OTTAWA LRT PROJECT DESIGN / PROCUREMENT / CITY CHALLENGES AND STRATEGIES Rail Implementation Office
38

923 2 wheeler_public privat partnerships

Jun 28, 2015

Download

Rail~Volution

Public-Private Partnerships: The P3 Experience AICP CM 1.5
Public-private partnerships (P3s) are on the upswing. After a strong start with vertical building delivery in the US and many transit projects in Canada, the P3 model for transit seems to be here to stay. Upcoming projects in Baltimore and Denver are piquing interest across the US. Is P3 right for your project? How have recent projects fared? Listen as panel members explore recent applications, trends and benefits of the P3 delivery method. Learn how to assess your own project in terms of the P3 model. Hear how P3 is helping accomplish broader community development, sustainability and mobility goals throughout North America.
Moderator: Bob Post, Vice President, Director of Transportation, URS, Portland, Oregon
Charles Wheeler, Senior Project Manager, URS, Richmond Hill, Ontario
Gregory P. Benz, RA, AICP, Senior Vice President, Principal, Professional Associate, Parsons Brinckerhoff, Baltimore, Maryland
Martin Nielsen, MAIBC, LEED AP, MRAIC, P.Eng., Principal, Dialog Design, Vancouver, British Columbia
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: 923 2 wheeler_public privat partnerships

OTTAWA LRT PROJECTDESIGN / PROCUREMENT / CITYCHALLENGES AND STRATEGIES

Rail Implementation Office

Page 2: 923 2 wheeler_public privat partnerships

INTRODUCTION

OLRT project is largest infrastructure project in City’s history since the Rideau Canal in 1840’s

$2.1 P3 DB project awarded to Rideau Transit Group (RTG) in February 2013

12.5 km, 13 station line extends from Blair to Tunney’s Pasture

2.5 km tunnel, 3 underground stations in the downtown core, each with 2 street level entrances

New maintenance and storage facility (MSF)

Conversion of a successful BRT to LRT a first in North America?

2

Page 3: 923 2 wheeler_public privat partnerships

3

PROJECT OVERVIEW

Procurement Approach MSF Stations

Vehicle Integrated Entrances Tunnel

DESIGN BUILD

FINANCE MAINTAIN

Page 4: 923 2 wheeler_public privat partnerships

THE CONFEDERATION LINE

4

`Maintenance andStorage Facility

Pimisi

Lyon

Parliament

Tunney’s

uOttawa

Tremblay

Page 5: 923 2 wheeler_public privat partnerships

5

WHY LRT?

Page 6: 923 2 wheeler_public privat partnerships

PROJECT CHALLENGES

City Council objectives:

“On time, on budget, fixed price” (Mayor)

Full risk transfer for geotechnical / tunnel risks

Shorten procurement process by 12 months

6

Page 7: 923 2 wheeler_public privat partnerships

PROJECT CHALLENGES Protect existing transit

operations / OC operating budget: Peak point demand of

9,300 pphpd in downtown core

Canada’s 150th Anniversary on July 2017

“Service proven” vehicle capable of operating in Ottawa climate

7

Page 8: 923 2 wheeler_public privat partnerships

PROJECT CHALLENGES High quality architectural

design in keeping with Nations Capital

TOD interest is “off the scale”

OC to operate, proponent to design, build,finance and maintain for 30 year concession period

How did we address major challenges?

8

Page 9: 923 2 wheeler_public privat partnerships

PROJECT STRATEGIES

9

A) Capital Costs / Risk Transfer

$300M in invested capital by consortium

Penalties for not providing specified service levels/quality tied to capital and maintenance payments

Encourages high quality design / construction as capital is at risk for 30 years

Allow proponents to select milestone payments from defined list

Page 10: 923 2 wheeler_public privat partnerships

PROJECT STRATEGIES

10

B) Project Readiness Date / Milestone

Ensures major downtown construction finished by Canada Day 2017

A “required” milestone / well defined scope completion

Page 11: 923 2 wheeler_public privat partnerships

PROJECT STRATEGIES

11

C) Define Service Proven Vehicle / Systems

Ensure compliance during bidding process

Service Proven Vehicle means a Vehicle that is substantially compliant with the following characteristics:1) The major vehicle sub system (including trucks, braking systems, propulsion systems,

articulation joints), have been integrated in a comparable LRV currently in revenue service; and

2) A minimum of 10 of these vehicles have been in Revenue Service for a minimum of two years; and

3) Have been operated in similar climatic conditions and service conditions to those specified for the OLRT project; and

4) Have authority data confirming that the Vehicle has attained a minimum “in-service” MDBF of 50,000 km. Failures are defined as malfunctions that cause Revenue Service delays of 4 minutes or more.

Page 12: 923 2 wheeler_public privat partnerships

PROJECT STRATEGIES

12

D) Mobility Matters (MM), Energy Matters (EM), & Operations Matters (OM)

Built into procurement / evaluation process to drive long term proponent behaviour

Add on to NPV of bids for evaluation purposes

“Pain share” / “Gain share” if targets not met

Page 13: 923 2 wheeler_public privat partnerships

DESIGN AND PROCUREMENT STRATEGIES

13

DESIGN

BUILD

FINANCE

MAINTAIN

A) Geotechnical Risk Transfer Evaluation of bids “geared” towards

proponents taking cost / schedule risk for tunnelling / geotechnical conditions

Extensive geotechnical data provided to proponents No geotechnical baseline report Financial bid incentives were varied by extent of risk

transfer

Page 14: 923 2 wheeler_public privat partnerships

DESIGN AND PROCUREMENT STRATEGIES

14

DESIGN

BUILD

FINANCE

MAINTAIN

B) Affordability Cap An important “gate” in the

procurement bid evaluation Bids need to be under the cap in order to

maximize financial adjustment to bid price An incentive to minimize capital costs of

bid in order to win financial evaluation

Page 15: 923 2 wheeler_public privat partnerships

DESIGN AND PROCUREMENT STRATEGIES

15

DESIGN

BUILD

FINANCE

MAINTAIN

C) Defined Alignment Envelope

Allows all potential construction methods

Lower limits for downtown station platforms

Page 16: 923 2 wheeler_public privat partnerships

16

Page 17: 923 2 wheeler_public privat partnerships

DESIGN AND PROCUREMENT STRATEGIES

17

DESIGN

BUILD

FINANCE

MAINTAIN

D) Defined Alignment Envelope

Downtown alignment under Canal defined by City as a requirement

Horizontal / Vertical alignment limits to drive drive shallow tunnel

Page 18: 923 2 wheeler_public privat partnerships

DESIGN AND PROCUREMENT STRATEGIES

18

DESIGN

BUILD

FINANCE

MAINTAIN

E) Defined “Station Innovation zones”

Platform can be between “x” and “y”

Minimum platform separation of “z”

Page 19: 923 2 wheeler_public privat partnerships

DESIGN AND PROCUREMENT STRATEGIES

19

DESIGN

BUILD

FINANCE

MAINTAIN

F) Integrated Station Entrances

Procurement requirements:

Two station entrances shall be integrated

Other opportunities for ISE’s identified but up to proponents

After preferred proponent selected:

Additional ISE’s negotiated with RTG / property owners (3 ISE’s)

Incorporated into contract at financial close

End result: 5 of 6 underground station entrances are integrated from start of revenue service

A significant project accomplishment!

Page 20: 923 2 wheeler_public privat partnerships

DESIGN AND PROCUREMENT STRATEGIES

20

DESIGN

BUILD

FINANCE

MAINTAIN

G) Station are Community Landmarks

Simple attractive designs

Eye-catching architectural themes throughout

Inviting & safe public spaces

Intuitive passenger flows

Integrated pedestrian pathways / MUPS

Page 21: 923 2 wheeler_public privat partnerships

PLANNING’S TOD STUDIES

21

Chris Brouwerand team

Page 22: 923 2 wheeler_public privat partnerships

TOD STUDY AREA BOUNDARIES

22

Page 23: 923 2 wheeler_public privat partnerships

TOD STUDY – TREMBLAY STATION - PLAN AREA

23

Page 24: 923 2 wheeler_public privat partnerships

TOD STUDY – TREMBLAY STATION - PEDESTRIAN

24

Page 25: 923 2 wheeler_public privat partnerships

TOD STUDY – TREMBLAY STATION - BICYCLE

25

Page 26: 923 2 wheeler_public privat partnerships

TOD STUDY – TREMBLAY STATION - STREETS

26

Page 27: 923 2 wheeler_public privat partnerships

TOD STUDY – TREMBLAY STATION – GREEN PLAN

27

Page 28: 923 2 wheeler_public privat partnerships

TOD STUDY – TREMBLAY STATION – LAND USE

28

Page 29: 923 2 wheeler_public privat partnerships

TOD STUDY – TREMBLAY STATION – DENSITY

29

Page 30: 923 2 wheeler_public privat partnerships

30

TOD STUDY – TREMBLAY STATION – TIMING

Page 31: 923 2 wheeler_public privat partnerships

RESULT OF CITY DESIGN AND SOUND PROCUREMENT STRATEGIES

31

Page 32: 923 2 wheeler_public privat partnerships

RESULT OF CITY DESIGN AND SOUND PROCUREMENT STRATEGIES

32

Page 33: 923 2 wheeler_public privat partnerships

From this…

33

Queen looking west from O’Connor

Page 34: 923 2 wheeler_public privat partnerships

… to this!

34

Page 35: 923 2 wheeler_public privat partnerships

From this…

35

MacKenzie King Bridge looking NW

Page 36: 923 2 wheeler_public privat partnerships

… to this!

36

Page 37: 923 2 wheeler_public privat partnerships

37

Thank you

Page 38: 923 2 wheeler_public privat partnerships

end

38