A PROJECT REPORT ON INVENTORY MANAGEMENT ACROSS THE SUPPLY CHAIN THROUGH KANBAN SYSTEM BY DHAVAL A. MUNDADA REG. NO. 200722210
A PROJECT REPORT
ON
INVENTORY MANAGEMENT
ACROSS THE SUPPLY CHAIN
THROUGH KANBAN SYSTEM
BY
DHAVAL A. MUNDADA
REG. NO. 200722210
SYMBIOSIS CENTRE FOR DISTANCE LEARNING
BATCH 2007-08
TO WHOMSOEVER IT MAY CONCERN
This is to certify that Mr. Dhaval Anand Mundada was an employee of PMP Components
Pvt Ltd during the period of May’2003 – May’2005. He was the core team member of
implementation of KANBAN system carried out in PMP.
We have no objection for him to carry out this implementation as a project work titled
“Inventory Management across the Supply Chain through KANBAN System” in our
organization & for submitting the same to the Director, SCDL as a part of fulfillment of the
PGDSCM Program.
We wish him all the success.
Seal of the company For PMP Components Pvt. Ltd.,
Mr. Jayen Nair
GM-Works (Satara)
Place: Satara
Date: 25/03/2009
DECLARATION BY LEARNER
This is to declare that I have carried out this project work myself in part fulfillment of the
PGDSCM Program of SCDL.
The work is original, has not been copied from anywhere else and has not been submitted to
any other University/Institute for an award of any degree/diploma.
Date: Signature:
Place: Name: Dhaval Anand Mundada
CERTIFICATE OF SUPERVISOR
Certified that the work incorporated in this Project Report “Inventory Management across the
Supply Chain through KANBAN System” submitted by Mr. Dhaval Anand Mundada is his
original work and completed under my supervision. Material obtained from other sources has
been duly acknowledged in the project report.
Date: Signature of Guide
Place:
TABLE OF CONTENTS
Chapters Page No.
Acknowledgement
1. Introduction----------------------------------------------- 01
2. Objective & Scope--------------------------------------- 04
3. Limitations------------------------------------------------ 05
4. Theoretical Perspective---------------------------------- 07
5. Methodology & Procedure of Work--------------------09
6. Analysis of Data------------------------------------------ 17
7. Findings, Inferences & Recommendations------------ 21
8. Conclusion------------------------------------------------- 28
9. Summary of the Project---------------------------------- 29
Annexures ----------------------------------------------------- 30
ACKNOWLEDGEMENT
I find myself fully engulfed with immense pleasure in expressing my sincere and profound
gratitude to ‘PMP Components Pvt Ltd.’ for giving me an opportunity to carry out this project.
I am very grateful to Mr. Jayen Nayar – GM (Works) for having shown confidence in us to
assign this project.
I express my sincere thanks to Mr. P. M. Dhole – Asst. GM, Supply chain for being helpful
and co-operative throughout the project.
I am also thankful to all staff members for their kind co-operation.
I take this opportunity to express my deep sense of gratitude & respect to my guide Mr.
Prashant Chandak without whose constant encouragement, it would not have been possible to
complete this work. I am also thankful to him for being highly co-operative & approachable.
Mr. Dhaval Mundada
Course:-PGDSCM
Reg. No.: 200722210
CHAPTER-1
INTRODUCTION
“The need for quality supply chain management where every action in the customer delivery
process adds customer value & where quality that forever improves, must be matched by value
for money solutions.”
It is this understanding that has driven the PMP group; to forever emerge as a customer value
provider in the business of quality Alternators. Highest importance is given to the customer
relationship and service. PMP tries to understand its customers and delivers a product exactly
as per customer’s needs.
PMP is part of US $ 400 million Piramal group headquartered at Mumbai. This is one of the
most progressive and reputed business houses in India. The highest corporate governance
standards are followed in conducting day-to-day business.
PMP has been in the business of auto-electrical components since 1962. There are two
manufacturing plants located at Mumbai and Satara. Both the plants have ISO 9001
accreditation.
PMP Components Pvt. Ltd., based in Satara, spread over 45000 sq. ft. of built up area and has
been in production since 1984.
PMP is manufacturing and marketing Alternators, Starter Motors, and D.C. motors, Horns,
Switches, Relays and Voltage Regulators for Vehicles manufactured in India and various
countries abroad. The company’s major business comes from reputed OEM customers in
India. Company also had a significant presence in the After Market in Europe, and USA.
Almost 150 professionals including designers, engineer technicians, skilled & semiskilled
workers perform in unison at PMP under the stewardship of its engineer founder CEO Mr.
S.N.Somani, to ensure that quality & commitment have become part of the fabric, which
drapes every aspect of PMP’s working.
OEM Customers
Segment Customers
Cars
Maruti Udyog Ltd.
TATA Motors - Indica
Hindustan Motors Ltd.
General Motors
FORD
Light
Commercial
Vehicles
TATA Motors
Bajaj Tempo Ltd.
Mahindra & Mahindra Ltd.
Heavy
Commercial
Vehicles
TATA Motors
Ashok Leyland Ltd.
Tractors
Mahindra & Mahindra Ltd
Eicher (good earth) Tractors Ltd.
L & T (John Deere) Tractors Ltd.
Gujarat Mahindra Tractor Ltd.
SAME DEUTZ
HMT Ltd.
New Holland
3 Wheelers
Bajaj Auto Ltd.
Bajaj Temp Ltd.
M&M Champion
Engine
Greaves Ltd.
Kirloskar Oil Engines Ltd.
Mahindra & Mahindra
Eicher Ltd.
PMP is exporting products to following countries:
USA, Canada, Australia, UK, Germany, France, Italy, Spain, Denmark, Finland,
Singapore, Belgium, Holland, Dubai, Sri Lanka & Taiwan.
CHAPTER-2
OBJECTIVE & SCOPE
To achieve a highly efficient & effective inventory system, which developed into an optimum
inventory environment leading to global competitiveness.
Following are the objectives while implementing KANBAN system:-
To minimize the inventory holding stock
To remove mismatch of quantities required to produce alternators.
To prevent stock out of items.
JIT Purchasing( eliminating waste in the purchase process, at the supplier’s end & in
the purchased inventory)
Quality at source
To keep pace with changing market conditions.
Continuous improvement.
The project was carried out to remove excessive inventory & streamline & increase the
production to fulfill the market demand in JIT.
This project aims at the benefits of KANBAN system while reducing the inventory &
increasing production, improving quality in radical manner. This helped company to change
its strategy & policies so that it can improve its services & the satisfaction level of customers.
This will enhance its brand loyalty which further helps to retain its customer base as well as
increase its market share.
CHAPTER-3
LIMITATIONS
PMP is one of the major vendors of Mahindra & Mahindra, Kandivali. The major order of
alternators comes from M&M. (around 40-45%). Also PMP is the single source for alternators
for their tractor division & light commercial vehicle division. An err in supply of alternators
leads to stoppage of Mahindra’s line & will be placed PMP in black listed vendor list.
To achieve a highly efficient & effective production system through customer delivery with
quality parts, PMP made a lot of investment in inventory to ensure timely dispatch of
alternators at customer’s end. Due to the changing scenario in market demand, PMP’s
inventory piled up leads to increased inventory holding costs.
Also due to mismatch in stock figures for some items, inventory held up by the company was
in terms of rupees of average of 45 days sales, which could not converted a single alternator &
which eventually leads to loss of sales. Over buying results due to errors in the estimation of
the quantity & also non realization of anticipated sales. Also the supplier’s minimum quantity
condition was yet another cause of overbuying.
All these factors lead to production losses due to stoppage of proper material & therefore
failure to match the delivery schedule. And to make up these losses PMP ran 3rd shift many
times increasing overhead costs.
As alternators are made of stator, rotor, bearings, voltage regulators, brushes, slip rings, heat
sink, fan, end heads ( which are basically made up of steel, copper alloy, aluminum alloy,
silicon diodes comes into A &B class items), they are very costly. Keeping these high valuable
sub parts without converting into alternator leads to huge inventory holding costs. Also
environmental factor comes in the picture for the steel components & sheet metal components.
Therefore the main problem is to reduce the inventory, to prevent loss of sale, implement JIT
purchasing & to remove waste from supply chain management. For sorting out the above
problem we decided to go through KANBAN System.
In this project we are covering solution only for supply chain management. Also JIT &
KANBAN for production cycle is beyond the scope of work of this project.
CHAPTER-4
THEOROTICAL PERSPECTIVE
PMP has a wide range of alternator models which were produced by either batch production or
custom oriented job order production. So we decided to go for a Japanese proven system i.e.
JIT purchasing through KANBAN system which suits to our environment. We also keen to
implement JIT manufacturing simultaneously to meet our monthly target. By eliminating all
waste & seeking continuous improvement, we aim at creating a manufacturing system that is
responsive to market needs.
The characteristics of JIT purchasing are as follows:
Prevalence of a multi-tier structure of dedicated, partially & fully owned ancillary
suppliers.
Extension of KANBAN information system to include the suppliers
Communication of smoothed production plans to the suppliers, to ensure readiness to
deliver as per the production plan.
Development of high quality suppliers, who have eliminated the need for incoming
inspection at the manufacturer’s site.
High degree of cooperation & trust between the suppliers & the manufacturers,
resulting in development of long term relationships
Wide spread use of a single source policy which has eliminated problems of excessive
multi-sourcing.
Innovative part packaging & material handling systems.
PMP rely on 100% on purchased part & therefore want to make effective purchasing to
achieve the following things:-
Controlling the inventory levels
Drastic reduction in buffer inventories
Reduction of storage space
Reduction of material handling
Reduction of wasted/damaged materials.
Criteria for selection of KANBAN system :-
KANBAN system used by Japanese people to meet the precise demands of customers for
different models with minimum delay & had been proven manufacturing philosophy used by
them. It not only achieved a greater quality product but also achieved continuous improvement
in the manufacturing environment.
M&M & other OEMs adapted this system & achieved improved results in reducing inventory
& increasing level of customer service in their organizations. So PMP decided to go for
KANBAN system.
Criteria for Part Selection & alternator models:-
Bill Of Material of an alternator is made of around 80-85 items including “A” & “B” class
items like copper wire, aluminum castings, ball bearings, diode, machined steel component &
electronic regulators & “C” class items like all types of hardware.(washers, nut, bolts, spacer
etc.)
Out of which more or less hardware items are common to different model types of alternators.
Also 7022 model of alternator constitutes of sale of 40% of annual sales of all alternator
models.
Hence we decided to select BOM of 7022 model first for the implementation of KANBAN.
CHAPTER-5
METHODOLOGY & PROCEDURE OF WORK
Methodology:-
What is KANBAN :-
KANBAN (Japanese) : KAN-Card & BAN- Signal i.e. Card signal or visual Record.
In the modern lean terminology, a KANBAN is a visual information system established to
maintain the discipline of a JIT system on the shop floor.
A signal that authorizes production. A signal that to understand everyone i.e. from worker to
officer.
The three main principles of JIT are:-
Takt
Pull
Flow----Information (to material people) ------KANABAN signaling.
All the activity associated with any replenishment system is non value added. The target for
improvement should be to eliminate or stream line each activity associated with the
replenishment system.
A little inventory leads to the issues of overproduction, tying up the resources, deterioration or
damage in storage & handling, wasted space, storage costs, delay & long lead time & hidden
problems like production imbalance, late supplier deliveries, defects, downtime, long setups.
By using KANBAN signaling the response time have been reduced drastically proven by
Japanese people. It is based on pull system i.e. work releases are authorized based upon the
actual customer order status that means the status of downstream operations dictate the
production requirements for upstream operations.
Prerequisites of KANBAN “Pull” system:-
For a pull system to perform effectively, following should be in place:-
Quick changeovers, cellular manufacturing, one piece flow, low variability, reliable process &
stable, flat demand.
If these are not done first, implementing KANBAN pull will force these to take place.
How a KANBAN system does works across supply chain:-
Two bin card system : - This system used when WIP cannot be handed from one process to
the next, thus necessitating an inbound stock point & outbound stock point for processing
stations. This system utilized in the environment of high complexity parts.
In this system 2 bins are kept at production bay, stores & at suppliers end. When one bin is
empty, then it signals to the upstream operations & ultimately to suppliers to fill up that bin
within lead time. Therefore all operations are running smoothly at both end i.e. at
manufacturers & suppliers. There is no delay in the order, no delay in the production.
KANBAN size calculations:-
Establish average monthly consumption of all items (A, B & C class items).
Then establish average daily consumption of all items. Decide the packing size of all items
considering total lead time required to bring those quantities from supplier end.
Establish design control level & no. of KANBAN for ship lot. Also establish total KANBAN
issued across the supply chain & operating control level of each item.
No. of authorized KANBAN cards/containers controls the amount of inventory in the system
at any given time. The no. of cards/containers in the system directly impacts the WIP
inventory & safety stock. Material spends some time in transit, actual processing, waiting in
queue, waiting in storage location. So at any given time in the system, containers carrying
material are in one of the above stages.
The key to determining number of cards/containers is estimating the average lead time needed
to produce a container of parts.
Number of cards = (Avg. demand during lead time + safety stock)/ KANBAN size (size of the
container)
Where Lead time is the function of the processing time per container at the upstream supplier
station & the waiting time at the down stream production process & for material handling.
Procedure of work
Obtaining a clear understanding of KANBAN & what is involved in implementing KANBAN
by attending training programs & visiting implementing companies. Made training schedule
for the employees, workers & suppliers.
Working out an implementation strategy tailored to the needs of the business & with
quantifiable objectives & time scales. (nearly 6 months to 1 year horizon period)
Identification of “C” class items & their suppliers
We calculated average monthly consumption of all items (A, B & C class items) in bill of
materials of 7022 & 7803 first. Then we broke down the quantities into average daily
consumption.
We put present shipping lot against each items of BOM & present replenishment interval also.
From the above we decided new ship lot i.e. KANBAN quantity & calculated new
replenishment interval.
We calculated vendor response time (VRT) i.e. the time required for vendor for supplies to
PMP & transit time(TT) i.e. time required for transporters to pick up & deliver the supplies.
Then total lead time (TLT), the addition of VRT & TT had been calculated. Finally lead time
factor (LTF) had been calculated by adding TLT, internal lead time (ILT) i.e. the time required
for receiving, inspection & issuing on the line & safety stock (SS) level.
Then established no. of KANBANs in the system by dividing design control level to the
container quantity or KANABAN quantity.
Finally we arrived at operating control level of all items by multiplying KANBAN quantity to
total KANBAN s issued across the system.
We took the suppliers in confidence & gave training about the whole KANBAN concept.
Meanwhile we printed KANBAN cards & put it on plastic containers. Containers filled up
with KANBAN quantity from the current inventory of the stores so that to remove mismatch
in the system. Initially bins which were emptied, generates KANBAN signal to the suppliers.
Suppliers made deliveries against KANBAN signal.
When the production started, 2 bins are kept on the shop floor. Once the bin was emptied, it
returned back to stores. Stores generated KANBAN signal to the supplier & supplier ensured
the delivery within lead time. In this way the KANBAN cycle started.
On the next page, a sample sheet given for KANBAN calculations for few items of 7022
model.
Sample data for Vendor system KANBAN Design
Usa
ge
Po
int
Par
t N
o.
Par
t N
ame
BO
M L
evel
UO
M
Ven
do
r N
ame
Ven
do
r L
oca
tio
n
1 DEH ASSLY 70930503BEARING RETAINER
3 EAAUTOMEK PRODUCTS
SATARA
2 ROTOR ASSLY. 70250206ROTOR POLE M/C
2 EA ARIHANT IND A'NAGAR
3 Alternator Assembly
70250104 SPACER 2 M SUNEETUL SATARA
4 COIL ASSLY 10007 23 SWG WIRE 2 Ea PRECISION WIRE SILVASA
5 SREH Assembly 70220605 SREH CASTING 3 Ea ISHAAN ENGG VAPI
6 SREH Assembly 78030605 SREH CASTING 2 EaSATARA TECHNOCRATE
SATARA
7 DEH Assembly 70220504 DEH CASTING 4 Ea ISHAAN ENGG VAPI
8 ST.STACK ASSLY
80107POLY.FILM 10MIL * 43 MM
3 Ea GUJARAT POLY SILVASA
9 ALU.CASTING 50003 ALU.INGOT 2 Ea GANGAJAMUNA SILVASA
Par
t N
o.
Par
t N
ame
Ave
rag
e D
aily
C
on
sum
pti
on
Pri
mar
y P
acki
ng
Pre
sen
t S
hip
pin
g
Lo
t
Pre
sen
t R
I
New
Sh
iplo
t
New
RI
1 70930503BEARING RETAINER
300 100 5000 17 500 1.67
2 70250206ROTOR POLE M/C
800 50 800 1 800 1.00
3 70250104 SPACER 600 100 5000 8 5000 8.33
4 10007 23 SWG WIRE 55 500 5000 91 1000 18.18
5 70220605SREH CASTING
400 500 5000 13 1000 2.50
6 78030605SREH CASTING
60 500 5000 83 1000 16.67
7 70220504DEH CASTING
400 100 200 1 200 0.50
8 80107POLY.FILM 10MIL * 43
0.5 100 250 500 100 200.00
MM9 50003 ALU.INGOT 325 12 200 1 100 0.31
Par
t N
o.
Par
t N
ame
VR
T(V
end
or
Res
po
nse
Tim
e)
TT
(T
ran
sit
Tim
e)
TL
T (
To
tal l
ead
ti
me)
ILT
(In
tern
al le
ad
tim
e)
SS
(saf
ety
sto
ck)
LT
F(L
ead
tim
e fa
cto
r)
KA
NB
AN
QT
Y
DE
SIG
N
CO
NT
RO
L L
EV
EL
1 70930503BEARING RETAINER
1 1 2 1 5 10.0 500 2900
2 70250206ROTOR POLE M/C
2 1 3 1 2 7.0 800 5600
3 70250104 SPACER 5 1 6 1 5 20.0 5000 12200
4 10007 23 SWG WIRE 2 1 3 1 2 24.2 1000 1330
5 70220605SREH CASTING
2 1 3 1 2 8.5 1000 3400
6 78030605SREH CASTING
2 1 3 1 2 22.7 1000 1360
7 70220504DEH CASTING
0.5 0.5 1 0.5 1 3.0 100 1200
8 80107POLY.FILM 10MIL * 43 MM
1 0.5 2 0.5 1 203.0 100 101.5
9 50003 ALU.INGOT 1 0.5 2 0.5 1 3.3 100 1075
Par
t N
o.
Par
t N
ame
NO
. OF
K
AN
BA
S F
OR
S
HIP
LO
T
NO
OF
K
AN
BA
NS
FO
R
CO
NT
RO
L
TO
TA
L
KA
NB
AN
S
ISS
UE
D
OP
ER
AT
ING
C
ON
TR
OL
L
EV
EL
Car
d S
r. N
o.
Sto
rag
e R
ack
No
.
Sh
elf
No
.
1 70930503BEARING RETAINER
1.00 5.8 6 3000 100001 SR 2
2 70250206ROTOR POLE M/C
1.00 7 7 5600 100005 SR 3
3 70250104 SPACER 1.00 2.44 3 15000 100010 SR 3
4 1000723 SWG WIRE
1.00 1.33 2 2000 100012 3 5
5 70220605SREH CASTING
1.00 3.4 4 4000 100016 36, 11B
6 78030605SREH CASTING
1.00 1.36 2 2000 100017 3 9
7 70220504DEH CASTING
2.00 12 12 1200 100026EWA
1
8 80107POLY.FILM 10MIL * 43 MM
1.00 1.015 2 200 100044 GD 1
9 50003 ALU.INGOT 1.00 10.75 11 1100 100063SR 4
A
Flow chart for the stages of Implementation of KANBAN system
Obtaining a clear understanding of KANBAN & top management's approval for the implementation
Training on KANABAN for employees, workers & suppliers
Establish average monthly consumption of all BOM items of 7022 alternator model
Draw the average daily consumption of each item
Put the primary packing size & present shipping lot
Present replenishment interval (RI) = present shipping lot / avg daily consumption
Calculate new RI=New ship lot /Avg daily consumption
Establish VRT (vendor response time), TT (Transit Time), TLT (Total Lead Time),ILT (Internal Lead Time),SS (Safety Stock) from past experience
Calculate lead time factor (LTF) by adding TLT, ILT, SS & new RI
Continued on next pageNew ship lot = KANBAN Quantity
Calculate Design control level=LTF * Avg daily consumption
Calculate no. of KANBANs for ship lot = new ship lot / KANBAN qty
Calculate no. of KANBANs for control level =Design control level / KANBAN qty
Calculate Operating control level (OCL) = Total no. of KANBAN * KANBAN qty
Min Inventory valuation = Cost/unit * KANBAN QtyMax Inventory valuation= Cost/unit * OCL
Print KANBAN sticker & put on binsPrint KANBAN cards & put in the Bin, KANBAN post & Supplier’s end
Place 2 bins on Shop floor & 2 in stores & 2 at Vendors
Once bin is empty on shop floor, return back to store & in return store give another KANBAN bin
Also store generate the signal to vendor to ensure the supply of KANBAN qty within lead time. Repeat the cycle.
CHAPTER-6
ANALYSIS OF DATA
During implementation of KANBAN we focused on the most running model of alternator
supplied by us i.e.7022 to OEMs. Most of the hardware items covered in 7022 BOM is
common to other alternator models. These are the “C” class items for which production line
sometime stopped due to stock outs of materials & leads to production loss & sales loss. To
prevent out this, we started to work on “C” class items.
PMP have MRP II environment for its repetitive manufacture of different models of
alternators. MRP II provides a comprehensive framework for integrative planning & control of
manufacturing resources & generally includes:-
Resources requirement planning
Production planning
Master Production Schedule
Materials Requirement Planning
Capacity Requirement Planning
Shop Loading & shop floor control
Inventory Control
All these functions had been done by computer & to read, respond & manage these reports,
MRP II requires no. of planners. MRP II is forward looking& it replenished the material if it is
predicted that more is needed.
In PMP marketing people from Mumbai office forwards the next month’s internal purchase
order (IPO) of alternators which includes the order from export & OEM customers to Satara
office.
Then Planning officer run MRP for one month production considering the production plan, bill
of material & availability of the material. Material requirement generated & sent material
schedule to the approved vendors. Day to day production planning has been done by planning
officer & according to priority based on the inputs from Marketing people. The details of
customer wise production made & dispatch details has been informed to Marketing people to
enable them to make next month’s IPO.
This system is not full proof as some human errors occurred always while doing the above
steps. Some of the reasons are:
1) As the system stock did not match with physical stock so every time we have to take
physical stock before sending the schedule which is ideally not possible in each case.
2) Any changes in planning schedule, supplier found hard to switchover the respective
supply of material in minimum time.
3) If any order is pending or cancelled, then inventory piled up for that alternator model
or order.
4) Supplier sent the scheduled material in a single delivery to reduce the freight cost, not
in staggered delivery.
5) Due to mismatch in synchronization & avoid sale loss, PMP run 3rd shift many times in
a month which ultimately increases overhead costs.
6) It may happen sometime that production of not required models has been taken place
which blocked resources & eventually kept in finished good store till its sales.
7) For the above reason overbuying took place which piled up inventory also.
8) Due to changes in design, some items become obsolete & lying as non-moving items.
9) Some items like ball bearings, regulators, diodes are imported so we have to give 4
month’s order in advance for these items.
Following facts observed in PMP:-
1) Yearly consumption of alternators : - Approx. 50,000 nos.
2) Monthly on an average : - Approx 4,200 nos.
3) Daily on an average : - Approx.175 nos.(25 working
days)
4) Monthly sale of alternators : - Approx Rs. 0.8-0.9 Crore
5) Annual sale of 7022 Alternator : - 17,000 nos.
6) Inventory lying at PMP : - approx Rs.1.1 Crore
(near about 45 days of alternators sale)
Details of inventory as below:-
“A” Class items like raw material copper wire, ball bearing, Aluminum ingot, job work
items & finished alternators :- Rs. 60 Lakhs
“B” class items like m/c steel components, WIP items : - Rs. 21 Lakhs
“C” class items like Hardware, washer, spacer etc : - Rs. 19 Lakhs
Nonmoving items : - Rs. 8 Lakhs
7) Manpower required for running third shift : - 25 workers + 1 Officer
8) No. of alternators produced in extra shift : - 100 nos.
9) Average no. of times to run extra shift in a month : - 4-5 times
10) Extra manpower cost: - no. of workers x man hrs. x cost/person in Rs/hr x no. of
times extra shift run = 25 x 8 x 30 x 5
= Rs. 30,000
11) Power cost for extra shift = Approx. 6000 Rs. / shift
12) Total power cost = 6000 x 5 = Rs.30,000
13) Avg Inventory carrying during each month :- Approx Rs.1.0 Crore
14) Therefore Annual avg inventory carrying cost = Inventory x interest rate
=1 Crore x 10%
=Rs. 10 Lakh
15) Loss of sale of 7022 model per month = approx 500 nos.
=500 x 1,600(Cost /alternator)
=Rs.8,00, 000
16) In addition to the above stock out cost considered as Rs.1, 00,000 due to idle men &
machine, loss of production profit, premium price paid to transporter, penalty paid to the
delayed OEM shipment.
If we add all the figures above i.e.
Total monetary loss = Extra manpower cost + Power cost + Loss of sale + stock out cost +
Avg inventory cost = 30,000 + 30,000 +8, 00,000 + 1, 00,000+ (10, 00,000/12)
= Rs.10, 43,335 per month
≈ Rs.10.5 Lakh Per month
≈ Rs.125 Lakhs per Annum i.e. approx. of one month’s sale of
alternators.
Therefore a huge cost is involved to streamline the production & timely supply to customers &
many others intangible things happened, which dilute the image of PMP.
Hence we had decided to correct our supply chain process & inventory management first. Our
aim is to reduce the waste (anything other than the absolute minimum resource of material,
machine & manpower required to add value to the product) in the supply chain & production.
We decided to remove mismatch of “C” class items & some of “B” class items. Also decided
to scrap non-moving items & after the modification some non-moving items would be used as
regular items.
CHAPTER-7
FINDINGS, INFERENCES & RECOMMENDATIONS
After implementation of KANBAN, we achieved drastic radical change in our system. We
have achieved a lot of tangible & intangible benefits from this system. Our morale becomes
high.
During implementation supplier played a major role in terms of delivery & quality of supplies.
We achieved to imbibe KANBAN system on them to large extent & extended our help in all
terms.
During the preliminary stage of first 6 months we achieved following data:-
1. Monthly Production increased for 7022 alternator : - 1000 nos.
2. Therefore monthly sales increases by=1000 x 1600 = Rs.16, 00,000.
3. No more extra shift which saved :-Rs.60, 000 than earlier
4. No stock out due to “B” or “C” items saves :-Rs.1,00,000 than earlier
5. Cost of KANBAN bins added :-Rs. 50,000
6. Cost of printing KANBAN cards & stickers added :-Rs. 5,000
7. Additional Freight cost added :-Rs. 20,000
8. Non moving items modification to moving items :-Rs.350,000
(melting aluminum casting, using modified washers, spacers in the replacement
product)
9. Non moving items sold as scrap :-Rs.50,000
(rejected copper wire, bearings, diode sold as scrap, through bolts & washers sold to
local spare part retailer)
10. Hence non moving inventory lies in the system :-Rs.3,00,000
11. “C” class items inventory reduced by 48% i.e. :-Rs. 9,00,000
(still Rs.10 Lakh inventory pending in the system)
12. “ B” class items inventory reduced by 42% i.e. :-Rs. 8,80,000
(still Rs.12.2 Lakh inventory pending in the system)
13. “A” class items inventory reduced by 34% i.e. :-Rs. 20,50,000
(still Rs. 39.5 Lakhs inventory pending in the system)
14. For imports item like ball bearing, voltage regulator, diodes, we reduced their delivery
schedule from 4 months to 2 months.
15. Now average inventory reduced in the system by 40%:- Rs. 43,00,000
16. Therefore inventory in sys = Non moving + A items + B items + C items
= 3L + 39.5L + 12.2L + 10L
= Rs. 64.7 Lakh
17. Inventory holding cost/month = (Avg inv in a month x bank interest for 1 yr/12)
= (Opening stock + closing stock)/ 2 x 10%/12
= (70 Lakh + 59.5Lakh) / 2 x 0.1 / 12
= Rs. 53920 / month
Sr. No.
Components Prev data per month
Current data per month
Prev expenditure in Rs
Current expenditure / gain in Rs
Savings per month in Rs
1 Manpower cost 60,000 ------- 60,0002 Inventory
Holding CostA-60Lakh, B-21 Lakh, C-19Lakh, non move items-8 Lakh
A-39.5Lakh, B-12.2 Lakh, C-10Lakh, Non move items – 3.5Lakhs
83,335 53,920 29,415
3 Addl Freight cost
------- 20,000 20,000
4 Loss of production / sale
- 500 nos +1000 nos 8,00,000 16,00,000 8,00,000
5 Stock out cost 100,000 ----- 1,00,000
6 Scrap cost by selling non move items
50,000/12 ≈4,000
4,000
Total savings in Rs.
973,415
Therefore total savings generated by implementing KANBAN system is approximately
Rs.9.75 Lakhs per month. We continued to improve our performance day by day by utilizing
the inventory efficiently & by streamlining the supply to fulfill the customer’s order timely.
Apart from the above, following tangible benefits we have achieved :-
A. Simplified system :-
Due to KANBAN cards, we established a pre-determined inventory buffer through out the
supply chain cycle. We have to monitor continuously on the KANBAN post where all
KANBAN cards put, not to count physically each & every item before sending the
schedule. Due to this visual signal, even store man also sent the signal to vendor for
KANABAN as soon as empty bin returned from the shop floor.
No need to use either the computer system or paperwork.
B. Prevention of stock out: -
Earlier due to small items like shaft nut, bearing cap or through bolts, production line got
to be stopped. Men & machine became idle or produced unwanted model of alternators or
halfway assembly of the alternators to achieve the target of shift. As the KANBAN system
designed with lead time consideration, it prevented stock out of items unless some major
disruptions at any work center or failures of machine at supplier’s end.
C. Increase in Delivery Performance by supplier:-
We involved the suppliers in a formal education program on KANBAN & JIT, utilizing
SPC methods, made a delivery commitment from them& helped to establish a quality
assurance plan at their plant. Two KANBANs were kept ready at any time at supplier’s
end. After receiving KANBAN signal, the supplier sent the delivery immediately. Also
delivery lot size should be just enough to satisfy the immediate higher level requirement. .
We have only to ensure that proper communication should happen.
D. Increase in Production & Sales:-
Due to uninterrupted supply of materials, we fulfilled the customer’s order timely &
achieved the monthly target. Earlier due to stock outs, whole production line was stopped
& we did not meet the schedule. But now we regularly meet the schedule, customer
showed confidence in us & increased the order. Ultimately our production of 7022 model
increased by 500 nos. per month. Also our per day’s target increased from 250 to 300 nos.
alternators.
E. Reduction in inventory:-
As the KANBAN bins introduced, we removed mismatch of quantities & established
maximum & minimum inventory across the supply chain. Import items lead time reduced
from 4 months to 2 months. Therefore we achieved reduction of holding cost of Imports
item. For local & “C” class items, we achieved small lots in delivery i.e. in KANBAN
quantity. Due to increase in production, a lot of inventory lying at our end has been
consumed. Some non moving items modified & some sold as scrap. Overall we reduced
the inventory holding cost by 40%.
F. Increase in supplier’s involvement
Now we are providing the fortnightly schedule to our supplier & tentative supply of
monthly KANBAN quantities well in advance so that they can plan accordingly. We
helped them to meet quality requirements. We encouraged them to use process control
charts instead of lot sampling inspection. We encouraged them to package in exact
quantities & provided them KANBAN bins. Also we encouraged them to reduce their
production lot size.
G. Increase in Inventory turnover ratio
Purchased material turnover during the period of implementation increased 1.5-2 times
than previous 0.5-1 times.
H. Increase in meeting the delivery schedule of OEMs
Due to this system, we regularly met the customer’s order on time. Delivery index of PMP
improved & got more orders from OEMs. Also M&M showed interest & help for starting
PMP’s plant at Rudrapur to start supply of alternators for M&M, Rudrapur division.
We achieved some Intangible benefits apart from tangible benefits:-
A. Improved Product quality:-
PMP improved quality & delivery performance of alternators. Hence at the same
manufacturing cost PMP improved its operating profitability by reducing waste across the
supply chain.
B. Improved Productivity:-
Resources were used efficiently & effectively & only produced when needed. Unwanted
production (apart from customer orders) of alternators was stopped, so resources were not
blocked & no time was spent in finished goods store for waiting to be ordered. Due to
efficient planning, workers achieved the shift’s target easily. There was no extra shift to be
run. Productivity improved significantly.
C. Improved plant efficiency:-
Plant efficiency was increased due to well coordination & support of other departments
also. Maintenance people carried out weekly, monthly, yearly maintenance according to
maintenance schedule on holidays. Daily maintenance also carried out during the start of
each shift. Manpower on the shop floor used effectively. Store people also issued material
efficiently in KANBAN bins. Overall keeping the same resources earlier, the plant outputs
substantially increased.
D. Better production scheduling:-
Customer’s monthly order was divided in day’s output, and then shift’s output, then hourly
output i.e. by going backtracking of the order in micro level & ensured work load
uniformity. Monitored the KANBAN cards & delivery of the respective item closely &
effectively. System provided flexibility for changing the production line to cope up
customer’s order. Better scheduling achieved with better flow of material & reduced setup
time.
E. Reduced inspection of incoming material:-
We provided suppliers loose specifications i.e. supplier relied more on performance
specifications rather than on design performance & encouraged the supplier to be more
innovative. We imbibed the concept of “Do it right, the first time, every time” & helped
them to meet quality requirements. Encouraged them to use SPC charts instead of lot
sampling inspection. Visited the supplier’s plant once in a month for sorting out any
quality issues.
F. Better Buyer Seller Relationship
We assumed supplier’s place as an extension of our buying centre & during KANBAN
implementation we encouraged supplier for the improved performance & helped in all
matters (e.g. educated them regarding JIT & KANBAN system, reduced their inventory,
encouraged in quality matters. We significantly changed our sourcing policy to shift single
source policy for long term contract & mutual benefits. We considered supplier’s
participation from the initial stages of this KANBAN project. We achieved supplier’s
reaction capability to our schedule changes without any special premium paid to the
transporter or carrying additional inventory carrying costs. Supplier’s business was
increased & operating profitability was also increased.
G. Improved morale in Production
People were more enthusiastic & energetic & responded well to this concept of KANBAN.
As the production streamlined, they achieved their shift’s target easily. No need for extra
shift even though the schedule was increased. Also there will be neither effect of
absenteeism nor the breakdown of the machine. All of them co-operated & helped each
other to achieve the target.
H. Reduction in paperwork
There was no need of computer to generate the work order & to check the stock. No print
of purchase order required. It saved a lot of time for the formal paperwork, changing the
delivery date & quantity required in PO.
I. Increased Market value & improved customer satisfaction
Due to better customer service, customer satisfaction level & market value of PMP
increased with respect to the competition. It would help PMP to build up its image as a
provider of “Value for Money” to its customers.
As the customer’s expectations were achieved, PMP got the major upcoming orders & a
lot of other new customers.
Recommendations:-
After gaining the above benefits, management decided to implement KANBAN for all
models of alternators & all of its products in phase wise manner. As the current system is
manual, we decided to go for computerized system since the new technology available in
the market. We recommended using the bar code on KANBAN cards for generating the
trigger to have errorless system.
CHAPTER-8
CONCLUSION
Inventory is an integral part of the any organization. Not only it adds value to the product
but adds to its cost. Organizations carries inventory to economize on buying /
manufacturing cost, to remain flexible with customer’s demand, to prevent stock outs, to
stabilize the production, to prevent loss of sale & to satisfy other business constraints (like
supplier’s condition of minimum quantity, government regulations, seasonal availability) .
But while satisfying the above facts, the inefficient use of handling inventory (ability to
convert it into finished product) becomes problem for any organization. Also wrong
buying methods & wrong calculations helps to pile up the inventory across the supply
chain.
The company is already running the heavy expenditure on the inventory to cope up the
customer’s requirement & stabilize the production in this competitive market. This
inventory issue can be improved by utilizing the available sources properly, structuring the
replenishment cycle efficiently & effectively & making effective sourcing policy, which
has been shown as an example of 7022 alternator in the project.
By using KANBAN system, PMP improved its sourcing policy, suppliers’ relations,
production scheduling, timely delivery to customers, product quality, inventory reduction,
sales of the product & competitive position in the market. PMP uses KANBAN & JIT
purchasing not just an inventory control or inventory reduction technique but a philosophy
or an approach to productivity which is applicable to all facets of manufacturing process,
including supply chain.
KANBAN & JIT purchasing implies a significant departure from the conventional
purchasing practice in a variety of ways. A phased approach will be therefore used for its
full implementation. As this effort intensifies, KANBAN & JIT purchasing might well
assume the character of “coordination of outside manufacturing & inside manufacturing”.
CHAPTER-9
SUMMARY OF THE PROJECT
This project carried out to remove excessive inventory, better inventory control, streamline
the production & continuous improvement in the organization.
Inventories are the physical stock of items that PMP keeps in hand for the efficient running
of its organization. But due to mismatch quantities of stocks, overbuying, inadequate
production planning, PMP failed to meet the customer’s requirement on time. Therefore
PMP’s inventory holding cost, procurement cost, overhead cost & stock out costs was high
& dented its profitability margin.
So PMP decided to implement Japanese technique “KANBAN” to keep better control on
the inventory. PMP selected 7022 model of alternator for the implementation of KANBAN
technique.
PMP got the fantastic results after initial implementation of KANBAN. Company achieved
the reduction in inventory with increased production & sales within 6 months period of
implementation. Customer satisfaction levels of company’s products increased.
PMP achieved increased market share & more orders from OEM & foreign customers.
From this PMP decided to go for the implementation of KANBAN on all alternator models
& company’s other products in phase wise manner. Also company decides to use latest
technology of bar code along with KANBAN system.
ANNEXURES
I) List of Diagrams ,charts
a) KANBAN Bins, carts, store & Supplier KANBAN card
b) Alternator yearly sale data
II) List of Tables
a) Alternator sale data before & after KANBAN system
b) KANBAN Bin Stickers
c) Comparison between Traditional purchasing & JIT Purchasing
KANBAN bins KANBAN cart KANBAN store
Supplier KANBAN Card:-
SUPPLIER KANBANPart Name
BRUSHCARD ASSEMBLY
Part No. UOM
70230720 Ea
KANBAN Qty Ship LotLead Time
300 300 3
BUYER MBJVendor
Samartha Enterprises
Storage Location 6 - 23, 24Card Sr. No. 100541
1 0 0 5 4 1 Card No. 1 of 4
Alternator yearly sale data
April to July : Before implementation of KANBAN system.
August to March : After implementation of KANBAN system.
Alternator Sale Figures
39574391
4710 4642
54355045
5525 54415963
54455735
5989
0
1000
2000
3000
4000
5000
6000
7000
April
May
June Ju
ly
Augus
t
Septe
mbe
r
Octobe
r
Novem
ber
Decem
ber
Janu
ary
Febru
ary
Mar
ch
Month
Alt
ern
ato
r Q
ty i
n n
os.
Series1
Yearly Sale figure of Alternator Models
Before implementation of KANBAN system
After implementation of KANBAN system
Model Ap
r' 0
4
May
' 04
Jun
e' 0
4
July
' 04
Au
g' 0
4
Sep
t' 0
4
Oc
t' 0
4
No
v' 0
4
De
c' 0
4
Jan
' 05
Feb
' 05
Mar
' 05
To
tal
7016 100 100 24216
2 10 100 125 45 8847017 5 57018 22 50 5 50 1277019 36 36
7021 124 180 100 62 50 2522
5 7667022 / oe 1152 783 1245
1088 1800
2150
2100
2050
2100
2200
2075 2115 20858
7023 8 17 5 307026 140 10 5 50 50 2557033 150 1507036 150 185 25 150 302 500 100 100 1512
7043 1 107 103 81 180 180 175 198 300 7010
0 14957046 30 50 807063 27 73 7 42 45 5 58 45 25 327
7065 14710
3 50 100 115 129 175 10020
0 50 11697068 100 90 130 18 50 388
07803/oe 949 1009 664
723 1200 805
1500 991
1460
1275
1300 1275 13151
7807 5 80 150 180 49 50 5147809 20 24 4 25 15 50 25 50 100 3137811 85 85
0
EFA 1312 1043 12991791 1225 875 700 689
1135 875
525 1318 12787
IFA 70A 408 780 944
495 400 450 200 576 80 300
1040 591 6264
IFA 90A 30 20 125 57 200
270 380 1082
Total 3957 4391 47104642 5435
5045
5525
5441
5963
5445
5735 5989 62278
KANBAN Bin Stickers :-
PART NO 70220501 PART NO 70220501DESCRIPTION DEH M/C
DESCRIPTION DEH M/C
STATION NO D-1 STATION NO D-1BIN QTY 40 BIN QTY 40 PART NO 70250104 PART NO 70250104DESCRIPTION SPACER
DESCRIPTION SPACER
STATION NO D-1 STATION NO D-1BIN QTY 900 BIN QTY 900 PART NO 70930213 PART NO 70930213DESCRIPTION BALL BEARING
DESCRIPTION BALL BEARING
STATION NO D-2 STATION NO D-2BIN QTY 150 BIN QTY 150 PART NO 70930503 PART NO 70930503DESCRIPTION BEARING RETAINER
DESCRIPTION BEARING RETAINER
STATION NO D-2 STATION NO D-2BIN QTY 900 BIN QTY 900 PART NO 70510503 PART NO 70510503DESCRIPTION BEARING RETAINER
DESCRIPTION BEARING RETAINER
STATION NO D-2 STATION NO D-2BIN QTY 600 BIN QTY 600
PART NO 70930502 PART NO 70930502DESCRIPTION BALL BEARING
DESCRIPTION BALL BEARING
STATION NO D-3 STATION NO D-3BIN QTY 150 BIN QTY 150 PART NO 70930105 PART NO 70930105DESCRIPTION WOODRUFF KEY
DESCRIPTION WOODRUFF KEY
STATION NO D-5 STATION NO D-5BIN QTY 600 BIN QTY 600PART NO 79010106 PART NO 79010106DESCRIPTION SHAFT NUT
DESCRIPTION SHAFT NUT
STATION NO D-5 STATION NO D-5BIN QTY 900 BIN QTY 900
Comparison between JIT Purchasing & Traditional purchasing
Purchasing Activity JIT Purchasing Traditional Purchase
Purchase lot size Purchase in small lots with frequent deliveries.
Purchase in large batch size with less frequent deliveries.
Selecting supplier Single source of supply of a given part in nearby geographical area with a long term contract.
Rely on multiple sources of supply for a given part and short term contracts.
Evaluating supplier Emphasis is placed on product quality, delivery performance, and price but no percentage of reject from supplier is acceptable.
Emphasis is placed on product quality, delivery performance and price by certain percentage reject is acceptable.
Receiving inspection Counting and receiving inspection of incoming parts is reduced and eventually eliminated.
Buyer is responsible for receiving, counting, and inspecting all incoming parts.
Negotiating and bidding process
Primary objective is to achieve product quality through a long term contract and fair price.
Primary objective is to get the lowest possible price.
Determining mode of transportation
Concern for both inbound and outbound freight, and
Concern for outbound freight and lower outbound
on-time delivery. Delivery schedule left to the buyer.
costs. Delivery schedule left to the supplier.
Product Specification “Loose” specifications. The buyer relies more on performance specs than on product design and the supplier is encouraged to be more innovative.
“Rigid” specifications. The buyer relies more on design specs than on product performance and suppliers have less freedom in design specs.
Paper work Less formal paperwork. Delivery time and quantity level can be changed by phone calls.
Requires great deal of time and formal paperwork; changes in delivery date and quantity require purchase orders.
Packaging Small standard containers used to hold exact quantity and to specify the precise specs.
Regular packaging for every part type and part number with no clear specs on product content.
ISO 9001 Certificate