Top Banner
PROF. DR. MESCHKE Master’s Thesis A case study of ground freezing simulation for the Wehrhahn Line in Düsseldorf Supervisor: Dr.-Ing. Meng-Meng Zhou Background: When contructing the Wehrbahn Line in Düsseldorf at the in- tersecting Heinrich-Heine-Allee Metro Station, the undertunneling of the Gal- leria Kaufhof on the Königsallee becomes the most challenging phase of the whole project. Under such special ground conditions, artificial ground freezing (AGF) is often applied during tunnel construction for excavation support and groundwater control. Task: Within this master thesis the following tasks are to be completed: -- Study on the existing THM coupled freezing soil model -- Data exploition for the case study of undertunneling on the Königsallee -- Establishment of the numerical simulation model -- Comparsion of the simulation results with the in-site measured data Contact: Dr.-Ing. Meng-Meng Zhou Raum: IC 6 / 169 Lehrstuhl für Statik und Dynamik Ruhr-Universität Bochum Tel: 0234-32-29059 Email: [email protected] www.sd.rub.de 3. Juli 2014
1

A case study of ground freezing simulation for the Wehrhahn ...leria Kaufhof on the Königsallee becomes the most challenging phase of the whole project. Under such special ground

Aug 29, 2021

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: A case study of ground freezing simulation for the Wehrhahn ...leria Kaufhof on the Königsallee becomes the most challenging phase of the whole project. Under such special ground

PROF. DR. MESCHKE

Master’s Thesis

A case study of ground freezing simulation for the Wehrhahn Line in Düsseldorf

Supervisor: Dr.-Ing. Meng-Meng Zhou

Background: When contructing the Wehrbahn Line in Düsseldorf at the in-tersecting Heinrich-Heine-Allee Metro Station, the undertunneling of the Gal-leria Kaufhof on the Königsallee becomes the most challenging phase of the whole project. Under such special ground conditions, artificial ground freezing (AGF) is often applied during tunnel construction for excavation support and groundwater control.

Task: Within this master thesis the following tasks are to be completed: -- Study on the existing THM coupled freezing soil model -- Data exploition for the case study of undertunneling on the Königsallee -- Establishment of the numerical simulation model -- Comparsion of the simulation results with the in-site measured data

Contact: Dr.-Ing. Meng-Meng Zhou Raum: IC 6 / 169 Lehrstuhl für Statik und Dynamik Ruhr-Universität Bochum Tel: 0234-32-29059 Email: [email protected]