A3 - dual carriageway link between London and Portsmouth 6.5km new road, 1.77km in bored tunnel £371 million Construction started January 2007 Project.

Dec 14, 2015

Download

Documents

Shania Emmott
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: A3 - dual carriageway link between London and Portsmouth 6.5km new road, 1.77km in bored tunnel £371 million Construction started January 2007 Project.
Page 2: A3 - dual carriageway link between London and Portsmouth 6.5km new road, 1.77km in bored tunnel £371 million Construction started January 2007 Project.

• A3 - dual carriageway link between London and Portsmouth

• 6.5km new road, 1.77km in bored tunnel• £371 million• Construction started January 2007• Project finish date 2012

Page 3: A3 - dual carriageway link between London and Portsmouth 6.5km new road, 1.77km in bored tunnel £371 million Construction started January 2007 Project.
Page 4: A3 - dual carriageway link between London and Portsmouth 6.5km new road, 1.77km in bored tunnel £371 million Construction started January 2007 Project.
Page 5: A3 - dual carriageway link between London and Portsmouth 6.5km new road, 1.77km in bored tunnel £371 million Construction started January 2007 Project.

Where?

Page 6: A3 - dual carriageway link between London and Portsmouth 6.5km new road, 1.77km in bored tunnel £371 million Construction started January 2007 Project.
Page 7: A3 - dual carriageway link between London and Portsmouth 6.5km new road, 1.77km in bored tunnel £371 million Construction started January 2007 Project.
Page 8: A3 - dual carriageway link between London and Portsmouth 6.5km new road, 1.77km in bored tunnel £371 million Construction started January 2007 Project.
Page 9: A3 - dual carriageway link between London and Portsmouth 6.5km new road, 1.77km in bored tunnel £371 million Construction started January 2007 Project.
Page 10: A3 - dual carriageway link between London and Portsmouth 6.5km new road, 1.77km in bored tunnel £371 million Construction started January 2007 Project.
Page 11: A3 - dual carriageway link between London and Portsmouth 6.5km new road, 1.77km in bored tunnel £371 million Construction started January 2007 Project.

Construction Overview• Twin Bore 2 lane Tunnel

• Tunnel Length – 1.2 miles

• Depth – Varies between 20 – 60m

• 7.3m wide 2 lane carriageway

• Estimated Earth Excavation – 300,000 cubic metres

• Longest non-estuarial crossing in England

Page 12: A3 - dual carriageway link between London and Portsmouth 6.5km new road, 1.77km in bored tunnel £371 million Construction started January 2007 Project.

Solution Adopted• Slope Stability

• Soil Nails

• Geogrid Reinforcement

• Minimising Visual Impact

• Soil Pouches

• Place Soil and Vegetation

• Hydroseed Spray

Page 13: A3 - dual carriageway link between London and Portsmouth 6.5km new road, 1.77km in bored tunnel £371 million Construction started January 2007 Project.

Solution Adopted continued…..

• Structural Reinforcement for Tunnel Face

• Rock Nails/Bolts

• Short

• Concrete Grout

• Ground Anchors

• Long

• High Tensile Steel

Page 14: A3 - dual carriageway link between London and Portsmouth 6.5km new road, 1.77km in bored tunnel £371 million Construction started January 2007 Project.

Solution Adopted continued…..

Sprayed Concrete Lining (SCL)

• Roof Supporting Spiles

• Primary sprayed concrete shell

• Waterproofing Membrane

• Reinforcement Steel

• Cast Concrete lining• Shotcrete• 200mm thick

Page 15: A3 - dual carriageway link between London and Portsmouth 6.5km new road, 1.77km in bored tunnel £371 million Construction started January 2007 Project.

Alternative Methods• New Austrian Tunneling Method (NATM)

• Tunnel Boring Machines (TBM) • New Tunnel PLS (Pre-Lining Support)

Page 16: A3 - dual carriageway link between London and Portsmouth 6.5km new road, 1.77km in bored tunnel £371 million Construction started January 2007 Project.

What Will It Look Like?

Page 17: A3 - dual carriageway link between London and Portsmouth 6.5km new road, 1.77km in bored tunnel £371 million Construction started January 2007 Project.

Thankyou for Listening

• Any Questions?