18 Jan 2006 PS & SPS Days Controls, Safety and Engineering Databases Access Safety Systems Modifications & tests in 2006 Presented by Rui Nunes TS-CSE-AAS
Feb 02, 2016
18 Jan 2006 PS & SPS Days
Controls, Safety and Engineering Databases
Access Safety SystemsModifications & tests in 2006
Presented byRui Nunes
TS-CSE-AAS
18 Jan 2006 PS & SPS Days
Controls, Safety and Engineering Databases
Topics
• Introduction– SPS project organisation
• SPS Primary Access System– INB Constraints– Project & Implications for 2006 (and beyond...)– SPS from CCC
• PS Primary Access System– Control from CCC / CSA– Long-term plan & constraints
• PS & SPS Experimental Areas Access System– Ongoing project
18 Jan 2006 PS & SPS Days
Controls, Safety and Engineering Databases
Introduction
• TS-CSE-AAS (all projects)– PS team : R. Bonzano, D. Chapuis– SPS team : M. Grill, R. Villard
• SPS Projects– SPS Primary system reengineering
• P. Lienard : Project Leader• G. Robin, C. Arimatea – AB/OP collaborators
– SPS INB documentation and safety studies• E. Manola-Poggioli• S. Grau
• PS Projects– PS CCC
• F. Havart, L. Hammouti, O. Ratcliffe, J. Duran-Lopez - AB/OP– (S)PS Experimental Areas
• H. Nissen, F. Havart
18 Jan 2006 PS & SPS Days
Controls, Safety and Engineering Databases
SPS Access Safety System - INB
• The SPS is now considered as part of an INB– “Installations Nucléaire de Base”
• Compliance problem– current SPS Access Safety System is
• PLC-based • Not redundant• Does not comply with the major criteria sought by the
INB authorities :– Common cause of failure
18 Jan 2006 PS & SPS Days
Controls, Safety and Engineering Databases
SPS Access Safety System
• Compensatory measures– Phase 1 - 2006 During Run
• Interlocking of 4 critical access doors in AUG !!• Blocking / Condemning all other doors
• SPS Reengineering – Phase 2 - 2006-2007 shutdown
• Development of a separate cabled loop to provide redundancy to PLC system (like LHC)
• Preparing for complete replacement of SPS Access Safety & Access Control Systems
– Phase 3 - 2007 and beyond• Deploy new access control in a phased manner
18 Jan 2006 PS & SPS Days
Controls, Safety and Engineering Databases
ATTENTION !!
Ouverture de cette Porte provoque
AUG
18 Jan 2006 PS & SPS Days
Controls, Safety and Engineering Databases
VETO Access
VETO Beam
18 Jan 2006 PS & SPS Days
Controls, Safety and Engineering Databases
SPS from CCC
Consoles are being put in place as we speak– “Old” LEP consoles (ugly
consoles – sorry…)
– Will stay until new SPS access system is functional
– 1 day access interruption to reconnect cables and test
Drawing by M. Grill
18 Jan 2006 PS & SPS Days
Controls, Safety and Engineering Databases
SPS from CCC
• SPS Access system has to be completely re-tested after 1 year of complete shutdown– 2 weeks technical verification– 3 days final testing before run
• Operation guidelines shall be given to AB/OP by project team– Patrol before run– Opening of machine
18 Jan 2006 PS & SPS Days
Controls, Safety and Engineering Databases
PS Primary Access Safety System
18 Jan 2006 PS & SPS Days
Controls, Safety and Engineering Databases
PS from CCC
• PLC-based safety signals– Key interlocks– Via optical fibres
• Supervision Hardwired Virtual– Hardwired console replaced by TIM
Virtual console
• CCC or CSA (not both)– Possibility to delegate to CSA if
needed during shutdown– No beam operation possible from
CSA Drawing by R. Bonzano
18 Jan 2006 PS & SPS Days
Controls, Safety and Engineering Databases
PS from CCC
• Control from CSA since November 2005• Control from CCC planned from 4/Feb/2006
“Genevoise” in MCR TIM Virtual Console in CCC
Drawing by R. Bonzano
18 Jan 2006 PS & SPS Days
Controls, Safety and Engineering Databases
PS Primary Access in the Long term
• PS Access system is an ageing system– Has suffered many modifications and has many layers due to
different technology for each modification– Must be replaced soon
• Not possible to maintain actual system much longer
• Should be replaced by LHC-type Access • Main difficulty
– PS has doors not “SAS” or turnstiles– Doors do not guarantee unique passage– Solution
• Either install “sas” or turnstiles• Or accept CCC operator supervision (maybe not acceptable)
• In any case investment is high but necessary– Risk is high : no PS no SPS no LHC beams
18 Jan 2006 PS & SPS Days
Controls, Safety and Engineering Databases
PS Experimental Areas
• Project to revamp PS Experimental areas has continued– Delayed by the PS CCC project– Implementation objective :
• AD Experimental area access control for 2006 Run• East Hall revamp during 2006-7 shutdown
– Extension to SPS if according to need
• Safety PLC-based system– 1 PLC per zone– 1 master PLC concentrator per “Super Zone”– Interface by physical pin matrix for zone re-configuration– Documentation available for the moment
• EDMS URD : 476292, SRD : 478678, ADD : 503535
• Accounts for requirements of PS and SPS– can be supervised remotely by the CCC via TIM
18 Jan 2006 PS & SPS Days
Controls, Safety and Engineering Databases
Drawing by R. Nunes & Access team
18 Jan 2006 PS & SPS Days
Controls, Safety and Engineering Databases
Conclusion
• CCC– No major problems in sight, but last phase due in the coming
weeks
• SPS Primary– Tight schedule constraints and uncertainties as to SPS
Access Control system renovation
• PS Primary– We have made the last major change (CCC) that will ever be
made before renovation is due
• (S)PS Experimental areas– A project constantly delayed by other projects
18 Jan 2006 PS & SPS Days
Controls, Safety and Engineering Databases
Thank you for your attention
Questions?
(hopefully answers too…..)