shall be properly backfilled, compacted and levelled at a tolerance no greater than ±10 mm. The Contractor shall not proceed with further Work until the bottom of the excavation and the prepared base have been inspected and accepted by BC Hydro’s Representative. Any soft areas or inappropriate materials, in the opinion of BC Hydro’s Representative, encountered at the bottom of the excavation shall be excavated and replaced with appropriate material.
Cover and Backfill Construction Acceptance
Location Modified Proctor Corrected Compacted Dry Density (%)
Non-traffic area (where the distance from the excavation to the roadway, sidewalk, curbs, walls or structures is greater than the excavated depth, otherwise section (b) below shall govern)
85 %
(b) All other areas: Depths within 1.2 metres of the finished surface Depths below 1.2 metres from the finished surface
95 % 95 %
Use only for doing work with or for BC Hydro. Complete Legal Acknowledgement is at www.bchydro.com/distributionstandards.