Abington Senior High School Construction Progress Update Presented to the Board of School Directors March 10, 2020
Abington Senior High School Construction Progress
Update
Presented to the
Board of School Directors
March 10, 2020
Schedule ProgressArea / Phase Description of Phase Projected Phase Completion
Phase 1 New Two-Story Addition 65% Complete In Progress – Phased Summer 2020
Phase 2 Administration / Entrance 75% Complete In Progress – May 1, 2020
Phase 3A Nurses Area 75% Complete In Progress – May 1, 2020
Phase 3B Family Consumer Science Completed – August 28, 2019
Phase 4A Mechanical Room Not Yet Started – July 1, 2021
Phase 4B Band Not Yet Started – May 1, 2021
Phase 5A Renovations Two-Story Classrooms Not Yet Started – July 3, 2021
Phase 5B Renovations Two-Story Stairs & Core Not Yet Started – December 1, 2020
Phase 6 New Cafeteria & Classrooms Not Yet Started – January 2, 2021
Phase 7 Renovate Cafeteria Not Yet Started – September 1, 2020
Phase 8 New Auxiliary Gym 25% Complete In Progress – September 15, 2020
Phase 9 Locker Rooms Not Yet Started – August 1, 2021
Phase 10 Renovation Classrooms G Not Yet Started – May 1, 2021
Phase 11 Renovations to Pool Area Not Yet Started – August 1, 2021
Phase 12 Renovation Existing Gym Not Yet Started – August 1, 2021
Project Considerations
Maintaining Schedule – The project team is working to maintain the progress
in the new classroom wing and planning is underway for the summer cleaning
and move-in
Reducing Costs – The project team is working to find ways continue to reduce
costs and provide options for scope reduction/cost reduction
Maintaining Utilities – The project team continues to work to keep all utilities
in operation throughout the building during the construction; this will be an
ongoing effort for the remainder of the project.
Project
Photographs
Phase 1
Project
Photographs
Phase 2
Project
Photographs
Phase 8