1 ABUTMENTS, RIPRAP & SHORING Bridge Construction Inspection School Keith Weakley, PE Abutments
45

Abutments - Virginia Department of Transportation

Jan 08, 2022

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Abutments - Virginia Department of Transportation

1

ABUTMENTS, RIPRAP & SHORING

Bridge Construction Inspection School

Keith Weakley, PE

Abutments

Page 2: Abutments - Virginia Department of Transportation

2

Cantilever Abutment

Cantilever Abutment

Page 3: Abutments - Virginia Department of Transportation

3

Shelf Abutment

Shelf Abutment

Page 4: Abutments - Virginia Department of Transportation

4

Abutment Loads & Terminology

Stem

Toe

Heel

*

*

*

*- Indicates location of Reinforcing Steel to resist bending.

Gravity Abutment

Batter on Backwall

Page 5: Abutments - Virginia Department of Transportation

5

MSE Abutment

MSE Abutment

Page 6: Abutments - Virginia Department of Transportation

6

MSE Abutment

Straps

MSE Abutments (Shop Drawings)

Page 7: Abutments - Virginia Department of Transportation

7

MSE Abutment

Traditional Abutment

Page 8: Abutments - Virginia Department of Transportation

8

Traditional Abutment

Water Damage at Joints

Page 9: Abutments - Virginia Department of Transportation

9

Integral Bridges

Integral Abutment

Page 10: Abutments - Virginia Department of Transportation

10

Integral Abutment

Integral Abutment

Page 11: Abutments - Virginia Department of Transportation

11

Beam Support

Dowels

Page 12: Abutments - Virginia Department of Transportation

12

Semi-Integral

Semi-Integral

Page 13: Abutments - Virginia Department of Transportation

13

Semi-Integral

Semi-Integral-Forming

Formwork should NOT be attached to the substructure.

Page 14: Abutments - Virginia Department of Transportation

14

Semi-Integral

Deck Extension

Page 15: Abutments - Virginia Department of Transportation

15

Deck Extension

Rub Plates

Page 16: Abutments - Virginia Department of Transportation

16

Rub Plates

Rub Plates

Page 17: Abutments - Virginia Department of Transportation

17

Semi-Integral

Backfilling Integrals

Page 18: Abutments - Virginia Department of Transportation

18

Structural Backfill

Structural Backfill

Page 19: Abutments - Virginia Department of Transportation

19

Elastic Inclusion (EPS)

Elastic Inclusion (EPS)

Page 20: Abutments - Virginia Department of Transportation

20

Virginia Abutment

Virginia Abutment

Page 21: Abutments - Virginia Department of Transportation

21

Virginia Abutment

Virginia Abutment

Page 22: Abutments - Virginia Department of Transportation

22

Weepholes

Weep Holes

Weep holes are necessary to reduce water pressure behind the abutment. It is critical that they are installed correctly, since they are part of the design.

Page 23: Abutments - Virginia Department of Transportation

23

Weep Holes

“Lowest Point Feasible for Free Drainage” means as low as you can get it, but still be above the ground, once all of the final grading has been completed. The weep hole will be the top of the water table behind the abutment, so it needs to be as low as possible to minimize the water pressure.

Weep Holes

“Lowest Point Feasible for Free Drainage” means as low as you can get it, but still be above the ground, once all of the final grading has been completed. The weep hole will be the top of the water table behind the abutment, so it needs to be as low as possible to minimize the water pressure.

Page 24: Abutments - Virginia Department of Transportation

24

Weep Hole Alternatives

You may encounter abutments that have no weep hole, but instead a piped drainage system. Just ensure this is installed per plan and “daylighted” so that it drains properly.

Weep Hole Alternatives

You may encounter abutments that have no weep hole, but instead a piped drainage system. Just ensure this is installed per plan and “daylighted” so that it drains properly.

Page 25: Abutments - Virginia Department of Transportation

25

Wall Drain

Geocomposite Wall Drains (Ameridrain, Miradrain, etc). See Sec. 401.03 (2016 Specs).-Overlap-Filter Fabric-Installation

Tooth Expansion Joints (Finger Joints)

Page 26: Abutments - Virginia Department of Transportation

26

Tooth Expansion Joints (Finger Joints)

Tooth Expansion Joints

Page 27: Abutments - Virginia Department of Transportation

27

Tooth Expansion Joints

Tooth Expansion Joints-Things to remember

• Alignment is extremely important!

• Realignment will likely be necessary after the deck pour(s). Both Vertical and Horizontal.

• The Construction Joint at the Finger Joint is there for a reason!

Page 28: Abutments - Virginia Department of Transportation

28

Approach Slabs

Traditional Approach Slabs

Page 29: Abutments - Virginia Department of Transportation

29

Traditional Approach Slabs

Buried Approach Slabs

Page 30: Abutments - Virginia Department of Transportation

30

Buried Slabs

Buried Approach Slabs

Page 31: Abutments - Virginia Department of Transportation

31

Shoring

Pier Excavation

Page 32: Abutments - Virginia Department of Transportation

32

Sheet Piling

Sheeting & Attachments

Page 33: Abutments - Virginia Department of Transportation

33

Soldier Piles

Soldier Piles

Page 34: Abutments - Virginia Department of Transportation

34

Soldier Piles

Tie Backs

Page 35: Abutments - Virginia Department of Transportation

35

Strut & Waler

Shoring

Page 36: Abutments - Virginia Department of Transportation

36

Things to keep in Mind

• When driving sheeting/piles, be sure that the depth reached meets or exceeds that specified by the approved shoring plans.

•Closely inspect all connections, especially those to, or near the abutments, as this is usually the deepest part of the excavation.

• Be sure to compare the approved plans to what is actually built in the field. If there are any differences, let someone know!

Things to keep in Mind

• Most important, lives may be at stake. The shoring may be holding up the roadway, but at a minimum is holding the excavation open for the workers & Inspectors.

• Closely monitor the shoring for movement. If you are unsure whether there is a danger-call your Construction Manager, or the Bridge office.

Page 37: Abutments - Virginia Department of Transportation

37

Shoring Payment

• In response to claims, and in a effort to reduce them, the Temporary Shoring bid item has been changed from Square Yard to Lump Sum. Check the plans for your specific job for the verbiage, but you should find that the Lump Sum bid item includes anything required to retain the excavation.

Crib Walls

Page 38: Abutments - Virginia Department of Transportation

38

Wire Wall

Slope Protection & Riprap

Page 39: Abutments - Virginia Department of Transportation

39

Riprap

Riprap

Page 40: Abutments - Virginia Department of Transportation

40

Riprap

RiprapRiprap

Page 41: Abutments - Virginia Department of Transportation

41

Riprap

Riprap

Page 42: Abutments - Virginia Department of Transportation

42

Riprap

Filter Fabric

Aggregate Material

These are important to prevent fines from washing through and causing the riprap to fail. They are part of the scour protection system, along with the riprap.

Grouted Riprap

Page 43: Abutments - Virginia Department of Transportation

43

Grouted Riprap-WRONG!

Concrete Slope Protection

Page 44: Abutments - Virginia Department of Transportation

44

Concrete Slope Protection

Things to keep in Mind

• If the plan details show bedding material and filter cloth, then make sure the contractor installs these items.

• The correct installation of riprap/slope protection will almost always require excavation. Unless specified otherwise, the contractor does not get paid for this excavation.

Page 45: Abutments - Virginia Department of Transportation

45

Things to keep in Mind

• When installing grouted riprap, pay particular attention to the plan details. “Grouted” does not mean “flooded”. The grout should barely be visible from the surface.

• When installing riprap in the stream, refer to the environmental permit sketch in the contract. This will direct what operations are allowed. Any deviation must be cleared with the Environmental Section.

Questions