A.Blas A.Blas APC meeting 12/5/2005 APC meeting 12/5/2005 1 Status of the PS Status of the PS TFB TFB Project triggered by: K. Schindl and R. Cappi Hardware: J. Belleman (PU amplifiers) T. Bohl, W. Hofle, F. Pedersen, V. Rossi (Signal processing) F. Caspers, J.L. Gonzalez, J. M. Lacroix, J.M. Roux (Kickers) S. Livesley, J. Sladen (Local oscillator) R. Louwerse, M. Paoluzzi (Power amplifiers) R. Louwerse (Power transformers) S. Mathot (ceramics) Hardware simulations: W. Hofle, J. Tuckmantel, V. Vendramini, E. Vogel Beam decoherence study: E. Benedetto, M. Martini, E. Metral, F. Zimmermann 1.System block- diagram 2.Background 3.Hardware overview 4.Power requirements
17
Embed
A.Blas APC meeting 12/5/2005 1 Status of the PS TFB Project triggered by: K. Schindl and R. Cappi Hardware: J. Belleman (PU amplifiers) T. Bohl, W. Hofle,
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Status of the PS Status of the PS TFBTFBProject triggered by: K. Schindl and R. Cappi
Hardware: J. Belleman (PU amplifiers) T. Bohl, W. Hofle, F. Pedersen, V. Rossi (Signal processing) F. Caspers, J.L. Gonzalez, J. M. Lacroix, J.M. Roux (Kickers) S. Livesley, J. Sladen (Local oscillator) R. Louwerse, M. Paoluzzi (Power amplifiers) R. Louwerse (Power transformers) S. Mathot (ceramics)
Hardware simulations: W. Hofle, J. Tuckmantel, V. Vendramini, E. Vogel
Beam decoherence study: E. Benedetto, M. Martini, E. Metral, F. Zimmermann
1. System block-diagram2. Background3. Hardware overview4. Power requirements
01/03 Project taken over by rf – kicker under BDI responsibilityStatus: 3kW Power amplifiers available (100 kHz HP cutoff !)
Horizontal magnetic kicker ordered
10/03 Successful test of a new electronic prototype and Pick-up amplifierswith the old kicker/amplifier pair
01/04 H kicker Delivered, Ceramic pipe not vacuum tight after brazing (weak metallization)
10/04 Order placed for re-metallization (SCT) and new ceramic rings (Hiperceramics)Transition pieces redesigned
12/04 Kickers measured by rf team (F.C., T.K.) because of the absence of resource from BDI.Result: bandwidth below requirements – can not cope with kicker ripple.
Prototype has been tested in October 2003 for the MD session.Successful test although the automatic delay was not fast enough to cope with acceleration
New design ongoing using the same hardware as for LHC(VME board with integrated control interface via the VME bus)
The bandwidth doesn’t allow handling the first Betatron line (40 kHz @ q = 0.1)The first Betatron line is intrinsically stable for q < 0.5, but the amplitude-phase response of the amplifier makes it unstable => compensation circuit to be developed.
PS TFBPS TFB Required power for the Strip-line kicker
η : kick efficiency (electrode shape + average Betatron phase)g : gap between electrodes = 14 cm (H) ; 6 cm (V)ZC : 112.5 or 50 Ω (practical values for transformers)∆u : initial steering error Td : requested damping time (1/e)
2
2
2
703
dcStripline T
u
Z
gP
⇒
For the strip-line kicker where B = μ0E/377
P ≥ 2 x 1764 W for the most demanding beampilot with 3 mm initial error => Td = 50 μsη=0.5 ZC=112.5 Ω – strip-line, β = 22 m
The 64 ns transit time measured on the magnetic kicker makes it incompatible with the request for 30 MHz BW (injection Kicker ripple)
Dividing the magnetic kicker length by a factor 3 would be ok for the BW (9 times more power required = 330 W for the pilot beam)
The strip-line kicker fulfills all LHC beams requirements with 1.8 kW if located at a favorable position: β = 22 m. Fitting both planes in one tank would required 3.5 kW per amplifier in the less favored plane: β = 11 m. This means that no more than 2.8 mm would be tolerated with 3 kW in this plane.
A strip-line H and V should be made available in 2006We could then have a complete operational setup that could cope with all LHC beams in the horizontal plane (only 2.8 mm error – instead of 3mm - accepted in the vertical plane). This means resources (see next slide)
Future possible upgradeVertical kicker in a separate tank to provide some headroom (now limited to 2.8 mm). This also means resources (see next slide)