Blackdog Progress Report - July Page 1 of 5
Aberdeen Offshore Wind Farm
Construction Progress Report-July 17
14/07/17
Prepared by: Allan Macdonald Site Manager 14/07/17
NAME ROLE DATE
Prepared by: Tom Ivey Construction Engineer 14/07/17
NAME ROLE DATE
Blackdog Progress Report - July Page 2 of 5
1.0 ONSHORE ACTIVITIES
The main activities on site this month were completing 132kv Building cladding, completing all
internal blockwork and preparation of rooms for installation of Mechanical and Electrical
equipment to commence in August.
All concrete foundation works were completed in the 66kv building. The surrounds of the structure
was backfilled in preperation for Structural Steel erection commencing later this month.
The design for the Filter Compound is nearing completion with construction to follow.
Safety checks on cladding specification undertaken.