CLIENT KONSORTIUM ABASS SDN BHD PROJECT UPGRADING LIGHTNING PROTECTION SYSTEM LOCATION BALANCING RESERVOIR TITLE LIGHTNING & EARTHING INSTALLATION DETAILS ITEM DESCRIPTION UNIT QUANTITY A Copper tape installation : - tokai 25mmx3mm 1 Ground Level a Line 3 panel to point C m 12 b line 5 panel to point B m 9 c Pump panel to point D m 25 d Point C to Point E m 32 e Point E to Point J m 62 f Point J to Putrajaya Panel m 115 g Point I to Point K m 7 h Point F to Point G m 12 i Ponit G to Point H m 4 2 ESE Pole a Inner Pole m 15 b Ground Pole to Line G-F m 2 3 Panel 1-3 a Panel 1 to panel 2 m 24 b Panel 3 to Point A m 9 c Panel 3 to Ground m 7 4 Roof (Switch Room) a Air terminal ring m 26 b Ring to Test Point m 3 Total installation 364 B Air terminal Installation 1 Lightning Pole (15m) a Alltec ESE TSP60 nos 1 2 Roof Switch Room a Tokai 500mmx15mm Air terminal c/w base nos 4
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
1 Ground Levela Line 3 panel to point C m 12b line 5 panel to point B m 9c Pump panel to point D m 25d Point C to Point E m 32e Point E to Point J m 62f Point J to Putrajaya Panel m 115g Point I to Point K m 7h Point F to Point G m 12i Ponit G to Point H m 4
2 ESE Polea Inner Pole m 15b Ground Pole to Line G-F m 2
3 Panel 1-3a Panel 1 to panel 2 m 24b Panel 3 to Point A m 9c Panel 3 to Ground m 7
4 Roof (Switch Room)a Air terminal ring m 26b Ring to Test Point m 3
Total installation 364
B Air terminal Installation
1 Lightning Pole (15m)a Alltec ESE TSP60 nos 1
2 Roof Switch Rooma Tokai 500mmx15mm Air terminal c/w base nos 4
ITEM DESCRIPTION UNIT QUANTITY REMARKSc Point B nos 1d Point D nos 1e Point F nos 1f Point G nos 1g Point H nos 1h Point I nos 1i Point J nos 1j Point K nos 1k Point L nos 1l Point M nos 1
m Point N nos 1n Point O nos 1
Total installation 14
D Pole 1 Highmast Pole 15m 1 Bq 10m pole
Total installation 1
CLIENT KONSORTIUM ABASS SDN BHDPROJECT UPGRADING LIGHTNING PROTECTION SYSTEMLOCATION GENSET
TITLE LIGHTNING & EARTHING INSTALLATION DETAILS
ITEM DESCRIPTION UNIT QUANTITY REMARKS
A Copper tape installation :- tokai 25mmx3mm
1 Ground Levela Point A to B m 0 Existing Tapeb Point B to C m 5c Point D to E m 3
2 ESE Pole 3M (Roof)a ESE point to Point A m 4.5
Total installation 12.5
B Air terminal Installation
1 Lightning Pole (15m)a Alltec ESE TSP60 nos 1
Total installation 1
B Earthing Point
1 Earth Chamber (SAG- HEAVY DUTY)a Point B nos 0 Exisiting b Point C nos 1c Point D nos 0 Exisiting d Point E nos 1
Total installation 2
2 Earth Rod a Point B nos 0 Exisiting b Point C nos 3c Point D nos 0 Exisiting d Point E nos 3
Total installation 6
3 Rod Couplera Point B nos 0 Exisiting b Point C nos 2c Point D nos 0 Exisiting d Point E nos 2
Total installation 4
C Termination1 Cadweld Termination (Erico)a Point A nos 1b Point B nos 1c Point C nos 1d Point D nos 1e Point E nos 1g Point F nos 1
1 Ground Levela Point A to C m 5.6b Point B to D m 13c Point C to Internal PA System m 4d Point D to E m 12e Point F to G m 11
2 ESE Pole 2 M (Water tank)a ESE point to Point G m 22
3 Roof (Surau)a Point M to L m 7
Total installation 74.6
B Air terminal Installation
1 Lightning Pole (15m)a Alltec ESE TSP60 nos 1
2 Roof (Surau)a Tokai 500mmx16mm Air terminal c/w base nos 5
Total installation 6
B Earthing Point
1 Earth Chamber (SAG- HEAVY DUTY)a Point A nos 1b Point B nos 0c Point D nos 0d Point F nos 1e Point G nos 1f Point I nos 1
Total installation 4
2 Earth Rod
a Point A nos 3b Point B nos 0c Point D nos 0d Point F nos 3e Point G nos 3f Point I nos 3
Total installation 12
3 Rod Couplera Point A nos 2b Point B nos 0c Point D nos 0d Point F nos 2e Point G nos 2f Point I nos 2
Total installation 8
C Termination1 Cadweld Termination (Erico)b Point A nos 1c Point B nos 1d Point C nos 1e Point D nos 1f Point E nos 1g Point F nos 1h Point G nos 1i Point I nos 1
Total installation 8
REMARKS
Exisiting Exisiting
Exisiting Exisiting
Exisiting Exisiting
CLIENT KONSORTIUM ABASS SDN BHDPROJECT UPGRADING LIGHTNING PROTECTION SYSTEMLOCATION SURAU / WATER TANK
TITLE LIGHTNING & EARTHING INSTALLATION DETAILS
ITEM DESCRIPTION UNIT QUANTITY REMARKS
A Copper tape installation :- tokai 25mmx3mm
1 Ground Levela Point A to B m 5b Point B to D m 13c Point C to Internal PA System m 4d Point D to E m 12e Point F to G m 13
2 ESE Pole 2 M (Water tank)a ESE point to Point G m 26
3 Roof (Surau)a Point M to L m 7
Total installation 80
B Air terminal Installation
1 Lightning Pole (15m)a Alltec ESE TSP60 nos 1
2 Roof (Surau)a Tokai 500mmx16mm Air terminal c/w base nos 1
Total installation 2
B Earthing Point
1 Earth Chamber (SAG- HEAVY DUTY)a Point A nos 1b Point B nos 0 Exisiting c Point D nos 0 Exisiting d Point F nos 1e Point G nos 1f Point I nos 1
Total installation 4
2 Earth Rod a Point A nos 3b Point B nos 0 Exisiting c Point D nos 0 Exisiting d Point F nos 3e Point G nos 3f Point I nos 3
Total installation 12
3 Rod Couplera Point A nos 2b Point B nos 0 Exisiting c Point D nos 0 Exisiting d Point F nos 2e Point G nos 2f Point I nos 2
Total installation 8
C Termination1 Cadweld Termination (Erico)b Point A nos 1c Point B nos 1d Point C nos 1e Point D nos 1f Point E nos 1g Point F nos 1h Point G nos 1i Point I nos 1
Total installation 8
D Pole 1 Galvanised Pole 2m 1
Total installation 1
CLIENT KONSORTIUM ABASS SDN BHDPROJECT UPGRADING LIGHTNING PROTECTION SYSTEMLOCATION CHLORINATION BUILDING
TITLE LIGHTNING & EARTHING INSTALLATION DETAILS
ITEM DESCRIPTION UNIT QUANTITY
A Copper tape installation :- tokai 25mmx3mm
1 Chlorination Control Rooma bonding of each panel inside m 12
Total installation 12
B Termination1 Cadweld Termination (Erico)a Point A nos 1b Point B nos 1
Total installation 2
REMARKS
CLIENT KONSORTIUM ABASS SDN BHDPROJECT UPGRADING LIGHTNING PROTECTION SYSTEMLOCATION RAW WATER PUMPING STATION
TITLE LIGHTNING & EARTHING INSTALLATION DETAILS
ITEM DESCRIPTION UNIT QUANTITY REMARKS
A Copper tape installation :- cable 35mmx1C
1 Ground Levela Busbar to PABX m 5 replace copper tape
Total installation 5
B PABX lightning protection1 Protection of Power Supplya nos 2 1 unit standbyb Novaris Telephone Surge Protector nos 40 2 unit standby