Accelerator Complex Controls Renovation Workshop, LHC excluded Beam Transfer Etienne CARLIER on behalf of the AB/BT Group Thanks to Jan BORBURGH, Tony FOWLER and Jan SCHIPPER
12

Accelerator Complex Controls Renovation Workshop, LHC excluded Beam Transfer

Feb 24, 2016

Download

Documents

Baby

Accelerator Complex Controls Renovation Workshop, LHC excluded Beam Transfer. Etienne CARLIER on behalf of the AB/BT Group Thanks to Jan BORBURGH, Tony FOWLER and Jan SCHIPPER. Outline. Motivation Strategy Initial Conditions Work Packages Concerns and Issues Summary. - PowerPoint PPT Presentation
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Accelerator Complex Controls Renovation Workshop, LHC excluded Beam Transfer

Accelerator Complex Controls Renovation Workshop, LHC excluded

Beam Transfer

Etienne CARLIER on behalf of the AB/BT Group

Thanks to Jan BORBURGH, Tony FOWLER and Jan SCHIPPER

Page 2: Accelerator Complex Controls Renovation Workshop, LHC excluded Beam Transfer

Outline

• Motivation• Strategy• Initial Conditions• Work Packages• Concerns and Issues• Summary

Accelerator Complex Controls Renovation Workshop, LHC excluded – Beam Transfer Etienne CARLIER – 03-12-2009

Page 3: Accelerator Complex Controls Renovation Workshop, LHC excluded Beam Transfer

PS

PSB

AD

LINACs

CTF3

LEIR

ISOLDEEast Hall

cvKicker

Electro-static septa

Electro-magnetic septa

Accelerator Complex Controls Renovation Workshop, LHC excluded – Beam Transfer Etienne CARLIER – 03-12-2009

Page 4: Accelerator Complex Controls Renovation Workshop, LHC excluded Beam Transfer

TI 2

TI 8

Kicker

Electro-static septa

Electro-magnetic septa

Extraction Protection devices

LHCSPS

Accelerator Complex Controls Renovation Workshop, LHC excluded – Beam Transfer Etienne CARLIER – 03-12-2009

Page 5: Accelerator Complex Controls Renovation Workshop, LHC excluded Beam Transfer

Motivation

• Clear indication of – AB/CO FEC performance limitation (RIO2) for BT equipment controls,– Decrease of reliability (end of bath curve) for equipment level hardware

under BT or CO responsibility.

• Good opportunity for – Eradication of obsolete of hardware,– Regain of expertise in low-level equipment controls (hardware &

software) and in integration of equipment controls in accelerator controls,

– Clarification of equipment controls responsibility between groups,– Homogenization of controls solutions (hardware & Software) within the

BT group.

Accelerator Complex Controls Renovation Workshop, LHC excluded – Beam Transfer Etienne CARLIER – 03-12-2009

Page 6: Accelerator Complex Controls Renovation Workshop, LHC excluded Beam Transfer

Strategy

• Renovation strategy for consolidation of BT equipment controls will be based on the responsibility sharing agreements between CO and equipment groups defined in the CO3 (so called “co-operative model”).

• Clear separation between the renovation of – “Accelerator Complex Controls” CO responsibility,– “Equipment low-level controls” BT responsibility.

• Renovation based 3 independent phases– Phase1: Identification with OP of missing operational functionality for the

control of BT equipment,– Phase2: Renovation of CO controls infrastructure and update to FESA of GM

classes on the basis of actual low-level hardware,– Phase3: Consolidation of low level hardware.

Accelerator Complex Controls Renovation Workshop, LHC excluded – Beam Transfer Etienne CARLIER – 03-12-2009

Page 7: Accelerator Complex Controls Renovation Workshop, LHC excluded Beam Transfer

Initial Conditions

Front-End Hardware

New FEC[CPU + OS]

Front-EndTiming

CTRx + LTIM

Front-End Software

FESA 2.10

Equipment Level Control

ConsolidationStatus

PS–Complex – Kickers 30% 20% 40% 50%

PS–Complex – Septa 10% 10% 10%

SPS – Kickers 10% 100% 100% 70%

SPS – Septa 50% 100% 100%

• FEC hardware situation– 21 VME – 18 RIO2 & 4 RIO3– 3 PC

• Migration to FESA 2.10 started• SL-EQUIP eradicated• MACSy eradicated• GM in progress

• Low-level control consolidation ongoing

Accelerator Complex Controls Renovation Workshop, LHC excluded – Beam Transfer Etienne CARLIER – 03-12-2009

Page 8: Accelerator Complex Controls Renovation Workshop, LHC excluded Beam Transfer

Work Packages

• Two different categories of work packages:– Category 1: Work packages induced by the “Accelerator Complex Controls

Renovation”,– Category 2: Work packages where renovation of equipment level controls

has no link with “Accelerator Complex Controls Renovation” or is planned to be done in accordance with “co-operative model”.

• For Category 1 work packages, no resources, manpower & budget, actually planned within BT. Some manpower resources can be retrieved from exploitation.

• For Category 2 work packages, resources, manpower & budget (including additional CO support) are planned within BT.

Accelerator Complex Controls Renovation Workshop, LHC excluded – Beam Transfer Etienne CARLIER – 03-12-2009

Page 9: Accelerator Complex Controls Renovation Workshop, LHC excluded Beam Transfer

Work PackagesCategory 1

Status Description Manpower

[FTE]

Cost

[kCHF]Draft In-source from AB/CO and consolidate PS-Complex

septa motion and slow control4 125

Draft In-source from AB/PO and consolidate PS-Complex electrostatic septa HV generator control

1 20

Draft Rationalise FECs used for control PS-Complex Septa system

0.5 10

Draft Migrate of GM classes to FESA for PS-Complex septa system

1.5 0

Draft Migrate from LynxOS to LINUX of existing FESA classes and FEC low level software

3 0

Accelerator Complex Controls Renovation Workshop, LHC excluded – Beam Transfer Etienne CARLIER – 03-12-2009

Planning to be in tune with CO

Page 10: Accelerator Complex Controls Renovation Workshop, LHC excluded Beam Transfer

Work PackagesCategory 2

Status Description Manpower

[FTE]

Cost

[kCHF]Active Migrate GM classes to FESA for PS-Complex kicker

system3 0

Active Consolidate PS-Complex kicker oil systems 4 150*Active Consolidate SPS LSS2 extraction electronics (end 2009) 4 300Active Consolidate AD Horn pulser electronics (Phase 1) 1.5 75

Planned Provide electronics for new SPS MKDV generators 4 250*Draft Consolidate SPS Kicker Timing Systems 2 150

* : Electronics & Controls part

Accelerator Complex Controls Renovation Workshop, LHC excluded – Beam Transfer Etienne CARLIER – 03-12-2009

Page 11: Accelerator Complex Controls Renovation Workshop, LHC excluded Beam Transfer

Open Issues / Concerns

• Responsibility clarification for – PS Complex Electro-static septa control (shared for the moment between AB/PO,

AB/CO & AB/BT),– Implementation of the “co-operative model” for slow & fast timing for kicker systems

across the injector chain.– Equipment control through generic classes.

• FEC sharing between different equipment group• Definition of FESA standard properties• Low-level controls homogeneity across the complete accelerator

complex (LHC included)– Same equipment level hardware and software used on 2 different platforms with 2

different operating systems,– Resources needed at equipment group level to maintain two different environments.

• OASIS

Accelerator Complex Controls Renovation Workshop, LHC excluded – Beam Transfer Etienne CARLIER – 03-12-2009

Page 12: Accelerator Complex Controls Renovation Workshop, LHC excluded Beam Transfer

Summary

• BT will follow the “Accelerator Complex Controls Renovation” as set up by the CO group.

• Expertise and manpower (from exploitation) available to perform the migration of GM classes to FESA.

• Ready to in-source some specific control functionalities only used by BT, but resources (funding and manpower) to be found.

• Some specific BT “non-blocking” technical issues still to be clarified with CO.

• Some concerns about resources needed to maintain a homogeneity at the low level across the complete accelerator chain.

Accelerator Complex Controls Renovation Workshop, LHC excluded – Beam Transfer Etienne CARLIER – 03-12-2009