Tecnología GIS integrada Subestaciones modulares en recintos prefabricados ABB Switzerland Ltd., Jessica Ponce de Leon, June 2013
56

ABB Switzerland Ltd., Jessica Ponce de Leon, June … · Tecnología GIS integrada Subestaciones modulares en recintos prefabricados ABB Switzerland Ltd., Jessica Ponce de Leon, June

Sep 21, 2018

Download

Documents

dinhdien
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: ABB Switzerland Ltd., Jessica Ponce de Leon, June … · Tecnología GIS integrada Subestaciones modulares en recintos prefabricados ABB Switzerland Ltd., Jessica Ponce de Leon, June

Tecnología GIS integrada Subestaciones modulares en recintos prefabricados

ABB Switzerland Ltd., Jessica Ponce de Leon, June 2013

Page 2: ABB Switzerland Ltd., Jessica Ponce de Leon, June … · Tecnología GIS integrada Subestaciones modulares en recintos prefabricados ABB Switzerland Ltd., Jessica Ponce de Leon, June

© ABB Group June 19, 2013 | Slide 2

Subestaciones GIS integradas Mas de 45 años de avance tecnológico

ABB es el líder global en tecnología GIS de alta tensión, con una base instalada de mas de 20.000 celdas en todo el mundo. En 2009, ABB puso en servicio una GIS diseñada para operar mas de un millón de voltios (1.100 kV).

En los años 60 del siglo pasado, fuimos pioneros de GIS de alta tensión, y con la GIS integrada continuamos impulsando la tecnología, introduciendo soluciones modernas. Nuestra gama de productos incluye el espectro completo de tecnología GIS, cubriendo los rangos de tensión de 72.5 kV a 1.200 kV.

Page 3: ABB Switzerland Ltd., Jessica Ponce de Leon, June … · Tecnología GIS integrada Subestaciones modulares en recintos prefabricados ABB Switzerland Ltd., Jessica Ponce de Leon, June

D

eliv

ered

bay

s

First Research First 500 kV GIS Claireville (CA)

First 170 kV GIS Sempersteig (CH)

Largest 500 kV GIS

Itaipu (BR)

First 500 kV GIS in China, Jiangmen

First 800 kV GIS Alpha (ZA)

19

56

First 1100 kV GIS Jingmen (CN)

Largest 420 kV GIS HHR (SA)

500 kV GIS Three Gorges (CN)

Largest Urban SS Ochakovo (RU)

20‘000

16‘000

12‘000

8‘000

24‘000

Subestaciones GIS integradas Mas de 45 años de avance tecnológico

Page 4: ABB Switzerland Ltd., Jessica Ponce de Leon, June … · Tecnología GIS integrada Subestaciones modulares en recintos prefabricados ABB Switzerland Ltd., Jessica Ponce de Leon, June

Subestaciones GIS integradas Portafolio

© ABB Group June 19, 2013 | Slide 4

ELK-3 6300A

ELK-14 4000A

ELK-04 4000A

kA

kV 72.5 145 170 245 300 362 1100 765 550 420

40

50

63

80

765

ELK-4 5000A

kV1100

45000A

ELK-5 5000A

252

ELK 44 ELKELK 5

ELK 3ELK 14

55000A

5

ELK-14 compacta

3150A

ELK-3 compacta

5000A

ENK 2500A

ELK-04

/ 145 3150A

6300A4000A

72.572.5

40

50

63 ELK-044000A

170170 245245 300300 362362 420420252252

ELK 04

245 252

ELKELK-14 14 compacta

3150A

362 420

ELKELK-33compacta

5000A

72.5

ENKENK2500A

145

ELKELK-04

/ 145/ 1453150A3150A1453150A1451453150A145

Page 5: ABB Switzerland Ltd., Jessica Ponce de Leon, June … · Tecnología GIS integrada Subestaciones modulares en recintos prefabricados ABB Switzerland Ltd., Jessica Ponce de Leon, June

© ABB Group June 19, 2013 | Slide 5

Creciente demanda de energía eléctrica en zonas urbanas y en industrias de minería, petróleo y gas.

Necesidad que el suministro de energía eléctrica sea flexible, confiable y este disponible en corto tiempo.

Crecimiento de la urbanización.

Reemplazo de viejas subestaciones existentes AIS, terreno valioso, disponible para otro uso.

Manejo simple y fácil – muchas compañías eléctricas hoy en día están reduciendo personal de operación y mantenimiento.

Las SGI pueden ser fácilmente embarcadas y transportadas a las cercanías del sitio de explotación de petróleo/gas/mina.

Una solución pre-diseñada y normalizada garantiza una alta calidad y confiabilidad.

La reducción importante del tiempo de instalación en comparación a las subestaciones convencionales se logra realizando todas las actividades de diseño, ensamble, pruebas y control de calidad en la fábrica GIS.

Subestaciones GIS integradas Aplicaciones

Page 6: ABB Switzerland Ltd., Jessica Ponce de Leon, June … · Tecnología GIS integrada Subestaciones modulares en recintos prefabricados ABB Switzerland Ltd., Jessica Ponce de Leon, June

© ABB Group June 19, 2013 | Slide 6

Permite la instalación o extensión de subestaciones en plazos muy cortos.

Podemos suministrar una SGI en un plazo de cinco meses después de la confirmación del pedido.

Tiempo de instalación – dos a tres semanas

Bajos costos de ejecución Suministro completo de una mano. Mínimo trabajo en sitio Re-uso de diseños existentes – poca necesidad de

entrenamiento de personal y de manejo de repuestos.

Aplicaciones para poco espacio. Requiere solo 10% a 20% de superficie de una

solución AIS. Sitios de instalación exigentes

Condiciones medioambientales extremas, para temperaturas -30°C y por encima de 40°C

Instalaciones “offshore” – en plataformas de petróleo y gas o parques eólicos

Requerimientos de movilidad o modularidad

Transportable entre sitios; montaje sobre un camión

No se requiere sótano para cables.

Paredes removibles

Subestaciones GIS integradas Energía eléctrica disponible a toda hora en todo lugar

Page 7: ABB Switzerland Ltd., Jessica Ponce de Leon, June … · Tecnología GIS integrada Subestaciones modulares en recintos prefabricados ABB Switzerland Ltd., Jessica Ponce de Leon, June

© ABB Group June 19, 2013 | Slide 7

Suministro rápido

Sistema flexible por módulos

configurables

Instalación y puesta en servicio

fácil y rápida (AT probada en fábrica)

. .

. .

. .

Subestación pequeña y compacta

Pocos interfaces de ingeniería

Celdas de entrada-salida

Configuraciones en H

Varias celdas (>5)

Recinto completo o Recintos modulares prefabricados

- Estructuras de acero - Componentes auxiliares

- Control - Protección - Comunicación - micro SCADA

GIS equipos primarios y secundarios

Subestaciones GIS integradas Una solución completa

Page 8: ABB Switzerland Ltd., Jessica Ponce de Leon, June … · Tecnología GIS integrada Subestaciones modulares en recintos prefabricados ABB Switzerland Ltd., Jessica Ponce de Leon, June

© ABB Group June 19, 2013 | Slide 9

Subestaciones GIS integradas Configuraciones, recintos y cimentaciones

Arreglo en Anillo Este arreglo permite incluso en caso de

mantenimiento de un CB una operación sin interrupción de todas las celdas.

Cantidad de interruptores y salidas son iguales. Mas económico que una configuración de 1½

interruptores.

Arreglo en H Para aplicaciones industriales o pequeñas

aplicaciones regionales. Solución optima – dos entradas de línea y dos

transformadores.

Unidades prefabricadas Calefacción, ventilación e iluminación incluidas. Servicios auxiliares, incluyendo protección anti

fuego.

Cimentaciones Fundaciones sencillas dependiendo de las

condiciones del suelo y/o requerimientos sísmicos. Tipo umbral o prefabricadas.

Esquema de gas de arreglo en anillo

Esquema de gas de arreglo en H

Page 9: ABB Switzerland Ltd., Jessica Ponce de Leon, June … · Tecnología GIS integrada Subestaciones modulares en recintos prefabricados ABB Switzerland Ltd., Jessica Ponce de Leon, June

© ABB Group June 19, 2013 | Slide 10

Subestaciones GIS integradas Opciones de recintos prefabricados

Doble unidad acoplada

Unidad sencilla

Múltiples unidades acopladas

Edificio prefabricado modular

Page 10: ABB Switzerland Ltd., Jessica Ponce de Leon, June … · Tecnología GIS integrada Subestaciones modulares en recintos prefabricados ABB Switzerland Ltd., Jessica Ponce de Leon, June

© ABB Group June 19, 2013 | Slide 11

Subestaciones GIS integradas Una manera moderna de construir subestaciones

Elementos prefabricados del recinto

GIS es ensamblada, probada y embarcada

por habia completa

Reducción de trabajo en sitio.

Instalación muy rápida del edificio.

Bajo riesgo de retraso del proyecto por obras civiles.

Modular building concept “ModCon” pictures courtesy of JACO Fabriks AB – Sweden.

Page 11: ABB Switzerland Ltd., Jessica Ponce de Leon, June … · Tecnología GIS integrada Subestaciones modulares en recintos prefabricados ABB Switzerland Ltd., Jessica Ponce de Leon, June

© ABB Group June 19, 2013 | Slide 12

En el año 2009, la cuidad de Anchorage en Alaska necesitaba una subestación nueva para poder enfrentar la creciente demanda de energía.

Adicionalmente a la escasez de tiempo, el cliente además solicitaba una subestación compacta ya que el lugar de instalación se encontraba próximo a un centro comercial.

Altos costos de instalación requieren tiempos de obra cortos.

La solución también tenía que resistir el clima frío de Alaska y los frecuentes eventos sísmicos.

ABB respondió suministrando una subestación completamente integrada ELK-04 / 145 kV, que fue instalada y energizada en pocas semanas. La subestación consiste de un anillo con cuatro interruptores, integrados en dos contenedores de 40 pies. Los armarios de control local también se encuentran completamente integrados en los recintos.

Los recintos cumplen IP55 con dos puertas y dispositivos de relevo de sobrepresión.

Subestaciones GIS integradas Caso exitoso – Anchorage, Alaska

Page 12: ABB Switzerland Ltd., Jessica Ponce de Leon, June … · Tecnología GIS integrada Subestaciones modulares en recintos prefabricados ABB Switzerland Ltd., Jessica Ponce de Leon, June

© ABB Group June 19, 2013 | Slide 13

Subestaciones GIS integradas Anchorage - Diagrama Unifilar

Page 13: ABB Switzerland Ltd., Jessica Ponce de Leon, June … · Tecnología GIS integrada Subestaciones modulares en recintos prefabricados ABB Switzerland Ltd., Jessica Ponce de Leon, June

© ABB Group June 19, 2013 | Slide 14

Subestaciones GIS integradas Anchorage – Layout solución convencional

AIS 4 interruptores en anillo

180ft x 150 ft

27,000 sqft

Page 14: ABB Switzerland Ltd., Jessica Ponce de Leon, June … · Tecnología GIS integrada Subestaciones modulares en recintos prefabricados ABB Switzerland Ltd., Jessica Ponce de Leon, June

© ABB Group June 19, 2013 | Slide 15

Subestaciones GIS integradas Anchorage – diseño que optimiza espacio

AIS 4 interruptores en anillo

180ft x 150ft

27,000 sqft

GIS – solución integrada 4 interruptores en anillo

40ft x 21ft

840 sqft

Page 15: ABB Switzerland Ltd., Jessica Ponce de Leon, June … · Tecnología GIS integrada Subestaciones modulares en recintos prefabricados ABB Switzerland Ltd., Jessica Ponce de Leon, June

© ABB Group June 19, 2013 | Slide 16

Subestaciones GIS integradas Anchorage – montaje al bastidor

Page 16: ABB Switzerland Ltd., Jessica Ponce de Leon, June … · Tecnología GIS integrada Subestaciones modulares en recintos prefabricados ABB Switzerland Ltd., Jessica Ponce de Leon, June

© ABB Group June 19, 2013 | Slide 17

Subestaciones GIS integradas Anchorage – montaje al bastidor

Page 17: ABB Switzerland Ltd., Jessica Ponce de Leon, June … · Tecnología GIS integrada Subestaciones modulares en recintos prefabricados ABB Switzerland Ltd., Jessica Ponce de Leon, June

© ABB Group June 19, 2013 | Slide 18

Subestaciones GIS integradas Anchorage – montaje al bastidor

Page 18: ABB Switzerland Ltd., Jessica Ponce de Leon, June … · Tecnología GIS integrada Subestaciones modulares en recintos prefabricados ABB Switzerland Ltd., Jessica Ponce de Leon, June

© ABB Group June 19, 2013 | Slide 19

Subestaciones GIS integradas Anchorage – llenado de gas SF6

Page 19: ABB Switzerland Ltd., Jessica Ponce de Leon, June … · Tecnología GIS integrada Subestaciones modulares en recintos prefabricados ABB Switzerland Ltd., Jessica Ponce de Leon, June

© ABB Group June 19, 2013 | Slide 20

Subestaciones GIS integradas Anchorage – cableado

Page 20: ABB Switzerland Ltd., Jessica Ponce de Leon, June … · Tecnología GIS integrada Subestaciones modulares en recintos prefabricados ABB Switzerland Ltd., Jessica Ponce de Leon, June

© ABB Group June 19, 2013 | Slide 21

Subestaciones GIS integradas Anchorage – listo para embarque

Page 21: ABB Switzerland Ltd., Jessica Ponce de Leon, June … · Tecnología GIS integrada Subestaciones modulares en recintos prefabricados ABB Switzerland Ltd., Jessica Ponce de Leon, June

© ABB Group June 19, 2013 | Slide 22

Subestaciones GIS integradas Anchorage – preparación del sitio

Page 22: ABB Switzerland Ltd., Jessica Ponce de Leon, June … · Tecnología GIS integrada Subestaciones modulares en recintos prefabricados ABB Switzerland Ltd., Jessica Ponce de Leon, June

© ABB Group June 19, 2013 | Slide 23

Subestaciones GIS integradas Anchorage – llegada a sitio

Page 23: ABB Switzerland Ltd., Jessica Ponce de Leon, June … · Tecnología GIS integrada Subestaciones modulares en recintos prefabricados ABB Switzerland Ltd., Jessica Ponce de Leon, June

© ABB Group June 19, 2013 | Slide 24

Subestaciones GIS integradas Anchorage – remoción de paredes temporales

Page 24: ABB Switzerland Ltd., Jessica Ponce de Leon, June … · Tecnología GIS integrada Subestaciones modulares en recintos prefabricados ABB Switzerland Ltd., Jessica Ponce de Leon, June

© ABB Group June 19, 2013 | Slide 25

Subestaciones GIS integradas Anchorage – listo para instalación

Page 25: ABB Switzerland Ltd., Jessica Ponce de Leon, June … · Tecnología GIS integrada Subestaciones modulares en recintos prefabricados ABB Switzerland Ltd., Jessica Ponce de Leon, June

© ABB Group June 19, 2013 | Slide 26

Subestaciones GIS integradas Anchorage – instalación del recinto

Page 26: ABB Switzerland Ltd., Jessica Ponce de Leon, June … · Tecnología GIS integrada Subestaciones modulares en recintos prefabricados ABB Switzerland Ltd., Jessica Ponce de Leon, June

© ABB Group June 19, 2013 | Slide 27

Subestaciones GIS integradas Anchorage – instalación del segundo recinto

Page 27: ABB Switzerland Ltd., Jessica Ponce de Leon, June … · Tecnología GIS integrada Subestaciones modulares en recintos prefabricados ABB Switzerland Ltd., Jessica Ponce de Leon, June

© ABB Group June 19, 2013 | Slide 28

Subestaciones GIS integradas Anchorage – instalación de boquillas

Page 28: ABB Switzerland Ltd., Jessica Ponce de Leon, June … · Tecnología GIS integrada Subestaciones modulares en recintos prefabricados ABB Switzerland Ltd., Jessica Ponce de Leon, June

© ABB Group June 19, 2013 | Slide 29

Subestaciones GIS integradas Anchorage – subestación GIS terminada

Page 29: ABB Switzerland Ltd., Jessica Ponce de Leon, June … · Tecnología GIS integrada Subestaciones modulares en recintos prefabricados ABB Switzerland Ltd., Jessica Ponce de Leon, June

© ABB Group June 19, 2013 | Slide 30

Subestaciones GIS integradas Anchorage – GIS conectada a la red…

Page 30: ABB Switzerland Ltd., Jessica Ponce de Leon, June … · Tecnología GIS integrada Subestaciones modulares en recintos prefabricados ABB Switzerland Ltd., Jessica Ponce de Leon, June

© ABB Group June 19, 2013 | Slide 31

Subestaciones GIS integradas Anchorage – … al transformador

Page 31: ABB Switzerland Ltd., Jessica Ponce de Leon, June … · Tecnología GIS integrada Subestaciones modulares en recintos prefabricados ABB Switzerland Ltd., Jessica Ponce de Leon, June

© ABB Group June 19, 2013 | Slide 32

Subestaciones GIS integradas Anchorage – vista interior

Page 32: ABB Switzerland Ltd., Jessica Ponce de Leon, June … · Tecnología GIS integrada Subestaciones modulares en recintos prefabricados ABB Switzerland Ltd., Jessica Ponce de Leon, June

© ABB Group June 19, 2013 | Slide 33

Subestaciones GIS integradas Anchorage – subestación terminada

Page 33: ABB Switzerland Ltd., Jessica Ponce de Leon, June … · Tecnología GIS integrada Subestaciones modulares en recintos prefabricados ABB Switzerland Ltd., Jessica Ponce de Leon, June

© ABB Group June 19, 2013 | Slide 34

Subestaciones GIS integradas 245kV LILO

Beneficios

Rápida entrega e instalación debido a su diseño prefabricado.

Significante ahorro del costo del proyecto debido al minimo trabajo en sitio.

Ahorro de espacio de hasta 80% en comparación con una subestación AIS convencional.

Ratings hasta 245kV, 3150A, 50kA.

Conexión con cable es posible.

Page 34: ABB Switzerland Ltd., Jessica Ponce de Leon, June … · Tecnología GIS integrada Subestaciones modulares en recintos prefabricados ABB Switzerland Ltd., Jessica Ponce de Leon, June

© ABB Group June 19, 2013 | Slide 35

Subestaciones GIS integradas

LILO: Diagrama Unifilar

245kV LILO

LILO = Line-In Line-Out

Page 35: ABB Switzerland Ltd., Jessica Ponce de Leon, June … · Tecnología GIS integrada Subestaciones modulares en recintos prefabricados ABB Switzerland Ltd., Jessica Ponce de Leon, June

© ABB Group June 19, 2013 | Slide 36

Subestaciones GIS integradas 245kV LILO

Bastidor sobre pilares de acero.

Preparado para fijación en sitio.

Marco de chapa de acero galvanizado.

Piso/Paredes: paneles tipo sándwich (lana de roca), cubierto con chapa de acero galvanizado .

Page 36: ABB Switzerland Ltd., Jessica Ponce de Leon, June … · Tecnología GIS integrada Subestaciones modulares en recintos prefabricados ABB Switzerland Ltd., Jessica Ponce de Leon, June

© ABB Group June 19, 2013 | Slide 37

Subestaciones GIS integradas Ensamble del edificio prefabricado

Page 37: ABB Switzerland Ltd., Jessica Ponce de Leon, June … · Tecnología GIS integrada Subestaciones modulares en recintos prefabricados ABB Switzerland Ltd., Jessica Ponce de Leon, June

© ABB Group June 19, 2013 | Slide 38

Subestaciones GIS integradas Ensamble del edificio prefabricado – Panel PAROC

Page 38: ABB Switzerland Ltd., Jessica Ponce de Leon, June … · Tecnología GIS integrada Subestaciones modulares en recintos prefabricados ABB Switzerland Ltd., Jessica Ponce de Leon, June

© ABB Group June 19, 2013 | Slide 39

Subestaciones GIS integradas Ensamble del edificio prefabricado – Panel PAROC

Page 39: ABB Switzerland Ltd., Jessica Ponce de Leon, June … · Tecnología GIS integrada Subestaciones modulares en recintos prefabricados ABB Switzerland Ltd., Jessica Ponce de Leon, June

© ABB Group June 19, 2013 | Slide 40

Subestaciones GIS integradas Ensamble del edificio prefabricado

Page 40: ABB Switzerland Ltd., Jessica Ponce de Leon, June … · Tecnología GIS integrada Subestaciones modulares en recintos prefabricados ABB Switzerland Ltd., Jessica Ponce de Leon, June

© ABB Group June 19, 2013 | Slide 41

Subestaciones GIS integradas 245kV LILO

Bahia 100% ensamblada y probada en fábrica.

Despues de las pruebas de rutina, la bahia y LCC se integran al edificio prefabricado.

HVAC, protección contra incendio, iluminación y ventilación bajo requerimiento pueden ser instalados.

Ductos y boquillas se envian a sitio para su instalación en sitio.

Page 41: ABB Switzerland Ltd., Jessica Ponce de Leon, June … · Tecnología GIS integrada Subestaciones modulares en recintos prefabricados ABB Switzerland Ltd., Jessica Ponce de Leon, June

© ABB Group June 19, 2013 | Slide 42

Subestaciones GIS integradas Ensamble del edificio prefabricado

Page 42: ABB Switzerland Ltd., Jessica Ponce de Leon, June … · Tecnología GIS integrada Subestaciones modulares en recintos prefabricados ABB Switzerland Ltd., Jessica Ponce de Leon, June

© ABB Group June 19, 2013 | Slide 43

Subestaciones GIS integradas Ensamble del edificio prefabricado

Page 43: ABB Switzerland Ltd., Jessica Ponce de Leon, June … · Tecnología GIS integrada Subestaciones modulares en recintos prefabricados ABB Switzerland Ltd., Jessica Ponce de Leon, June

© ABB Group June 19, 2013 | Slide 44

Subestaciones GIS integradas Equipos Auxiliares

HVAC

Unidades de ventilación

Aire acondicionado / calefacción

Iluminación.

Protección contra incendio.

Detectores de humo o gas.

Dispositivos de relevo de sobrepresión

Page 44: ABB Switzerland Ltd., Jessica Ponce de Leon, June … · Tecnología GIS integrada Subestaciones modulares en recintos prefabricados ABB Switzerland Ltd., Jessica Ponce de Leon, June

© ABB Group June 19, 2013 | Slide 45

Subestaciones GIS integradas 245kV LILO

Edificio prefabricado cuenta con argollas en el borde del techo para su elevación y colocación en sitio.

Pilares de acero listo para fijación.

Ductos, boquillas y apartarrayos se instalan en sitio.

Conexión al sistema de tierras.

Prueba de Alta tensión.

Conexión al transformador y a la línea.

Puesta en servicio.

Page 45: ABB Switzerland Ltd., Jessica Ponce de Leon, June … · Tecnología GIS integrada Subestaciones modulares en recintos prefabricados ABB Switzerland Ltd., Jessica Ponce de Leon, June

© ABB Group June 19, 2013 | Slide 46

Subestaciones GIS integradas Edificios prefabricados

Page 46: ABB Switzerland Ltd., Jessica Ponce de Leon, June … · Tecnología GIS integrada Subestaciones modulares en recintos prefabricados ABB Switzerland Ltd., Jessica Ponce de Leon, June

© ABB Group June 19, 2013 | Slide 47

Subestaciones GIS integradas Edificios prefabricados

Page 47: ABB Switzerland Ltd., Jessica Ponce de Leon, June … · Tecnología GIS integrada Subestaciones modulares en recintos prefabricados ABB Switzerland Ltd., Jessica Ponce de Leon, June

© ABB Group June 19, 2013 | Slide 48

Subestaciones GIS integradas 245kV – Otras configuraciones

Incoming lines

Transformers

Tie breaker

CB CB

CB TIE breaker housing

Page 48: ABB Switzerland Ltd., Jessica Ponce de Leon, June … · Tecnología GIS integrada Subestaciones modulares en recintos prefabricados ABB Switzerland Ltd., Jessica Ponce de Leon, June

© ABB Group June 19, 2013 | Slide 49

Subestaciones GIS integradas 245kV – Otras configuraciones

Page 49: ABB Switzerland Ltd., Jessica Ponce de Leon, June … · Tecnología GIS integrada Subestaciones modulares en recintos prefabricados ABB Switzerland Ltd., Jessica Ponce de Leon, June

© ABB Group June 19, 2013 | Slide 50

Subestaciones GIS integradas 245kV – Otras configuraciones

Page 50: ABB Switzerland Ltd., Jessica Ponce de Leon, June … · Tecnología GIS integrada Subestaciones modulares en recintos prefabricados ABB Switzerland Ltd., Jessica Ponce de Leon, June

© ABB Group June 19, 2013 | Slide 51

Subestaciones GIS integradas 245kV – Otras configuraciones

Page 51: ABB Switzerland Ltd., Jessica Ponce de Leon, June … · Tecnología GIS integrada Subestaciones modulares en recintos prefabricados ABB Switzerland Ltd., Jessica Ponce de Leon, June

© ABB Group June 19, 2013 | Slide 52

Subestaciones GIS integradas 420kV LILO – solución con excelente movilidad

Beneficios

Rápida entrega e instalación debido a si diseño prefabricado.

Significante ahorro del costo del proyecto debido al minimo trabajo en sitio.

Ahorro de espacio de hasta 80% en comparación con una subestación AIS convencional.

No se requiere equipo de prueba adicional en sitio para prueba de Alta tensión.

Unidad desensamblable – no hay necesidad de dejar el trailer dentro de la subestación.

Ratings hasta 420kV, 5000 A, 63 kA.

Dimensiones estandar ISO 40’ con boquillas removibles– fácil transportación en cualquier trailer.

Conexión con cable es posible.

Trailer opional

Page 52: ABB Switzerland Ltd., Jessica Ponce de Leon, June … · Tecnología GIS integrada Subestaciones modulares en recintos prefabricados ABB Switzerland Ltd., Jessica Ponce de Leon, June

© ABB Group June 19, 2013 | Slide 53

Subestaciones GIS integradas 420kV LILO – solución con excelente movilidad

Con boquillas SF6/Aire

Con conexión SF6/cable

Page 53: ABB Switzerland Ltd., Jessica Ponce de Leon, June … · Tecnología GIS integrada Subestaciones modulares en recintos prefabricados ABB Switzerland Ltd., Jessica Ponce de Leon, June

© ABB Group June 19, 2013 | Slide 57

Subestaciones GIS integradas Bajo impacto medioambiental

Publicamos certificados de impacto medioambiental para todos los productos que fabricamos.

Tres fases de ciclo de vida (ELK-04): Fabricación, uso y eliminación.

Fabricación Diseño compacto – uso de menos aluminio y otros metales. Bajas pérdidas térmicas – selección de materiales. Certificado según ISO 14001.

Uso Monitoreo en línea para mantenimiento preventivo. Bajo consumo de energía para servicios auxiliares. Pruebas tipo certificando pérdidas SF6 menores a 0.1 % p.a. Sistemas de sellado bien probados.

Fase de eliminación Uso de materiales reciclables y de fácil eliminación. Procedimientos de mantenimiento mejorados – evitando pérdidas de gases y aceites

Page 54: ABB Switzerland Ltd., Jessica Ponce de Leon, June … · Tecnología GIS integrada Subestaciones modulares en recintos prefabricados ABB Switzerland Ltd., Jessica Ponce de Leon, June

© ABB Group June 19, 2013 | Slide 58

Diseño, ingeniería y fabricación

Integración de equipos selectos en los recinto(s)

Pruebas funcionales y de rutina – Listo!

Transporte

Unidades prefabricadas pueden ser transportadas por tierra, aire y barco; y están previstas con argollas para su elevación y manejo durante transporte.

Instalación y puesta en servicio

Colocar el(los) recinto(s) sobre la cimentación.

Instalar boquillas y/o cables – LISTO!

Para algunas configuraciones, se realiza la prueba de Alta Tensión – LISTO!

Energizar

Después de un corto periodo de instalación la SGI esta lista para energizarse.

Subestaciones GIS integradas Ejecución del proyecto

Page 55: ABB Switzerland Ltd., Jessica Ponce de Leon, June … · Tecnología GIS integrada Subestaciones modulares en recintos prefabricados ABB Switzerland Ltd., Jessica Ponce de Leon, June

© ABB Group June 19, 2013 | Slide 59

Page 56: ABB Switzerland Ltd., Jessica Ponce de Leon, June … · Tecnología GIS integrada Subestaciones modulares en recintos prefabricados ABB Switzerland Ltd., Jessica Ponce de Leon, June

© ABB Group June 19, 2013 | Slide 60

Subestaciones GIS integradas Terminales CD 145 de ABB Kabeldon

Tipo seco (Dry type)

Enchufable

Un tipo de aislador cubre el rango de 300-2.000 mm²

Enchufable por resortes de contacto

Fijación por medio de resortes pre-tensados

Presión mecánica continua

Aislador de resina estanco a presión

Conexión a tierra robusta

Fijación excelente por abrazaderas

Conector enchufable

Resorte pre-tensados

Abrazadera de fijación

Cono

Resorte de contacto

Conector de puesta a tierra

Carcasa

Fijación

Aislador CDI 145

Resorte de contacto

Probado según IEC 60840 Um 145 kV