7/28/2019 9th Oil and Gas Conference Presentation
1/31
Contents
Some CDM points of departure Some brief examples of CDM projects
An example of using natural gas to replace
coal and electricity
What is the market for CERs?
What is required Designated NationalAuthority
7/28/2019 9th Oil and Gas Conference Presentation
2/31
CDM points
A CDM project activity is mostly a part of a largerproject
CDM is available for emissions mitigationprojects and certain sequestration projects
CDM is market based
CDM is project based
CDM outputs are Certified Emissions Reductions
(CER) = 1 tonne CO2equivalent CERs give annex 1 countries possibility to emit
one tonne of CO2 = globally neutral
7/28/2019 9th Oil and Gas Conference Presentation
3/31
Points of departurefor CDM
CDM is the first multi-lateral trade mechanisminsisting on Sustainable Development article12 of KP assist Parties not included in
Annex 1 in achieving SustainableDevelopment and contributing to the ultimateobjective of the Convention.
CDM assists Annex 1 countries in meeting
their emissions reduction targets in return forincome for credits derived from projects thatcontribute to sustainable development
7/28/2019 9th Oil and Gas Conference Presentation
4/31
Experience limited to thefront end of the cycle
7/28/2019 9th Oil and Gas Conference Presentation
5/31
First project participant
7/28/2019 9th Oil and Gas Conference Presentation
6/31
Bellville South Reducedlandfill gas to industryreplacing LSO/HFO
124000 CO2etonnes/year
7/28/2019 9th Oil and Gas Conference Presentation
7/31
Insulated ceilings, solarwater heaters and CFLsreduce electricity forservices
Kuyasa low costhousing upgrades
7/28/2019 9th Oil and Gas Conference Presentation
8/31
2.8 tonnesCO2/house/year
2.8 tonnes CO2e/house/year Total 6558 tonnes CO2e/year
7/28/2019 9th Oil and Gas Conference Presentation
9/31
7/28/2019 9th Oil and Gas Conference Presentation
10/31
Biomass replaces coal andmethane avoided
122000 tonnes CO2e /year
Mondi Richards Bay
biomass project
7/28/2019 9th Oil and Gas Conference Presentation
11/31
Example of fuel
switch to NG
Fuels Combusted CO2kgs/unit energy
(GJ)
Value ofemissions
reductions for
1 million GJ
Coal 90 US$ 386 000
Natural Gas 51 (57% of coal) -
SA Electricity 269 US$2.45m
Note: CH4 has 21 times the globalwarming potential of CO2
7/28/2019 9th Oil and Gas Conference Presentation
12/31
Case study
Mondi Business Paper (large paper mill inRichards Bay)
Natural Gas powered cogeneration
27.5MW (electricity) plus process heat Replacing coal for steam
Replacing grid electricity
7/28/2019 9th Oil and Gas Conference Presentation
13/31
Rationale for project
Require autonomous electricity supplybecause of production losses as a result ofdecreasing quality of supply and cost
escalations. Co-benefits of process heat.
7/28/2019 9th Oil and Gas Conference Presentation
14/31
Grid electricity
27 MW CCGT
Steam for plant process
heat Y GJ/year
GAS piped
Electricity to plant
X MWh/year
Plantconsuming heat
and power
Gas leaks
Existing Power
BoilersCoal
heat
Self generatedelectricity
Projectboundary
Gas
provide
Emissions of heat, CO2,
CH4 and N2O
Grid Electricity
Coal Ash
Emissions
from coal
transport
Emissions
from ash
transport
Emissions from the use of NG
in producing synthetic gas
NaturalGas
Emissions of Y GJ/year
heat, CO2, CH4 and N2O
7/28/2019 9th Oil and Gas Conference Presentation
15/31
Process of project
identification and design
Concept Project Identification Note (PIN) Pre-feasibility
Feasibility (technical, financial, legal etc.)
Project Design Document (PDD) isrequired to register a CDM project
www.cdmguide.com
http://www.cdmguide.com/http://www.cdmguide.com/7/28/2019 9th Oil and Gas Conference Presentation
16/31
Project design
document sections
A: Introduction
B: Baseline scenario and additionality test
C: Crediting period
D: Monitoring Plan E: Calculations
F: Environmental impacts
G: Stakeholder comments Annexes include contact details, baseline data,
public funding and methodologies
7/28/2019 9th Oil and Gas Conference Presentation
17/31
Methods employed in
design
Size (small-scale)
7/28/2019 9th Oil and Gas Conference Presentation
18/31
Small-scale
methodologies
Type II: Efficiency of demand and supply sideType III: Other
- Switching fossil fuels
- Emission reductions from low GreenhouseGas emitting vehicles
7/28/2019 9th Oil and Gas Conference Presentation
19/31
Regular size
Methodologies
AM0008: Industrial fuel switching from coaland petroleum to natural gas withoutextension of capacity and lifetime of
capacityAM0009: Recovery and utilisation of gas
from oil wells that would otherwise be
flaredAM0014: Natural Gas-based package co-
generation
I G T bi
7/28/2019 9th Oil and Gas Conference Presentation
20/31
In Gas Turbineproject
Regular size project None of the approved methods fit
Conclude to design new methodology
using 3 others, plus using acceptedadditionality tool
7/28/2019 9th Oil and Gas Conference Presentation
21/31
Additionality Theory
What would have happened in the absence of theproject activity?
Additionality test: Standard tool may be applied
Investment analysis (IRR/NPV/Payback of base-case i.e. without emissions reductions) is thisconservatively below the investment threshold?
Barrier tests (are there technical, normative,
investment, other barriers)
7/28/2019 9th Oil and Gas Conference Presentation
22/31
Additionality case study:
Investment analysis
Total capital costs: 15.2million Euros Operational costs: cost of gas, less cost of
coal and electricity
Full conservative discounted cash flowanalysis with and without CDM
IRR (including inflation after tax over 15years) = 22.3% (if company threshold of25% is required project would not havehappened without CDM
7/28/2019 9th Oil and Gas Conference Presentation
23/31
Technology barrier
test
7/28/2019 9th Oil and Gas Conference Presentation
24/31
Emissions
calculations
Baseline emissions: heat: 128 000 tonnes/year
electricity: 251 000 tonnes/year
Project activity emissions:
Cogeneration: 123 000 tonnes/year Less leakage: positive: physical leaking from
pipeline, negative ash removal from coal
Total less leakage: 256 000 tonnes/year worth +/-Euros 2.5million/year
Total project return on investment: 30.6% (at 10Euro per tonne up to 2012)
7/28/2019 9th Oil and Gas Conference Presentation
25/31
Project status
Project methodologies being reviewed (seewww.UNFCCC.int)
Project design validation against approvedmethodologies to follow
Project is to register as a unilateral project
Mass and energy balance with Sasol underwayfor 2.5 million GJ/year (Sasol total 450million
GJ/year plus) Gas price negotiations and contracting underway
P j t t t
http://www.unfccc.int/http://www.unfccc.int/7/28/2019 9th Oil and Gas Conference Presentation
26/31
Project status:
Transaction costs
Cost of validation: Euro 12 000 Cost of design: Euro 26 000 (estimate) plus
share of risks Cost of registration: Euro 15 000
Costs of adaptation levy: 2% of CERs Cost of govt. approval: varies (SA=0) Costs of monitoring, verification, issuance, tax: ? Income from CERs: Euro 2.5m/year (nominal)
total discounted to 2012: Euro 12.3m Plus operational savings (on electricity, coal and
downtime because of outages less cost of gas)
7/28/2019 9th Oil and Gas Conference Presentation
27/31
Markets for ERs
Markets: Compliance (CERs)
Verified (VERs)
Offset (VERs) Gold Standard (high quality CERs)
Incremental cost (GEF not market)
M h i f l /
7/28/2019 9th Oil and Gas Conference Presentation
28/31
Mechanisms for sale/
purchase of CERs
Multilateral funds (World Bank PCF, CDCF, etc.) Bilateral procurements through tenders: Austria,
Netherlands, Belgium, Finland, Japan etc.
Private purchases
Transfer within multinationals
Brokers
Project developer/wholesale purchases
Spot (still to come) Forward purchases, guarantees, rights of refusal,
options etc
7/28/2019 9th Oil and Gas Conference Presentation
29/31
Prices
Prices going up (early PCF price$3.5/CER)
Bilateral procurements Euro 8/CER
Current price range reported 8 to Euros10/CER
EU Emissions Trading Scheme (EUETS)
Euro 18 to 20/tonne CO2 for allowances VERs Euro 2 to 10/tonne CO2
D i t d N ti l
7/28/2019 9th Oil and Gas Conference Presentation
30/31
Designated National
Authority
To be able to participate in CDM country must bea party to Kyoto Protocol and establish a DNA Required to cede emissions reductions to project
participant
Required to approve the projects againstsustainable development requirements Required to be established in law in host country Approval is part of validation of project activities
DNA must put project out for public comment DNA can be a promoter of projects DNA should be fast and transparent
D i CDM i th
7/28/2019 9th Oil and Gas Conference Presentation
31/31
Doing CDM in the
South
CDM is not easyit requires specialists It results in no net emissions reductions
CDM has very little to do with Sustainable
Developmentsadly Attracting FDI appears to be higher priority that SD.
CDM can leverage technology leapfrogging
There are few points of leverage for the South:choosing projects, choosing partners, timingtransactions.