Top Banner

of 28

9A0F5d01

Aug 08, 2018

Download

Documents

Nayan Manna
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • 8/22/2019 9A0F5d01

    1/28

    TOPICAL REPORT NUMBER 25 SEPTEMBER 20

    Power Plant Optimization

    Demonstration Projects

  • 8/22/2019 9A0F5d01

    2/28

    Cover Photos:

    Top let: Coal Creek Station

    Top right: Big Bend Power Station

    Bottom let: Baldwin Energy Complex

    Bottom right: Limestone Power Plant

    A report on our projects conducted under separate cooperative

    agreements between the U.S. Department o Energy and:

    Great River Energy

    Tampa Electric Company

    Pegasus Technologies

    NeuCo. , Inc.

  • 8/22/2019 9A0F5d01

    3/28

    Power Plant Optimization

    Demonstration Projects

    Executive Summary .......................................................................................4

    Background: Power Plant Optimization ......................................................5

    Lignite Fuel Enhancement Project ...............................................................8

    Introduction ......................................................................................................... 8

    Project Objectives ................................................................................................. 9

    Project Description ............................................................................................. 10

    Benefts ............................................................................................................... 11

    Neural Network-Intelligent Sootblower Optimization Project ..................11

    Introduction ........................................................................................................ 11Project Objectives ............................................................................................... 12

    Project Description ............................................................................................. 12

    Results................................................................................................................. 14

    Conclusions ........................................................................................................ 14

    Mercury Specie and Multi-Pollutant Control Project ...............................15

    Introduction ........................................................................................................ 15

    Project Objectives ............................................................................................... 16

    Project Description ............................................................................................. 16

    Anticipated Benefts ........................................................................................... 19

    Demonstration o Integrated Optimization Sotware at the Baldwin

    Energy Complex Project ..............................................................................19

    Introduction ........................................................................................................ 19Project Objectives ............................................................................................... 20

    Project Description ............................................................................................. 21

    Anticipated Benefts ........................................................................................... 22

    Conclusions ................................................................................................. 23

    Bibliography .................................................................................................24

    Acronyms and Abbreviations .......................................................................26

  • 8/22/2019 9A0F5d01

    4/28

    Executive Summary

    The Clean Coal Technology Demon-

    stration Program (CCTDP) and the two

    ollowing programsthe Power Plant

    Improvement Initiative (PPII) and the

    Clean Coal Power Initiative (CCPI)

    are government and industry co-unded

    programs. The goal o these programs is to

    demonstrate a new generation o innovative

    coal-utilization technologies in a series

    o projects carried out across the country.

    These demonstrations are conducted ona commercial scale to prove the technical

    easibility o the technologies and to

    provide technical and nancial inormation

    or uture applications.

    A urther goal o these programs is to

    urnish the marketplace with a number

    o advanced, more eicient coal-based

    technologies that meet increasingly strict

    environmental standards. These technologies

    will help mitigate the economic and

    environmental barriers that limit the ull

    utilization o coal.

    To achieve these goals, beginning in 1985

    a multi-phased eort has been administered

    by the U.S. Department o Energy (DOE)

    National Energy Technology Laboratory

    (NETL). The CCTDP, the earliest program,

    initiated ve separate solicitations. The next

    program, the PPII, sent out one solicitation,

    and the CCPI has had two solicitations to

    date. The projects selected through these

    solicitations have demonstrated technology

    options with the potential to meet the needs

    o the energy markets while satisying

    relevant environmental requirements.

    This report describes our projects

    aimed at improving or optimizing the

    perormance o coal-red power plants. All

    our projects are being conducted under the

    CCPI and PPII programs. The rst project

    deals with upgrading high moisture lignite

    by partial drying to enhance its quality

    and improve overall plant perormance.

    The remaining three projects involve the

    development o sotware that optimizes

    overall power plant perormance or some

    aspect o perormance by incorporating

    eatures o articial intelligence (AI), a

    decision-making capability that simulates

    the human brain.

    The Lignite Fuel Enhancement proj

    is demonstrating improved plant per

    mance by using waste heat to partia

    dry lignite, which is normally high

    moisture.

    The Neural Network-Intelligent So

    blowing (NN-ISB) project with t

    Tampa Electric Company (TECO) B

    Bend Power Station was intended

    demonstrate improved eciency a

    lower emissions o nitrogen oxid

    (NOX) by using a computer-based neu

    network to determine when sootblowi

    is needed.

    The Mercury Specie and Multi-Pollut

    Control project with Pegasus Techno

    gies is demonstrating the capability

    optimize mercury speciation and cont

    o emissions rom an existing power pl

    using state-o-the art sensors and neu

    network-based optimization sotware

    NRG Texass Limestone Station.

    The Demonstration o Integrated Optim

    zation Sotware project at Dynegy Midw

    Generations Baldwin Energy Compl

    where NeuCo, Inc., is demonstrating t

    integration o ve separate optimizati

    computer programs to optimize over

    power plant operation.

    Great River Energys Coal Creek Station

  • 8/22/2019 9A0F5d01

    5/28

    Background: Power

    Plant Optimization

    Overall optimization o a coal-red

    power plant is a highly complex process.

    One must rst decide what constitutes

    optimal perormance. Obvious answers

    include maximum thermal eciency,

    lowest possible emissions, lowest possible

    cost, readily marketable by-products, and

    maximum system availability or power

    generation. In reality, these goalsand

    othersare interrelated. In some cases,however, these optimization goals are at

    odds with each other. For example, high

    excess air will result in better carbon

    burnout and less carbon monoxide but will

    also result in higher emissions o nitrogen

    oxides (NOX). These interactions must

    be kept in mind and addressed with any

    optimization program.

    There are a number o relatively xed

    items that aect overall plant operation.

    These include boiler design, cooling water

    conditions, burner type, design steam

    conditions, and environmental control

    systems that capture and remove particulate

    matter, sulur dioxide (SO2), NOX, and

    mercury. Coal quality is also a major

    actor that aects plant perormance. High

    moisture and/or ash content decreases

    eciency and increases wear and power

    requirements on the pulverizers. High

    sulur content results in more reagent

    consumption and increased by-product

    generation.

    The benets o optimizing the overall

    process o generating power rom coal are

    signicant. Eciency is increased, total

    maintenance costs are reduced, emissions

    are decreased, and reliability is improved.

    While the greatest benet can be achieved by

    optimizing the overall operation, important

    benets can also be achieved by optimizing

    one or more o the actors that contribute to

    the overall eciency o the plant.

    Many optimizations can yield substantial

    positive results. For instance, use o lignite

    and sub-bituminous coals, which are high

    in moisture, lowers the boiler eciency,

    increases the load on the pulverizers, and

    increases fue gas volume. Drying the coal

    beore it is ed to the preparation system is

    generally not practical due to the energy

    required. Switching to a higher quality

    coal, even i available, is oten not practical

    either due to cost or to the act that a boiler

    designed or a specic coal may not unction

    as well with other coals. I such a switch

    is made, the unit may need to be de-rated.So, i drying the coal can be economically

    integrated into the overall power plant

    process, potential benets are substantial.

    There are several obvious systems that

    can be optimized independently and result

    in better perormance. Some involve simply

    upgrading a specic piece o equipment.

    Power Plant OptimizationDemonstration ProjectsTopical Report Number 25

  • 8/22/2019 9A0F5d01

    6/28

    For example, a reurbished steam turbine

    will improve heat rate and result in less uel

    consumption per megawatt (MW). The

    cost o electricity is then reduced, as are the

    emission rates o some pollutants.

    In some cases, optimizing one aspect o

    boiler operation can have several benets.

    For example, during boiler operation, ash

    slowly builds up on boiler tubes. This causes

    reduced heat transer to the boiler eed water

    and steam which results in lower eciency

    and higher NOX emissions. The buildup is

    removed by blowing it o the tubes with

    high-pressure steam. But when sootblowing

    occurs, the electrostatic precipitator (ESP),

    or baghouse, is temporarily overwhelmed

    by the high particulate load at the inlet.

    Sootblowing is traditionally done on a

    set schedule rather than as needed. Thisresults in some boiler sections accumulating

    excessive ash on the tubes while others,

    having little ash buildup, are serviced when

    it is not required. Optimized sootblowing

    can solve these problems by using sensors

    and articial intelligence (AI) sotware

    to determine when a particular section o

    the boiler needs to have the ash removed

    rom the tubes, thus minimizing steam

    consumption (and improving heat rate),

    reducing the requency o a high particulate

    load in the fue gas, and reducing NOX

    ormation.

    As one would expect, optimizing the

    operation o multiple components normally

    gives better results than optimizing one

    aspect o the operation. Maximizing the

    overall perormance o multiple pieces

    o equipment does not normally have an

    adverse eect on the other power plant

    components. However, when using AI/

    neural network systems to optimize multiple

    aspects o power plant operation, care must

    be taken to consider the possible negative

    impact on other parameters. This can bestbe accomplished by designing the sotware

    packages to communicate with each other

    through a management sotware package.

    This document describes our opti-

    mization projects within the PPII and

    CCPI programs. The ollowing are brie

    descriptions o the our projects:

    In the Lignite Fuel Enhanceme

    project, Great River Energy has installed

    ull-scale prototype dryer module to supp

    one-sixth o the coal required or a 546 M

    unit. Results to date have shown improv

    perormance in overall operation o t

    unit. In the next phase o this project, GrRiver Energy will design, construct, a

    perorm ull-scale, long-term operation

    testing on a complete set o dryer modu

    to supply all the coal needed or the

    operation o this unit.

    The Neural Network-Intellige

    Sootblower (NN-ISB) project with

    Tampa Electric Company (TECO) Big Be

    Power Station is complete. This proj

    showed that the concept o using a neu

    network system to optimize the sootblow

    process is sound but that additiondevelopment and better equipment

    needed. Mechanical problems with sens

    and water cannons were encountered a

    overall results were aected by these issu

    However, some benet was obtained w

    respect to stack opacity and nitrogenoxid

    reduction.

    In the Mercury Specie and Mul

    Pollutant Control project, Pegas

    Technologies will utilize state-o-th

    art sensors and neural-network-bas

    optimization and control technologies maximize the proportion o mercury spec

    that are easy to remove rom the boi

    fue. This project will demonstrate h

    integrating sensors, controls, and advanc

    analysis techniques into multiple ac

    o plant operation can lead to improv

    economics and environmental complianc

    With the Demonstration of Integrat

    Optimization Software project

    Dynegy Midwest Generations Baldw

    Energy Complex, NeuCo, Inc.,

    integrating and optimizing their sotwaSCR-Opt, CombustionOpt, SootOpt

    PerormanceOpt, and MaintenanceOpt

    ProcessLink is the integration sotw

    that coordinates these programs to achie

    overall plant goals. The project is ongoi

    as o this time and results to date appe

    promising.

  • 8/22/2019 9A0F5d01

    7/28

    Artifcial Intelligence

    Articial intelligence (AI) is commonly dened as the science and engineering o makingintelligent machines, especially intelligent computer programs. Relative to applications with coal-red power plants, AI consists o aspects or considerations that deal with the ollowing:

    Neural networks, which mimic the capacity o the human brain to handle complex nonlinearrelationships and learn new relationships in the plant environment

    Advanced algorithms or expert systems that ollow a set o pre-established rules written in

    codes or computer language

    Fuzzy logic, which involves evaluation o process variables in accordance with approximate

    relationships that have been determined to be suciently accurate to meet the needs o plantcontrol systems

    Neural networks (NNs) are a class o algorithms that simulate the operation o biologicalneurons. The NN learns the relationships between operating conditions, emissions, andperormance parameters by processing the test data. In the training process, the NN developsa complex nonlinear unction that maps the system inputs to the corresponding outputs. Thisunction is passed on to a mathematical minimization algorithm that nds optimum operating

    conditions.

    NNs are composed o a large number o highly interconnected processing elements that workin parallel to solve a specic problem. These networks, with their extensive ability to derivemeaning rom complicated or imprecise data, can be used to extract patterns and detect trendsthat are too complex to be detected by either humans or other computer techniques. NNsare trainable systems that can learn to solve complex problems and generalize the acquiredknowledge to solve unoreseen problems. A trained NN can be thought o as an expert in thecategory o inormation it has been given to analyze. NNs are considered by some to be bestsuited as advisors, i.e., advanced systems that make recommendations based on various types odata input. These recommendations, which will change as power plant operations change, suggestways in which plant equipment or technologies can be optimized.

    Advanced algorithms, on the other hand, are programmed to incorporate establishedrelationships between input and output inormation based on detailed knowledge o a specic

    process. They are used by computers to process complex inormation or data using a step-by-step,problem-solving procedure. In particular, genetic algorithms provide a search technique to nd trueor approximate solutions to optimization problems. These algorithms must be rigorously denedor any computational process since an established procedure is required or solving a problem ina nite number o steps. Algorithms must tell the computer what specic steps to perorm andin what specic order so that a specied task can be accomplished. Advanced algorithms are nowpart o the sophisticated computational techniques being successully applied to power plants toincrease plant eciency and reduce unwanted emissions.

    Fuzzy logic (FL), the least specic type o AI sotware, is equipped with a set o approximate rulesused whenever close enough is good enough. Fuzzy logic is a problem-solving control-systemmethodology that has been used successully with large, networked, multi-channel computers orworkstation-based data-acquisition and control systems. FL can be implemented via hardware,sotware, or a combination o both. Elevators and camera auto-ocusing systems are primaryexamples o uzzy logic systems. Fuzzy logic stops an elevator at a foor when it is within a certainrange, not at a specic point.

    FL has proven to be an excellent choice or many control system applications since it mimicshuman control logic. By using an imprecise but very descriptive language, FL deals with input datamuch like a human operator. FL is very robust and provides a simple way to arrive at a deniteconclusion based upon vague, ambiguous, imprecise, or missing input inormation. However, whilethe FL approach to solving control problems mimics human decision-making, FL is much aster. TheFL model is empirically based, relying on operator experience rather than technical understandingo the system.

  • 8/22/2019 9A0F5d01

    8/28

    Lignite Fuel

    Enhancement Project

    Introduction

    The use o low-rank coals (lignite and

    subbituminous) has seen a signiicant

    increase in recent years. Because o the

    low sulur content o such coals, many units

    have adopted uel switching to meet sulur

    emissions specications, and other units

    have been built specically to burn low-

    rank coals. However, a major disadvantage

    o low-rank coals is their high moistu

    content, typically 25 to 40 percent. Wh

    such coal is burned, considerable ener

    is required to vaporize the moisture

    contains, thus raising the heat rate o

    power plant and lowering its eciency.

    Fuel moisture has many eects on u

    operation, perormance, and emissions.

    uel moisture decreases, the uels heati

    value increases so that less coal needs to

    red to produce the same electric pow

    thus reducing the burden on the co

    handling system. Drier coal is easier

    convey as well, which reduces maintenan

    costs and increases availability o the co

    to the handling system. When the crush

    coal is gravity-ed into bunkers, the dr

    coal fows more readily than the wet co

    causing ewer eed hopper bridging aplugging problems. Drier coal is easier

    pulverize as well so that less mill power

    needed to achieve the same coal nene

    Finally, with less moisture in the uel mo

    complete drying o coal can be achiev

    in the mill, which results in an increas

    mill exit temperature, better conveying

    coal in the coal pipes, and ewer coal pi

    plugging problems.

    The mixture o pulverized coal a

    air rom the pulverizers is combusted

    the burners. With drier coal, the fatemperature is higher since there is le

    moisture to evaporate. At the same tim

    heat transer processes in the urnace

    modied. The higher fame temperatu

    results in a larger radiation heat fux to t

    urnace walls. Also, drier coal results

    less moisture in the fue gas, which chang

    the radiation properties o the fame. T

    change in the fame emissivity also ae

    the radiation fux to the wall. With a high

    fame temperature, the temperature o c

    ash particles is correspondingly high

    which could increase urnace ouling aslagging, reducing heat transer and resulti

    in a higher fue gas temperature at the urna

    exit. However, the reduction in coal fow r

    as uel moisture is reduced also reduces t

    amount o ash entering the boiler, which lea

    to less solid-particle erosion in the boiler a

    decreased boiler maintenance cost.

    The Clean Coal Technology Program

    The DOE commitment to clean coal technology development hasprogressed through three phases. The rst phase was the Clean CoalTechnology Demonstration Program (CCTDP) , a model o government andindustry cooperation that advanced the DOE mission to oster a secure andreliable energy system. With projects completed, the CCTDP has yieldedtechnologies that provide a oundation or meeting uture energy demandsthat utilize the vast U.S. reserves o coal in an environmentally sound manner.Begun in 195, the CCTDP represents a total investment value o over$.25 billion. The DOE share o the total cost is about $1.0 billion, orapproximately 0 percent. The project industrial participants (non-DOE)

    have provided the remainder, nearly $2 billion.

    Two programs have ollowed that have built on the successes o theCCTDP. The rst is the Power Plant Improvement Initiative (PPII), a cost-shared program patterned ater the CCTDP and directed toward improvedreliability and environmental perormance o the nations coal-burning powerplants. Authorized by the U.S. Congress in 2001, the PPII involves veprojects that ocus on technologies enabling coal-red power plants to meetincreasingly stringent environmental regulations at the lowest possible cost.Four projects have been completed and one is still active. The total value othese projects is $71.5 million, with DOE contributing $1.5 million or .percent.

    The second program is the Clean Coal Power Initiative (CCPI), alsopatterned ater the CCTDP. Authorized in 2002, the CCPI is a 10-year

    program having a goal o accelerating commercial deployment o advancedtechnologies to ensure that the nation has clean, reliable, and aordableelectricity. Total Federal unding will be up to $2 billion, with a matchingcost share by industrial participants o at least 50 percent. To date, twosolicitations have been completed and nine projects have been awarded orare in negotiation. These projects have a total value o approximately $2.billion. The DOE share is $5 million or 19.9 percent .

  • 8/22/2019 9A0F5d01

    9/28

    The fue-gas fow rate rom a urnace

    ring dry coal is lower than one ring wet

    uel, and the specic heat o the fue gas

    is lower due to its lower moisture content.

    A lower fue gas fow rate also results in

    a lower rate o convective heat transer.

    Thereore, despite an increase in initial fuegas temperature with drier uel, less heat

    will be transerred to the water or steam in

    the boiler convective pass.

    Drier coal is expected to lower the

    temperature o lue gas leaving the

    economizer and air preheater (APH).

    APH perormance will also be aected by

    changes in the ratio o air and fue gas fows

    through the APH and changes in specic

    heat. Improved overall process eciency

    will result rom drier coal as the auxiliary

    power decreases due to decrease in orceddrat, induced drat, and primary air an

    power as well as decrease in mill power.

    Previously, a number o proposals have

    been advanced to dry low-rank coals prior

    to combustion, but none o these eorts

    has resulted in a successul commercial

    operation. The two major problems with

    drying schemes beore this have been the

    cost o the energy required and the act that

    low-rank coals become pyrophoric when

    dried beyond a certain point. The Great

    River Energy Lignite Fuel EnhancementProject overcomes these problems by using

    waste heat to dry the coal and removing only

    about 25 percent o the moisture, enough to

    appreciably improve plant perormance but

    not enough to cause handling problems.

    Project Objectives

    The objective o this project is to

    demonstrate an economic process o

    moisture reduction o lignite, thereby

    increasing its value as a uel in powerplants. The project is being conducted

    at the Great River Energys Coal Creek

    Station in Underwood, North Dakota. The

    demonstration activities ocus on using low

    grade condenser waste heat and fue gas

    in the plant to lower the moisture content

    o the coal by about 10 percentage points

    Aerial view o Great River Energys Coal Creek Station lignite power plant

    (e.g., reduce the lignite moisture rom 40

    to 30 percent). A phased implementation

    is planned: In the rst phase, a ull-scale

    prototype dryer module was designed or

    operation o one o the pulverizers on one

    o the two 546 MW units at the Coal Creek

    Station.

    The objectives o prototype testing were

    to gain operating experience, conrm pilot

    results, and determine the eect o air fow

    rate, bed coils, bed depth, and coal eed

    rate on dryer operation in order to optimize

    perormance. The lessons learned rom the

    prototype were incorporated into the design

    o the dryers being installed in the second

    phase. A total o our dryers will be built

    or Unit 2. Although operating with wet

    lignite requires seven pulverizers, six will

    provide all the dried lignite required by theboiler.

    Following successul demonstration

    in the rst phase, Great River Energy is

    designing and constructing a ull-scale,

    long-term operational test on a complete

    set o dryer modules needed or ull power

  • 8/22/2019 9A0F5d01

    10/28

    10

    operation o one 546 MW unit (our

    dryers). The coal will be dried to a number

    o dierent moisture levels. The eect

    o coal drying on plant perormance will

    be measured with respect to increase in

    plant eciency and availability, reduction

    in emissions, and improvements in plant

    economics. The dryer design and operating

    conditions will be determined or optimal

    plant perormance.

    Project Description

    In response to the rst round o the Clean

    Coal Power Initiative, Great River Energy

    (GRE) submitted a proposal or a ull-scale

    test o a lignite-drying technology that

    they had been developing since the 1990s.

    The previous work included bench-scale

    research and development, eld trials, andpreliminary drying studies. These studies

    convinced GRE o the technical easibility

    and economic benets o lignite drying and

    prompted the submittal o their proposal.

    The Department o Energy evaluated and

    selected their proposal, and a cooperative

    agreement was awarded on July 9, 2004.

    The project team or the Lignite Fu

    Enhancement Project consists o GR

    participant and site provider; the Elect

    Power Research Institute, collaborat

    Lehigh University, collaborator; B

    Engineering, lignite handling; and Falk

    Mining and Couteau Properties, lignsupplier. The project is sited at GREs C

    Creek Station in Underwood, North Dako

    Coal Creek Station is a mine-mouth pla

    burning approximately seven million to

    o lignite per year and consisting o t

    546 MW, tangentially red Combusti

    Engineering boilers. Steam is produc

    at 2,400 psig and 1,000 oF with a 1,000

    reheat temperature. The Coal Creek stati

    has eight pulverizers per unit (seven acti

    and one spare). The station has two sin

    reheat General Electric G-2 turbines.

    The gure at let provides a simpli

    fow diagram o the lignite drying proce

    Warm cooling water rom the turbi

    exhaust condenser goes to an air hea

    where ambient air is heated beore being se

    to the fuidized bed-coal dryer. The cooli

    water leaving the air heater is returned

    the cooling tower. A separate water strea

    is passed through coils in the fuidiz

    bed-coal dryer (a two-stage dryer is us

    to enhance heat transer). The purpose

    these coils is to provide additional heat

    the fuidized bed to reduce the amount air required. The dried coal leaving t

    fuidized bed is sent to a pulverizer a

    then to the boiler. Air leaving the fuidiz

    bed is ltered beore being vented to t

    atmosphere.

    The technical aspects o the proj

    are being implemented in two phas

    The rst phase involved the constructi

    and operation o a prototype dryer, a u

    sized dryer with a maximum capacity

    112.5 tons/hour (225,000 lb/hour). It w

    designed to reduce the moisture conte

    o lignite rom 38 percent to 29.5 perce

    and improve the higher heating value ro

    6,200 Btu/lb to 7,045 Btu/lb. The prototy

    unit was ully automated and integrat

    into the plant control system. The rst c

    was introduced into the prototype dryer

    January 30, 2006, and perormance testi

    was carried out in March and April 2006

    Schematic o Lignite Coal Drying Using Waste Heat From Condenser Water and Flue Gas

  • 8/22/2019 9A0F5d01

    11/28

    Benefts

    Firing drier coal results in improved

    boiler eiciency and unit heat rate,

    primarily due to lower stack loss and lower

    auxiliary power (lower an, pulverizer,

    cooling tower, and coal handling power).This perormance improvement will allow

    greater electrical output with existing

    equipment. Perormance o back-end

    environmental control systems (scrubbers

    and electrostatic precipitators) will also

    improve with drier coal due to the lower

    fue gas fow rate and longer residence time.

    The reduction in required coal-fow rate and

    modied temperature prole will directly

    translate into lower emissions o NOX,

    carbon dioxide (CO2), SO2, and particulates.

    For units equipped with wet scrubbers,

    mercury emissions resulting rom ringdrier coal would also be reduced. This is

    due to reduced APH gas outlet temperature,

    which avors the ormation o mercuric

    oxide and mercuric chloride at the expense

    o elemental mercury. These oxidized

    orms o mercury are water-soluble and can

    thereore be removed in a scrubber.

    During testing o the prototype coal

    dryer in 2006, at a eed rate o 75 tons/

    hour (14 percent o total uel rate to the 546

    MW unit), there were no major operating

    problems. The moisture o the total coalwas reduced by only about 1.1 percentage

    points. Yet there were signicant benets

    in the prototype dryer operation or the

    546 MW unit.

    Perormance measures showed that

    the lignite fow rate was reduced by 2

    percent, pulverizer power was reduced by

    3.3 percent, boiler eciency improved

    0.5 percent (absolute), net unit heat rate

    improved 0.5 percent, NOX emissions

    decreased 7.5 percent, and SO2 emissions

    decreased 1.9 percent. These results indicatethat there will be signicant improvements

    in operations once the project is ully

    implemented.

    The potential market or GREs coal-

    drying technology is quite sizeable.

    There are 29 units with a total capacity

    o 15.3 gigawatts (GW) that are burning

    lignite directly, and another 250 units

    with a total capacity o over 100 GW

    burning Powder River Basin coal. I all

    these units were to adopt coal drying,

    the economic and environmental benets

    would be quite large.

    Neural Network

    Intelligent-Sootblower

    Optimization Project

    Introduction

    A neural-network-driven computer

    system oers the potential to optimize

    sootblowing in coal plant boilers, reduce

    NOX emissions, improve heat rate and unit

    eciency, and reduce particulate matter

    emissions. Installed at the Tampa Electric

    Company (TECO) Big Bend Power Station

    in Hillsborough County, Florida, the

    Pegasus Technologies neural network-

    intelligent sootblowing (NN-ISB) system

    was designed to be used in conjunction

    with advanced instrumentation and water

    cannons to prevent soot rom building up ina boiler. O the our coal-red units at the

    power station, Unit No. 2 was selected or

    installation o the NN-ISB control system.

    Fired with bituminous coal, this wet bottom

    pressurized Riley Stoker single-drum

    radiant boiler has a total o 48 coal nozzles

    on a single elevation, 24 on each side, ring

    toward the center line o the urnace. The

    nal project cost or the NN-ISB control

    system (equipment/instrumentation, sotware,

    testing, and reporting included) was $3.4

    million, including a 27 percent Department

    o Energy (DOE) cost share. Sotware costso a ew hundred thousand dollars were a

    small part o the total cost. Project testing

    o the NN-ISB was completed in December

    2004, and the nal report on the system was

    issued in September 2005.

    Tampa Electric Big Bend Power Station

  • 8/22/2019 9A0F5d01

    12/28

    12

    Project Objectives

    The project objective at the Big Bend

    plant was to develop a neural-network-

    driven system that could initiate, control,

    and optimize sootblowing in response to

    real-time events or conditions within the

    coal-plant boiler rather than relying on

    general rule-based protocols. The project

    demonstrated and assessed a range o

    technical and economic issues associated

    with the sensing, management, display,

    and human interace o sootblowing goals

    as they relate to emissions and eciency

    o a coal-red utility boiler. Specically,

    this optimization process targeted reducing

    baseline NOX emissions by up to 30 percent,increasing unit eciency by 2 percent, and

    reducing particulate matter (stack opacity)

    by 5 percent.

    Project Description

    This neural network project was

    implemented under the Power PlantImprovement Initiative (PPII), a DOE

    program designed to demonstrate plant

    improvement technologies and processes

    in commercial settings. At the time o the

    award, this installation was the rst domestic

    project to use neural network technology to

    optimize the sootblowing process within

    a boiler. Started in 2001 ater a series

    o brownouts and blackouts had plagued

    major regions o the country, the initiative

    targeted new technologies that could help

    coal plants boost their output and improve

    their environmental perormance. The BigBend project was designed to be a ull-

    scale demonstration o the neural-network-

    driven technology on a large commercial

    boiler, using state-o-the-art controls and

    instruments to optimize boiler operation

    and systematically control boiler slagging

    and ouling.

    Communications Architecture at Big Bend Power Station

    In a coal-red boiler, the continui

    buildup o ash and soot on the boiler tub

    leads to reduced boiler eciency. I perio

    ash and soot removal (sootblowing) is nperormed, this leads in turn to higher f

    gas temperatures and ultimately to high

    NOX ormation and reduced ecien

    Thereore, cleaning the heat-absorbi

    suraces is one o the most importa

    boiler auxiliary operations. Typical

    sootblowing uses mechanical devices

    online cleaning o reside boiler ash and s

    deposits on a periodic basis. Sootblow

    clean by directing steam or water throu

    nozzles against the accumulated soot a

    ash on the heat-transer suraces in ord

    to remove the deposits and maintain hetranser eciency. Basically, sootblow

    consist o our components: a tube or lan

    that is inserted into the boiler and carries t

    cleaning medium, nozzles in the tip o t

    lance to accelerate and direct the cleani

    medium, a mechanical system to insert

    rotate the lance, and a control system.

  • 8/22/2019 9A0F5d01

    13/28

    Because it either uses steam that would

    otherwise be used to generate electric

    power or it requires energy or pumps or

    compressors, sootblowing has a direct

    impact on plant eciency. Thus, optimizing

    sootblower operation is important in

    maximizing unit eiciency. Typically,sootblowers operate on a specied timed

    cycle or, alternatively, operation is initiated

    by an operator who believes sootblowing

    is needed. The purpose o an intelligent

    sootblowing system is to decide when to

    sootblow based on inormation rom boiler

    instruments. The overall objective is to

    sootblow when, and only when, necessary.

    The Pegasus Technologies NN-ISB

    control system uses a neural network to

    model the characteristics o the boiler.

    Designed to recognize patterns in inputdata, this network must be trained using

    historical data beore it can associate a

    particular pattern with a corresponding

    plant state. Once this training has been

    completed, the system can respond rapidly

    to new inputs. An advantage o a neural

    network is that i any inputs are aulty

    the prediction capability degrades only

    gradually compared to most other modeling

    techniques.

    The project installed at Big Bend Unit

    No. 2 includes 16 heat fux sensors, 8 slagsensors, a heat transer advisor, acoustic

    pyrometers, a sootblower control system,

    an online perormance monitor (OPM),

    and an advanced calibration monitor

    (ACM). For the communications layout,

    the combustion optimizing system and

    intelligent sootblowing (ISB) sotware

    were loaded into one computer. For this

    application, the models were partitioned

    so they could unction separately or work

    interactively. This approach was important

    since it permits upgrades to existing power

    plants as well as applications to new boilers.Although the demonstration was carried

    out on the hardware and sotware systems

    developed or this project, the equipment

    (including the distributed control system)

    could be obtained rom any manuacturer.

    Ater verication that the core elements

    o the NN-ISB system were satisactorily

    installed and operational, detailed model

    tuning was completed. During this task,the unit was operated under a variety

    o conditions, including some non-ideal

    variations. This helped to dene acceptable

    operating limits and constraints used by the

    neural network while optimizing the system.

    During system optimization, appropriate

    adjustments were made to allow the system

    to learn and to make recommendations

    on Unit 2 operation, including both manual

    or advisory (open-loop) and automatic

    (closed-loop) operation. The advisory mode

    provided recommendations to the operatorsand engineers, who used those results to

    urther tune the system. This activity

    also proved very valuable in assessing and

    recording the perormance and status o the

    new sensors and systems.

    Pegasus Technologies NN- ISB Control System

  • 8/22/2019 9A0F5d01

    14/28

    1

    NRG Texass Limestone Power Plant in Jewett, Texas

    Results

    The automated closed-loop activation

    o the sootblowers during this projectconrmed that neural-network, adaptive

    sootblowing can benet eciency. There

    was a clear improvement at low loads, with

    the benet decreasing as the load increased.

    During closed-loop operation o the NN-

    ISB, Pegasus reported that eciency gains

    were in the range o 0.1 to 0.4 percentage

    points compared to baseline. Results with

    open-loop operation were slightly lower.

    With more operating experience, gains at

    the high end o the load range should be

    achievable.

    NN-ISB closed-loop (automatic)

    operation was shown to be better than

    open-loop (non-neural network baseline)

    operation. Other Pegasus results indicated

    an improvement o 1.0 to 1.5 percent in

    opacity or closed-loop compared to open-

    loop operation during certain tests.

    While it is reasonable to expect th

    optimizing sootblowing would be benec

    or NOX reduction (due to an improv

    temperature prole in the urnace),

    Big Bend project was unable to clea

    demonstrate this. Supporting equipm

    and material issues (e.g., unavailabilo the water cannons during the N

    ISB tests, underperormance o much

    the instrumentation) greatly limited

    optimization sotware rom perorming

    expected.

    Prior to this project, sensors and contr

    related to sootblowing were usually trea

    as isolated systems. In contrast, the Big Be

    NN-ISB system had the ability to understan

    evaluate, and optimize the process as an ent

    system with multiple, real-time objectiv

    Integration o the sensors went well acommunication was established to the neu

    network system with all sensors and eleme

    o the project. The project demonstrated t

    such systems can be linked together desp

    the use o proprietary networks. Further

    conrmed that the sensors can provide d

    that can be correlated to achieve a set

    objectives. Generally, the NN-ISB syst

    appears to have merit and can improve boi

    perormance.

    Conclusions

    The major conclusion rom th

    project is that the Pegasus Technolog

    NN-ISB control system is a sound id

    with signicant potential. The Big Be

    project successully demonstrated a neu

    network, closed-loop operation on a u

    scale boiler without causing unit ups

    or violating any constraintsand it a

    achieved operator acceptance. The NN-I

    appears to provide generating compan

    with an integrated solution that will ass

    in optimal economic and environmenreal-time, online operation o a unit.

    The NN-ISB is modular in design a

    can be readily applied to a variety o pow

    generating units. The solution architectu

    and inrastructure are designed to all

    ull or staged deployment, depending

  • 8/22/2019 9A0F5d01

    15/28

    the needs o the generating company. The

    technology applied throughout allows unit

    fexibility (i.e., existing systems can be

    integrated within the overall solution) and

    is extendible (new modules/new equipment

    can be readily modeled and incorporated).

    In general, the project provided a testing

    ground or several innovative measurement

    devices and eedback on their operation

    that may also lead to improved instruments.

    Since some equipment and instrumentation

    (e.g., water cannons, heat fux sensors,

    slag sensors, and acoustic pyrometers) did

    not ully operate as expected during this

    testing, an additional project with improved

    equipment and instrumentation may be

    needed in order to ully quantiy all the

    benets. Other project goals were also

    achieved:

    Promoted the use o coal by making

    coal more uel-ecient automatically,

    reducing all pollutants on a per megawatt-

    hour basis. In addition, reducing NOXemissions should lower the resistance to

    coal use or electrical generation.

    Enabled rapid deployment into the

    market. All coal-ired boilers employ

    sootblowers which, in turn, require

    control systems. Since current systems

    cannot achieve the desired results

    in sootblowing operations, a neural

    network control system appears to oer

    signicant advantages. Further, no new

    hardware needs to be developed since the

    hardware is o the shel and readily

    available.

    Expanded U.S. revenues through world-

    wide market acceptance. The same rapid

    deployment capability and acceptance by

    domestic plants should apply to oshore

    coal-ired boilers. Since the United

    States is presently the world leader in

    AI (o which the neural network system

    is a subset) there should be minimal

    competition rom oshore suppliers.

    In summary, the project provided

    valuable inormation on neural networks

    and the positive results should encourage

    other power plants to install these systems

    to control sootblowing, improve boiler

    eciency, reduce NOX emissions, and

    improve other aspects o their operations.Although equipment and instrumentation

    issues may have precluded the NN-ISB

    project rom achieving all o its goals, the

    project clearly demonstrated the validity o

    using AI to control a major aspect o boiler

    operation.

    Mercury Specie and

    Multi-Pollutant

    Control Project

    Introduction

    Implemented under the CCPI, the proj

    at the NRG Texas (ormerly Texas Genc

    Limestone Power Plant in Jewett, Texas

    designed to demonstrate the capability

    optimize mercury speciation and cont

    emissions rom an existing power pla

    NRG Texas, with a generating capacity

    more than 14,000 MW, has plants primar

    based on ossil uels and is an importa

    producer o electricity in Texas.

    Perormed by Pegasus Technologi

    Inc., a division o NeuCo, Inc., this demo

    stration is occurring on an 890 MW util

    boiler that uses 14,500 tons o coal p

    day. The Pegasus technology provid

    plant operators with the ability to asse

    detailed plant operating parameters th

    aect mercury capture eciency, over

    heat rate, particulate removal, and fue g

    desulurization (FGD) eciencies. The

    data are also provided to a neural netwo

    optimization system that controls pla

    subsystems to provide the lowest possipollutant emissions, highest heat rate, a

    least risk o environmental non-complian

    all with minimal capital expenditure.

    NRGs Limestone Power Plant

  • 8/22/2019 9A0F5d01

    16/28

    1

    Once demonstrated, this technology

    is anticipated to have broad application to

    existing coal-red boilers and a positive

    impact on the quality o saleable by-

    products such as ly ash. The project

    began in April 2006, with perormance

    testing targeted or December 2008. Thisestimated $15.6 million project will be

    38 months in duration, with a DOE cost

    share o 39 percent.

    Project Objectives

    On a large utility coal-ired boiler,

    Pegasus Technologies is demonstrating

    the ability to aect and optimize mercury

    speciation and multi-pollutant control

    using non-intrusive advanced sensor and

    optim ization technologies. Plant-wideadvanced control and optimization systems

    are being integrated into a coal-red, ste

    electric power plant in order to minim

    emissions while maximizing the ecien

    and by-products o the plant. Advanc

    solutions utilizing state-o-the-art sens

    and neural-network-based optimizati

    and control technologies are being usto maximize the portion o the mercu

    vapor in the boiler fue gas that is oxidiz

    or captured in particle and chemical bon

    resulting in lower uncontrolled releases

    mercury.

    This neural-network-based control a

    optimization system gathers data rom c

    composition, combustion gas compositio

    mercury species, eed rates, etc., and u

    this inormation to optimize power pl

    operations. The greatest advantage o neu

    networks in power plants is their abilitygeneralize rom previous inormation a

    develop possible similar patterns or utu

    use. Such intelligent control is expected

    improve mercury capture by over 40 perce

    reduce NOX emissions by 10 percent, redu

    uel consumption by 0.5 to 2.0 percent, a

    improve operating fexibility.

    Project Description

    The estimated 48 tons o mercu

    emitted annually by domestic coal-rpower plants is about one-third o t

    total amount o mercury released annua

    rom all human activities in the Uni

    States. Mercury emissions take a num

    o chemical ormsor speciesincludi

    the pure element, as part o a gaseo

    compound, or bound to particulates

    fue gas. Certain mercury species, su

    as mercury that is adsorbed onto fy-a

    particles or bound in the FGD, are relativ

    easy to remove rom fue gas. Adjust

    certain parameters during combusti

    can optimize the speciation process amaximize the mercury captured in parti

    bonds. This results in greater capture

    mercury and lower uncontrolled releases

    Control System Schematic or NRG Texas Limestone Power Plant

  • 8/22/2019 9A0F5d01

    17/28

    The NRG Texas demonstration power

    plant is equipped with a tangentially-red

    boiler that uses a blend o 70 percent Texas

    lignite and 30 percent Powder River Basin

    subbituminous coal, which are known to

    emit relatively high levels o elemental

    mercury under routine combustionconditions. Pegasus Technologies will

    apply sensors at key locations to evaluate

    the mercury species (elemental and

    oxidized mercury), develop optimization

    sotware that will result in the best plant

    conditions to promote mercury oxidation

    and minimize emissions in general, and

    use neural networks to determine the

    optimization conditions.

    The unit is equipped with a cold-side

    ESP rated at approximately 99.8 percent

    particulate removal eciency and a wetlimestone FGD system rated at approximately

    90 percent SO2 removal eciency. Both

    devices are capable o high mercury-capture

    eciency, especially when the mercury is in

    an oxidized state rather than an elemental

    vapor state.

    Using a neural network to aect and

    optimize mercury speciation and multi-

    pollutant control, the non-intrusive advanced

    sensor and optimization technologies will

    act as a highly trained operator, making

    decisions on inputs to the process bymeasuring and learning the outputs. By

    using AI and simulation technologies,

    Pegasus will minimize the use o raw

    material resources and pollutant emissions

    while simultaneously optimizing the

    operating capabilities o the plant.

    This project involves the installation and

    demonstration o sensors and optimization

    sotware in six separate technology

    packages. While the modular design is

    transparent to this project, it is important to

    the uture marketing o this system becauseo the fexibility needed with utilities to

    include or exclude a particular module

    based on either the existing equipment or

    budget or a specic plant. Many o the

    sensors and optimizer technologies that will

    be installed are utilized across the modules;

    thereore, they have been included under

    the module in which they are most used.

    The technology packages or this project

    include the ollowing:

    The intelligent uel management system

    (FMS): The FMS is composed o the

    Pegasus Combustion Optimizer system,

    the Ready Engineering CoalFusion

    system, and a Sabia elemental analyzer.

    The mercury specie control system:

    This system includes the boiler areaoptimization, Pegasus virtual online

    analyzers, and various sensors. Mercury

    emissions will be measured through

    continuous emission monitors.

    The advanced ESP optimization

    system: The ESP optimization system

    is composed o a carbon-in-ash virtual

    online analyzer, a carbon-in-ash sensor,

    and Pegasus ESP optimization sotware.

    The advanced ISB system: The ISB

    system is made up o Pegasus ISBsotware. This module has been

    previously demonstrated.

    The advanced FGD optimization system:

    The FGD System is composed o Pegasus

    FGD optimization sotware.

    Key locations where sensors will be applied to evaluate mercury specie s

  • 8/22/2019 9A0F5d01

    18/28

    1

    The intelligent plant (unit optimization):

    This is the Pegasus i-Plant Optimization

    System that will contain a simulator and

    will arbitrate among the solutions or the

    above systems. This system will interace

    with users through a commercially

    available computer.

    Each technology package includes

    non-intrusive sensors and the appropriate

    sotware needed or data acquisition,

    optimization, and integration with the

    overall neural network. In using this

    approach, all acets o coal-red power

    plant operation will be optimized by

    balancing the inputs and outputs o the plant

    within a realm o multiple constraints. The

    intended result is to improve the eciency

    o plant operations while operating within

    regulatory and commercial constraints.

    During the rst o three perormance

    phases, sensor installation, sotware system

    design, and baseline operating metric testing

    will be completed. Instruments or instrument

    technology packages to be installed include

    a coal elemental analyzer (part o the uel

    management system), mercury sensors,

    coal fow sensors, laser-based urnace gas

    speciation sensors, online carbon-in-ash

    sensor (located in the ESP), communications

    links or data acquisition and control, and

    related computers, controllers, and Pegasusoptimization products.

    Baseline testing will be perormed

    to establish comparative data or the

    operational testing that will ollow in

    Phase 3. Ater initial baseline testing,

    parametric testing will be perormed to

    exercise various combinations o control

    variables to determine their eect on

    mercury speciation and by-product

    generation and to determine overall plant

    perormance. These data will be used in

    Phase 2 to adjust the neural network oroptimization control.

    During Phase 2, sotware installation,

    data communications modication, and

    distributed control system modication

    will be achieved. The test plan data and

    historical data (i applicable) will be

    evaluated to conrm that no irregularit

    exist prior to model development. A

    extraneous data (e.g., calibrations) a

    eliminated rom the data set, operati

    issues and constraints will be review

    as part o urther model developme

    Control models will be developed characterize the eect o control variab

    on the operational characteristics o t

    boiler, mercury speciation, and by-produ

    generation. Models will be created th

    accurately and robustly represent the ee

    that changes in the unit have on the outp

    to be optimized. Beore the control mod

    are implemented in an online system, ofi

    simulation will be perormed. The mod

    will then be evaluated and demonstrat

    to Limestone Power Plant operators a

    engineers so their input can be used

    nalize the behavior o the models.

    Pegasus uses pre-designed and custo

    methods or constraining the models und

    various design and operational limitatio

    These are dynamic constraints that fuctu

    with load, number o burners in service, r

    o change, etc. Ater the initial modeli

    is completed, a shorter series o tests w

    be conducted. These will involve setti

    up operational parameters to veriy

    predictive capabilities o the neural netwo

    model and to assure that the model h

    been properly trained. During this perithe models will be coarse-tuned. Cont

    loops will rst be tested one at a time a

    then as groups to deal with the individu

    loop characteristics beore dealing with t

    interactive characteristics.

    At the end o Phase 2, a decision w

    be made whether to initiate work und

    Phase 3 or to conclude the project a

    the successul demonstration o close

    loop operability or neural networks a

    controllers.

    Phase 3 plans include demonstrati

    and validation o all systems as well as

    comparison o the test results with the proj

    objectives. Extended mercury and mu

    pollutant testing will be conducted. T

    technology packagesthe uel managem

    system, combustion and mercury cont

  • 8/22/2019 9A0F5d01

    19/28

    system, ESP system, ISB system, FGD system,

    and intelligent plant (i-Plant) systemwill

    all be demonstrated during closed-loop

    operation. Operator and engineering training

    will also be conducted during Phase 3.

    Anticipated Benefts

    In this project, Pegasus Technologies and

    NRG Texas are attempting to put together

    all o the required best-o-class articial

    intelligence and simulation technologies

    to prove that mercury speciation and

    multi-pollutant reduction benets can be

    measured, optimized, and controlled. I

    successul, Pegasus will demonstrate the

    capability o sophisticated control processes

    and advanced sensor technologies to

    simultaneously reduce harmul emissionso mercury and increase plant eciency.

    Increased control o SO2, NOX, and

    particulate matter should also result, along

    with a reduction in water usage. Since

    these technologies are designed to control

    and optimize all major acets o power plant

    operations, the demonstration is expected

    to provide the capability to maximize plant

    eciency or electricity production while

    reducing mercury emissions. This project

    is also expected to address concerns that

    higher mercury concentrations in existing

    by-products, such as ash, may adverselyaect the commercial value o those by-

    products.

    This project should demonstrate an

    operating environment that simultaneously

    oers higher-than-average compliance with

    environmental requirements and better

    control o emissions, resulting in both a

    smaller risk o non-compliance to the utility

    and minimization o capital expenditures.

    In general, the project is expected to

    demonstrate how integrating sensors

    and advanced controls into a total plantsolution can lead to improved economics

    while being environmentally compliant.

    The technologies being demonstrated are

    expected to have widespread application

    since they can be directly retrotted to the

    existing coal feet or integrated into uture

    new plant designs.

    Demonstration

    o Integrated

    Optimization Sotware

    at the Baldwin EnergyComplex Project

    Introduction

    As part o the CCPI, sophisticated

    computational techniques are being applied

    to an Illinois coal-red power plant to show

    how new technology can increase power

    plant eciency and reliability and reduce air

    emissions. NeuCo, Inc., o Boston, MA, is

    designing and demonstrating an integratedonline optimization system at the Dynegy

    Midwest Generation power plant located

    in Baldwin, IL. The Baldwin Energy

    Complex (BEC) consists o two 585 MW

    cyclone-red boilers with selective catalytic

    reduction (SCR) and a 595 MW tangentially

    red boiler with low NOX burners.

    Dynegy Midwest Generations Baldwin Energy Complex

  • 8/22/2019 9A0F5d01

    20/28

    20

    The ve system optimization modules

    being developed include cyclone combustion,

    sootblowing, SCR operations, overall unit

    thermal perormance, and maintenance

    optimization. This project builds on the

    NeuCo proprietary ProcessLink technology

    platorm. Power plants operate in manydierent conditions and plant processes are

    highly complex and interrelated. The goal

    o optimization is to continuously assess and

    adjust (or provide actionable advice about) the

    settings o the many variables aecting plant

    perormance so that the optimal balance o

    plant emissions, uel eciency, capacity, and

    reliability is achieved. The total cost o this

    45-month project is estimated at $19 million,

    including a 45 percent DOE cost share.

    Project Objectives

    The overall objective o applyi

    integrated optimization sotware is

    improve the emissions prole, ecien

    maintenance requirements, and pla

    asset lie or coal-based power generatiin order to extend the use o abund

    coal resources in the United States in

    environmentally sound manner. In gener

    sotware optimization oers seve

    advantages to power plants, includi

    the ability to control key parameters on

    consistent basis, compensate or chang

    in coal quality, optimize controls to m

    specic plant objectives, and help

    understanding the available data and

    use or improved operations. The proj

    at BEC will demonstrate and quant

    the environmental and emissions beneassociated with deployment o a u

    integrated set o sotware solutions

    optimization o plant perormance or co

    red power generation.

    Because retrots, repowering, mod

    cations, and new technologies are stead

    increasing the complexity o modern pow

    plants, an integrated process-optimizati

    approach is required to maximize equipm

    perormance and minimize operating cos

    Optimization solutions are now availab

    or a variety o power plant control systemlinking these systems together will provi

    overall plant-level optimization that

    expected to yield additional benets.

    Thereore, the primary objective

    this project is to demonstrate integrati

    o existing controls and control system

    sensors, and computer hardware w

    advanced optimization techniques at BE

    and to link the individual optimizati

    modules through the NeuCo ProcessLink

    platorm. Collectively, these modules

    expected to provide optimization solutioor this 1,765 MW coal-red power pla

    by reducing emissions, increasing pla

    eciency, and increasing the availability

    the plant or power generation.

    The Baldwin Energy Power Plant at sunset

  • 8/22/2019 9A0F5d01

    21/28

    Project Description

    NeuCo is designing and demonstrating

    an integrated online optimization sotware

    system or the Dynegy Midwest Generation

    power plant using advanced computational

    techniques that are expected to achieve peakperormance rom the three coal-red units

    at the energy complex. NeuCo is using its

    ProcessLink technology platorm o neural

    networks, expert systems (heuristics), rst

    principle models, advanced algorithms, and

    uzzy logic to maximize perormances rom

    the power plant combustor, soot removal

    system, and emission controlsthe rst time

    that all o these modules have been integrated

    into a computerized process network.

    Five separate modules are being

    designed and demonstrated by NeuCo atBEC and then integrated to provide unied

    plant optimization.

    CombustionOpt uses neural network-

    based optimization, model predictive

    control, and other technologies to

    extract knowledge about the combustion

    process, determine the optimal balance

    o uel and air fows in the urnace,

    and respond to changing conditions.

    CombustionOpt directly adjusts the

    distributed control system to more

    consistently position the dampers, burner

    tilts, overre air, and other controllable

    parameters at their optimal settings or

    given sets o conditions, objectives, andconstraints. This module should reduce

    uel consumption and NOX emissions; it

    should also improve carbon monoxide

    control, reduce opacity, and improve loss

    on ignition.

    SootOpt optimizes sootblowing to

    reduce adverse ouling conditions

    and unplanned outages that soot and

    sootblowing can cause. It also expands

    Planned Integration Concept or the Baldwin Energy Complex

    eiciency improvements, reduc

    emissions, and drives boiler-cleani

    actions toward optimal plant heat ra

    emissions, and reliability goals. T

    SootOpt adaptive neural network mod

    identiy the equipment and actions m

    eective or achieving plant ecienreliability, and emissions objectiv

    and then bias control activity towa

    those objectives. The neural mod

    work within boundaries dened

    expert rules to ensure all applicable un

    specic constraints are considered.

    SCR-Opt uses neural-network-bas

    optimization, model predictive contr

    and other technologies to make t

    operation o the SCR as eicient

    possible. SCR-Opt is expected

    minimize ammonia usage and reduNOX emissions.

    PerormanceOpt uses a rigoro

    rst-principles-based thermodynam

    model o the boiler and steam cyc

    to conduct both what is and wh

    i simulations o unit operatio

    Continuously monitoring the actu

    versus the expected perorman

    levels o key equipment and proce

    Control Room at the BaldwinEnergy Complex

  • 8/22/2019 9A0F5d01

    22/28

    22

    conditions, PerormanceOpt detects

    when perormance deviates rom what

    is achievable under current operating

    conditions and calculates the impact o

    that deviation so that remedial actions

    can be prioritized. PerormanceOpt is

    expected to improve heat rate, steamtemperatures, and generating capacity.

    MaintenanceOpt helps engineers

    manage the entire lie-cycle o reliability,

    capacity, and eciency problems more

    eciently and eectively. It uses neural

    network technology to constantly search

    or gaps between actual and expected

    behavior across a broad range o

    process and equipment health variables.

    Its powerul diagnostics knowledge

    base also helps to lter alse alarms,

    determine the root causes and correctiveactions o identied problems, and aid

    in problem resolution and tracking.

    MaintenanceOpt is expected to increase

    annual power output and assist in

    providing lower costs o electricity to the

    consumer.

    These advanced computational capa-

    bilities will be used to comprehensively

    optimize a variety o systems within BEC by

    using existing control technologies and then

    linking these systems to each other. This

    innovative project will provide solutionsthat use system-speciic optimization

    applications as data sources and actuators.

    In general, the overall architecture o this

    control platorm is designed to permit

    lexible deployment strategies. Rather

    than requiring that all data and logic reside

    on a single computer, the service model

    allows applications to leverage networked

    computational resources. The application

    architecture is built around interoperable

    services that should result in more ecient

    plant operations. The planned integration

    concept is shown below.

    This integrated optimization sotware

    project at BEC consists o two phases.

    Phase I, which has been completed, entailed

    the development and installation o initial

    versions o each o the ve optimization

    modules, as well as their integration through

    the ProcessLink platorm to address theull scope o plant operations and relevant

    system interactions.

    Extensive operating experience will be

    required to quantiy the benets associated

    with control system optimization. The goal

    during Phase I was to establish each system

    and demonstrate its role in unied plant

    optimization. Phase I activities ocused

    on developing, deploying, integrating,

    and testing prototypes or each o the ve

    optimization modules; identiying and

    addressing issues required or the modulesto integrate with plant operations; and

    systematically collecting and assimilating

    eedback to improve subsequent module

    releases.

    The goal o Phase II is to improve

    upon the sotware installed and tested in

    Phase I and to perorm rigorous analysis

    o operating data in order to quantiy the

    benets o the integrated system. Phase

    II entails quantication o results at BEC;

    renement o the sotware installed and

    demonstrated in Phase I to support additionalcommercial releases o the ve products;

    installation and beta testing at BEC; and

    commercialization o the solutions, taking

    into account both what is learned at BEC

    and eedback systematically incorporated

    rom other operators o U.S. coal-red

    power generation plants.

    During both phases, best practices

    iterative sotware development methods

    will be applied toward integration,

    ull-scale demonstration, and eventual

    commercialization o these ve solutions. Allsystem sotware engineering, applications

    engineering, and systems integration will

    proceed through a multi-step, iterative

    process that supports a structured, modu

    approach to determining sotware a

    hardware requirements and unction

    denitions along with various desig

    development, test, installation, and start

    activities. This iterative developme

    process is specically designed to depla commercially viable product as soon

    possible, while at the same time applyi

    host-site eedback and what is learn

    toward maximizing unctionality a

    benets in subsequent releases.

    Anticipated Benefts

    This optimization initiative is expect

    to reduce NOX emissions by 5 percent a

    increase thermal eciency by 1.5 perce

    The increased thermal eciency is expectto reduce emissions o CO2, mercury, a

    particulates. Ammonia consumption

    expected to be reduced by 15 perce

    accompanied by a one-year extension o t

    SCR catalyst. The optimization initiat

    is expected to also result in improv

    power plant capacity and reliability whic

    in turn, is expected to increase net annu

    electrical power production by 1.5 perce

    Consumers should benet through low

    electricity costs.

    The NeuCo ProcessLink architectuoers plant operators a highly fexib

    control system platorm. Optimizat i

    modules can be designed and applied

    individual subsystems in a plant, leveragi

    existing sensors, actuators, and network

    computational resourcesand then linki

    them to other individual subsystems

    provide overall plant-level integration

    controls responsive to plant operator a

    corporate criteria. This integrated proc

    optimization approach will likely be

    important tool or plant operators as pla

    complexity increases through retrot arepowering applications, installation o n

    technologies, and plant modications.

  • 8/22/2019 9A0F5d01

    23/28

    Conclusions

    The U.S. Department o Energy Clean

    Coal Technology programs continue to

    sponsor projects that develop technologiesor optimizing power plant operation.

    These technologies help keep the cost

    o electricity low, reduce emissions, and

    conserve our uel supply.

    The Lignite Fuel Enhancement project

    demonstrates a technology that reduces

    the moisture content o low-rank coals,

    which results in a number o benets to

    power plant operation. Coal consumption

    is reduced, thereby reducing CO2 and other

    emissions. Parasitic power requirements

    are also reduced. When the technology isapplied to new plants, capital costs will be

    reduced in several major subsystems, such

    as SO2 removal, pulverizers, and cooling

    towers. This technology achieves these

    benets using only waste heat to remove the

    moisture rom the uel.

    While the Neural Network-Intelligent

    Sootblower project did not reach all o its

    goals, the NN-ISB control system was ound

    to be a sound idea with signicant potential.

    The project successully demonstrated a

    neural network, closed-loop operation on aull-scale boiler without causing unit upsets

    or violating any constraintsand also

    achieved operator acceptance.

    Although not yet completed, the

    Mercury Specie and Multi-Pollutant

    Control project and the Demonstrationof Integrated Optimization Software

    project have demonstrated the ability o NN

    and AI technologies to provide signicant

    economic, operational, and environmental

    beneits to power plant operation. The

    demonstrated technologies are applicable

    to all types o coal-red boilers and do not

    require the purchase o major equipment.

    Given the benets and relatively low cost,

    these types o technologies are likely to nd

    a ready market.

    The continuing development o sot-ware to control overall power plant

    operation, or selected aspects o it, has

    shown substantial progress in optimizing

    power plant perormance. These sotware

    packages allow operators to more easily

    stay within their emission limits while

    improving power plant eiciency and

    lowering the cost o power production.

    While doing so, the participants have

    produced products that are expected to

    nd a substantial market both in the United

    States and abroad.

  • 8/22/2019 9A0F5d01

    24/28

    2

    Bibliography

    Bullinger, Charles, Mark Ness, and Nenad Sarunac. Coal Creek Prototype Fluidized

    Bed Coal Dryer: Perormance Improvement, Emissions Reduction, and Operating

    Experience, Paper presented at 31st International Technical Conerence on Coal

    Utilization and Fuel Systems, Clearwater, Florida, May 21-25, 2006.

    Gollakota, Sai. Great River Energy Project Benets Presentation. Paper presented on

    February, 2007.

    Great River Energy. Great River Energy Lignite Fuel Enhancement Proposal to DOE

    Solicitation DE-PS26-02NT4142 8Public Abstract, August 1, 2002, http://www.

    netl.doe.gov/technologies/coalpower/cctc/ccpi/proposal-pd/greabs.pd.

    Ness, Mark, and Charles Bullinger. Pre-Drying the Lignite to CREs Coal Creek Statio

    May, 2005.

    NeuCo, Inc. Technical Progress Reports #11 to the U.S. Department o Energy, Oce o

    Fossil Energy, National Energy Technology Laboratory. Cooperative Agreement DEFC26-04NT41768. September 30, 2006.

    NeuCo, Inc. Technical Progress Report #12 to the U.S. Department o Energy, Oce o

    Fossil Energy, National Energy Technology Laboratory. Cooperative Agreement DE

    FC26-04NT41768, February 5, 2007.

    Tampa Electric Company and Pegasus Technologies, Inc. Project Perormance and

    Review: Neural Network Based Intelligent Sootblowing System, Tampa Electric

    Company Big Bend Unit #2. April 2005

    U. S. Department o Energy. Clean Coal Technology Programs: Program Update 2006,

    September 2006, pp. 3-54, http://www.netl.doe.gov/technologies/coalpower/cctc/ccp

    pubs/2006_program_update.pd.

    U. S. Department o Energy, Oce o Fossil Energy, National Energy Technology

    Laboratory. Advanced Coal Conversion Process Demonstration: A DOE

    Assessment, April 2005, http://www.netl.doe.gov/technologies/coalpower/cctc/cctd

    bibliography/demonstration/pds/rsbud/NETL-1217_as%20sent%20to%20OSTI.pd

    U.S. Department o Energy, Oce o Fossil Energy, National Energy Technology Laborator

    Big Bend Power Station Neural Network-Intelligent Sootblower Optimization.

    Project Brie, Sept. 2005. http://www.netl.doe.gov/technologies/coalpower/cctc/PPI

    bibliography/demonstration/environmental/neural/bigbenddemo.pd

    U.S. Department o Energy, Oce o Fossil Energy, National Energy Technology

    Laboratory. Big Bend Power Station Neural Network-Intelligent Sootblower

    Optimization. Project Fact Sheet, Dec. 2006. http://www.netl.doe.gov/publicationsactsheets/project/Proj233.pd

    Contacts or Participants

    in CCT ProjectsDavid Wroblewski, Senior VP

    Development

    Pegasus Technologies100 Seventh Avenue, Suite 210

    Chardon, OH 020-25-779

    [email protected]

    John McDermott, Vice President,

    Product ManagementNeuCo, Inc.

    200 Clarendon Street, HancockTower, T-1Boston, MA 0211

    [email protected]

    Charles Bullinger

    Great River Energy

    275 Third St., SWUnderwood, ND 557-959

    [email protected]

    Mark Rhode

    TECO Energy

    P.O.Box 111Tampa, FL 01

    1-22-152

    [email protected]

  • 8/22/2019 9A0F5d01

    25/28

    U. S. Department o Energy, Oce o Fossil Energy, National Energy Technology

    Laboratory. Big Bend Power Station Neural Network-Sootblower Optimization: A

    DOE Assessment, DOE/NETL-2006/1234, June 2006. http://www.netl.doe.gov/

    technologies/coalpower/cctc/PPII/bibliography/demonstration/environmental/neural/

    BigBendSootblowerPPA_Final_061306.pd

    U.S. Department o Energy, Oce o Fossil Energy, National Energy Technology

    Laboratory. Cleaner Air by the Numbers. TechLine, March 17, 2004. http://www.

    netl.doe.gov/publications/press/2004/tl_ccpi_neucoaward.html

    U.S. Department o Energy, Oce o Fossil Energy, National Energy Technology

    Laboratory. Demonstration o Integrated Optimization Sotware at the Baldwin

    Energy Complex. Project Brie, 2006. http://www.netl.doe.gov/technologies/

    coalpower/cctc/ccpi/bibliography/demonstration/environmental/ccpi_demo.html

    U.S. Department o Energy, Oce o Fossil Energy, National Energy Technology

    Laboratory. Demonstration o Integrated Optimization Sotware at the BaldwinEnergy Complex. Project Fact Sheet, Dec. 2006. http://www.netl.doe.gov/

    publications/actsheets/project/Proj221.pd.

    U.S. Department o Energy, Oce o Fossil Energy, National Energy Technology

    Laboratory. DOE, Tampa Electric Sign Agreement to Add Intelligent Computer

    System to Florida Power Plant. TechLine, August 21, 2002.TechLine, August 21, 2002. http://www.netl.doe.gov/

    technologies/coalpower/cctc/PPII/bibliography/demonstration/environmental/neural/

    neural_tech.pd

    U.S. Department o Energy, Oce o Fossil Energy, National Energy Technology

    Laboratory. Mercury Specie and Multi-Pollutant Control. Project Brie, 2006.

    http://www.netl.doe.gov/technologies/coalpower/cctc/ccpi/project_bries/CCPI_

    Pegasus.pd.

    U.S. Department o Energy, Oce o Fossil Energy, National Energy Technology

    Laboratory. Mercury Specie and Multi-Pollutant Control Project. Project Fact Sheet,

    Dec. 2006. http://www.netl.doe.gov/publications/actsheets/project/Proj372.pd

    U.S. Department o Energy, Oce o Fossil Energy, National Energy Technology

    Laboratory. Pegasus Project Selected as Part o Clean Coal Power Initiative.October 28, 2004. TechLine. http://www.netl.doe.gov/publications/press/2004/tl_

    ccpi2_pegasus.html

    Contacts or U.S.

    Departmento Energy CCT Program

    John Rockey, Project ManagerNeural Network-Intelligent

    Sootblowing Optimization

    National Energy TechnologyLaboratory

    10 Collins Ferry RoadP.O. Box 0

    Morgantown, WV 2507-00

    [email protected]

    Sai Gollakota, Project Manager

    Lignite Fuel Enhancement

    National Energy TechnologyLaboratory

    10 Collins Ferry RoadP.O. Box 0

    Morgantown, WV 2507-000-25-151

    [email protected]

    George Pukanic, Project Manager

    Demonstration o IntegratedOptimization Sotware

    National Energy TechnologyLaboratory2 Cochrans Mill Road

    P.O. Box 1090Pittsburgh, PA 152-090

    12--05

    [email protected]

    Michael McMillian, Project ManagerMercury Specie and Multi-Pollutant

    ControlNational Energy Technology

    Laboratory

    10 Collins Ferry Road

    P.O. Box 0Morgantown, WV 2507-000-25-9

    [email protected]

  • 8/22/2019 9A0F5d01

    26/28

    2

    To Receive Additional

    Inormation

    To be placed on the Departmento Energys distribution list oruture inormation on the Clean

    Coal Demonstration Programs,the projects they are nancing,

    or other Fossil Energy Programs,please contact:

    John L. Grasser, DirectorOce o Communication

    FE-5/Forrestal BuildingU.S. Department o Energy

    1000 Independence Ave., SW

    Washington, DC 2055202-5-0

    202-5-51 [email protected]

    David J. AnnaOce o Public Aairs Coordination

    U.S. Department o EnergyNational Energy Technology

    Laboratory

    P.O. Box 1090

    Pittsburgh, PA 152-09012--12--195 ax

    [email protected]

    Acronyms and Abbreviations

    ACM Advanced calibration monitor

    AI Articial intelligence

    APH Air preheater

    BEC Baldwin Energy Complex

    CCPI Clean Coal Power Initiative

    CCTDP Clean Coal Technology Demonstration Program

    CO2 Carbon dioxide

    DOE Department o Energy

    ESP Electrostatic precipitator

    FGD Flue gas desulurization

    FL Fuzzy logic

    FMS Fuel management system

    GRE Great River Energy

    ISB Intelligent sootblowing

    MW Megawatt

    NETL National Energy Technology Laboratory

    NN Neural network

    NN-ISB Neural network-intelligent sootblowing

    NOx Nitrogen Oxides

    OPM Online perormance monitor

    PPII Power Plant Improvement Initiative

    SCR Selective catalytic reduction

    SO2 Sulphur dioxide

    TECO Tampa Electric Company

  • 8/22/2019 9A0F5d01

    27/28

  • 8/22/2019 9A0F5d01

    28/28

    National Energy

    Technology Laboratory

    1450 Queen Avenue SW

    Albany, OR 97321-2198

    541-967-5892

    2175 University Avenue South, Suite 201

    Fairbanks, AK 99709

    907-452-2559

    3610 Collins Ferry Road

    P.O. Box 880

    Morgantown, WV 26507-0880

    304-285-4764

    626 Cochrans Mill Road

    P.O. Box 10940

    Pittsburgh, PA 15236-0940

    412-386-4687

    One West Third Street, Suite 1400Tulsa, OK 74103-3519

    918-699-2000

    Visit the NETL website at:

    www.netl.doe.gov

    Customer Service:

    1-800-553-7681

    U.S. Department o Energy

    Oce o Fossil Energy

    Printed in the United States on recycled paper