MDOT. I-94 Acclerated Construction Technology Detroit, Michigan April 17-19, 2007. ACTT WORKSHOP. MDOT ACTT WORKSHOP. UTILITIES/ RAILROAD COORDINATION Initial Presentation. Utilities/Railroad Coordination. Team Members Marion Leaphart, Utilities Manager, SC DOT - PowerPoint PPT Presentation
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: ACTT WORKSHOP
Page 2: ACTT WORKSHOP

MDOT ACTT WORKSHOP

UTILITIES/ RAILROADCOORDINATION

Initial Presentation

Page 3: ACTT WORKSHOP

Utilities/Railroad CoordinationTeam MembersMarion Leaphart, Utilities Manager, SC DOTVeena Jasuja, MDOT, Detroit TSCNick Lefke, MDOT, Lansing, DesignBill Stonebrook, MDOT, Lansing, DesignSteve Rapp, MDOT, Lansing, DesignFacilitator:Anu Taneja, MDOT, Lansing, Contract ServicesNotes:Lynn Venturino, MDOT, Lansing, Design Support

Page 4: ACTT WORKSHOP

Goals for Skill Set

• Identify utility relocation opportunities (public and private)

• Define ideas to maintain railroad traffic

• Coordinate placement of fiber optic utilities with the railroad ROW

• Identify issues with existing utilities

Page 5: ACTT WORKSHOP

Designate a full time MDOT Utilities Coordinator

• Oversee all aspects of utility coordination

• Act as “go to” person for MDOT and utilities.

• Report to project manager or have final authority for utility coordination

• Streamline communication between other skill sets

Page 6: ACTT WORKSHOP

Utilize Subsurface Utility Engineering (SUE)

• Have a SUE provider available during the design phase

• Update the current SUE data• Make full use of all data • Share the SUE deliverables

with other skill sets and utilities• Expedited utility information to

resolve conflicts

Page 7: ACTT WORKSHOP

Identify and resolve major municipal utility issues

• Early and often involvement of utilities

• Identify potential “show stoppers” early

• Identify all relocation work• Identify all new work

Page 8: ACTT WORKSHOP

Identify and resolve private/public utility issues• Early and often involvement of

utilities• Identify potential “show stoppers”

early• Identify all relocation work• Identify all new work• Identify reimbursable relocations• Advance utility relocation• Coordination with other skill sets

Page 9: ACTT WORKSHOP

Incentives• Participate in preliminary

engineering costs for private/public utilities

• Pilot project

Page 10: ACTT WORKSHOP

Form steering committee comprised of high level MDOT and RR officials

• Expedite railroad decision making

• Improve communications between RR and MDOT

Page 11: ACTT WORKSHOP

Form a Design Engineering Committee

• Early identification of design constraints

• Early and often involvement of railroads

• Identify potential “show stoppers” early

Page 12: ACTT WORKSHOP

Contract with qualified vendor knowledgeable in

RR operations and in securing RR approvals

• Designate MDOT RR expert

for consultant selection of RR coordination