7/23/2019 95268739 Project Report on Thermal Plant
1/63
Industrial TrainingReport
On Water Treatment and Coaltesting At
Guru Nanak Dev Thermal
Plant Bathinda
Submitted By: Sapandeep Singh 2012052
7/23/2019 95268739 Project Report on Thermal Plant
2/63
!nder the guidan"e o#
$rs%&r%$e"hani"al Dptt%'dd% S%&% T%T% "ellGNDTP(Bathinda
Department of MechanicalEngineering
S!!M MA"#A$ "STT%TE O& TEC'"O$O()*
MA+TA,
')*N+,-&DG&$&NT
DECLARATION
hereby declare that the pro-ect .or/ entitled 0Water treatment
and coal testing1 is an authentic record of my o.n .or/ carried
out at Bathinda as re2uirements of si3 months ndustrial Training
for the a.ard of the degree of B4E4 at %ni5ersity nstitute of
Engineering 6 Technology* #an-ab %ni5ersity* Chandigarh under
the guidance of Er4 T4"4Bansal and Mrs4 An-ali (upta* during 7-an8
9May 9;794
7/23/2019 95268739 Project Report on Thermal Plant
3/63
student
Date: 9
7/23/2019 95268739 Project Report on Thermal Plant
4/63
;;mm to 7;mm4 Then the coal is sent to secondary crusher
through for.ard con5eyors .here it is crushed from 7;mm to
9;mm as re2uired at the mills4 Then the coal is sent to boilers
.ith the help of primary fans4 The coal is burnt in the boiler4 Boiler
includes the pipes carrying .ater through them heat produced
from the combustion of coal is used to con5ert .ater in pipes into
steam4 This steam generated is used to run the turbine4 When
turbine rotates* the shaft of generator* .hich is mechanically
coupled to the shaft of turbine* gets rotated so* three phases
electric supply is produced4
The basic re2uirements are:8
&uel coal
Boiler
Steam turbine
(enerator
Ash handling system
%nit au3iliaries
.IST+R/
4
7/23/2019 95268739 Project Report on Thermal Plant
5/63
Due to high rate of increasing population day by day* .idening
gap bet.een po.er demand and its a5ailability .as one the basic
reason for en5isaging the (4"4D4T4#4 for the state of #un-ab4 The
other factors fa5oring the installation of the thermal po.er station
.ere lo. initial cost and comparati5ely less gestation period as
compared to hydro electric generating stations4 The foundation
stone of (4"4D4T4#4 at bathinda .as laid on 7th"o5ember 7>*
the auspicious occasion of ;;thbirth anni5ersary of great (uru
"ana/ De5 +i4
The historic to.n of bathinda .as selected for this =rst andprestigious thermal pro-ect of the state due to its good rail.ay
connections for fast transportations of coal* a5ailability of canal
.ater and pro3imity to load center4
The total installed capacity of the po.er station ;MW .ith
four units of 77;MW each4 The =rst unit of the plant .as
commissioned in September* 7F4 Subse2uently second* third
and fourth units started generation in September 7F* March
7F
7/23/2019 95268739 Project Report on Thermal Plant
6/63
-'ND$'R*S
').I&&D
(4"4D4T4#4 .on an a.ard of ,s4 G47> crores from (o5t4 of
ndia for better performance in 7
7/23/2019 95268739 Project Report on Thermal Plant
7/63
(4"4D4T4#4 had achie5ed a generation of 9F99; $%1s at
a #$f of F;H and registering an oil consumption as lo. as
74F>ml?/.h during the year 7G8 has bro/en all pre5ious
records of performance since the inception of plant4
,+R*ING 'T GNDTP
Coal recei5ed from collieries in the rail .agon is
mechanically unloaded by Wagon Tippler and carried by belt
Con5eyor System Boiler ,a. Coal Bun/ers after crushing in the
coal crusher4 The crushed coal .hen not re2uired for ,a. Coal
Bun/er is carried to the coal storage area through belt con5eyor4
The ra. coal feeder regulates the 2uantity of coal from coal
bun/er to the coal mill* .here the coal is pul5eri@ed to a =ne
po.der4 The pul5eri@ed coal is then suc/ed by the 5apour fan and
=nally stored in pul5eri@ed coal bun/ers4 The pul5eri@ed coal is
then pushed to boiler furnace .ith the help of hot air steam
supplied by primary air fan4 The coal being in pul5eri@ed state
gets burnt immediately in the boiler furnace* .hich is comprised
of .ater tube .all all around through .hich .ater circulates4 The.ater gets con5erted into steam by heat released by the
combustion of fuel in the furnace4 The air re2uired for the
combustion if coal is supplied by forced draught fan4 This air is
7/23/2019 95268739 Project Report on Thermal Plant
8/63
ho.e5er heated by the outgoing Iue gases in the air heaters
before entering the furnace4
The products of combustion in the furnace are the Iue gases
and the ash4 About 9;H of the ash falls in the bottom ash hopper
of the boiler and is periodically remo5ed mechanically4 The
remaining ash carried by the Iue gases* is separated in the
electrostatic precipitators and further disposed oJ in the ash
damping area4 The cleaner Iue gases are let oJ to atmosphere
through the chimney by induced draught fan4
The chemically treated .ater running through the .ater
.alls of boiler furnace gets e5aporated at high temperature into
steam by absorption of furnace heat4 The steam is further heated
in the super heater4 The dry steam at high temperature is then led
to the turbine comprising of three cylinders4 The thermal energy
of this steam is utili@ed in turbine for rotating its shaft at high
speed4 The steam discharged from high pressure '4#4 turbine is
returned to boiler reheater for heating it once again before
passing it into the medium pressure M4#4 turbine4 The steam is
then let to the coupled to turbine shaft is the rotor of the
generator* .hich produces electricity4 The po.er from the
generator is pumped into po.er grid system through the
generator transformer by stepping up the 5oltage4
7/23/2019 95268739 Project Report on Thermal Plant
9/63
The steam after doing the useful .or/ in turbine is condensed to
.ater in the condenser for recycling in the boiler4 The .ater is
pumped to deaerator from the condenser by the condensate
e3traction pumps after being heated in the lo. pressure heater$4#4' from the deaerator* a hot .ater storage tan/4 The boiler
feed pump discharge feed .ater to boiler at the economi@er by
the hot Iue gases lea5ing the boiler* before entering the boiler
drum to .hich the .ater .alls and super heater of boiler are
connected4
The condenser is ha5ing a large number of brass tubesthrough .hich the cold .ater is circulated continuously for
condensing the steam passing out sides the surface of the brass
tubes* .hich has discharged do.n by circulating it through the
cooling to.er shell4 The natural draught of cold air is created in
7/23/2019 95268739 Project Report on Thermal Plant
10/63
the cooling to.er* cools the .ater fall in the sump and is then
recirculated by circulating .ater pumps to the condenser4
P-'NTS S'-I&NT
&'T!R&S
PR+3&)T 'R&'4
#o.er plant 9G< acres
Ash disposal
7/23/2019 95268739 Project Report on Thermal Plant
11/63
Total area 7
7/23/2019 95268739 Project Report on Thermal Plant
12/63
,ated pressure 7G; /g?cmK
,ated temperature GC
Condenser 5acuum ;4 /g?cmK
G&N&R'T+R4
Manufacturers B4'4E4$4
,ated output
%nit8 7 6 9 79;;;!A
%nit 8G 6 7GF;;;!A
(enerator 5oltage 77;;; 5olts
,ated phase current
%nit N7 6 9 >>; Amps4
unit NG 6 F99; Amps4
(enerator cooling hydrogen
B+I-&R &&D P!$PS4
"umber per unit t.o of 7;;H duty each
Type centrifugal
,ated discharge T?hr4
Discharge head 7>; MWC4
Speed ;; r4p4m4
7/23/2019 95268739 Project Report on Thermal Plant
13/63
)IR)!-'TING ,'T&R P!$PS4
"umbers for t.o units =5e of ;H duty each
Type mi3ed Io.
,ated discharge ;; T?hr4
Discharge head 9 MWC4
)++-ING T+,&RS4
"umbers four
Water cooled 7
7/23/2019 95268739 Project Report on Thermal Plant
14/63
Coal crusher 9; !W
#rimary air fan G9; !W
&orced draught fan G9; !W
Boiler feed pump G;; !W
nduced draught fan ;;?7;;; !W
Condensate pump 7F !W
DI&R&NT )&--S +
P-'NT
).P 8)oal .andling Plant9
The (4"4D4T4#4 units are primarily coal8=red units and the coal
consumption at ma3imum continuous rating M4C4,4 per unit is
about < T?'r4 the coal used at (4"4D4T4#4 is of bituminous and
sub8bituminous type and this is recei5ed from some collieries of
M4#4 and Bihar4
7/23/2019 95268739 Project Report on Thermal Plant
15/63
!N-+'DING + )+'-4
n order to unload coal from the .agons* t.o ,otaside
Tipplers of Elecon ma/e are pro5ided4 Each is capable of
unloading 79 open types of .agons per hour4 "ormally one tippler
.ill be in operation .hile the other .ill be standby4 The loaded
.agons are brought to the tippler side by the loco shunters4 Then
.ith the help of inhaul beetle one .agon is brought on the tippler
table4 The .agon is then tilted upside do.n and emptied in the
hopper do.n belo.4 The tippler is e2uipped .ith the integral
.eighbridge machine4 This machine consists of a set of .eighingle5ers centrally disposed relati5e to tippler4 The rail platform rests
on the .eighing girders and free from rest of the tippler .hen the
.agon is being .eighed4 After .eighing the loaded .agons is
tipped and returned empty to the .eighing girders and again
.eighed4 Thus the diJerence of the gross .eight and the tare
.eight gi5es the .eight of the .agon contents4 The tipplers are
run by motors of
7/23/2019 95268739 Project Report on Thermal Plant
16/63
screen gets bloc/ed* a pay loader truc/ can be employed .hich
.ill lift all the o5er si@ed coal and ta/e it to a suitable place .here
it can be bro/en either manually or by a crusher4 Thus it .ill sa5e
time as the trolleys can be emptied faster* sa5ing damages4
!S& + -+'D )&-- T/P& ,&IG.BRIDG& +R ,&IG.$&NT
IN $+TI+N 4
$oad ceil type .eighbridges are sometimes called dynamic
.eighbridge because the .agons can be handled o5er them at a
ma3imum speed of up to 79 m4p4h4 They consists of t.o platforms
one for gross and one for tare .eights4 Each .agon .eight is
automatically printed out and so is the rail.ay loop4 &irst the
gross .eights are established and memori@ed* then the train is
mo5ed o5er the rail trac/ hopper for discharge* after the emptytrain is mo5ed out o5er the tare .eighbridge platform .here the
tare .eights are printed out4 &inally the total net .eight is
computed and printed out4 The load cells at each .eighbridge are
connected to a digiti@er suitable for con5erting the analogue
output of the load cell into digital form4
7/23/2019 95268739 Project Report on Thermal Plant
17/63
Wagon Tippler
When coal reaches the plant* normal si@e of coal is about ;;mm
primary crusher 79;mm secondary crusher 9mm
coal mill pul5arised coal *feeded in boiler4
Before this boiler is preheated .ith oil upto G;;c*then oil supply
is cut do.n4
7/23/2019 95268739 Project Report on Thermal Plant
18/63
Con5eyer Belt
7/23/2019 95268739 Project Report on Thermal Plant
19/63
Boilers
t is a single drum* balanced draught* natural circulation* reheat
type* 5ertical combustion chamber consists of seamless steel
tubes on all its sides through .hich .ater circulates and is
con5erted into steam .ith the combustion of fuel4 The
temperature inside the furnace .here the fuel is burnt is of the
order of 7;;C4 The entire boiler structure is of 9meter height4
B+I-&R ).I$N&/4 The Iue from the boiler* after remo5al of ash in the
precipitators* is let oJ to atmosphere through boiler chimney* a
tall &erro8concrete structure standing as high as the historic utab
Minar4 &our chimneys* one for each unit* are installed4 The
chimney is lined .ith =re bric/s for protection of &erro8concrete
against hot Iue gases4 A protecti5e coating of acid resistant paint
is applied outside on its top 7; meters4
Boilers burn the fuel transferred from the tan/ and use the
resulting heat to con5ert .ater into steam4 nside the boilers are
tens of thousands of .ater8carrying tubes4 When combustion
commences* the temperature inside the boilers rises to bet.een
7*7;; and 7*;;PC* the .ater inside the tubes is turned into high8temperature and high8pressure steam* and the steam is
transferred to the steam turbines4
7/23/2019 95268739 Project Report on Thermal Plant
20/63
)IR)!-'TING ,'T&R P!$P4
T.o nos4 of circulating .ater pumps pro5ided for each unit*
circulate .ater at the rate of 7F9;; T?hr4 in a closed cycle
comprising of Turbine Condenser and Cooling To.er4 An additional
Circulating Water #ump pro5ided ser5es by for t.o units4 The
.ater re2uirement for bearing cooling of all the plant au3iliaries is
also catered by these pumps4
Boiler
7/23/2019 95268739 Project Report on Thermal Plant
21/63
Boiler spe"i:"ations
&eed .ater temperature 9;C
&inal super heater?reheater temperature ;C
Super heater outlet pressure 7G/g?cmK
ELciency H
Coal consumption per day per unit 7;; tones
Appro3imate
7/23/2019 95268739 Project Report on Thermal Plant
22/63
Tur;ines
The steam rotates the turbine blades at a high speed of G*;;;
rpm4 This turns the po.er generator* .hich is directly connected
to the turbines* and electricity is produced as a result4 This
electric po.er is then deli5ered along po.er transmission lines
and through substations to the homes of customers4
Turbine is a prime mo5er for the (enerator in the po.er plant4 n
steam turbine* the potential energy of steam is transformed into
/inetic energy and later in its turn is transformed into the
mechanical energy of the rotation of the turbine shaft4 The
common types of turbines are:8
I$P!-S& T!RBIN&4n this type of turbine* steam
e3pands in the no@@les and its pressure does not alter as it
mo5es o5er the blades4
R&')TI+N T!RBIN&4n this type of turbine* the
steam e3pands continuously as it passes o5er the blades andthus there is a gradual fall in pressure during e3pansion4
7/23/2019 95268739 Project Report on Thermal Plant
23/63
I$P!-S&
T!RBIN& R&')TI+N T!RBIN&
DiJerent types of steam turbines are used in Thermal #o.er
#lant but the ones .hich are used at (4"4D4T4#4 are categori@ed as
follo.s:8
Sr% No% T
7/23/2019 95268739 Project Report on Thermal Plant
24/63
G4 mpulse?,eaction mpulse
4 Condensing?"on8condensing Condensing
4 ,eheat?"on8reheat ,eheat
>4 ,egenerati5e?"on8 ,egenerati5e With bypass
ST87
F4 With bypass?Without bypass Without bypass
ST89
MA" TEC'"CA$ DATA
a The basic parameters:
,ated output measured at Terminal of the generator4
77;4;;;!W
Economical output4
4;;;!W
,ated speed4 G4;;;,#M
,ated temp4 of stearn -ust before the stop 5al5e4
GC
Ma3 Temp4 of steam before the stop 5al5e4
C
7/23/2019 95268739 Project Report on Thermal Plant
25/63
,ated pressure of steam before the M# casing4
G74>GC
Ma34 pressure of steam before the M# casing
GC
,ated temp4 of steam before the M# casing4
GC
Ma34 temp4 of steam before the M# casing4
C
b System of turbine:
(o5erning 5al5es Q9 interceptor 5al5es '# cylinder8 9 ,o.
Curtis .heel Q< mo5ing .heels4
Wt4 Of '# rotor appro34 *;; !g4
M# cylinder 8 79 Mo5ing .heels4
Wt4 Of M# rotor4 Appro34 77*;;; !g4
$# cylinder 8 Mo5ing .heels of double Io. design4
Wt4 Of M# rotor appro34 9*;;; !g4
Direction of the turbine rotation 8 To the right* .hen loo/ing at the
turbine from the front bearing pedestal4
7/23/2019 95268739 Project Report on Thermal Plant
26/63
General Spe"i:"ations o# Tur;ine
Manufacturers B4'4E4$4
,ated output 77; MW4
,ated speed G;;; r4p4m4
"umber of cylinders three
,ated pressure 7G; /g?cmK
7/23/2019 95268739 Project Report on Thermal Plant
27/63
,ated temperature GC
T!RB+G&N&R'T+R4
The hydrogen8cooled generator is directly coupled to the
turbine shaft rotating at speed of G;;; rpm generating electricity
at 77;;; 5olts4 The turbine is hori@ontal* three casings* reheat*
steam condensing* regenerati5e and of impulse type e2uipped
.ith a precise oil operated speed go5ernor4 The generated 5oltage
is stepped by unit po.er transformer to state grid system4
)ir"ulating =ater pump4
T.o nos4 of circulating .ater pumps pro5ided for each unit*
circulate .ater at the rate of 7F9;; T?hr4 in a closed cycle
comprising of Turbine Condenser and Cooling To.er4 An additional
Circulating Water #ump pro5ided ser5es by for t.o units4 The
.ater re2uirement for bearing cooling of all the plant au3iliaries is
also catered by these pumps4
N&&D + ' )+ND&NS&R4 A condenser .here the e3haust
steam from the turbine is condensed* operates at a pressure
lo.er than atmosphere4 There are t.o ob-ects of using a
7/23/2019 95268739 Project Report on Thermal Plant
28/63
condenser in a steam plant4 There are t.o ob-ects of using a
condenser in a steam plant:8
- To reduce the turbine e3haust pressure so as to increase the
speci=c output of turbine4 f the CW cooling .ater
temperature in a condenser is lo. enough4 t creates a bac/
pressure 5acuum for the turbine4 This pressure is e2ual to
the saturation pressure corresponding to the condensing
steam temperature4 Which is a function of cooling .ater
temperature4 t is /no.n that the enthalpy drop or turbine
.or/ per unit pressure drop is much greater at the lo.
pressure end than at the high pressure end of a turbine4
- A condenser by lo.ering the bac/ pressure say 74;7G to
;4;F bar* thus increases the plant eLciency and reduces
the steam Io. for a gi5en output4 The lo.er the pressure*
the greater the output and eLciency4 t is important to use
lo.est possible cooling .ater temperature4
This reduces the temperature rise of cooling .ater in the
condenser tubes to 8
7/23/2019 95268739 Project Report on Thermal Plant
29/63
T/P&S4There are t.o broad classi=cations:8
a Direct contact type condenser:8 .here the condensate and
cooling .ater directly mi3 and come out as a single
stream4
b Surface condenser:8 .hich are shell and tube heat
e3changers .here the t.o Iuids do not come in direct
contact and heat released by the condensation of steam is
transferred through .alls of the tubes into the cooling
.ater continuously circulating inside them4
DIR&)T )+NT')T )+ND&NS&RS4
- Spra< "ondenser
- Barometri" "ondenser
- 3et "ondenser
n the spray condenser* the cooling .ater is sprayed into the
steam4 Steam by mi3ing directly .ith cold .ater gets
condensed4 The e3haust steam from the turbine at state 9
mi3es .ith cooling .ater at state to produce saturated .ater
at state G* .hich is pumped to state 4
n barometric condenser* the cooling .ater is made to fall in
a series of baRes to e3pose large surface area for the steam
fed from belo. to come in direct contact4 The steam condenses
and falls in a tail pipe to the hot .ell belo.4 By 5irtue of its
static head* the tail pipe compresses the mi3ture to
atmospheric pressure4
7/23/2019 95268739 Project Report on Thermal Plant
30/63
n a -et condenser* the height of the tail pipe is reduced by
replacing it .ith a diJuser4 The diJuser helps raising the
pressure in a short distance than a tail pipe4
S!R')& )+ND&NS&RS4 Surface condenser is another type
of condenser used in po.er plants4 n (%,% "A"A! DE
T'E,MA$ #$A"T surface condensers are used4 These are
essentially shell and tube heat e3changers4 &or the
con5enience of cleaning and maintenance cooling .ater Io.s
through the tubes and steam condenses outside the tubes4 n
our plant surface condenses t.o passes of .ater bo3es on each
side4 The hot .ell acts as a reser5oir of the condensate4 The
condenser plays a 5ital role4 n our plant t.o surface
condensers are used in one plant1s unit4 There are >
7/23/2019 95268739 Project Report on Thermal Plant
31/63
)+ND&NS'T& )/)-&4 Steam after .or/ing in the three
casings of the turbine i4e4 '4#4* M4#4 and $4#4 casing is considered
in t.o surface condensers in each unit installed -ust belo. the
$4#4 turbine1s e3haust hood4 The condenser so to call hot .ell
from .here it is pumped up to deaerator by condensate
e3traction pumps through diJerent heating stages4 The
diJerent heating stages through .hich the condensate Io.s
and gets heated up gradually before =nally reaching the
deaerator feed .ater tan/ are as belo.:8
.&'TING ST'G& T&$P% RIS& 'T !-- -+'D
Main steam -et air e-ector G8
7/23/2019 95268739 Project Report on Thermal Plant
32/63
)+ND&NS&R4 The function of the surface condenser is to
condense the steam e3hausted from the $4#4 casing and to
create 5acuum in order to increase the heat drop4 Capacity of
each hot .ell is >9;; liters and the temperature of condensate
in the hot .ell is about ;8C4
P'RTI)!-'RS + )+ND&NS'T&4
&7TR')TI+N P!$P4
"umber of pumps: G for each unit .ith ;H capacity each* one
stand by4
"umber of stages: >
Discharge pressure: 9;4894 /g?cmK
Suction pressure: 8;4< to N;4 /g?cmK
ST&'$ 3&T 'IR &3&)T+R4
The main function of steam -et air e-ector is to maintain the5acuum in the steam condenser by e-ecting the air and non8
condensate gases4 The steam from pressure reducing station is
supplied to steam -et air e-ector4 This steam .hen passed through
the no@@les in a 5enturi de5elops pressure drop* .hich causes the
air and non considerable gases to rush from the condenser* thus
maintaining the re2uired 5acuum in the condenser4 After that heat
of this steam is utili@ed in heating up the main condensate Io.ing
through in the steam -et air e-ector4 The steam -et air e-ector is
built up in the condenser4
7/23/2019 95268739 Project Report on Thermal Plant
33/63
-+, PR&SS!R& .&'T&RS4
There are =5e numbers of $4#4 heaters through .hich the main
condensate Io.s and gets heated up gradually in each stage of
heaters before =nally going to the deaerator4
The $4#4 heaters 7 and 9 are in t.o parts and placed in the
e3haust hood of condenser i4e4 e3haust hood of $4#4 turbine and
are connected in series4 $4#4'48G* $4#4'48 and $4#4'48 are placed in
chimney steam condenser and gland steam condenser in the
condensate Io. circuit4 The charging steam to these heaters is
gi5en from the steam e3tractions ta/en from the $4#4 6 M4#4
cylinders of the turbine4 Steam e3traction to $4#4'487 is ta/en from
$4#4 casing in t.o parallel Io.s* same in $4#4'4894 Steam to $4#4'48G
is also ta/en from $4#4 casing4 Where as steam to $4#4'48 and
$4#4'48 is ta/en from M4#4 casing4
The main condensate gets heated up by about 7;;C after
passing through these heating stages4 The condensate of heating
steam in these $4#4 heaters is /no.n as drip4
).I$N&/ ST&'$ )+ND&NS&R4
t is a sort of heater in .hich .aste chimney steam* ta/en from
the outer lea/s of the gland seals of '4#4* M4#4 and $4#4 cylinders of
the turbine* is utili@ed in heating up the main condensate4 The
drip of chimney steam condenser is generally mi3ed .ith air and
is collected in impure condensate tan/ from .here it is pumped to
Ioor drains4
7/23/2019 95268739 Project Report on Thermal Plant
34/63
G-'ND ST&'$ )+ND&NS&R4
t is also a sort of heaters* steam to gland steam condenser is
ta/en from inner lea/s of the sealing glands of '4#4 and front
gland of M4#4 cylinders of the turbine and after heating the main
condensate* the drip of gland steam condenser being pure* is
directly ta/en to the hot .ell4
7/23/2019 95268739 Project Report on Thermal Plant
35/63
)ooling to=ers4
)ooling To=ers
7/23/2019 95268739 Project Report on Thermal Plant
36/63
Cooling To.ers of the po.er plant are the land mar/ of the
Bathinda City e5en for a far distance of
7/23/2019 95268739 Project Report on Thermal Plant
37/63
'sh pre"ipitators
,+R*ING PRIN)IP-& + &SP
7/23/2019 95268739 Project Report on Thermal Plant
38/63
The electrostatic precipitator installed at ("DT#*Bathinda
units to e3tract dust* utili@es electrostatic forces to separate dust
particles from the gas be cleaned4 The gas is conducted to a
chamber containing Curtains of 5ertical steel plates4 These
curtains di5ide the chamber into a number of parallel gas
passages4 A frame .ith secured .ires is located .ithin each
passage4 All the frames are lin/ed to each passage4 The frames
are lin/ed to each other to form a rigid frame.or/4
The entire frame .or/s is held in place by four support
insulators* .hich is electrically from all* .hich are grounded4
A high 5oltage direct current is applied bet.een the
frame.or/ the ground thereby creating a strong electrical =eld
bet.een the .ires in the frame.or/ and the steel curtains4 The
electrical become strongest near the surface of the .ires* so
strong that an electrical discharge4 The corona discharge
de5elops along the .ires4 The gas is ioni@ed in the corona
discharge and large 2uantity of positi5e and negati5e ions are
formed4 The positi5e ions are immediately attracted to.ards the
negati5e .ires by the strength of the =eld indicate the negati5e
ions ho.e5er ha5e to tra5erse the entire space bet.een the
electrodes to reach positi5e curtains4
Enroute to.ards the steel curtains* the ions collide and
adhere to the particles in the gas4 The particles thereby become
electrically charged and also begin to tra5el in the same direction
as the ions to.ards the steel curtains4 The electrical force on each
7/23/2019 95268739 Project Report on Thermal Plant
39/63
particle becomes much greater than the gra5itational force on the
particle4 The speed of migration to.ards to steel curtains is
therefore much greater than the speed of sedimentation in free
fall4
The Iy ash carried by outgoing Iue gases is arrested at t.o
stages4 n the mechanical precipitators* the coarse ash particles
are separated out by centrifugal action4 n the Electrostatic
#recipitators* the =ner ash particles in the Iue gases are made to
pass through high 5oltage electric =eld* .here these particles get
ioni@ed and are attracted to.ards the collecting electrodes4 The
dry ash is collected in the hoppers underneath and further
deposited oJ in Ash Disposal Area4
7/23/2019 95268739 Project Report on Thermal Plant
40/63
Pro>e"t
,ater treatment and )oal
testing
Boiler is the heart of thermal plant* its main purpose is to con5ert
.ater into steam4
"atura l . ater is a5ai lable in abundance* but it contains
impurities in many forms .hich are as follo.ing types4
Types of impuritiesU4
7/23/2019 95268739 Project Report on Thermal Plant
41/63
Water hardness is primarily because of calcium and
magnesium minerals* and hardness is responsible for
scale formation4
Carbonates or temporary hardness8 0Ca1 and 0Mg1bicarbonates are responsible for al/aline hardness* but
on applying heat release )+2 and form soft scale4
"on8Carbonates or permanent hardness8 due to presence of
salt of calcium and magnesium but in form of sulphates and
chlorides4 On applying heat these ppt4 out and form
hard scale* .hich is diLcult to remo5e4
Water Al/alinity is because of bicarbonates*
carbonates4
Al/alinity can con5ert to )+2 in steam4 This
causes corrosion4
When p' is belo. the recommended range chances of
corrosion increases* and .hen it is abo5e
recommended 5alue then chances of scaling increases4
Boiler scale lo.ers heat transfer due to lo. thermalconducti5ity4 'eat transfer may be reduced as much as
87;H by the presence of scale4
7/23/2019 95268739 Project Report on Thermal Plant
42/63
Due to s"aling #ollo=ing are the negative e?e"ts on
the =orking o# plant
a4 increased fuel bill by decreasing the operating eLciencyb4 thermal damage
c4 increased cleaning time and cleaning costs
d4 reduced .or/ing life of a boiler4
Pre Treatment o#
,ater
)anal =ater
-ake
-ake
-ake
Intake pump
7/23/2019 95268739 Project Report on Thermal Plant
43/63
)lari:er 8'lumdosing9
To ma/e .ater free from suspended* colloidal and organic
impurities*process in5ol5ed in pre8treatment are:8'9 Settling and )oagulation
Coagulant turbidity* micro8organismsreacts .ith the
al/alinity of the .ater to form a gelatinous precipitate
)lear =ell
7/23/2019 95268739 Project Report on Thermal Plant
44/63
)lear =ell
Pump )lear =ell
iii ii i
7/23/2019 95268739 Project Report on Thermal Plant
45/63
Sand ilters
Sand :lters
B9 iltration
#assage of Iuid through a porous medium using sand =lter
arrangement to remo5e matters holding suspension4
74 Suspended silt
94 Clay
G4 Colloids
4 Micro organisms including algae* bacteria and 5irus
7/23/2019 95268739 Project Report on Thermal Plant
46/63
Demineralisation
S
7/23/2019 95268739 Project Report on Thermal Plant
47/63
D$ Plant -a
7/23/2019 95268739 Project Report on Thermal Plant
48/63
)ation e@"hangermainly remo5es Calcium* Magnesium*
sulfates* chloride* nitrates and sodium salts al/alinity from
ra. .ater4
n cation e3changer positi5e ion of the salt is e3changedby the'Q ion
On discharging* it is charged .ith ;;!g of G;H'cl4
)ation &@"hanger
7/23/2019 95268739 Project Report on Thermal Plant
49/63
Carbon dio3ide generated by dissociation of carbonic acid at
cation outlet .ater* is remo5ed by degassersystem4
Water from outlet of cation e3changer is made to fall
from a height* and a pressuri@ed air is blo.n upstream
of the .ater Io. to separate gases4
Degasser Blo=er
Degasser
Tan/
7/23/2019 95268739 Project Report on Thermal Plant
50/63
'nion e@"hangersremo5e the highly dissociated acids li/e
'9So* '"oG*
'cl from the eRuent of cation e3changer4
n anion e3changer negati5e charged part of the salt is
e3changed by the O'8ion4
On discharging* it is charged .ith 9;;!g of
F4H"aO'4
'nion &@"hanger
7/23/2019 95268739 Project Report on Thermal Plant
51/63
$i@ed;ed
Deionisation
ERuent .ater after anion e3changer may still ha5e some saltsdue to them its conducti5ity is around 787 micro4mhos4 F
p' 7;* so it is further passed through Mi3ed Bed Deioniser* as
sho.n belo.4The mi3ed bed mi3ture of Cation and Anion resins
form in=nite numbers of demineralising stages through .hich DM
.ater passing and thus remo5ing the traces of minerals4 By this
method demineralised .ater of e3tremely pure 2uality is
achie5ed4
$i@ ;ed deioniser
7/23/2019 95268739 Project Report on Thermal Plant
52/63
On discharging* it is charged .ith 7;;/g in-ection of each 'cl
and "aO'4
GNDTP has 2 units o# D$ Plant( ea"h having "apa"it