Addendum No. 2 Project MTC 16-001 (MRN01.01) 1 Date February 8th, 2018 Project Title Project MTC 16-001 Cadaver Lab and HTC Renovation Marion Technical College Marion, Marion County, Ohio To All Plan Holders Purpose Modify the Bid Documents Distribution All Plan Holders Marion Technical College Design Team TO ALL BIDDERS: This Addendum supplements and amends the original Plans and Specifications and shall be taken into account in preparing proposals and shall become a part of the contract documents. REQUESTS FOR INTERPRETATIONS: Item 1. Q. Who pays for the “authorized independent physicist to inspect the lead lined partitions? A. Refer to spec. section 00 72 13, 3.3.1. The architect will apply for, secure, and pay for special inspections. Item 2. Q. Door 168 is an existing door to be reused. Is the frame to be reused as well? A. Yes, reuse and reinstall existing door frame. Item 3. Q. Does the Lead lined frame get relocated along with the door? Drawings mention door only. A. Yes, relocate frame as well. Item 4. Q. Verify that all restroom accessories are provided by owner. A. Please refer to Toilet Accessory Schedule on sheet H-A600. Any necessary accessories for the Cadaver Lab will also be owner furnished, contractor installed. Item 5. Q. How are we addressing the saw cutting that extends into Hall 111, there will be carpet to patch? Does the owner have any of this carpet left over as attic stock? A. Resilient flooring will be installed in this location. Refer to revised sheet C-A101 (sheet re-issued). Item 6. Q. I want to verify that we are to bid the metal cabinets by quantities stated on the drawings. A. Yes. Per metal casework legend on sheet C-A600, “confirm quantities with casework elevations and casework schedule. Report discrepancies to architect”. Item 7. Q. Is the contractor responsible for the asbestos abatement? A. Yes, refer to spec. section 02 82 20 and sheet C-HM101. Note: Hazardous Materials Assessment Report is included in specification.
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Addendum No. 2 Project MTC 16-001 (MRN01.01)
1
Date February 8th, 2018
Project Title Project MTC 16-001 Cadaver Lab and HTC Renovation Marion Technical College Marion, Marion County, Ohio
To All Plan Holders
Purpose Modify the Bid Documents
Distribution All Plan Holders Marion Technical College Design Team
TO ALL BIDDERS:
This Addendum supplements and amends the original Plans and Specifications and shall be taken into account
in preparing proposals and shall become a part of the contract documents.
REQUESTS FOR INTERPRETATIONS:
Item 1. Q. Who pays for the “authorized independent physicist to inspect the lead lined partitions?
A. Refer to spec. section 00 72 13, 3.3.1. The architect will apply for, secure, and pay for special inspections.
Item 2. Q. Door 168 is an existing door to be reused. Is the frame to be reused as well?
A. Yes, reuse and reinstall existing door frame.
Item 3. Q. Does the Lead lined frame get relocated along with the door? Drawings mention door only.
A. Yes, relocate frame as well.
Item 4. Q. Verify that all restroom accessories are provided by owner.
A. Please refer to Toilet Accessory Schedule on sheet H-A600. Any necessary accessories for the Cadaver Lab will also be owner furnished, contractor installed.
Item 5. Q. How are we addressing the saw cutting that extends into Hall 111, there will be carpet to patch? Does the owner have any of this carpet left over as attic stock?
A. Resilient flooring will be installed in this location. Refer to revised sheet C-A101 (sheet re-issued).
Item 6. Q. I want to verify that we are to bid the metal cabinets by quantities stated on the drawings.
A. Yes. Per metal casework legend on sheet C-A600, “confirm quantities with casework elevations and casework schedule. Report discrepancies to architect”.
Item 7. Q. Is the contractor responsible for the asbestos abatement?
A. Yes, refer to spec. section 02 82 20 and sheet C-HM101. Note: Hazardous Materials Assessment Report is included in specification.
Addendum No. 2 Project MTC 16-001 (MRN01.01)
2
Item 8. Q. Please provide more detail on the tall wood cabinets in the Cadaver Lab. Glass type, glass thickness, door thickness and verify that these are plastic laminate finish.
A. Add the following to spec. section 06 40 23 (section not re-issued):
a. “2.02 CABINET HARDWARE AND ACCESSORIES
M. Glass for Glazed Doors: Clear tempered glass complying with ASTM C 1048, Kind FT, Condition A, Type I, Class 1, Quality-Q3; not less than 5.0 mm thick.
Item 9. Q. Door jamb detail on sheet H-A700 shows a ½” rounding on the door jamb edges. Could you clarify this detail?
A. This is just a graphic misrepresentation. Sealant should be provided on both sides of door frame. Refer to drywall jamb detail on sheet C-A700 for clarification.
Item 10. Q. Can you provide a model # for the wall mounted beds?
A. Please use Hausmann Industries Model 4075 Wall Folding Treatment/Changing Table as a basis of design.
Item 11. Q. Can you provide a detail for the mechanical pad screen wall and screen wall doors? Will this be painted?
A. See revised sheet C-A700. Design should match that of existing mechanical screen wall on campus as closely as possible. All components of wall to be powder-coated to match existing (sheet re-issued).
Item 12. Q. Drawings for equipment pad says to verify pad size with equipment size. Pad will be bid as 40’x13’.
A. That is correct. Ensure that north and south end of equipment pad align with center of pilasters on column lines 4 and 5.
Item 13. Q. Provide casework end panel type in room 112B.
A. Casework end panel to be Wilsonart, Dove Grey (D92-60).
Item 14. Q. What is the type of finish for cubbies?
A. Plastic laminate. Refer to elevation 4/C-A600.
Item 15. Q. Are there any allowances on the project?
A. No. Please refer to item 12 on addendum 1.
Item 16. Q. In the communications specifications, 27 10 00. 1.1.B, it states that Black Box is to provide and install the data/voice work. Is Black Box contracted through the College to do the work, or do we need to include their price with our price? If we need to include their price, will any equal contractors be accepted to do the data/voice work?
A. The contractor shall include Black Box’s price in the bid. The College has standardized on Black Box products and installation; no equals should be accepted unless approved by the College.
Item 17. Q. Will all the casework be metal?
A. Please refer to Metal Casework Legend on sheet C-A600 for extent of metal casework.
Item 18. Q. Who will be responsible for the permit fees, GC or owner?
A. Please refer to spec. section 00 72 13, 5.2.
Item 19. Q. Do you have carpet specs? (Patch areas)
A. Refer to revised sheet C-A101.
Addendum No. 2 Project MTC 16-001 (MRN01.01)
3
Item 20. Q. Would there be an issue with working longer days or weekends?
A. Please refer to spec. section 00 72 13, 6.10.5.3.
Item 21. Q. Do you have a manufacturer of the surgical light and camera?
A. The contractor shall furnish and install the surgical lights, double articulating arms, and cameras as described in Coded Note #1 on sheet C-E101. Manufacturer and model numbers are listed in the note.
Item 22. Q. Sheet C-H101 shows a 22x10 return duct from IDF-1 going into the South Corridor? Does terminate with just a grill below the ceiling in this corridor? I am curious why this duct would go outside of the Cadaver Lab?
A. The 22”x10” exhaust duct going to the south of the lab room should drop down in the chase by the door. The duct then extends down to the floor and a Type D grille is mounted at 12” above the floor. Provide a manual damper in the 22”x10” duct above the ceiling in the lab. This should be the same for the 22”x10” duct and grille located adjacent to the prep room in the lab.
Item 23. Sheet C-H101 RTU-1 Note #6 “Furnish unit with BACNET Interface for BAS integration”. Do we just bid providing the equipment with the BACNET and owner is doing the tie-in with their controls contractor?
A. The equipment being provide by the HVAC contractor shall be tied into the existing temperature controls contractor. The temperature controls contractor will be Siemens and their work shall be provided under the HVAC contractor.
Item 24. Q. Are lifts able to be used in either building?
A. Only electric lifts may be used. Per the specifications, the contractor is responsible for any damage caused by these lifts.
Item 25. Q. I don’t see any lab casework. Did you delete the following specification sections :12 35 53 Laboratory Casework, 11 53 63 Laboratory Accessories, 11 53 43 Laboratory Service Fittings and Fixtures, and 11 53 13 Laboratory Fume hoods?
A. These spec. sections were included in the project manual. Information for the metal casework is on sheet C-A600.
Item 26. Q. What kind of ductwork insulation are they requiring for this installation (liner, external wrap and R value)?
A. Supply air ductwork inside the building shall be wrapped with 1-1/2” fiberglass insulation.
B. Exterior ductwork shall be provided with 2” rigid duct board with aluminum jacket and banding. Provide a high point on top of the ductwork to shed the water off the top of the duct. See revised specification information listed below.
Item 27. Q. As for the ductwork that will be on the outside of the building what kind of detail for insulation for ductwork will be required for that?
A. Exterior ductwork shall be provided with 2” rigid duct board with aluminum jacket and banding. Provide a high point on top of the ductwork to shed the water off the top of the duct. See revised specification information listed below.
Item 28. Q. Since this is such a high volume of air I suggest using "Ductmate" connectors. This basically requires a flanged connection that bolts together. Will that be sufficient?
A. Flanged duct connections are acceptable.
Addendum No. 2 Project MTC 16-001 (MRN01.01)
4
Item 29. Q. What is going to be the required air temperature for the structure?
A. The required air temperature shall be 75 degrees for summer and 72 for the winter condition.
Item 30. Q. Specification section 26 05 33 2.05 B states “all electrical metallic tubing (EMT) conduits shall be compression fittings” but section 3.01 B states “concealed or exposed conduit .75 inch up to 1.75 inch, shall be EMT with set screw fittings.” Please advise which is required; set screw fittings or compression fittings.
A. Set screw fittings are acceptable.
Item 31. Q. If MC cables are not allowed in walls, will the general contractor be cutting and repairing slots in existing walls to install conduit to new outlets?
A. Flexible metallic conduit will be acceptable for fishing existing walls. Flexible conduit shall transition to EMT within 6’ of entering/exiting the wall.
SPECIFICATIONS REVISIONS:
Item 32. Section 06 40 23 revised to include glazed doors in casework (see above) (section not re-issued).
Item 33. Following paragraph added to section 06 40 23 (section not re-issued):
A. 2.03 MISCELLANEOUS MATERIALS
D. Hardboard Pegboard: 1/4-inch-thick perforated hardboard, complying with
ANSI A135.4, Class 1 tempered.
Item 34. Section 23 07 00 – HVAC Insulation. Revise Paragraph 3.02 to read as follows (section not re-
issued):
A. “3.02 Insulate Supply Air and exhaust Air Ducts. Cover as follows:
A. All supply air ducts shall be insulated with 1-1/2" thick, 1 lb. density blanket
flexible duct insulation.
B. Adhere insulation to duct surface with Foster No. 85-20 adhesive applied in 6" wide
strips on 12" centers. Butt all edges of insulation and seal all joints with a foil-skrim-kraft
tape or flange adhered over the joint. Secure insulation with flare door staples until the
adhesive sets.
C. Seal all breaks and joints in vapor barrier with 2-1/2" wide pressure sensitive tape
to match vapor barrier facing. Adhere with Foster 85-20 adhesive where necessary.
D. Cover all round low pressure supply air ductwork (including that on the
downstream side of the air terminal boxes).
E. Exterior supply and exhaust ductwork shall be covered with 2” rigid, 6 lb./cu.ft.
density rigid duct insulation. Cover insulation with 0.016” embossed aluminum jacket and
banding. Jacket shall factory colored to match existing brick wall. Seal all joints watertight.
Provide a high point on top of ductwork to shed water.”
Item 35. Section 23 31 13.16 – High Pressure Ductwork
Item 38. Section 23 36 18 – Laboratory Airflow Control System
A. Delete Specification section in its entirety.
Item 39. Section 23 75 00 – Single Zone Rooftop Unit.
A. Add the entire section attached.
Addendum No. 2 Project MTC 16-001 (MRN01.01)
5
Item 40. Section 25 00 00 – Building Management System
A. Revise entire section (section re-issued).
Item 41. Section 25 90 00 – Sequence of Operations
A. Revise entire section (section re-issued).
Item 42. Section 26 05 33 – Raceway and Boxes for Electrical Systems
A. Revise entire section (section re-issued).
DRAWING REVISIONS:
Item 43. Resilient flooring added to corridor on sheet C-A101 (sheet re-issued). Item 44. Equipment Screen Elevation added to sheet C-A700 (sheet re-issued). Item 45. Drawings C-H101 – HVAC Plans (sheet not re-issued).
A. RTU Schedule – Delete remark 8 from the schedule. Unit to be provided with gas heat. B. Revise all the 24”x16” supply air ductwork from the unit plenum curb and in the building to
38”x16” ductwork C. Revise all the 24”x16” exhaust ductwork from the exhaust fan and in the building to
or an approved equal. Flexible metallic fittings shall be; “Steel City”, “AFC”, “Cable
Organizer”, Raco”, or an approved equal.
D. "Mineralac" type supports and "Unistrut" type one bolt supports with square ends shall
not be used at any location.
PART 3 - EXECUTION
3.01 CONDUIT APPLICATION
A. All conduit shall be run/routed to be concealed, behind walls, above ceilings, or under
floors. Notify the Architect right away where any conduit cannot be concealed, so any
installation issue, can be reviewed and resolved.
B. Concealed or exposed conduit 0.75-inch up to 1.75-inch, shall be EMT with set screw
fittings.
C. Concealed or exposed conduit 2.0-inch and above shall RMC or IMC.
D. All RMC, IMC, and EMT conduit terminations shall be bushed.
3.02 INSTALLATION
A. All intermediate (IMC) conduit entering cabinets, pull boxes, junction boxes or outlet
boxes shall be secured with double lock nuts and bushed ends.
B. No more than four (4) 90° bends will be allowed in any one conduit run. Where more
bends are necessary in any single run, a pull box shall be installed. Pull boxes shall also
be installed in long runs at a maximum separation of 100'-0". All conduits, except in
concrete slab or earth, shall be routed parallel or perpendicular to the lines of the
building. No out of plumb or diagonal conduit lines will be accepted.
Marion Technical College BHDP-MRN01.01 January 15, 2018
Cadaver Lab and HTC Renovation Contract Documents
Marion, Ohio
RACEWAY AND BOXES FOR ELECTRICAL SYSTEMS 26 05 33 - 4
C. All conduits shall be supported within 3-feet of any box, or any turn of 90-degrees. All
conduits shall be substantially supported by threaded rods, suitable clamps or hangers
that are attached to the elements of the building structure to provide rigid installation. In
no case shall conduit be attached to or supported from adjoining pipe, or installed in such
a manner as to prevent the ready removal of other pipe for repairs.
D. Self-locking ties may be used to support conduits up to 1-inch in size which are running
horizontally on top of small structural members or through bar joist by; “Thomas and
Betts”, “New Tech”, “Panduit”, “Label Master”, or an approved equal.
E. Strap iron hangers and wire will not be approved as means of conduit support.
F. No conduit shall rest on or be supported from acoustical tile ceilings or the ceiling tile
suspension system.
G. RNC conduit in poured concrete or buried beneath concrete slabs shall have a 1-inch
minimum concrete cover.
H. Where conduit runs across building expansion joints or where necessary to compensate
for thermal expansion or contraction, expansion unions shall be provided.
I. Exercise necessary precautions to prevent accumulation of water, dirt or concrete in
conduits during execution of electrical work. Conduit in which water or foreign material
has been permitted to accumulate shall be thoroughly cleaned or replaced where such
accumulations cannot be removed.
J. All conduits must be kept dry and free of water or debris with approved pipe plugs or
caps. Care shall be given that plugs or caps are installed before pouring concrete.
K. Flexible conduit may only be used as follows:
1. Lighting fixtures may be supplied with short lengths not longer than 6'-0".
2. All expansion joints, flexible connections and vibration isolators shall be bridged
with short lengths not longer than 2'-0".
L. All connections to rotating machinery and heating elements shall be made with short
lengths, minimum 12", of liquid-tite conduit. Where motors are mounted on sliding
bases, the flexible connection shall be long enough to allow full travel of the motor on
the base, maximum 36".
M. Pull Wires
1. A pull wire shall be installed in all empty conduits. In dry locations, pull wire
shall be #14 gauge galvanized steel or nylon pull cord.
Marion Technical College BHDP-MRN01.01 January 15, 2018
Cadaver Lab and HTC Renovation Contract Documents
Marion, Ohio
RACEWAY AND BOXES FOR ELECTRICAL SYSTEMS 26 05 33 - 5
2. Both ends of all pull wires shall be identified by means of labels or tags, reading
"PULL WIRE" and shall be numbered to refer to the same pull wire.
N. Seal all conduits entering from outside the building water and moisture tight.
O. Seal all conduits penetrating rated assemblies (wall or floor) with firestopping. Refer to
specification section 26 00 16, FIRESTOPPING.
P. Conduit sleeves thru the floor shall terminate at a minimum of 6-inches AFF, unless a
higher elevation is indicated in the documents.
Q. Any exposed conduit installed shall be painted to match the adjacent finished surface.
END OF SECTION
1. CONTRACTOR TO PROVIDE BLOCKING IN PARTITIONS FOR PARTITION MOUNTED ITEMS AS INDICATED. CONTRACTOR ALSO TO COORDINATE QUANTITY AND LOCATIONS WITH THE OWNER FOR OWNER FURNISHED / CONTRACTOR INSTALLED ITEMS.
2. PARTITIONS ARE EXISTING TO REMAIN UNLESS NOTED ON PLAN.
5
M N
9' -
7 1
/8"
5' - 1 3/4"
5' - 0"5' - 0" 3' - 0 3/4"
5' -
0"
3' -
0"
3' -
0"
PREP
112B
ENTRY
112A
CADAVER LAB
112
CORRIDOR
111
C-A600
1
C-A600
3
C-A6006
C-A6004
5
2
118
112A
118
112B
112
G10:S0--G3:S0--
G3:S0--
C-A600
15
101
102
103 103
13' - 0" 3' - 0"
104
TYP.105
TYP.105
F4:S0--
F4:S0--
F4:S0--
F4:S0--
CLEAR
2' - 6"
CLE
AR
1' -
6"
107
107
107
108
108
109
17
16' - 4 1/2" 7' - 0 5/8"
4
101
18
C-A600
13
C-A700
TYP
+/-
40
' - 0
" V
.I.F
.
EQ
EQ
EQ
EQ
TYP.
4' - 0"
4"
TY
P.
6' -
8"
TYP.105
TYP.110
111
4" TYP.
4"
TY
P.
TY
P.
4' -
0"
TYP.
4' - 0"
104C-A700 14
5
M N
114
112
111
118
008
006006006
002
005
005
014014
014
003
003
001001
CEILING HEIGHT TAG
2'-0" X 2'-0" CEILING GRID & ACOUSTICAL PANELS. REFER TO FINISH SCHEDULE.
RECESSED 2'-0" X 4'-0" LIGHT FIXTURE
RECESSED 2'-0" X 2'-0" LIGHT FIXTURE
MECHANICAL SUPPLY DIFFUSER
MECHANICAL RETURN DIFFUSER
CEILING MOUNTED PROJECTION SCREEN
1'-0"
ACCESS PANEL
GYPSUM BOARD
2'-0" X 4'-0" CEILING GRID & ACOUSTICAL PANELS. REFER TO FINISH SCHEDULE.
1. REFER TO PLUMBING, MECHANICAL AND ELECTRICAL DRAWINGS FOR LOCATIONS OF SPRINKLER HEADS, EXIT SIGNS AND ADDITIONAL CEILING MOUNTED DEVICES. NOTE: NOT ALL CEILING MOUNTED DEVICES ARE SHOWN ON THIS PLAN.
2. REFER TO PLUMBING, MECHANICAL, AND ELECTRICAL DRAWINGS FOR DEVICE & FIXTURE SIZES AND SPECIFFIC TYPES.
3. THESE DRAWINGS SHALL BE USED FOR LAYOUT OF ALL CEILING DEVICES. CONSULT WITH ARCHITECT IF A CONFLICT ARISES WITH PLUMBING, MECHANICAL, AND ELECTRICAL DRAWINGS. ALL FIXTURES ARE DIMENSIONED TO CENTERLINE OF FIXTURE.
4. PROVIDE ACCESS PANELS IN GYPSUM BOARD CEILINGS WHERE NECESSARY FOR ACCESS TO EQUIPMENT AND CONTROLS. REVIEW LOCATION WITH ARCHITECT PRIOR TO INSTALLATION.
5. ALL LAY-IN CEILING GRID SHALL BE EQUAL FROM OPPOSING EDGES OF ROOM UNLESS NOTED OTHERWISE. AVOID CUT SIZES SMALLER THAN 3 INCHES.
6. REFER TO ROOM FINISH SCHEDULE FOR ACOUSTICAL CEILING PANEL TYPE AND SOFFIT PAINT COLORS.
7. CENTER ALL SPRINKLER HEADS WITHIN CEILING TILES. COORDINATE WITH LIGHTING, DIFFUSERS, EXHAUST VENTS, PROJECTORS, AND ALL OTHER CEILING MOUNTED ITEMS. SEE MEP DRAWINGS.
8. ALL VERTICAL FACES OF SOFFIT TO BE FINISHED TO MATCH ADJACENT SURFACE MATERIALS. THE HORIZONTAL SURFACE TO BE PAINTED CEILING WHITE.
9. WHERE SPECIFIC ACCENT PAINT FINISHES ARE NOTED THE VERTICAL AND HORIZONTAL SURFACES OF THE SOFFIT ARE TO BE PAINTED THE SPECIFIED COLOR. REFER TO THE ROOM FINISH SCHEDULE AND SELECTIONS IN THE SPECIFICATIONS MANUAL.
10. IN ALL ROOMS WITH EXPOSED CEILINGS (EXCEPT MECHANICAL ROOMS AND JANITOR CLOSETS), PAINT ALL EXPOSED PIPES, DUCTS, VALVES, FITTINGS, CONDUITS, INSULATION, AND PIPING TO MATCH ADJACENT SURFACES.
11. PATCH AND REPAIR TO MATCH EXISTING CONDITIONS WHERE REQUIRED TO REMOVE EXISTING CEILING ELEMENTS.
12. PROVIDE NEW CEILING PANELS TO MATCH EXISTING WHERE LIGHT FIXTURES REMOVED.
REFER TO INDEX SHEET FOR ADDITIONAL NOTES.
1. SOLID LINES ON FLOOR PLANS REPRESENT BUILDING ELEMENTS TO REMAIN. DASHED LINES REPRESENT BUILDING ELEMENTS TO BE DEMOLISHED OR RELOCATED. ALL AREAS DENOTED ON THE ROOM FINISH SCHEDULE TO RECEIVE NEW FINISHES WILL REQUIRE THE DEMOLITION OF EXISTING FLOOR FINISHES AND CEILING SYSTEMS.
2. REMOVE ALL PLUMBING, MECHANICAL AND ELECTRICAL WORK CONTAINED IN OR ATTACHED TO WALLS WHICH ARE TO BE REMOVED. REFER TO PLUMBING, MECHANICAL, AND ELECTRICAL DRAWINGS FOR FURTHER DEMOLITION REQUIREMENTS.
3. CUTTING OF EXISTING BEAMS AND STRUCTURAL ELEMENTS IS PROHIBITED, UNLESS NOTED IN STRUCTURAL DRAWINGS.
4. PROVIDE FLOOR SUBSTRATE SURFACES SMOOTH AND FLUSH WITH EXISTING FLOOR SURFACES, FREE OF RIDGES, RIPPLES, DEPRESSIONS, AND OTHER DEFECTS. CHECK FLOOR SURFACES WITH A TEN FOOT LONG METAL STRAIGHTEDGE AND USING APPROPRIATE MATERIALS, FILL TROUGHS AND DEFLECTIONS OF FLOOR SURFACES, CLEAN AND PREPARE SUBFLOOR SURFACES TO RECEIVE NEW FINISH FLOORING MATERIALS AFTER REMOVAL OF EXISTING FLOORING MATERIALS. REMOVE EXISTING ADHESIVES AND SURFACE IRREGULARITIES WHICH WOULD TELEGRAPH THROUGH THE NEW FLOOR SURFACE. GRIND RIDGES AND RAISED AREAS. FILL DEPRESSIONS AND REPAIR CRACKS. SUBFLOOR SURFACES SHALL BE CLEAN, SMOOTH, LEVEL WITH NO APPARENT VARIATION AND SUITABLE TO RECEIVE NEW FINISH FLOOR MATERIALS.
5. REMOVE EXISTING RESILIENT TILE AND BASE, CARPET BASE, FINISH CARPENTRY, CERAMIC FLOOR AND WALL TILE, VINYL WALL FABRIC AND OTHER EXISTING FINISH MATERIALS FROM SURFACES RECEIVING NEW FINISHES, PREPARE SURFACES TO RECEIVE NEW FINISHES IN ACCORDANCE WITH ROOM FINISH SCHEDULE.
6. GENERAL CONTRACTOR SHALL BRACE ALL EXISTING STRUCTURAL ELEMENTS AS NECESSARY DURING DEMOLITION.
7. IT IS THE RESPONSIBILITY OF THE CONTRACTOR TO MAINTAIN THE INTEGRITY OF FIRE RATED ASSEMBLIES AT ALL EDGES AND PENETRATIONS. EXISTING FIREPROOFING OR FIRE ASSEMBLIES WHICH ARE DAMAGED DURING DEMOLITION SHALL BE REPAIRED TO CONFORM TO FIRE PROTECTION REQUIREMENTS.
8. PATCH WALLS AT OWNER-REMOVED EQUIPMENT AND PREPARE FOR NEW FINISHES.
9. THE OWNER SHALL REMOVE ALL NON-FIXED SALVAGE ITEMS PRIOR TO DEMOLITION. CONTRACTOR SHALL COORDINATE WITH OWNER PRIOR TO DEMOLITION REGARDING FIXED ITEMS TO BE TURNED OVER TO THE OWNER AS SALVAGED ITEMS.
10. ACCESS FOR HVAC, PLUMBING AND ELECTRICAL WORK SHALL BE COORDINATED WITH OWNER'S REPRESENTATIVE IN ADVANCE OF PLANNING WORK AT AREAS ABOVE AND BELOW PLANNED WORK.
CODED NOTE
EXISTING TO REMAIN
EXISTING TO BE REMOVED
AREA NOT IN CONTRACT
?001
5
M N
009
009
007
5
M N
9' - 4"
AC1
9' - 4"
AC19' - 4"
AC1
5
M N
PREP
112B ENTRY
112A
CADAVER LAB
112
CORRIDOR
111
118
TRAVEL DISTANCE = 111' FEET
USE GROUP: BUSINESS (UNCHANGED)
OCCUPANCY COUNT: 1,208 SF / 50 = 25 OCCUPANTS (REDUCED FROM ORIGINAL)
USE GROUP: BUSINESS
(UNCHANGED)
OCCUPANCY COUNT: 154 SF / 50 = 4 OCCUPANTS
(REDUCED FROM ORIGINAL)
USE GROUP: BUSINESS (UNCHANGED)
OCCUPANCY COUNT: 67 SF / 300 = 1 OCCUPANTS (REDUCED FROM ORIGINAL)
FINISH TAG
ROOM FINISHES TAGWall
Floor
Ceiling
Base
P1
FINISH & MATERIAL ABBREVIATIONS
* = INDICATES MORE THAN ONE FINISH. REFER TO GENERAL FINISH NOTES
A. CONTRACTOR TO PROVIDE ALL LEVELING MATERIAL AS REQUIRED TO ENSURE AN ADEQUATE LEVEL SUBSTRATE FOR FINISH MATERIAL INSTALLATION.
B. AT DOOR OPENINGS THE TRANSITION BETWEEN DISSIMILAR MATERIALS IS TO OCCUR DIRECTLY AT THE CENTERLINE OF THE DOOR IN THE CLOSED POSITION.
C. AT CASED OPENINGS THE TRANSITION BETWEEN DISSIMILAR MATERIALS IS TO OCCUR DIRECTLY AT THE CENTERLINE OF THE OPENING.
D. COLOR CHANGES ON WALLS ARE TO OCCUR AT INSIDE AND OUTSIDE CORNERS. ALL DEISCREPANCIES ARE TO BE REVIEWED WITH THE ARCHITECT.
E. CONTRACTOR TO PROVIDE ALL NECESSARY TRANSITION STRIPS BETWEEN DISSIMILAR MATERIALS. TRANSITION STRIP MATERIALS ARE TO BE SUBMITTED FOR APPROVAL.
F. REFER TO REFLECTED CEILING PLANS FOR CEILING TYPES AND FINISHES.G. ALL GYPSUM BOARD WALLS TO BE PAINTED P1 UNLESS NOTED OTHERWISE.
REVIEW ALL DISCREPANCIES WITH THE ARCHITECT.
P*
EF1
AC1
EF1
P1
EF1
AC1
EF1
P*
EF1
AC2
EF1
P5
P3
P3
7' -
6"
101
RF3
FINISH LEGEND
PAINT (P)
P1
FIELD
MFG:
COLOR:
SHERWIN WILLIAMS
ORIGAMI WHITE SW7636
P2
DOOR
FRAMES
MFG:
COLOR:
SHERWIN WILLIAMS
ACIER SW9170
P3
ACCENT
MFG:
COLOR:
SHERWIN WILLIAMS
WOOD VIOLET SW6557
P4
ACCENT
MFG:
COLOR:
SHERWIN WILLIAMS
FOREVER LILAC SW9067
P5 MFG:
COLOR:
SHERWIN WILLIAMS
TO MATCH EXISTING
EF1 FLECKS:
SW6557 WOOD VIOLET
SW9067 FOREVER LILAC
SW7004 SNOWBOUND
SW7066 GRAY MATTERS
PROVIDE 4" HIGH INTEGRAL BASE
EPOXY FLOORING (EF)
COLOR:
NOTE:
AC1 MFG:
STYLE:
SIZE:
COLOR:
GRID:
ACOUSTIC CEILING TILE (AC)
AC2 MFG:
STYLE:
SIZE:
COLOR:
GRID:
ARMSTRONG
OPTIMA SQUARE LAY IN, FINE TEXTURE
24" X 24"
WHTIE
SUPRAFINE 15/16" SUSPENSION SYSTEM
L1 MFG:
COLOR:
PLASTIC LAMINATE (L)
WILSONART
FIELD ELM 7999K-12 SOFT GRAIN FINISH
WC1 WALL TALKERS
JUST RITE
48" WIDE (WOVEN BACK)
WHITE
J-CAP @ TOP
WALL COVERING (WC)
MFG:
PRODUCT:
SIZE:
COLOR:
HARDWARE:
ARMSTRONG
CERAMAGUARD, UNPERFORATED, SQUARE LAY IN
24" X 24"
WHITE
15/16" PRELUDE
WF1 SOLYX
SXWF-WM
60" WIDE
WHITE MATTE
WINDOW FILM (WF)
MFG:
PRODUCT:
SIZE:
FINISH:
RF3AZROCK
VCT
TBD (SELECT FROM MFR. FULL COLOR RANGE)
12" X 12"
1/8" GAUGE
RESILIENT FLOORING (RF)
MFG:
STYLE:
COLOR:
SIZE:
THICKNESS:
2017 OHIO BUILDING CODE (OBC)
PH
ON
E
919.6
83.1
084
150 F
AYETTEV
ILLE S
TREET
RA
LEIG
H,
NC
27601
SU
ITE 8
20
RALEIG
H
PH
ON
E
614.4
86.1
960
274 M
ARC
ON
I BLV
D
CO
LU
MBU
S,
OH
43215
SU
ITE 2
00
CO
LU
MBU
S
PH
ON
E
513.2
71.1
634
302 W
EST 3
RD S
TREET
CIN
CIN
NA
TI,
OH
45202
SU
ITE 5
00
CIN
CIN
NATI
websi
te
ww
w.b
hdp.c
om
This
do
cu
men
t is
the
pro
du
ct a
nd
pro
pe
rty o
f B
axte
r H
od
ell
Don
ne
lly P
resto
n,
Inc.
N
eith
er
the
docum
ent
no
r th
e info
rma
tio
n it
co
nta
ins m
ay b
e c
opie
d o
r used
for
oth
er
than
th
e s
pecific
pro
ject
for
whic
h it w
as p
rep
are
d w
itho
ut
the w
ritte
n c
onsen
t o
f B
axte
r H
ode
ll D
onn
elly
Pre
sto
n, In
c.
1 2 3 4 5 6 7 8 10 11 12 13 14 15 16 17
B
A
9
1 2 3 4 5 6 7 8 10 11 12 13 14 15 16 179
Drawn
Project Manager
Checked
Contract Drawing Date
Project Number
Q
P
N
M
L
K
J
H
G
F
E
D
C
B
A
18 19
18 19
Q
P
N
M
L
K
J
H
G
F
E
D
C
B
PAUL D. ORBAN, LICENSE #13276EXPIRATION DATE: 12/31/2018
C:\Users\bhosfeld\Documents\Cadaver [email protected] 2/7/2018 9:38:58 AM
B.HOSFELD
P. ORBAN
L. BROCKWAY
01/15/18
MRN01.01
C-A101
FIR
ST
FLO
OR
PLA
N, D
EM
O P
LA
N, R
CP
'S, A
ND
LIF
E S
AF
ET
Y P
LA
N
CA
DA
VE
R L
AB
AN
D H
TC
RE
NO
VA
TIO
NS
MA
RI O
N T
EC
HN
I CA
L C
OLLE
GE
PR
AT
ER
EN
GIN
EE
RIN
G A
SS
OC
IAT
ES
GENERAL ARCHITECTURAL NOTES
CODED NOTES
001 REMOVE EXISTING PARTITION AS INDICATED. COORDINATE DEVICEREMOVAL WITH MEP.
002 REMOVE EXISTING DOOR, FRAME, AND HARDWARE IN ITSENTIRETY.
003 REMOVE EXISTING VCT FLOORING AND EXISTING BASE IN IT'SENTIRETY, INCLUDING ADHESIVES. PREPARE FLOOR FOR NEWFINISHES.
005 PORTION OF WALL TO BE REMOVED. REFER TO NEW WORK PLANFOR EXTENT.
006 REMOVE PLUMBING FIXTURE AND CASEWORK. CAP EXISTINGPLUMBING LINES AND LEAVE IN PLACE. REFER TO PLUMBINGDRAWINGS.
007 REMOVE EXISTING OPERABLE PARTITION TRACK IN ITS ENTIRETY,INCLUDING ALL SUPPORTS, STRUCTURE, AND HARDWARE.
008 REMOVE EXISTING OPERABLE PARTITION IN IT'S ENTIRETY,INCLUDING ALL SUPPORTS, HARDWARE, AND FRAMING. PATCH ANDREPAIR AS NECESSARY. ENSURE SURFACE IS READY FOR NEWFINISH.
009 REMOVE EXISTING ACT CEILING SYSTEM IN ITS ENTIRETY BACK TOSTRUCTURAL DECK ABOVE; INCLUDING BUT NOT LIMITED TOCEILING SYSTEM, HANGERS, LIGHTS AND ALL MEP ITEMS, REFER TOMEP DRAWINGS.
014 REMOVE EXISTING MILLWORK BASE CABINETS, WALL CABINETS,COUNTERTOP AND SINK. REFER TO PLUMBING DRAWINGS.
101 ALIGN
102 PATCH FLOORING TO MATCH EXISTING EXACTLY. TOOTH INTOEXISTING FLOORING. PROVIDE SAMPLE TO ARCHITECT FORAPPROVAL.
103 UNIVERSITY TO PROVIDE NEW 80" WALL MOUNTED MONITOR.CONTRACTOR TO PROVIDE AND INSTALL COMPATIBLE WALLMOUNT. COORDINATE WITH UNIVERSITY. PROVIDE ALLNECESSARY BLOCKING AND SUPPORT. PROVIDE NECESSARYPOWER. REFER TO ELECTRICAL DRAWINGS.
104 CONTRACTOR TO PROVIDE NEW CONCRETE PAD FOR MECHANICALEQUIPMENT. REFER TO MEP DRAWINGS. REFER TO TYPICALEXTERIOR MECHANICAL EQUIPMENT PAD DETAIL.
105 POWDER-COATED MECHANICAL EQUIPMENT SCREEN WALLPROVIDED AND INSTALLED BY CONTRACTOR. BASIS OF DESIGN ISOHIO GRATINGS INC. PW PRODUCT. CONTRACTOR TO PROVIDENECESSARY ATTACHMENT HARDWARE. SCREEN WALL TO BE 7'-0"HIGH. REFER TO SPEC. FOR FINISH. REFER TO TYPICAL EXTERIORMECHANICAL EQUIPMENT PAD DETAIL. COORDINATE WITHUNIVERSITY BEFORE ORDERING. PROVIDE POWDER-COATINGFINISH.
107 UNIVERSITY TO PROVIDE AND INSTALL STAND-ALONE CARDREADER.
108 CUT FLOOR FOR NEW FLOOR DRAIN. PATCH AND REPAIRSURROUNDING FLOOR. PREPARE FLOOR FOR NEW FINISH. REFERTO PLUMBING DRAWINGS FOR EXACT SIZE AND LOCATION.
109 CUT FLOOR FOR NEW FLOOR BOX OUTLET. PATCH AND REPAIRSURROUNDING FLOOR. PREPARE FLOOR FOR NEW FINISH. REFERTO ELECTRICAL DRAWINGS FOR EXACT SIZE AND LOCATION.
110 CONTRACTOR TO PROVIDE STEEL-POST TO SUPPORT MECHANICALSCREEN WALL PANELS. COORDINATE POST SPACING WITH SCREENWALL MANUFACTURER. POWDER-COAT TO MATCH THAT OFSCREEN WALL PANELS. REFER TO TYPICAL EXTERIOR MECHANICALEQUIPMENT PAD DETAIL.
111 METAL FABRICATED SCREEN WALL DOOR. CONTRACTOR TOPROVIDE ALL NECESARRY METAL TUBING. METAL SCREEN WALLPANEL IN NOTE 105 TO BE PROVIDED IN DOORS. PROVIDE ALLNECESSARY MOUNTING HARDWARE. COORDINATE DESIGN WITHARCHITECT BEFORE ORDERING. PROVIDE POWDER-COAT FINISH.
N
1/4" = 1'-0"C-A101
01 FIRST FLOOR PLAN AND FURNITURE PLANN
1/8" = 1'-0"C-A101
02 FIRST FLOOR DEMOLITION PLAN
REFLECTED CEILING PLAN LEGENDGENERAL RCP NOTES
GENERAL DEMOLITION NOTES
DEMOLITION PLAN LEGEND
N
1/8" = 1'-0"C-A101
04 FIRST FLOOR DEMOLITION RCP
N
1/8" = 1'-0"C-A101
3 FIRST FLOOR RCP
N
1/8" = 1'-0"C-A101
5 FIRST FLOOR LIFE SAFETY PLAN
FINISH LEGEND
GENERAL FINISH PLAN NOTES
N
1/8" = 1'-0"C-A101
6 FIRST FLOOR FINISH PLAN
No.
Issue
/Revis
ion
/Subm
issio
nD
ate
3C
ON
TR
AC
T D
OC
UM
EN
TS
01
/15/1
8
4A
DD
EN
DU
M 2
02
/08/1
8
4
4
1. CONTRACTOR TO PROVIDE BLOCKING IN PARTITIONS FOR PARTITION MOUNTED ITEMS AS INDICATED. CONTRACTOR ALSO TO COORDINATE QUANTITY AND LOCATIONS WITH THE OWNER FOR OWNER FURNISHED / CONTRACTOR INSTALLED ITEMS.
2. PARTITIONS ARE EXISTING TO REMAIN UNLESS NOTED ON PLAN.
1 2 3-X
F = FRAME WIDTH1 1/2" AT ALUMINUM FRAMES2" AT HOLLOW METAL FRAMES2" AT STOREFRONT FRAMES
F WIDTH F
FH
EIG
HT
HE
IGH
T4"
FWIDTHF
4"H
EIG
HT
F WIDTH F X F
4"
F FG
HE
IGH
T
WIDTH WIDTH
HE
IGH
T
6"1'
- 0
"
6"6"
AL = ALUMINUMEX = EXISTINGF = FLUSHFG = FULL GLASSFIN = FINISHHG = HALF GLASSHM = HOLLOW METALMATL = MATERIALNL = NARROW LITE
RATED ASSEMBLY TYPE:- = NOT A RATED ASSEMBLYA = SMOKE PARTITIONB = FIRE PARTITIONC = FIRE BARRIERD = FIRE & SMOKE BARRIERE = RATED STRUCTUREF = RATED STRUCTURE &
SMOKE BARRIERG = FIRE WALL
8"
1' -
6"
3' -
6"
6' -
8"
8" 4 1/8"
LOCATIONS FOR DOORS W/O SIDELITES
ADA COMPLIANT FIRE STROBE ALARM
THERMOSTAT / C02 / RELATIVE HEAT SENSORS
PROJECTOR SCREEN SWITCH
LIGHT SWITCHES-GANG ALL SWITCH WHERE POSSIBLE
NOTE: LOCATIONS SHOWN ARE TYPICAL FOR ALL DOORS WHETHER DOOR RECEIVES ALL ITEMS LISTED OR NOT. CONSULT ARCHITECT FIELD REP. FOR NON-TYPICAL CONDITIONS WHERE OBSTACLES/DIMENSIONS MAKE TYPICAL INSTALLATION VOID.
8"
1' -
6"
3' -
6"
6' -
8"
DOOR SHOWN IN OPEN POSITION.
ADA COMPLIANT FIRE STROBE ALARM.
THERMOSTAT/C02/RELATIVE HUMIDITY SENSORS
INTERIOR OF ROOM
LIGHT SWITCHES - GANG ALL SWITCHES WHERE POSSIBLE
NOTE: LOCATIONS SHOWN ARE TYPICAL FOR ALL DOORS WHETHER DOOR RECEIVES ALL ITEMS LISTED OR NOT. CONSULT ARCHITECT FIELD REP. FOR NON-TYPICAL CONDITIONS WHERE OBSTACLES/DIMENSIONS MAKE TYPICAL INSTALLATION VOID.
STRUCTURE
SEALANT, FIRE RATEDWHERE REQUIRED
PARTITION TO STUCTURE
ACOUSTICAL SEALANT
DEFLECTION TRACK
5/8" GYPSUM WALL BOARD
SAFING INSULATION
1"
FIRE RATED SEALANT, 1/2" OVERLAP, BOTH SIDES
*UL: HW-D-0042
FIRE STOP IN FLUTES AT
RATED POINTS
ACOUSTICAL SEALANT
REFER TO FLOOR PLAN FOR PARTITION TYPE
MATCH WALL DEPTH UP TO 8", HOLD GLAZED SIDE OF FRAME FLUSH WITH CMU
CONCRETE MASONRY UNIT
LINTEL, REFER TO STRUCTURAL
SEALANT AT BOTH SIDES
HOLLOW METAL FRAME
GROUT AS REQUIRED FOR FIRE RATING
4"
METAL STOP
GLAZING - SEE SCHEDULE
#4 @ 12" O.C. E.W.
#4 @ 16" O.C.
OPTIONAL CONST. JT.
CONC. GRADE BM. W/ (1) #5 CONT. TOP & BOT. (TYP. ALL SIDES OF PAD)
3' -
0"
MIN
.6
"
6"
CHAMFER / EASE ALL EDGES
CONTRACTOR INVOLVED
VERIFY SIZE REQUIRED W/
8"
W/ CONT'R
COORD. T/PAD
2'-6"2'-6"
2" RIGID INSULATION
8"
HSS4X4X3/16 POST
1/2" X 7" SQ. BASE PLATE
(4) 1/2" Ø EPOXY ANCHORS W/ 4" MIN. EMBED.
54
601601601601
111 111
TYP.110
TYP.105
*NOTE: CONSTRUCTION OF MECHANICAL SCREEN WALL TO MATCH THAT OF EXISTING SCREEN WALL ON CAMPUS AS CLOSELY AS POSSIBLE.
PH
ON
E
919.6
83.1
084
150 F
AYETTEV
ILLE S
TREET
RA
LEIG
H,
NC
27601
SU
ITE 8
20
RALEIG
H
PH
ON
E
614.4
86.1
960
274 M
ARC
ON
I BLV
D
CO
LU
MBU
S,
OH
43215
SU
ITE 2
00
CO
LU
MBU
S
PH
ON
E
513.2
71.1
634
302 W
EST 3
RD S
TREET
CIN
CIN
NA
TI,
OH
45202
SU
ITE 5
00
CIN
CIN
NATI
websi
te
ww
w.b
hdp.c
om
This
do
cu
men
t is
the
pro
du
ct a
nd
pro
pe
rty o
f B
axte
r H
od
ell
Don
ne
lly P
resto
n,
Inc.
N
eith
er
the
docum
ent
no
r th
e info
rma
tio
n it
co
nta
ins m
ay b
e c
opie
d o
r used
for
oth
er
than
th
e s
pecific
pro
ject
for
whic
h it w
as p
rep
are
d w
itho
ut
the w
ritte
n c
onsen
t o
f B
axte
r H
ode
ll D
onn
elly
Pre
sto
n, In
c.
1 2 3 4 5 6 7 8 10 11 12 13 14 15 16 17
B
A
9
1 2 3 4 5 6 7 8 10 11 12 13 14 15 16 179
Drawn
Project Manager
Checked
Contract Drawing Date
Project Number
Q
P
N
M
L
K
J
H
G
F
E
D
C
B
A
18 19
18 19
Q
P
N
M
L
K
J
H
G
F
E
D
C
B
PAUL D. ORBAN, LICENSE #13276EXPIRATION DATE: 12/31/2018
112 3' - 6" 7' - 0" F WD ST -- 3-30 HM PT NR 3&5/C-A700 4,6,&8/C-A700 7/C-A700
112A 3' - 0" 7' - 0" F WD ST -- 1 HM PT -- 1/C-A700 2/C-A700 --
112B 3' - 0" 7' - 0" F WD ST -- 1 HM PT -- 1/C-A700 2/C-A700 --
118 3' - 0" 7' - 0" F WD ST -- 2 HM PT -- 3/C-A700 4/C-A700 --
GENERAL ARCHITECTURAL NOTES
CODED NOTES
105 POWDER-COATED MECHANICAL EQUIPMENT SCREEN WALL PROVIDEDAND INSTALLED BY CONTRACTOR. BASIS OF DESIGN IS OHIO GRATINGSINC. PW PRODUCT. CONTRACTOR TO PROVIDE NECESSARYATTACHMENT HARDWARE. SCREEN WALL TO BE 7'-0" HIGH. REFER TOSPEC. FOR FINISH. REFER TO TYPICAL EXTERIOR MECHANICALEQUIPMENT PAD DETAIL. COORDINATE WITH UNIVERSITY BEFOREORDERING. PROVIDE POWDER-COATING FINISH.
110 CONTRACTOR TO PROVIDE STEEL-POST TO SUPPORT MECHANICALSCREEN WALL PANELS. COORDINATE POST SPACING WITH SCREENWALL MANUFACTURER. POWDER-COAT TO MATCH THAT OF SCREENWALL PANELS. REFER TO TYPICAL EXTERIOR MECHANICAL EQUIPMENTPAD DETAIL.
111 METAL FABRICATED SCREEN WALL DOOR. CONTRACTOR TO PROVIDEALL NECESARRY METAL TUBING. METAL SCREEN WALL PANEL IN NOTE105 TO BE PROVIDED IN DOORS. PROVIDE ALL NECESSARY MOUNTINGHARDWARE. COORDINATE DESIGN WITH ARCHITECT BEFOREORDERING. PROVIDE POWDER-COAT FINISH.