Study Committee A3 HIGH VOLTAGE EQUIPMENT Working Group Activity Report WG A3.24 AR 2014 Page No.: 1 Activity Report 2014 WG A3.24 Tools for Simulating Internal Arc Testing Convener: Nenad Uzelac (USA) Secretary: Mietek Glinkowski (USA) Year of Kick-off: 2009 Number of Members: 20 Regular Members: 19 Corresponding Members: 1 Retiring Members: No retiring members New Members: Proposed for approval by SC A3 No new members A3-14(AG01)023-IWD
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Study Committee A3 HIGH VOLTAGE EQUIPMENT
Working Group Activity Report WG A3.24 AR 2014 Page No.: 1
Activity Report 2014
WG A3.24 Tools for Simulating Internal Arc TestingConvener: Nenad Uzelac (USA)Secretary: Mietek Glinkowski (USA)
Year of Kick-off: 2009
Number of Members: 20
Regular Members: 19
Corresponding Members: 1
Retiring Members: No retiring members
New Members:Proposed for approval by SC A3
No new members
A3-14(AG01)023-IWD
Study Committee A3 HIGH VOLTAGE EQUIPMENT
Working Group Activity Report WG A3.24 AR 2014 Page No.: 2
Technical activities & discussion items
Meetings:• First meeting in Delft, Holland (March 2009)
• 10th meeting in San Sebastian, Spain (January 2013)
• 11th (and Last) held in Stockholm, Sweden (June 2013)
• Attendance: 60% on average.
• Used Skype effectively.
Study Committee A3 HIGH VOLTAGE EQUIPMENT
WG A3.24 AR 2014
Progress of work:• Completed short Tutorial (1 hour)
• Completed REV 11 of the technical brochure
• Submitted TB to Technical Committee
Working Group Activity Report Page No.: 3
Technical activities & discussion items (cont)
130 pages
7 ANNEXES 60 pages
Study Committee A3 HIGH VOLTAGE EQUIPMENT
Working Group Activity Report WG A3.24 AR 2014 Page No.: 4
Next StepsPublication on behalf of the WG (Title, way of publication, stage of preparation, approximate date of final version