© ABB Group 17. juni 2012 | Slide 1 Subsea Longer Deeper Colder ABB, 2012-06-05
12

ABB, 2012-06-05 Subsea Longer Deeper Colderfile/Subsea+-+Borghild+Lunde.pdf · Taking subsea power and automation Longer, deeper, colder Enabling subsea production and processing

Apr 18, 2018

Download

Documents

dinhthien
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: ABB, 2012-06-05 Subsea Longer Deeper Colderfile/Subsea+-+Borghild+Lunde.pdf · Taking subsea power and automation Longer, deeper, colder Enabling subsea production and processing

© ABB Group 17. juni 2012 | Slide 1

SubseaLonger Deeper Colder

ABB, 2012-06-05

Page 2: ABB, 2012-06-05 Subsea Longer Deeper Colderfile/Subsea+-+Borghild+Lunde.pdf · Taking subsea power and automation Longer, deeper, colder Enabling subsea production and processing

Towards subsea factories

© ABB Group June 17, 2012 | Slide 2

Page 3: ABB, 2012-06-05 Subsea Longer Deeper Colderfile/Subsea+-+Borghild+Lunde.pdf · Taking subsea power and automation Longer, deeper, colder Enabling subsea production and processing

© ABB GroupJune 17, 2012 | Slide 3

2011 2013 2015 2020

23

100

18%

Subsea opportunityMarket growing at 18% CAGR reaching ~$100Bn by 2020

• Eliminate costly topside solutions• Deeper, longer distance, marginal fields• Increased recovery at falling pressure

Subsea drivers

Page 4: ABB, 2012-06-05 Subsea Longer Deeper Colderfile/Subsea+-+Borghild+Lunde.pdf · Taking subsea power and automation Longer, deeper, colder Enabling subsea production and processing

Taking subsea power and automationLonger, deeper, colder

Enabling subsea production and processing

Long distance power transmission

High number of subsea loads

Subsea power distribution

Availability

Improved Oil Recovery

HSE

Cost and technology

© ABB Group June 17, 2012 | Slide 4

Page 5: ABB, 2012-06-05 Subsea Longer Deeper Colderfile/Subsea+-+Borghild+Lunde.pdf · Taking subsea power and automation Longer, deeper, colder Enabling subsea production and processing

© ABB GroupJune 17, 2012 | Slide 5© ABB Group June 17, 2012 | Slide 5

Evolvement of subsea power distributionTowards longer step-out

Long step-out drive systemCable transfer ~50km

Page 6: ABB, 2012-06-05 Subsea Longer Deeper Colderfile/Subsea+-+Borghild+Lunde.pdf · Taking subsea power and automation Longer, deeper, colder Enabling subsea production and processing

Statoil – ÅsgardWorld’s first subsea compression

Customers needs

A system that can transmit enough power a distance of 43 km between a drive on the floating production facility and a compressor on the seabed, with the highest voltage and frequency ever delivered

ABB’s solution

A variable speed drive system designed to avoid harmonic disturbances and voltage drops. System consists of a drive and transformer on the platform, and a cable to the transformer and the motor on the seabed.

Customer value

Cost and energy efficient, reliable power for the compressor.

© ABB Group June 17, 2012 | Slide 6

Page 7: ABB, 2012-06-05 Subsea Longer Deeper Colderfile/Subsea+-+Borghild+Lunde.pdf · Taking subsea power and automation Longer, deeper, colder Enabling subsea production and processing

© ABB GroupJune 17, 2012 | Slide 7

ABB’s Subsea initiativeDrawing upon our global capabilities

Norway Sweden Finland

Poland

SwitzerlandUK

US

Page 8: ABB, 2012-06-05 Subsea Longer Deeper Colderfile/Subsea+-+Borghild+Lunde.pdf · Taking subsea power and automation Longer, deeper, colder Enabling subsea production and processing

© ABB GroupJune 17, 2012 | Slide 8

ABB a reliable subsea providerDrawing upon ABB’s global capabilities

Domain knowledge

ABB’s global competencies geared towards subsea power and automation

Project execution Products

R&D

Page 9: ABB, 2012-06-05 Subsea Longer Deeper Colderfile/Subsea+-+Borghild+Lunde.pdf · Taking subsea power and automation Longer, deeper, colder Enabling subsea production and processing

© ABB Group June 17, 2012 | Slide 9

Today

Page 10: ABB, 2012-06-05 Subsea Longer Deeper Colderfile/Subsea+-+Borghild+Lunde.pdf · Taking subsea power and automation Longer, deeper, colder Enabling subsea production and processing

© ABB Group June 17, 2012 | Slide 10

Tomorrow

Page 11: ABB, 2012-06-05 Subsea Longer Deeper Colderfile/Subsea+-+Borghild+Lunde.pdf · Taking subsea power and automation Longer, deeper, colder Enabling subsea production and processing

© ABB GroupJune 17, 2012 | Slide 11© ABB Group June 17, 2012 | Slide 11

Offshore electrification, more than subsea

HVDC

HVDC

HVDCAC

AC