Top Banner
ACEC/NCDOT Spliced Girder Workshop 1 Reid W. Castrodale, PhD, P.E. Carolina Stalite Company Salisbury, NC ACEC/NCDOT Spliced Girder Workshop January 9, 2007
22

ACEC/NCDOT Spliced Girder Workshop · 2012-08-06 · 2 ACEC/NCDOT Spliced Girder Workshop • Fabricate girders in pieces shorter than final structure-For fabrication, handling...

Mar 19, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: ACEC/NCDOT Spliced Girder Workshop · 2012-08-06 · 2 ACEC/NCDOT Spliced Girder Workshop • Fabricate girders in pieces shorter than final structure-For fabrication, handling ortransportation-Partial

ACEC/NCDOT Spliced Girder Workshop

1

Reid W. Castrodale, PhD, P.E.Carolina Stalite Company

Salisbury, NC

ACEC/NCDOT Spliced Girder WorkshopJanuary 9, 2007

Page 2: ACEC/NCDOT Spliced Girder Workshop · 2012-08-06 · 2 ACEC/NCDOT Spliced Girder Workshop • Fabricate girders in pieces shorter than final structure-For fabrication, handling ortransportation-Partial

2

ACEC/NCDOT Spliced Girder Workshop

• Fabricate girders in pieces shorter thanfinal structure- For fabrication, handling or

transportation- Partial or full span segments

• Assembled at site to obtain finalstructure

• Cast-in-place concrete at splices• Post-tensioning is typically used to join

the pieces

Spliced Girder Bridges

Page 3: ACEC/NCDOT Spliced Girder Workshop · 2012-08-06 · 2 ACEC/NCDOT Spliced Girder Workshop • Fabricate girders in pieces shorter than final structure-For fabrication, handling ortransportation-Partial

3

ACEC/NCDOT Spliced Girder Workshop

Spliced Concrete GirdersMakes long-span concrete solutions viable

• Provides a new design alternate thatleads to improved economy

Not a new concept• Built in US as early as 1954

Can lead to dramatic span increases

Details are very important

Page 4: ACEC/NCDOT Spliced Girder Workshop · 2012-08-06 · 2 ACEC/NCDOT Spliced Girder Workshop • Fabricate girders in pieces shorter than final structure-For fabrication, handling ortransportation-Partial

4

ACEC/NCDOT Spliced Girder Workshop

Overview• Introduction• Reasons to use spliced girders• Typical applications• Basic concepts and special issues• Examples of spliced girder bridges• NCHRP Report 517

Page 5: ACEC/NCDOT Spliced Girder Workshop · 2012-08-06 · 2 ACEC/NCDOT Spliced Girder Workshop • Fabricate girders in pieces shorter than final structure-For fabrication, handling ortransportation-Partial

5

ACEC/NCDOT Spliced Girder Workshop

Reasons to Use Spliced Concrete Girders• Design Issues• Construction Issues• Economical Issues

Page 6: ACEC/NCDOT Spliced Girder Workshop · 2012-08-06 · 2 ACEC/NCDOT Spliced Girder Workshop • Fabricate girders in pieces shorter than final structure-For fabrication, handling ortransportation-Partial

6

ACEC/NCDOT Spliced Girder Workshop

Design IssuesProvide longer spans

• Avoid placing piers in water• Avoid other obstacles• Eliminate piers for safety• Reduce number of substructure units• Minimize structure depth• Reduce number of girder lines• Eliminate joints• Improve aesthetics• Continuity for seismic or impact loads

Page 7: ACEC/NCDOT Spliced Girder Workshop · 2012-08-06 · 2 ACEC/NCDOT Spliced Girder Workshop • Fabricate girders in pieces shorter than final structure-For fabrication, handling ortransportation-Partial

7

ACEC/NCDOT Spliced Girder Workshop

Construction IssuesFull-span girders are too large

• Fabrication and handling• Transportation• Erection

Depends on • Fabricator’s facility and equipment• Access to the site• Contractor’s preferences and equipment

Page 8: ACEC/NCDOT Spliced Girder Workshop · 2012-08-06 · 2 ACEC/NCDOT Spliced Girder Workshop • Fabricate girders in pieces shorter than final structure-For fabrication, handling ortransportation-Partial

8

ACEC/NCDOT Spliced Girder Workshop

Economical IssuesGenerally requires a compelling issue

• Reduced construction costs• Reduced fabrication time• Increased costs for PT• Increased costs for temporary supports

New approaches to contracts whereContractors are lead party

• Design/Build• Value Engineering

Page 9: ACEC/NCDOT Spliced Girder Workshop · 2012-08-06 · 2 ACEC/NCDOT Spliced Girder Workshop • Fabricate girders in pieces shorter than final structure-For fabrication, handling ortransportation-Partial

9

ACEC/NCDOT Spliced Girder Workshop

Typical Applications• Simple Spans• Continuous Spans• Seismic Applications

Page 10: ACEC/NCDOT Spliced Girder Workshop · 2012-08-06 · 2 ACEC/NCDOT Spliced Girder Workshop • Fabricate girders in pieces shorter than final structure-For fabrication, handling ortransportation-Partial

10

ACEC/NCDOT Spliced Girder Workshop

Simple Spans• Very long spans

- Single Point Urban Interchanges (SPUIs)

• Remote sites• Sites with limited access• Limitations of fabricator’s or contractor’s

equipment

Page 11: ACEC/NCDOT Spliced Girder Workshop · 2012-08-06 · 2 ACEC/NCDOT Spliced Girder Workshop • Fabricate girders in pieces shorter than final structure-For fabrication, handling ortransportation-Partial

11

ACEC/NCDOT Spliced Girder Workshop

Continuous Spans• Very long spans

- Intracoastal Waterway- Other waterways- Viaducts

• Minimum depth or fewer girders• Limited substructure locations

Page 12: ACEC/NCDOT Spliced Girder Workshop · 2012-08-06 · 2 ACEC/NCDOT Spliced Girder Workshop • Fabricate girders in pieces shorter than final structure-For fabrication, handling ortransportation-Partial

12

ACEC/NCDOT Spliced Girder Workshop

Seismic Applications• Continuity• Integral connection to substructure

(integral caps )• Compared to cast-in-place construction

- Eliminate or reduce falsework- More rapid construction

Page 13: ACEC/NCDOT Spliced Girder Workshop · 2012-08-06 · 2 ACEC/NCDOT Spliced Girder Workshop • Fabricate girders in pieces shorter than final structure-For fabrication, handling ortransportation-Partial

13

ACEC/NCDOT Spliced Girder Workshop

Basic Concepts & Design Issues• Design issues• Fabrication details• Erection details• Splice details• Post-tensioning and grouting

Page 14: ACEC/NCDOT Spliced Girder Workshop · 2012-08-06 · 2 ACEC/NCDOT Spliced Girder Workshop • Fabricate girders in pieces shorter than final structure-For fabrication, handling ortransportation-Partial

14

ACEC/NCDOT Spliced Girder Workshop

Design Issues• Post-tensioning

- Post-tensioned in the field for splicing, oftenstaged

- Losses- Secondary moments- Deformations during PT

Stage 1Tendons

Stage 2 Tendons – after deck cast

Page 15: ACEC/NCDOT Spliced Girder Workshop · 2012-08-06 · 2 ACEC/NCDOT Spliced Girder Workshop • Fabricate girders in pieces shorter than final structure-For fabrication, handling ortransportation-Partial

15

ACEC/NCDOT Spliced Girder Workshop

Design IssuesRestrained deformations

• Time-dependent effect may becomesignificant

• More refined analysis

Cross-section types• I- or Bulb Tee girders• Open-topped boxes

Page 16: ACEC/NCDOT Spliced Girder Workshop · 2012-08-06 · 2 ACEC/NCDOT Spliced Girder Workshop • Fabricate girders in pieces shorter than final structure-For fabrication, handling ortransportation-Partial

16

ACEC/NCDOT Spliced Girder Workshop

Fabrication IssuesPost-tensioning ducts

End blocks and anchorages

Haunched pier segments

More intensive fabrication effort

Page 17: ACEC/NCDOT Spliced Girder Workshop · 2012-08-06 · 2 ACEC/NCDOT Spliced Girder Workshop • Fabricate girders in pieces shorter than final structure-For fabrication, handling ortransportation-Partial

17

ACEC/NCDOT Spliced Girder Workshop

Erection IssuesTemporary towers

Strong-backs

Launching

Splicing before placement

Page 18: ACEC/NCDOT Spliced Girder Workshop · 2012-08-06 · 2 ACEC/NCDOT Spliced Girder Workshop • Fabricate girders in pieces shorter than final structure-For fabrication, handling ortransportation-Partial

18

ACEC/NCDOT Spliced Girder Workshop

Splice DetailsDuct splicing

Wet joints

Match-cast or machined forms

Shear keys

Page 19: ACEC/NCDOT Spliced Girder Workshop · 2012-08-06 · 2 ACEC/NCDOT Spliced Girder Workshop • Fabricate girders in pieces shorter than final structure-For fabrication, handling ortransportation-Partial

19

ACEC/NCDOT Spliced Girder Workshop

Post-Tensioning & GroutingDetails

Procedures

Specifications

Inspection• Construction• Long-term

•Continue

Page 20: ACEC/NCDOT Spliced Girder Workshop · 2012-08-06 · 2 ACEC/NCDOT Spliced Girder Workshop • Fabricate girders in pieces shorter than final structure-For fabrication, handling ortransportation-Partial

ACEC/NCDOT Spliced Girder Workshop

Examples of Spliced Girder Bridges

Page 21: ACEC/NCDOT Spliced Girder Workshop · 2012-08-06 · 2 ACEC/NCDOT Spliced Girder Workshop • Fabricate girders in pieces shorter than final structure-For fabrication, handling ortransportation-Partial

21

ACEC/NCDOT Spliced Girder Workshop

Examples of Spliced Girder Bridges

Simple Spans• Remote Site• Urban Site

Continuous Spans• Urban Site• Interstate Crossing• Rivers & Coastal• Seismic

Page 22: ACEC/NCDOT Spliced Girder Workshop · 2012-08-06 · 2 ACEC/NCDOT Spliced Girder Workshop • Fabricate girders in pieces shorter than final structure-For fabrication, handling ortransportation-Partial

22

ACEC/NCDOT Spliced Girder Workshop

Spliced Concrete Girder Projects

Simple Spans• Klickitat County, WA• Rock Cut Bridge, WA• I-15 Reconstruction, Salt Lake City, UT

•Continue