A photographic history of our church Twelve Apostles Parish
Jan 15, 2016
A photographic history of our church
Twelve Apostles Parish
13 August 2012
Building Our House on a Rock Solid Foundation
Concrete footings
are poured in the
ground
underneath the
floor of basement.
They serve as the
foundation of the
foundation. Seen
from the east end
, the footings
trace the
“footprint” of the
lower level.
Safety First!
To strengthen the
footings, metal
rebar is placed
inside the
concrete as it is
poured. The
orange plastic
caps are placed
on the ends of the
rebar to prevent
injuries to
workers on site.
Keeping Our Balance
This interior
footing has four
bolts placed
within it. The
base of a support
column will later
be placed atop
these bolts. The
nuts will then be
adjusted to level
the base so the
column is
perfectly vertical.
“He sets up walls and ramparts to protect us”-Is 26:1
Concrete will be
poured into these
forms to create
the walls of the
lower level. The
metal rebar
provides interior
strength to the
concrete; the
walls will also be
buttressed with
steel beams on
the inside.
18 August 2012
The Upper Parking Lot
Click icon to add picture
The outlines of
the circle drive
and the upper lot
are seen in this
photo, taken from
the site of the
future front door
of the church.
This arrangement
will allow folks to
be dropped off
right at the front
door.
The Upper Parking Lot
This is the upper
lot seen from the
west end, facing
the front of the
church. The
forms for the
basement stand
just beyond the
lot’s edge. The
black plastic on
the right prevents
erosion of the
exposed soil.
The South Terrace
The south terrace,
viewed from the
southwest. The
lower level– which
houses the future
classrooms, parish
hall, and offices—
opens directly into
this area. The
Prius, trailer, and
outhouse will be
removed prior to
occupancy!
The Lower Parking Lot
This lot sets
directly south of
the church. It
provides
convenient access
for entry to the
lower level of the
church where the
future offices,
classrooms, and
fellowship hall
will be located.
Safety First!
The future church
will accommodate
over 400 people,
so it is necessary
to provide
adequate fire
protection. These
hydrants will be
installed near the
south side of the
church to
facilitate fire
control.
The Lower Level
This is a view of
the lower level of
the church from
the northeast
corner. Due to
the height of the
walls, scaffolding
is required just to
install the forms.
Concrete will
soon be poured
into these forms
to make the
outside walls.
This is the electricity
meter for the new
facility. Since the
church sets back several
hundred feet from the
road, it is necessary to
run as much electrical
line to bring power to it.
The extensive power
requirements of our
church, necessitated by
the high demands for
heating and cooling a
large volume of space,
also require specially
designed power
distribution systems.
Let There Be Light!
3 Sept 2012
Basement Walls in Progress
The walls in the
lower level
continue to be
erected. Some
have already
been built, as
seen on the left;
the forms of
others have been
built, but
concrete will be
poured later;
finally, some of
the forms, shown
in center, still
await assembly.
Plumbing
These vertical
white pipes are
for plumbing.
One Last Look . . .
The walls shown
here will
eventually be
buried
underground.
Curbing on the Grade
These curbs show
the outlines of the
roundabout and
driveway out to
Humphrey’s
Road.
Storm Sewers
The impermeable
surfaces of the
parking lot and
driveway create
large amounts of
runoff water.
This storm sewer
conducts the
water to a
detention pond
which delays its
entry into the
drainage ditch
and thereby
prevents flooding.
Making a Highway for Our God, and
His People
The high amount
of traffic entering
and leaving the
campus at Mass
times will affect
traffic flow on
Humphrey’s
Road. In order to
lessen the impact,
we are required
to add an extra
lane along the
frontage of our
property.
Making Connections
In order to get
water to the
building, 1800 feet
of pipe was run
from the
intersection of N
Hwy to the parish
campus. Here the
valve connecting
the main to the
campus is shown.
The concrete vault
on the left will
contain the water
meter and pump.
Making Connections,
Part II
Electricity to the
campus is now
hooked up. The
three strips of
conduit on the
left of the power
pole contain the
wiring which
carry power to
the building.
Power is already
needed for
lighting the
trailer and
running other
construction
equipment.
22 September 2012
Basement Lower Level
Floor
The floor in the
lower level is
seen in this
photo. The
concrete was just
poured this week.
The concrete
slab is sawed into
square sections to
prevent unwanted
cracking.
Lower Level Floor—Part II
The pillars
supporting the
upper level floor
will rest directly
on the footings
below the
basement floor,
hence forms were
placed around the
bases for the
pillars.
The Kitchen
Due to cost
limitations, the
proposed kitchen
cannot be built in
the first phase of
construction. To
facilitate later
construction, this
section of the floor
is deliberately left
unfinished. The
doorway will
provide easy access
to the kitchen from
the outside.
Wall Exterior
The black
material on the
exterior of the
wall is
waterproofing.
The blue
Styrofoam
insulates the wall
to prevent water
condensation on
the interior wall
during cool
weather.
Wall Exterior—Part II
The exterior of
the walls is
backfilled with
gravel rather
than dirt. The
gravel makes it
easier for water
to drain away and
thereby reduces
strain on the
exterior due to
water pressure
and freezing.
Driveway
Prior to the
paving of the
driveway, a base
layer of gravel is
placed on the
driveways and
parking lots.
Hole-y Ground
This photo shows
the water line
connection near
the church. The
yellow caution
tape warns
onlookers—both
Anglo and
Latino--that
falling into a hole
may cause
serious injury.
The contractor is
not responsible
for harm suffered
by illiterates.
28 September 2012
Taking Shape
The structural steel
framework
supports the floor
of the upper level
and buttresses the
lower level walls
too. The concrete
piers will support
the exterior
pilasters in the
finished church.
The remaining
lower level walls
will be made of
wood rather than
concrete.
Bell Tower
This steel frame
is the structural
support for the
bell tower. Due to
budget
constraints, no
bell will be
installed in the
tower at first.
Eventually, a
carillon
(electronic) bell
system will be
installed.
A Stairway to Heaven
The stairway on
the right provides
access from the
lower to the
upper levels of
the building. The
square hole on
the left is the
base of the
elevator shaft.
Due to budgetary
constraints, the
elevator will not
be installed in the
first stage of
construction.
Pier-ing Inside
These concrete
piers mark the
main entrance of
the church. They
will support the
overhang
structure at the
front door that
will shield
worshipers
entering the
church from
inclement
weather.
Side Entrance
These steel posts
frame the side
entrance of the
church. This
entrance will be
situated near a
circle drive. It will
allow for people to
be dropped off
near the church.
Eventually the
section of the
drive near this
entrance will be
covered.
Holy-Mole-y?
Is this the work of
a gigantic
mutant mole?
Not exactly. This
lengthy mound of
dirt traces the
waste disposal
line which runs
from the north
side of the
building to the
northwest corner
of the campus
where the septic
system has been
installed.
A New Kind of Irrigation
The facility’s waste
will be disposed of
in a septic system
on the northwest
corner of the
campus. The
white pipes
indicate the site of
lateral lines of the
plumbing network.
After the county
sewer line is built
to the north, the
waste line will be
connected to it.
5 October 2012
Closing In
The lower walls
on the south and
east sides of the
structure are
made of wood.
The studs and
other support
elements are
shown here. The
doorways and
windows can be
seen from this
view from the
south.
Closing In, Part II
This is a view
from the east.
The doorway into
the lower level
can be seen on
the left. This end
of the lower level
will eventually be
turned into
administrative
offices for the
parish.
Closed In
This is a view
from the inside of
the lower level
looking outside
towards the
southwest. A
doorway and
window openings
can be seen.
Let There Be Light . . . Poles
The base for one
of the parking lot
lights is shown
here.
Coincidentally,
there are twelve
poles in the lots,
corresponding to
the twelve
apostles. As the
Lord told them in
the Sermon on
the Mount: You
are the light of
the world!
Dirty Jobs
These concrete
covers grant
access to the
septic tanks so
that they can be
serviced as
needed. The
tanks are located
to the east of the
church.
Main Entrance
These steel
beams will
support the
overhang above
the front
entrance into the
church.
A Bend in the Road
A change in the
construction
plans was
recently made. It
was decided to
finish paving all
the parking lots.
So additional
preparation work
is being done to
complete this
easternmost
section of the
lower parking lot.
Pooch Pilgrimage
Site?
It is said that all
dogs go to
heaven. We hope
they all don’t go
here! In fact, this
fire hydrant is
located near the
front entrance to
ensure adequate
emergency water
service in the
event of a fire.
12 October 2012
Lower Level-East End
The lower level
walls are being
installed. The
outlines of
doorways and
windows can be
seen in this photo
taken of the east
end of the
building.
Lower LevelSouth Side
This view of the
south side of the
lower level shows
the outlines of the
windows and
doorways. The
lower level will
house the
classrooms,
fellowship hall,
and parish
offices.
Come on in, the Door’s
Open!
The outlines of
the walkway from
the parking lot to
the lower level
are traced by the
gravel path. A
sidewalk will be
installed here
later.
Looking from the Inside Out
This is a view
from the interior
of the south
doorway. The
gravel path leads
to the parking lot.
TJI Fridays
These wooden
floor joists are
known as “TJIs.”
They provide
support for the
upper level floor.
Upper Level Flooring
Plywood is being
placed on the
floor joists to
serve as the base
for the rest of the
upper level
flooring.
Future Kitchen
The kitchen will
eventually be
installed in the
northeast corner
of the lower level,
so this area was
left open for the
installation of the
necessary
equipment in the
future. The pipes
connecting to the
future drains and
sewers can just
barely be seen.
My Friend, Go Up Higher!
. . . But you’ll
have to take the
stairs! This
square opening is
the base of the
shaft of the future
elevator. It will
be covered with a
temporary floor
at first; this floor
section will then
be removed when
the elevator is
installed.
A View from Above
This photo shows
the plywood
being affixed to
the top of the
floor joists.
Main Ent;ry
This photo shows
the main entry of
the church. The
approximate level
of the floor is now
beginning to
appear.
Let the Sun Shine In!
It was a cloudy
day for the Age of
Aquarius.
Nonetheless, by
leaving the
southwest corner
of the flooring
until last, workers
were able to
make use of
natural
illumination. A
set of TJIs rests
just inside the
side entry from
the north.
A Bump in the Road
The concrete has
been poured at
the entry of the
driveway. The
asphalt paving of
the rest of the
drive should
begin soon. In
the meantime,
traffic is entering
from a temporary
driveway on the
east end of the
frontage.
26 October 2012
Glulams
Glulam is
shorthand for
Glued Laminated
Timber. These
are supporting
elements that
support the roof
and upper walls
of the church. A
pair of the
glulams are being
installed here.
Glulams: A Closer Look
Glulams are
actually
composite beams
made of
numerous
wooden beams
(approximately 1”
x 4”) which are
bent and then
glued together
and laminated.
Meeting in the Middle
The glulams are
erected in pairs.
The two glulams
are connected at
top by several
bolts which are
run through these
pre-drilled holes.
Making Connections
The metal
bracket at the
base of this
glulam is called a
“shoe.” The shoe
joins the glulam
base to the steel
frame below.
Working in High Places
Yes, those who
work for the
Church work in
“high places,” but
we usually speak
in figurative
terms. Not so
here! Due to the
high of the
glulams,
scaffolding must
be erected to
enable workers to
fasten the beams
together at top.
Decking
Once the glulams
are in place, the
wooden decking
shown here
(wrapped in
protective plastic)
will be ready to
install. This
decking will be
fastened to the
top of the glulams
and will
constitute the
church ceiling.
Work in Progress
Getting material
into place for
assembly is a job in
itself! The orange
forklift in front is
used to lift the
material from the
ground to the floor
of the church for
assembly. The
wooden frame for
one of the dormers
on the south side
has just been
installed in the
center.
More Work in Progress
Two cranes are
used to raise the
glulams into place.
Wind has proved to
be a significant
challenge due to
the high elevation
of the site and the
height of the
glulams. The
glulams are
fastened to one
another and also
attached by cables
to the floor for
stability.
Handle with Care
The protective
plastic and other
materials are
used to shield the
glulams from
damage during
assembly.
Shortening the Long and
Winding Road
The asphalt
surfacing has
made the trip up
the driveway a
little shorter, or
at least, a bit
smoother.
Parking Lot
The asphalt has
also been laid
down on the
parking lots.
Quite a Handful
This orange
instrument is
used by a worker
on the floor to
steady the glulam
while it is being
hoisted by the
crane.
Taking Shape
This photo is
taken from the
vicinity of the
future choir area
in the north
transept, looking
into the main
nave. It gives
some idea of how
the structure will
appear when
finished.
Worshipers will
not be required to
wear hardhats!
Safety Railing
Temporary safety
railing is erected
around the floor
during
construction to
prevent workers
and authorized
visitors from
falling off.
Holding It Together
At this stage of
construction, the
glulams must be
kept stable using
cables attached
to the floor as
well as by
fastening them to
each other.
Dormers
This is the
wooden frame,
partially
assembled, for
one of the
dormers which
run along the
sides of the
church. The
frames are
assembled on the
floor and then
raised into place
along the walls.
Taking Shape—Main Entrance
This photo from
the west gives the
viewer a sense of
the how the
outline of the east
side of the church
will appear. The
steeple of the bell
tower will rise
slightly higher
than the top of
the crane on the
right.
2 Nov 2012
Ridgebeam & Purlins : The glulams are now being connected to each other via the ridgebeam running along the top of the structure and the purlins which run horizontally from one glulam to another.
X Marks the Spot
These diagonal
beams in the bell
tower denote
shear walls. The
shear walls help
reinforce the
structure against
the stresses
induced by high
winds.
Narthex
This pair of
smaller glulams
in the foreground
gives the
observer a sense
of the narthex,
that is, the
gathering area at
the front of the
church. It has a
lower roof that
segregates it
from the nave,
that is, the main
body of the
church.
Taking Shape: This perspective lets one see the outline of the different sections of the church: the north transept on the left, the main body of the church in the center, and the narthex on the right.
It’s Beginning to Look a Bit
Like Christmas
. . . but not too
much! This
temporary
lighting in the
lower level allows
work to continue
downstairs even
during inclement
weather.
Gas Line
This is the gas
line coming from
the east. Natural
gas will be used
to heat the
church.
Some Assembly
Required . . . Still
This light pole
still needs to be
attached to its
base on the edge
of the upper
parking lot.
As Ye Sow, Ye Shall Reap! The exposed earth in the background is a “swale”, an excavated channel that will conduct water to the detention basin on the south end of the campus. To prevent erosion, rye is being
sown in the swale.
9 November 2012
Light Poles
The light poles
have now been
erected. They
provide
illumination to
the upper and
lower parking
lots.
Circuit Box
This circuit box
has been installed
in the lower level.
It contains the
circuit breakers
and power
switches which
regulate
electricity coming
into the building.
Glulams etc.: The glulams and other support elements have almost been completely installed now. The decking will begin to be installed next week. Some of the studs for the side walls in the upper level have also been put in.
Front Entrance: This updated photo of the front entrance shows the glulams and ridgebeam for the side entrance in profile. In subsequent construction, the north side of the structure will have a covered drive thru entrance for dropping off worshipers.
Safety Concerns
Although the
bright red fire
hydrants are hard
to miss, it can be
done! So this
long beam has
been attached to
one in a high
traffic area to
alert operators of
man-lifts,
forklifts, etc.