DAFTAR HARGA SATUAN UPAH KABUPATEN PASER BIDANG KE CIPTA KARYAAN TAHUN ANGARAN 2012 Ket NO Uraian Upah (Rp) 1 2 12 13 1 Buruh Terampil/Pekerj 55,000.00 1 hari = 7 jam kerja 2 Tukang Kayu 75,000.00 1 hari = 7 jam kerja 3 Tukang Batu 75,000.00 1 hari = 7 jam kerja 4 Tukang Besi 75,000.00 1 hari = 7 jam kerja 5 Tukang Cat 75,000.00 1 hari = 7 jam kerja 6 Kepala Tukang 80,000.00 1 hari = 7 jam kerja 7 Mandor 90,000.00 1 hari = 7 jam kerja 8 Pembantu Supir 50,000.00 1 hari = 7 jam kerja 9 Mekanik 75,000.00 1 hari = 7 jam kerja 10 Pembantu Mekanik 50,000.00 1 hari = 7 jam kerja 11 Operator 80,000.00 1 hari = 7 jam kerja 12 Pembantu Operator 50,000.00 1 hari = 7 jam kerja
57
Embed
91904162 Master Standar Bahan Upah Dan Analisa 2012 Keciptakaryaan
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
DAFTAR HARGA SATUAN UPAH KABUPATEN PASER
BIDANG KE CIPTA KARYAAN
TAHUN ANGARAN 2012
KetNO Uraian Upah
(Rp)
1 2 12 13
1 Buruh Terampil/Pekerja 55,000.00 1 hari = 7 jam kerja2 Tukang Kayu 75,000.00 1 hari = 7 jam kerja3 Tukang Batu 75,000.00 1 hari = 7 jam kerja4 Tukang Besi 75,000.00 1 hari = 7 jam kerja5 Tukang Cat 75,000.00 1 hari = 7 jam kerja6 Kepala Tukang 80,000.00 1 hari = 7 jam kerja7 Mandor 90,000.00 1 hari = 7 jam kerja8 Pembantu Supir 50,000.00 1 hari = 7 jam kerja9 Mekanik 75,000.00 1 hari = 7 jam kerja10 Pembantu Mekanik 50,000.00 1 hari = 7 jam kerja11 Operator 80,000.00 1 hari = 7 jam kerja12 Pembantu Operator 50,000.00 1 hari = 7 jam kerja
DAFTAR HARGA SATUAN MATERIAL KONSTRUKSI KABUPATEN PASER
BIDANG KE CIPTA KARYAAN
TAHUN ANGARAN 2012
Harga Galian C Benefit 10 %No Nama Barang Ukuran / Tipe Satuan Harga Dasar Ket.
Harga Galian C Benefit 10 %No Nama Barang Ukuran / Tipe Satuan Harga Dasar Ket.
CETAKAN BETON1 Batu Bata Ukuran 10 x 10 x 20 cm Buah 1,000 900 10 90 2 Glass block Ukuran 20 x 20 cm Buah 26,400 24,000 2,400 3 Loster Ukuran 10 x 20 x 20 cm Buah 6,050 5,500 550 4 Bataco Ukuran 10 x 20 x 40 cm Buah 7,700 7,000 700 5 Paving Block Abu-abu Kecil Ukuran Tbl 6 cm Buah 9,350 8,500 850 6 Paving Block Abu-abu Besar Ukuran Tbl 6 cm Buah 3,300 3,000 300 7 Buis Beton Bulat Bertulang Ukuran Ø 80 x P 50 cm x Tbl 10 Buah 412,500 375,000 37,500 8 Buis Beton Bulat Bertulang Ukuran Ø 60 x P 50 cm x Tbl 10 Buah 313,500 285,000 28,500 9 Buis Beton Bulat Bertulang Ukuran Ø 40 x P 100 cm x Tbl 10 Buah 198,000 180,000 18,000 10 Buis Beton Bulat Bertulang Ukuran Ø 30 x P 100 cm x Tbl 10 Buah 187,000 170,000 17,000 11 Buis Beton Bulat Tidak Bertulang Ukuran Ø 80 x P 50 cm x Tbl 10 Buah 165,000 150,000 15,000 12 Buis Beton Bulat Tidak Bertulang Ukuran Ø 60 x P 50 cm x Tbl 10 Buah 126,500 115,000 11,500 13 Buis Beton Bulat Tidak Bertulang Ukuran Ø 40 x P 100 cm x Tbl 10 Buah 159,500 145,000 14,500 14 Buis Beton Bulat Tidak Bertulang Ukuran Ø 30 x P 100 cm x Tbl 10 Buah 137,500 125,000 12,500
Kayu Ulin
1 Kayu Ulin Ukuran 20 cm x 20 cm x 4 m 4,950,000 4,500,000 450,000
2 Kayu Ulin Ukuran 15 cm x 15 cm x 4 m 4,950,000 4,500,000 450,000
3 Kayu Ulin Ukuran 12 cm x 12 cm x 4 m 4,950,000 4,500,000 450,000
4 Kayu Ulin Ukuran 10 cm x 10 cm x 4 m 4,950,000 4,500,000 450,000
5 Kayu Ulin Ukuran 5 cm x 10 cm x 4 m 5,500,000 5,000,000 500,000
6 Kayu Ulin Ukuran 5 cm x 7 cm x 4 m 5,500,000 5,000,000 500,000
7 Kayu Ulin Ukuran 5 cm x 5 cm x 4 m 5,720,000 5,200,000 520,000
8 Papan Ulin Ukuran 2.5 cm x 20 cm x 4 m 6,600,000 6,000,000 600,000
9 Papan Ulin Ukuran 2 cm x 10 cm x 4 m 5,500,000 5,000,000 500,000
10 Kayu Ulin Ukuran 5 cm x 20 cm x 4 m 5,500,000 5,000,000 500,000
11 Kayu Ulin Ukuran 7 cm x 14 cm x 4 m 5,500,000 5,000,000 500,000 Kayu Meranti
1 Kayu Meranti Ukuran 2 cm x 3 cm x 4 m 2,695,000 2,450,000 245,000
2 Kayu Meranti Ukuran 5 cm x 3 cm x 4 m 2,695,000 2,450,000 245,000
3 Kayu Meranti Ukuran 5 cm x 5 cm x 4 m 2,640,000 2,400,000 240,000
4 Kayu Meranti Ukuran 5 cm x 7 cm x 4 m 2,640,000 2,400,000 240,000
5 Kayu Meranti Ukuran 5 cm x 10 cm x 4 m 2,640,000 2,400,000 240,000
6 Kayu Meranti Ukuran 6 cm x 12 cm x 4 m 2,640,000 2,400,000 240,000
7 Kayu Meranti Ukuran 10 cm x 10 cm x 4 m 2,640,000 2,400,000 240,000
8 Papan Meranti Ukuran 2.5 cm x 20 cm x 4 m 2,750,000 2,500,000 250,000
9 Papan Meranti Ukuran 2 cm x 4 cm x 4 m 2,695,000 2,450,000 245,000
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
Harga Galian C Benefit 10 %No Nama Barang Ukuran / Tipe Satuan Harga Dasar Ket.
Kayu Bengkirai
1 Kayu Bengkirai Ukuran 3 cm x 5 cm x 4 m 3,520,000 3,200,000 320,000
2 Kayu Bengkirai Ukuran 5 cm x 5 cm x 4 m 3,520,000 3,200,000 320,000
3 Kayu Bengkirai Ukuran 5 cm x 7 cm x 4 m 3,520,000 3,200,000 320,000
4 Kayu Bengkirai Ukuran 5 cm x 10 cm x 4 m 3,520,000 3,200,000 320,000
5 Kayu Bengkirai Ukuran 7 cm x 14 cm x 4 m 3,520,000 3,200,000 320,000
6 Kayu Bengkirai Ukuran 10 cm x 10 cm x 4 m 3,520,000 3,200,000 320,000
7 Papan bengkirai Ukuran 2.5 cm x 20 cm x 4 m 3,850,000 3,500,000 350,000
8 Papan bengkirai Ukuran 2 cm x 20 cm x 4 m 3,850,000 3,500,000 350,000 Kayu Kawi
1 Kayu Kawi Ukuran 5 cm x 5 cm x 4 m 3,465,000 3,150,000 315,000
2 Kayu Kawi Ukuran 5 cm x 7 cm x 4 m 3,465,000 3,150,000 315,000
3 Kayu Kawi Ukuran 5 cm x 10 cm x 4 m 3,465,000 3,150,000 315,000
4 Kayu Kawi Ukuran 10 cm x 10 cm x 4 m 3,025,000 2,750,000 275,000
5 Papan Kawi Ukuran 2.5 cm x 20 cm x 4 m 3,465,000 3,150,000 315,000
6 Papan Kawi Ukuran 2 cm x 20 cm x 4 m 3,465,000 3,150,000 315,000
7 Kayu Campuran ( Bekisting) 2,200,000 2,000,000 200,000 8 Formite/penjaga jarak bekisting/spacer bh 27,500 25,000 2,500 9 Kayu .Galam Ø 10 - 12 panjang 4 m Batang 27,500 25,000 2,500
BAHAN MEBEL/MOULDING
1 Papan Moulding (Meranti) Ukuran 15 x 18 x 400 cm 2,750,000 2,500,000 250,000 2 Papan Ruiter (Meranti) Ukuran 15 x 18 x 400 cm bh 44,000 40,000 4,000 3 Kusen Kayu Bengkirai m' 63,800 58,000 5,800 4 Kusen Kayu Ulin m' 74,800 68,000 6,800 5 Jalusi Kayu m' 11,550 10,500 1,050 6 Jalusi Dinding Layar 5 Segi Buah 396,000 360,000 36,000 7 List Profille Sudut 3/5 kayu Batang 16,500 15,000 1,500
8 Lumber zering moulding Ukuran 1 x 8 x 400 cm 3,025,000 2,750,000 275,000 9 Daun Pintu Panil kayu ulin Ukuran 4 x 75 x 210 cm Buah 770,000 700,000 70,000 10 Daun Pintu Panil kayu ulin Ukuran 4 x 90 x 210 cm Buah 825,000 750,000 75,000 11 Daun Pintu Panil kayu ulin 2 Daun Ukuran 4 x 60 x 210 cm Pasang 1,595,000 1,450,000 145,000 12 Daun Pintu Panil kayu bengkirai Ukuran 4 x 75 x 210 cm Buah 660,000 600,000 60,000 13 Daun Pintu Panil kayu bengkirai Ukuran 4 x 90 x 210 cm Buah 693,000 630,000 63,000 14 Daun Pintu Panil kayu Bangkirai 2 Daun Ukuran 4 x 60 x 210 cm Pasang 1,375,000 1,250,000 125,000 15 Daun jendela bengkirai Ukuran 110 x 77 cm + Kaca Buah 302,500 275,000 27,500 16 Daun jendela bengkirai Ukuran 110 x 55 cm + Kaca Buah 302,500 275,000 27,500 17 Daun jendela ulin Ukuran 110 x 77 cm + Kaca Buah 346,500 315,000 31,500 18 Daun jendela ulin Ukuran 110 x 55 cm + Kaca Buah 346,500 315,000 31,500
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
Harga Galian C Benefit 10 %No Nama Barang Ukuran / Tipe Satuan Harga Dasar Ket.
SEWA ALAT1 CONCRETE MIXER 0.3-0.6 M3 ( Molen ) Jam 25,000.00 2 DUMP TRUCK Jam 340,000.00 3 GENERATOR SET Jam 530,000.00 4 CONCRETE VIBRATOR Jam 25,000.00 5 WATER PUMP 70-100 mm Jam 33,000.00 6 WATER TANKER 3000-4500 L. Jam 310,000.00 7 PILE DRIVER + HAMMER Jam 495,000.00 8 Alat Pancang Manual Jam 25,000.00
Keterangan :# Harga diatas merupakan harga rata - rata tertinggi pada ibukota kabupaten / pusat kecamatan
# Harga sudah termasuk :
a. keuntungan(benefit) 10%b. Restribusi tambang Galian C
ANALISA HARGA SATUANBIDANG KECIPTA KARYAAN
NO. NAMA PEKERJAAN HARGA SATUAN UPAH BAHAN JUMLAH HARGA
( Rp ) ( Rp ) ( Rp ) ( Rp ) A. Pekerjaan PersiapanA.1 1 m2 Pembersihan lapangan dan peralatan
0.1000 or Pekerja 55,000.00 5,500.00 5,500.00 0.0050 or Mandor 90,000.00 450.00 450.00
Jumlah 5,950.00 5,950.00 A.2 1 m' Pengukuran dan pemasangan bouwplank
0.0120 m3 Kayu meranti 5/7 cm 2,640,000.00 31,680.00 31,680.00 0.0200 kg Paku biasa 2 s/d 5 inchi 16,500.00 330.00 330.00 0.0070 m3 Papan kayu meranti 2.5/20 cm 2,750,000.00 19,250.00 19,250.00 0.1000 or Tukang kayu 75,000.00 7,500.00 7,500.00 0.1000 or Pekerja 55,000.00 5,500.00 5,500.00 0.0100 or Kepala tukang 80,000.00 800.00 800.00 0.0050 or Mandor 90,000.00 450.00 450.00
Jumlah 14,250.00 51,260.00 65,510.00 B. Pekerjaan BongkaranB.1 1 m3 Membongkar pasangan batu kali
0.4000 or Pekerja 55,000.00 22,000.00 22,000.00 4.0000 or Tukang batu 75,000.00 300,000.00 300,000.00
Jumlah 322,000.00 322,000.00 B.2 1 m3 Pembongkaran pasangan dinding bata
6.6670 or Pekerja 55,000.00 366,685.00 366,685.00 0.3330 or Mandor 90,000.00 29,970.00 29,970.00
Jumlah 396,655.00 396,655.00 B.3 1 m3 Pembongkaran beton bertulang
6.6670 or Pekerja 55,000.00 366,685.00 366,685.00 0.3330 or Mandor 90,000.00 29,970.00 29,970.00
Jumlah 396,655.00 396,655.00 B.4 10 m2 Mengupas plesteran lama
1.2500 or Pekerja 55,000.00 68,750.00 68,750.00 0.1250 or Mandor 90,000.00 11,250.00 11,250.00
Jumlah 80,000.00 80,000.00 Untuk 1 m2 pekerjaan bongkaran 8,000.00
B.5 10 m2 Membongkar lantai tegel/keramik untuk dipakai kembali
2.0000 or Pekerja 55,000.00 110,000.00 110,000.00 0.1000 or Mandor 90,000.00 9,000.00 9,000.00
Jumlah 119,000.00 119,000.00 Untuk 1 m2 pekerjaan bongkaran 11,900.00
B.6 1 m2 Menurunkan atap sirap/gentengyang tidak dipakai kembali
0.0542 or Pekerja 55,000.00 2,981.00 2,981.00 0.0027 or Mandor 90,000.00 243.00 243.00
Jumlah 3,224.00 3,224.00 B.7 10 m2 Menurunkan atap sirap/genteng
yang dipakai kembali2.0000 or Pekerja 55,000.00 110,000.00 110,000.00 0.1000 or Mandor 90,000.00 9,000.00 9,000.00
Jumlah 119,000.00 119,000.00 Untuk 1 m2 pekerjaan bongkaran 11,900.00
B.8 1 m3 Membongkar kayu balok loteng, kuda-kuda,gelagar jembatan,rangka rumah dll(kayu bongkaran dipakai lagi)
6.0000 or Tukang kayu 75,000.00 450,000.00 450,000.00 4.0000 or Pekerja 55,000.00 220,000.00 220,000.00 0.6000 or Kepala tukang 80,000.00 48,000.00 48,000.00 0.2000 or Mandor 90,000.00 18,000.00 18,000.00
Jumlah 736,000.00 736,000.00 B.9 1 m3 Membongkar kayu balok loteng,
kuda-kuda,gelagar jembatan,rangka rumah dll(kayu bongkaran tidak dipakai lagi)
1.0000 or Pekerja 55,000.00 55,000.00 55,000.00 0.2000 or Mandor 90,000.00 18,000.00 18,000.00
Jumlah 73,000.00 73,000.00 B.10 10 m2 Membongkar atap seng
0.5000 or Pekerja 55,000.00 27,500.00 27,500.00 1.0000 or Mandor 90,000.00 90,000.00 90,000.00
Jumlah 117,500.00 117,500.00 Untuk 1 m2 pekerjaan bongkaran 11,750.00
B.11 10 m2 Menurunkan rangka atap dari kayu(kayu bongkaran dipakai lagi)
0.6000 or Tukang kayu 75,000.00 45,000.00 45,000.00 2.0000 or Pekerja 55,000.00 110,000.00 110,000.00 0.0600 or Kepala tukang 80,000.00 4,800.00 4,800.00 0.1000 or Mandor 90,000.00 9,000.00 9,000.00
Jumlah 168,800.00 168,800.00 Untuk 1 m2 pekerjaan bongkaran 16,880.00
NO. NAMA PEKERJAAN HARGA SATUAN UPAH BAHAN JUMLAH HARGA
( Rp ) ( Rp ) ( Rp ) ( Rp )
B.12 1 m2 Menurunkan rangka atap dari kayu(kayu bongkaran tidak dipakai lagi)
2.0000 or Pekerja 55,000.00 110,000.00 110,000.00 0.1000 or Mandor 90,000.00 9,000.00 9,000.00
Jumlah 119,000.00 119,000.00 Untuk 1 m2 pekerjaan bongkaran 11,900.00
C. Pekerjaan TanahC.1 1 m3 Galian tanah biasa sedalam 1 m'
0.7500 or Pekerja 55,000.00 41,250.00 41,250.00 0.0250 or Mandor 90,000.00 2,250.00 2,250.00
Jumlah 43,500.00 43,500.00 C.2 1 m3 Galian tanah biasa sedalam 2 m'
0.9000 or Pekerja 55,000.00 49,500.00 49,500.00 0.0450 or Mandor 90,000.00 4,050.00 4,050.00
Jumlah 53,550.00 53,550.00 C.3 1 m3 Galian tanah biasa sedalam 3 m'
1.0500 or Pekerja 55,000.00 57,750.00 57,750.00 0.0670 or Mandor 90,000.00 6,030.00 6,030.00
Jumlah 63,780.00 63,780.00 C.4 1 m3 Menggali tanah keras sedalam 1 m'
1.0000 or Pekerja 55,000.00 55,000.00 55,000.00 0.0320 or Mandor 90,000.00 2,880.00 2,880.00
Jumlah 57,880.00 57,880.00 C.5 1 m3 Menggali tanah yang banyak batu bundar
0.8571 or Pekerja 55,000.00 47,140.50 47,140.50 0.0429 or Mandor 90,000.00 3,861.00 3,861.00
Jumlah 51,001.50 51,001.50 C.6 1 m3 Menggali tanah lumpur
0.7895 or Pekerja 55,000.00 43,422.50 43,422.50 0.0395 or Mandor 90,000.00 3,555.00 3,555.00
Jumlah 46,977.50 46,977.50 C.7 1 m3 Menggali tanah lumpur sedalam 1 m'
1.2000 or Pekerja 55,000.00 66,000.00 66,000.00 0.0450 or Mandor 90,000.00 4,050.00 4,050.00
Jumlah 70,050.00 70,050.00 C.8 1 m3 Menggali tanah cadas sedalam 1 m'
1.5000 or Pekerja 55,000.00 82,500.00 82,500.00 0.0600 or Mandor 90,000.00 5,400.00 5,400.00
Jumlah 87,900.00 87,900.00 C.9 1 m3 Membuang tanah sejauh 15 m'
0.3300 or Pekerja 55,000.00 18,150.00 18,150.00 0.0100 or Mandor 90,000.00 900.00 900.00
Jumlah 19,050.00 19,050.00 C.10 1 m3 Urugan tanah kembali
1/3 m3 Pekerjaan Galian Tanah (C.1) 43,500.00 14,500.00 14,500.00 Jumlah 14,500.00 14,500.00
C.11 1 m3 Urugan tanah pilihan1.2000 m3 Tanah urug 38,550.00 46,260.00 46,260.00 0.3000 or Pekerja 55,000.00 16,500.00 16,500.00 0.0150 or Mandor 90,000.00 1,350.00 1,350.00
Jumlah 17,850.00 46,260.00 64,110.00 C.12 1 m3 Urugan pasir
1.2000 m3 Pasir urug 94,000.00 112,800.00 112,800.00 0.3000 or Pekerja 55,000.00 16,500.00 16,500.00 0.0100 or Mandor 90,000.00 900.00 900.00
Jumlah 17,400.00 112,800.00 130,200.00 C.13 1 m3 Memadatkan tanah per-20 cm
0.5000 or Pekerja 55,000.00 27,500.00 27,500.00 0.0500 or Mandor 90,000.00 4,500.00 4,500.00
Jumlah 32,000.00 32,000.00 C.14 1 m2 Memasang lapisan ijuk tebal 10 cm untuk bidang resapan
6.0000 kg Ijuk 16,500.00 99,000.00 99,000.00 0.1500 or Pekerja 55,000.00 8,250.00 8,250.00 0.0150 or Mandor 90,000.00 1,350.00 1,350.00
Jumlah 9,600.00 99,000.00 108,600.00 C.15 1 m2 Memasang sirtu padat untuk peninggian lantai bangunan
1.2000 m3 Sirtu 151,000.00 181,200.00 181,200.00 0.2500 or Pekerja 55,000.00 13,750.00 13,750.00 0.0250 or Mandor 90,000.00 2,250.00 2,250.00
Jumlah 16,000.00 181,200.00 197,200.00
NO. NAMA PEKERJAAN HARGA SATUAN UPAH BAHAN JUMLAH HARGA
( Rp ) ( Rp ) ( Rp ) ( Rp )
D Pekerjaan Tiang PancangD.1 Memancang tiang per m` - 20/20, tanah lunak
(dihitung bagian yang masuk tanah)0.1250 or Tukang kayu 75,000.00 9,375.00 9,375.00 0.2917 or Pekerja 55,000.00 16,043.50 16,043.50 0.0125 or Kepala tukang kayu 80,000.00 1,000.00 1,000.00 0.0007 or Mandor 90,000.00 63.00 63.00 1.0000 ls Sewa alat Pancang 25,000.00 25,000.00 25,000.00
Jumlah 26,481.50 25,000.00 51,481.50 D.2 1 m1 Tanah biasa - 20/20
1.2500 Upah (D.1) 51,481.50 64,351.88 64,351.88 Jumlah 64,351.88 64,351.88
D.3 1 m1 Tanah keras - 20/201.5000 Upah (D.1) 51,481.50 77,222.25 77,222.25
Jumlah 77,222.25 77,222.25 D.4 1 m1 Tanah keras - 10/10
1.0000 Upah (D.1) 51,481.50 51,481.50 51,481.50 Jumlah 51,481.50 51,481.50
Jumlah 102,963.00 102,963.00 D.6 1 m1 Tanah pasir - 10/10
2.6667 Upah (D.1) 51,481.50 137,285.72 137,285.72 Jumlah 137,285.72 137,285.72
D.7 1 bh membuat cincin kepala tiang pancang & dilancipkan balok kayu ulin ukuran 20/20 cm
0.2250 or Tukang kayu 75,000.00 16,875.00 16,875.00 0.0750 or Pekerja 55,000.00 4,125.00 4,125.00 0.0225 or Kepala tukang kayu 80,000.00 1,800.00 1,800.00 0.0038 or Mandor 90,000.00 342.00 342.00
Jumlah 23,142.00 23,142.00 D.8 1 bh Membuat cincin kepala tiang pancang &
Jumlah 11,571.00 11,571.00 D.9 Membuat cincin kepala tiang pancang &
dilancipkan kayu galam dia 12 - 20 cm0.5000 Upah (D.7) 11,571.00 5,785.50 5,785.50
Jumlah 5,785.50 5,785.50 D.10 1 bh Membuat sunduk pada pancang kayu 5/7-50 cm
0.0019 m3 Kayu ulin 5,500,000.00 10,450.00 10,450.00 0.0600 or Tukang kayu 75,000.00 4,500.00 4,500.00 0.0600 or Pekerja 55,000.00 3,300.00 3,300.00 0.0060 or Kepala tukang kayu 80,000.00 480.00 480.00 0.0030 or Mandor 90,000.00 270.00 270.00
Jumlah 8,550.00 10,450.00 19,000.00 D.11 1 psg Membuat pen dan lobang pada
tiap kepala kayu (tiap-tiap pasang)0.2000 Tukang kayu 75,000.00 15,000.00 15,000.00 0.0200 Kepala tukang kayu 80,000.00 1,600.00 1,600.00
Jumlah 16,600.00 16,600.00 E Pekerjaan Pondasi
E.1 1 m3 Memasang batu kosong / Aanstamping 1.2000 m3 Batu belah ( 15 s/d 20) cm 204,800.00 245,760.00 245,760.00 0.4320 m3 Pasir urug 94,000.00 40,608.00 40,608.00 0.3900 or Tukang batu 75,000.00 29,250.00 29,250.00 0.7800 or Pekerja 55,000.00 42,900.00 42,900.00 0.0390 or Kepala tukang 80,000.00 3,120.00 3,120.00 0.0390 or Mandor 90,000.00 3,510.00 3,510.00
Jumlah 78,780.00 286,368.00 365,148.00 E.2 1 m3 Memasang pondasi batu belah campuran 1 : 3
1.2000 m3 Batu belah ( 15 s/d 20) cm 204,800.00 245,760.00 245,760.00 0.4850 m3 Pasir pasang 100,600.00 48,791.00 48,791.00
202.0000 kg Semen Pc 50 kg 1,342.00 271,084.00 271,084.00 0.7500 or Tukang batu 75,000.00 56,250.00 56,250.00 1.5000 or Pekerja 55,000.00 82,500.00 82,500.00 0.0750 or Kepala tukang 80,000.00 6,000.00 6,000.00 0.0750 or Mandor 90,000.00 6,750.00 6,750.00
Jumlah 151,500.00 565,635.00 717,135.00 E.3 1 m3 Memasang pondasi batu belah campuran 1 : 4
1.2000 m3 Batu belah ( 15 s/d 20) cm 204,800.00 245,760.00 245,760.00 0.5200 m3 Pasir pasang 100,600.00 52,312.00 52,312.00
163.0000 kg Semen Pc 50 kg 1,342.00 218,746.00 218,746.00 0.7500 or Tukang batu 75,000.00 56,250.00 56,250.00 1.5000 or Pekerja 55,000.00 82,500.00 82,500.00 0.0750 or Kepala tukang 80,000.00 6,000.00 6,000.00 0.0750 or Mandor 90,000.00 6,750.00 6,750.00
Jumlah 151,500.00 516,818.00 668,318.00
NO. NAMA PEKERJAAN HARGA SATUAN UPAH BAHAN JUMLAH HARGA
( Rp ) ( Rp ) ( Rp ) ( Rp )
E.4 1 m3 Rangka bawah dari kayu ulin(tongkat, sunduk)
1.1000 m3 Kayu ulin 4,950,000.00 5,445,000.00 5,445,000.00 9.0000 or Tukang kayu 75,000.00 675,000.00 675,000.00 9.0000 or Pekerja 55,000.00 495,000.00 495,000.00 0.9000 or Kepala tukang 80,000.00 72,000.00 72,000.00 0.4500 or Mandor 90,000.00 40,500.00 40,500.00 1.0000 ls Alat bantu (Bor listrik, dll) 20,000.00 20,000.00 20,000.00
Jumlah 1,282,500.00 5,465,000.00 6,747,500.00 F Pekerjaan Rangka Kayu
F.1 1 m3 Mengerjakan sloof dan lenger1.1000 m3 Kayu ulin 4,950,000.00 5,445,000.00 5,445,000.00 5.2238 kg Paku ulin 22,000.00 114,923.60 114,923.60
10.0000 or Tukang kayu 75,000.00 750,000.00 750,000.00 6.0000 or Pekerja 55,000.00 330,000.00 330,000.00 1.0000 or Kepala tukang 80,000.00 80,000.00 80,000.00 0.3000 or Mandor 90,000.00 27,000.00 27,000.00 1.0000 ls Alat bantu (Bor listrik, dll) 25,000.00 25,000.00 25,000.00
1.1000 m3 Kayu meranti 2,640,000.00 2,904,000.00 2,904,000.00 2.6493 kg Paku kayu 16,500.00 43,713.45 43,713.45
12.0000 or Tukang kayu 75,000.00 900,000.00 900,000.00 5.7143 or Pekerja 55,000.00 314,286.50 314,286.50 2.5000 or Kepala tukang 80,000.00 200,000.00 200,000.00 0.4688 or Mandor 90,000.00 42,192.00 42,192.00 1.0000 ls Alat bantu (mesin ketam, dll) 30,000.00 30,000.00 30,000.00
Jumlah 1,456,478.50 2,977,713.45 4,434,191.95 F.3 1 m3 Mengerjakan rangka rumah kayu ulin
1.1000 m3 Kayu ulin 4,950,000.00 5,445,000.00 5,445,000.00 2.6493 kg Paku ulin 22,000.00 58,284.60 58,284.60
25.0000 or Tukang kayu 75,000.00 1,875,000.00 1,875,000.00 9.3750 or Pekerja 55,000.00 515,625.00 515,625.00 2.5000 or Kepala tukang 80,000.00 200,000.00 200,000.00 0.4688 or Mandor 90,000.00 42,192.00 42,192.00 1.0000 ls Mesin ketam 30,000.00 30,000.00 30,000.00
Jumlah 2,632,817.00 5,533,284.60 8,166,101.60 G. Pekerjaan StrukturG.1 1 m2 Memasang bekisting untuk pondasi
0.0400 m3 Papan kayu klas III 2,200,000.00 88,000.00 88,000.00 0.3000 kg Paku 5 s/d 10 cm 16,500.00 4,950.00 4,950.00 0.1000 ltr Minyak bekisting 9,900.00 990.00 990.00 0.2600 or Tukang kayu 75,000.00 19,500.00 19,500.00 0.5200 or Pekerja 55,000.00 28,600.00 28,600.00 0.0260 or Kepala tukang 80,000.00 2,080.00 2,080.00 0.0260 or Mandor 90,000.00 2,340.00 2,340.00
Jumlah 50,180.00 93,940.00 146,460.00 Untuk bekisting 2 x pakai 73,230.00
G.2 1 m2 Memasang bekisting untuk sloof 0.0450 m3 Papan kayu klas III 2,200,000.00 99,000.00 99,000.00 0.3000 kg Paku 5 s/d 10 cm 16,500.00 4,950.00 4,950.00 0.1000 ltr Minyak bekisting 9,900.00 990.00 990.00
0.2600 or Tukang kayu 75,000.00 19,500.00 19,500.00 0.5200 or Pekerja 55,000.00 28,600.00 28,600.00 0.0260 or Kepala tukang 80,000.00 2,080.00 2,080.00 0.0260 or Mandor 90,000.00 2,340.00 2,340.00
Jumlah 50,180.00 104,940.00 157,460.00 Untuk bekisting 2 x pakai 78,730.00
G.3 1 m2 Memasang bekisting untuk kolom 0.0400 m3 Papan kayu klas III 2,200,000.00 88,000.00 88,000.00 0.4000 kg Paku 5 cm s/d 12 cm 16,500.00 6,600.00 6,600.00 0.2000 ltr Minyak bekisting 9,900.00 1,980.00 1,980.00 0.0150 m3 Balok kayu klas II 2,640,000.00 39,600.00 39,600.00 0.3500 lbr Plywood tebal 9 mm 167,200.00 58,520.00 58,520.00 2.0000 btg 27,500.00 55,000.00 55,000.00
panjang 4m'0.3300 or Tukang kayu 75,000.00 24,750.00 24,750.00 0.6600 or Pekerja 55,000.00 36,300.00 36,300.00 0.0330 or Kepala tukang 80,000.00 2,640.00 2,640.00 0.0330 or Mandor 90,000.00 2,970.00 2,970.00
Jumlah 63,690.00 249,700.00 316,360.00 Untuk bekisting 2 x pakai 158,180.00
Dolken kayu galam, Ø (8 - 10) cm,
NO. NAMA PEKERJAAN HARGA SATUAN UPAH BAHAN JUMLAH HARGA
( Rp ) ( Rp ) ( Rp ) ( Rp )
G.4 1 m2 Memasang bekisting untuk balok 0.0400 m3 Papan kayu klas III 2,200,000.00 88,000.00 88,000.00 0.4000 kg Paku 5 cm s/d 12 cm 16,500.00 6,600.00 6,600.00 0.2000 ltr Minyak bekisting 9,900.00 1,980.00 1,980.00 0.0180 m3 Balok kayu klas II 2,640,000.00 47,520.00 47,520.00 0.3500 lbr Plywood tebal 9 mm 167,200.00 58,520.00 58,520.00 2.0000 btg 27,500.00 55,000.00 55,000.00
panjang 4m'0.3300 or Tukang kayu 75,000.00 24,750.00 24,750.00 0.6600 or Pekerja 55,000.00 36,300.00 36,300.00 0.0330 or Kepala tukang 80,000.00 2,640.00 2,640.00 0.0330 or Mandor 90,000.00 2,970.00 2,970.00
Jumlah 63,690.00 257,620.00 324,280.00 Untuk bekisting 2 x pakai 162,140.00
G.5 1 m2 Memasang bekisting untuk plat lantai0.0400 m3 Papan kayu klas III 2,200,000.00 88,000.00 88,000.00 0.4000 kg Paku 5 cm s/d 12 cm 16,500.00 6,600.00 6,600.00 0.2000 ltr Minyak bekisting 9,900.00 1,980.00 1,980.00 0.0150 m3 Balok kayu klas II 2,640,000.00 39,600.00 39,600.00 0.3500 lbr Plywood tebal 9 mm 167,200.00 58,520.00 58,520.00 6.0000 btg 27,500.00 165,000.00 165,000.00
panjang 4m'0.3300 or Tukang kayu 75,000.00 24,750.00 24,750.00 0.6600 or Pekerja 55,000.00 36,300.00 36,300.00 0.0330 or Kepala tukang 80,000.00 2,640.00 2,640.00 0.0330 or Mandor 90,000.00 2,970.00 2,970.00
Jumlah 63,690.00 359,700.00 426,360.00 Untuk bekisting 2 x pakai 213,180.00
G.6 1 m2 Memasang bekisting untuk dinding 0.0300 m3 Papan kayu klas III 2,200,000.00 66,000.00 66,000.00 0.4000 kg Paku 5 cm s/d 12 cm 16,500.00 6,600.00 6,600.00 0.2000 ltr Minyak bekisting 9,900.00 1,980.00 1,980.00 0.0200 m3 Balok kayu klas II 2,640,000.00 52,800.00 52,800.00 0.3500 lbr Plywood tebal 9 mm 167,200.00 58,520.00 58,520.00 3.0000 btg 27,500.00 82,500.00 82,500.00
panjang 4m'4.0000 bh Formite/penjaga jarak bekisting/ 27,500.00 110,000.00 110,000.00
spacer0.3300 or Tukang kayu 75,000.00 24,750.00 24,750.00 0.6600 or Pekerja 55,000.00 36,300.00 36,300.00 0.0330 or Kepala tukang 80,000.00 2,640.00 2,640.00 0.0330 or Mandor 90,000.00 2,970.00 2,970.00
Jumlah 63,690.00 378,400.00 445,060.00 Untuk bekisting 2 x pakai 222,530.00
G.7 1 m2 Memasang bekisting untuk tangga 0.0300 m3 Papan kayu klas III 2,200,000.00 66,000.00 66,000.00 0.4000 kg Paku 5 cm s/d 12 cm 16,500.00 6,600.00 6,600.00 0.1500 ltr Minyak bekisting 9,900.00 1,485.00 1,485.00 0.0150 m3 Balok kayu klas II 2,640,000.00 39,600.00 39,600.00 0.3500 lbr Plywood tebal 9 mm 167,200.00 58,520.00 58,520.00 2.0000 btg 27,500.00 55,000.00 55,000.00
panjang 4m'0.3300 or Tukang kayu 75,000.00 24,750.00 24,750.00 0.6600 or Pekerja 55,000.00 36,300.00 36,300.00 0.0330 or Kepala tukang 80,000.00 2,640.00 2,640.00 0.0330 or Mandor 90,000.00 2,970.00 2,970.00
Jumlah 63,690.00 227,205.00 293,865.00 Untuk bekisting 2 x pakai 146,932.50
G.8 1 m2 Memasang jembatan untuk pengecoran beton 0.0264 m3 Papan kayu klas III 2,200,000.00 58,080.00 58,080.00 0.6000 kg Paku 5 cm s/d 12 cm 16,500.00 9,900.00 9,900.00 0.5000 btg Dolken kayu galam (kasau), 27,500.00 13,750.00 13,750.00
Ø (8 - 10) cm, panjang 4m'0.0500 or Tukang kayu 75,000.00 3,750.00 3,750.00 0.1500 or Pekerja 55,000.00 8,250.00 8,250.00 0.0050 or Kepala tukang 80,000.00 400.00 400.00 0.0080 or Mandor 90,000.00 720.00 720.00
Jumlah 13,120.00 81,730.00 94,850.00
Dolken kayu galam, Ø (8 - 10) cm,
Dolken kayu galam, Ø (8 - 10) cm,
Dolken kayu galam, Ø (8 - 10) cm,
Dolken kayu galam, Ø (8 - 10) cm,
NO. NAMA PEKERJAAN HARGA SATUAN UPAH BAHAN JUMLAH HARGA
336.0000 kg Semen Pc 50 kg 1,342.00 450,912.00 450,912.00 350.0000 ltr Air bersih 39.60 13,860.00 13,860.00
0.3500 or Tukang batu 75,000.00 26,250.00 26,250.00 2.0000 or Pekerja 55,000.00 110,000.00 110,000.00 0.0350 or Kepala tukang 80,000.00 2,800.00 2,800.00 0.1000 or Mandor 90,000.00 9,000.00 9,000.00 1.0000 ls alat bantu pengecoran 100,600.00 100,600.00 100,600.00
218.0000 kg Semen Pc 50 kg 1,342.00 292,556.00 292,556.00 350.0000 ltr Air bersih 39.60 13,860.00 13,860.00
0.2500 or Tukang batu 75,000.00 18,750.00 18,750.00 1.6500 or Pekerja 55,000.00 90,750.00 90,750.00 0.0250 or Kepala tukang 80,000.00 2,000.00 2,000.00 0.0800 or Mandor 90,000.00 7,200.00 7,200.00 1.0000 ls alat bantu pengecoran 100,600.00 100,600.00 100,600.00
Jumlah 118,700.00 522,836.00 742,136.00 G.11
0.7756 m3 Batu pecah 2-3 cm 395,000.00 306,344.44 306,344.44 0.5983 m3 Pasir beton 105,000.00 62,820.00 62,820.00
371.0000 kg Semen Pc 50 kg 1,342.00 497,882.00 497,882.00 215.0000 ltr Air bersih 39.60 8,514.00 8,514.00
0.2750 or Tukang batu 75,000.00 20,625.00 20,625.00 1.6500 or Pekerja 55,000.00 90,750.00 90,750.00 0.0280 or Kepala tukang 80,000.00 2,240.00 2,240.00 0.0830 or Mandor 90,000.00 7,470.00 7,470.00 1.0000 ls alat bantu pengecoran 100,600.00 100,600.00 100,600.00
Jumlah 121,085.00 875,560.44 1,097,245.44 G.12 10 kg Pekerjaan pembesian dengan besi polos
10.5000 kg Besi beton polos 12,533.69 131,603.77 131,603.77 0.1500 kg kawat beton 23,100.00 3,465.00 3,465.00 0.0700 or Tukang besi 75,000.00 5,250.00 5,250.00 0.0700 or Pekerja 55,000.00 3,850.00 3,850.00 0.0070 or Kepala tukang 80,000.00 560.00 560.00 0.0040 or Mandor 90,000.00 360.00 360.00
Jumlah 10,020.00 135,068.77 145,088.77 Untuk 1 kg pembesian besi polos 14,508.88
G.13 10 kg Pekerjaan pembesian dengan besi ulir 10.5000 kg Besi beton ulir 16,687.50 175,218.75 175,218.75 0.1500 kg kawat beton 23,100.00 3,465.00 3,465.00 0.0700 or Tukang besi 75,000.00 5,250.00 5,250.00 0.0700 or Pekerja 55,000.00 3,850.00 3,850.00 0.0070 or Kepala tukang 80,000.00 560.00 560.00 0.0040 or Mandor 90,000.00 360.00 360.00
Jumlah 10,020.00 178,683.75 188,703.75 Untuk 1 kg pembesian besi ulir 18,870.38
G.14 Peralatan tambahan untuk 1 m3Beton mutu K-225, K-275, K-350
1.9640 jam Cone mixer (molen) 25,000.00 49,100.00 49,100.00jam Water tanker
1.9600 jam Cone vibrator 25,000.00 49,000.00 49,000.001.0000 ls Alat bantu tukang batu 2,500.00 2,500.00 2,500.00
Jumlah 100,600.00 100,600.00
H. Pekerjaan DindingH.1 1 m2 Pasangan batu bata 1 : 2, tebal 1 bata
100.0000 bh Batu bata 1,000.00 100,000.00 100,000.00 0.0800 m3 Pasir pasang 100,600.00 8,048.00 8,048.00
43.5000 kg Semen Pc 50 kg 1,342.00 58,377.00 58,377.00 0.2000 or Tukang batu 75,000.00 15,000.00 15,000.00 0.6000 or Pekerja 55,000.00 33,000.00 33,000.00 0.0200 or Kepala tukang 80,000.00 1,600.00 1,600.00 0.0300 or Mandor 90,000.00 2,700.00 2,700.00
Jumlah 52,300.00 166,425.00 218,725.00 H.2 1 m2 Pasangan batu bata 1 : 2, tebal 1/2 bata
50.0000 bh Batu bata 1,000.00 50,000.00 50,000.00 0.0380 m3 Pasir pasang 100,600.00 3,822.80 3,822.80
18.9500 kg Semen Pc 50 kg 1,342.00 25,430.90 25,430.90 0.1000 or Tukang batu 75,000.00 7,500.00 7,500.00 0.3000 or Pekerja 55,000.00 16,500.00 16,500.00 0.0100 or Kepala tukang 80,000.00 800.00 800.00 0.0150 or Mandor 90,000.00 1,350.00 1,350.00
NO. NAMA PEKERJAAN HARGA SATUAN UPAH BAHAN JUMLAH HARGA
( Rp ) ( Rp ) ( Rp ) ( Rp )
H.3 1 m2 Pasangan batu bata 1 : 4, tebal 1 bata100.0000 bh Batu bata 1,000.00 100,000.00 100,000.00
0.0930 m3 Pasir pasang 100,600.00 9,355.80 9,355.80 26.5500 kg Semen Pc 50 kg 1,342.00 35,630.10 35,630.10 0.2000 or Tukang batu 75,000.00 15,000.00 15,000.00 0.6000 or Pekerja 55,000.00 33,000.00 33,000.00 0.0200 or Kepala tukang 80,000.00 1,600.00 1,600.00 0.0300 or Mandor 90,000.00 2,700.00 2,700.00
Jumlah 52,300.00 144,985.90 197,285.90 H.4 1 m2 Pasangan batu bata 1 : 4, tebal 1/2 bata
50.0000 bh Batu bata 1,000.00 50,000.00 50,000.00 0.0430 m3 Pasir pasang 100,600.00 4,325.80 4,325.80
11.5000 kg Semen Pc 50 kg 1,342.00 15,433.00 15,433.00 0.1000 or Tukang batu 75,000.00 7,500.00 7,500.00 0.3000 or Pekerja 55,000.00 16,500.00 16,500.00 0.0100 or Kepala tukang 80,000.00 800.00 800.00 0.0150 or Mandor 90,000.00 1,350.00 1,350.00
Jumlah 26,150.00 69,758.80 95,908.80 H.5 1 m2 Memasang plesteran 1 : 2, tebal 15 mm
0.0200 m3 Pasir pasang 100,600.00 2,012.00 2,012.00 10.2240 kg Semen Pc 50 kg 1,342.00 13,720.61 13,720.61 0.1500 or Tukang batu 75,000.00 11,250.00 11,250.00 0.3000 or Pekerja 55,000.00 16,500.00 16,500.00 0.0150 or Kepala tukang 80,000.00 1,200.00 1,200.00 0.0150 or Mandor 90,000.00 1,350.00 1,350.00
Jumlah 30,300.00 15,732.61 46,032.61 H.6 1 m2 Memasang plesteran 1 : 4, tebal 15 mm
0.0240 m3 Pasir pasang 100,600.00 2,414.40 2,414.40 6.2400 kg Semen Pc 50 kg 1,342.00 8,374.08 8,374.08 0.1500 or Tukang batu 75,000.00 11,250.00 11,250.00 0.3000 or Pekerja 55,000.00 16,500.00 16,500.00 0.0150 or Kepala tukang 80,000.00 1,200.00 1,200.00 0.0150 or Mandor 90,000.00 1,350.00 1,350.00
Jumlah 30,300.00 10,788.48 41,088.48 H.7 1 m2 Memasang plesteran 1 : 2, tebal 20 mm
0.0270 m3 Pasir pasang 100,600.00 2,716.20 2,716.20 13.6320 kg Semen Pc 50 kg 1,342.00 18,294.14 18,294.14 0.2000 or Tukang batu 75,000.00 15,000.00 15,000.00 0.4000 or Pekerja 55,000.00 22,000.00 22,000.00 0.0200 or Kepala tukang 80,000.00 1,600.00 1,600.00 0.0220 or Mandor 90,000.00 1,980.00 1,980.00
Jumlah 40,580.00 21,010.34 61,590.34 H.8 1 m2 Memasang plesteran 1 : 4, tebal 20 mm
0.0320 m3 Pasir pasang 100,600.00 3,219.20 3,219.20 8.3200 kg Semen Pc 50 kg 1,342.00 11,165.44 11,165.44 0.2000 or Tukang batu 75,000.00 15,000.00 15,000.00 0.4000 or Pekerja 55,000.00 22,000.00 22,000.00 0.0200 or Kepala tukang 80,000.00 1,600.00 1,600.00 0.0220 or Mandor 90,000.00 1,980.00 1,980.00
Jumlah 40,580.00 14,384.64 54,964.64 H.9 1 m2 Memasang acian dinding
3.2500 kg Semen Pc 50 kg 1,342.00 4,361.50 4,361.50 0.1000 or Tukang batu 75,000.00 7,500.00 7,500.00 0.2000 or Pekerja 55,000.00 11,000.00 11,000.00 0.0100 or Kepala tukang 80,000.00 800.00 800.00 0.0100 or Mandor 90,000.00 900.00 900.00
Jumlah 20,200.00 4,361.50 24,561.50 H.10 1 m' Pekerjaan nat tali air 1 : 3
0.0086 m3 Pasir pasang 100,600.00 865.16 865.16 0.0770 zak Semen Pc 50 kg 67,100.00 5,166.70 5,166.70 0.0600 or Tukang batu 75,000.00 4,500.00 4,500.00 0.1600 or Pekerja 55,000.00 8,800.00 8,800.00 0.0060 or Kepala tukang 80,000.00 480.00 480.00 0.0250 or Mandor 90,000.00 2,250.00 2,250.00
Jumlah 16,030.00 5,166.70 21,196.70 H.11 1 m2 Dinding keramik 20 x 20
26.5000 bh Keramik 20 x 20 2,464.00 65,296.00 65,296.00 0.0180 m3 Pasir pasang 100,600.00 1,810.80 1,810.80 9.3000 kg Semen Pc 50 kg 1,342.00 12,480.60 12,480.60 1.9400 kg Semen warna 2,860.00 5,548.40 5,548.40 0.4500 or Tukang batu 75,000.00 33,750.00 33,750.00 0.9000 or Pekerja 55,000.00 49,500.00 49,500.00 0.0450 or Kepala tukang 80,000.00 3,600.00 3,600.00 0.0450 or Mandor 90,000.00 4,050.00 4,050.00
Jumlah 90,900.00 85,135.80 176,035.80
NO. NAMA PEKERJAAN HARGA SATUAN UPAH BAHAN JUMLAH HARGA
( Rp ) ( Rp ) ( Rp ) ( Rp )
H.12 1 m2 Dinding keramik 30 x 301.0000 dos Keramik 30 x 30 60,500.00 60,500.00 60,500.00 0.0171 m3 Pasir pasang 100,600.00 1,720.26 1,720.26 0.1416 zak Semen Pc 50 kg 67,100.00 9,501.36 9,501.36 0.0140 kg Semen warna 2,860.00 40.04 40.04 0.6000 or Tukang batu 75,000.00 45,000.00 45,000.00 0.9000 or Pekerja 55,000.00 49,500.00 49,500.00 0.0600 or Kepala tukang 80,000.00 4,800.00 4,800.00 0.0450 or Mandor 90,000.00 4,050.00 4,050.00
Jumlah 103,350.00 71,761.66 175,111.66 H.13 1 m2 Dinding keramik 20 x 25
1.0000 dos Keramik 20 x 25 61,600.00 61,600.00 61,600.00 0.0171 m3 Pasir pasang 100,600.00 1,720.26 1,720.26 0.1416 zak Semen Pc 50 kg 67,100.00 9,501.36 9,501.36 0.0140 kg Semen warna 2,860.00 40.04 40.04 0.6000 or Tukang batu 75,000.00 45,000.00 45,000.00 0.9000 or Pekerja 55,000.00 49,500.00 49,500.00 0.0600 or Kepala tukang 80,000.00 4,800.00 4,800.00 0.0450 or Mandor 90,000.00 4,050.00 4,050.00
Jumlah 103,350.00 72,861.66 176,211.66 H.14 1 m' Plint keramik 10 x 20
5.0000 bh Plint keramik 10 x 20 7,700.00 38,500.00 38,500.00 0.0017 m3 Pasir pasang 100,600.00 171.02 171.02 0.0200 zak Semen Pc 50 kg 67,100.00 1,342.00 1,342.00 0.0058 kg Semen warna 11,000.00 63.80 63.80 0.1000 or Tukang batu 75,000.00 7,500.00 7,500.00 0.0500 or Pekerja 55,000.00 2,750.00 2,750.00 0.0100 or Kepala tukang 80,000.00 800.00 800.00 0.0025 or Mandor 90,000.00 225.00 225.00
. Jumlah 11,275.00 40,076.82 51,351.82 H.15 1 m' Plint keramik 10 x 30
3.5000 bh Plint keramik 10 x 30 8,250.00 28,875.00 28,875.00 0.0016 m3 Pasir pasang 100,600.00 160.96 160.96 0.0200 zak Semen Pc 50 kg 67,100.00 1,342.00 1,342.00 0.0058 kg Semen warna 11,000.00 63.80 63.80 0.1000 or Tukang batu 75,000.00 7,500.00 7,500.00 0.0500 or Pekerja 55,000.00 2,750.00 2,750.00 0.0100 or Kepala tukang 80,000.00 800.00 800.00 0.0025 or Mandor 90,000.00 225.00 225.00
Jumlah 11,275.00 30,441.76 41,716.76 H.16 1 m2 Dinding skat
Double Plywood 3.6 mm + rangka0.7639 lbr Plywood 3,6 mm 55,000.00 42,014.50 42,014.50 0.0161 m3 Kayu meranti 2,640,000.00 42,504.00 42,504.00 0.0494 kg Paku kayu 16,500.00 815.10 815.10 0.1765 or Tukang kayu 75,000.00 13,237.50 13,237.50 0.0880 or Pekerja 55,000.00 4,840.00 4,840.00 0.0177 or Kepala tukang 80,000.00 1,416.00 1,416.00 0.0044 or Mandor 90,000.00 396.00 396.00
. Jumlah 19,889.50 85,333.60 105,223.10 H.17 1 m2 Dinding sekat/partisi (tdk termasuk finishing)
Double gypsum 12 mm + rangka kayu0.7639 lbr Board gypsum 12 mm 202,400.00 154,613.36 154,613.36 0.0161 m3 Kayu meranti 2,640,000.00 42,504.00 42,504.00 0.0494 kg Paku 16,500.00 815.10 815.10 0.4286 or Tukang kayu 75,000.00 32,145.00 32,145.00 0.2143 or Pekerja 55,000.00 11,786.50 11,786.50 0.0429 or Kepala tukang 80,000.00 3,432.00 3,432.00 0.0107 or Mandor 90,000.00 963.00 963.00
Jumlah 48,326.50 197,932.46 246,258.96 H.18 1 m2 Dinding sekat/partisi (tdk termasuk finishing)
Double Calsiboard 4 mm + rangka kayu0.7639 lbr Calsiboard 4 mm 59,950.00 45,795.81 45,795.81 0.0161 m3 Kayu meranti 2,640,000.00 42,504.00 42,504.00 0.0494 kg Paku 16,500.00 815.10 815.10 0.4286 or Tukang kayu 75,000.00 32,145.00 32,145.00 0.2143 or Pekerja 55,000.00 11,786.50 11,786.50 0.0429 or Kepala tukang 80,000.00 3,432.00 3,432.00 0.0107 or Mandor 90,000.00 963.00 963.00
Jumlah 48,326.50 89,114.91 137,441.41 H.19 1 m2 Dinding susun sirih papan meranti
0.0281 m3 Papan kayu meranti 2,695,000.00 75,729.50 75,729.50 0.0676 kg Paku 16,500.00 1,115.40 1,115.40 0.4000 or Tukang kayu 75,000.00 30,000.00 30,000.00 0.2000 or Pekerja 55,000.00 11,000.00 11,000.00 0.0400 or Kepala tukang 80,000.00 3,200.00 3,200.00 0.0100 or mandor 90,000.00 900.00 900.00
Jumlah 45,100.00 76,844.90 121,944.90
NO. NAMA PEKERJAAN HARGA SATUAN UPAH BAHAN JUMLAH HARGA
( Rp ) ( Rp ) ( Rp ) ( Rp ) H.20 1 m2 Dinding susun sirih papan meranti dilapisi
calsiboard 4 mm + rangka0.0281 m3 Papan kayu meranti 2,695,000.00 75,729.50 75,729.50 0.3820 lbr Calsiboard 4 mm 59,950.00 22,900.90 22,900.90 0.0161 m3 Kayu meranti 2,640,000.00 42,504.00 42,504.00 0.2372 kg Paku 16,500.00 3,913.80 3,913.80 0.4206 or Tukang kayu 75,000.00 31,545.00 31,545.00 0.2143 or Pekeja 55,000.00 11,786.50 11,786.50 0.0428 or kepala tukang 80,000.00 3,424.00 3,424.00 0.0107 or Mandor 90,000.00 963.00 963.00
Jumlah 47,718.50 145,048.20 192,766.70 H.21 1 m2 Dinding
Plywood 3.6 mm + rangka0.3820 bh Plywood 3.6 mm 55,000.00 21,010.00 21,010.00 0.0161 m3 Kayu meranti 2,640,000.00 42,504.00 42,504.00 0.0494 kg Paku kayu 16,500.00 815.10 815.10 0.1500 or Tukang kayu 75,000.00 11,250.00 11,250.00 0.0750 or Pekerja 55,000.00 4,125.00 4,125.00 0.0150 or Kepala tukang 80,000.00 1,200.00 1,200.00 0.0038 or Mandor 90,000.00 342.00 342.00
Jumlah 16,917.00 64,329.10 81,246.10 H.22 1 m2 Dinding skat double multiplek 9 mm
dan rangka0.7639 bh Multiplek 9 mm 167,200.00 127,724.08 127,724.08 0.0161 m3 Kayu meranti 2,640,000.00 42,504.00 42,504.00 0.0494 kg Paku kayu 16,500.00 815.10 815.10 0.1765 or Tukang kayu 75,000.00 13,237.50 13,237.50 0.0880 or Pekerja 55,000.00 4,840.00 4,840.00 0.0177 or Kepala tukang 80,000.00 1,416.00 1,416.00 0.0044 or Mandor 90,000.00 396.00 396.00
Jumlah 19,889.50 171,043.18 190,932.68 H.23 1 m2 Glass block 20 x 20
25.0000 bh Glass block 20 x 20 26,400.00 660,000.00 660,000.00 0.0230 m3 Pasir pasang 100,600.00 2,313.80 2,313.80 0.1390 kg Semen Pc 50 kg 1,342.00 186.54 186.54 2.0000 or Tukang batu 75,000.00 150,000.00 150,000.00 1.0000 or Pekerja 55,000.00 55,000.00 55,000.00 0.2000 or Kepala tukang 80,000.00 16,000.00 16,000.00 0.0500 or Mandor 90,000.00 4,500.00 4,500.00
Jumlah 225,500.00 662,500.34 888,000.34 H.24 1 m2 Dinding roster 20 x 20
25.0000 bh Roster beton 20 x 20 6,050.00 151,250.00 151,250.00 0.0230 m3 Pasir pasang 100,600.00 2,313.80 2,313.80 0.1390 kg Semen Pc 50 kg 1,342.00 186.54 186.54 1.2000 or Tukang batu 75,000.00 90,000.00 90,000.00 0.7200 or Pekerja 55,000.00 39,600.00 39,600.00 0.1200 or Kepala tukang 80,000.00 9,600.00 9,600.00 0.0360 or Mandor 90,000.00 3,240.00 3,240.00
Jumlah 142,440.00 153,750.34 296,190.34 H.25 1 m2 Dinding papan ulin diketam dgn alur lidah
0.0234 m3 Papan kayu ulin 5,500,000.00 128,700.00 128,700.00 0.1126 kg Paku ulin 22,000.00 2,477.20 2,477.20 0.6000 or Tukang kayu 75,000.00 45,000.00 45,000.00 0.3000 or Pekerja 55,000.00 16,500.00 16,500.00 0.0600 or Kepala tukang 80,000.00 4,800.00 4,800.00 0.0150 or Mandor 90,000.00 1,350.00 1,350.00 1.0000 ls Alat bantu (ketam listrik) 3,000.00 3,000.00 3,000.00
Jumlah 67,650.00 134,177.20 201,827.20 H.26 1 m2 Dinding papan meranti diketam dgn alur lidah
0.0234 m3 Papan kayu meranti 2,695,000.00 63,063.00 63,063.00 0.0100 m3 kayu meranti 2,640,000.00 26,400.00 26,400.00 0.1126 kg Paku kayu 16,500.00 1,857.90 1,857.90 0.6000 or Tukang kayu 75,000.00 45,000.00 45,000.00 0.3000 or Pekerja 55,000.00 16,500.00 16,500.00 0.0600 or Kepala tukang 80,000.00 4,800.00 4,800.00 0.0150 or Mandor 90,000.00 1,350.00 1,350.00 1.0000 ls Alat bantu (ketam listrik) 3,000.00 3,000.00 3,000.00
Jumlah 67,650.00 94,320.90 161,970.90 I. Pekerjaan LantaiI.1 1 m2 Lantai keramik 20 x 20
10.4000 kg Semen Pc 50 kg 1,342.00 13,956.80 13,956.80 1.6200 kg Semen warna 11,000.00 17,820.00 17,820.00 0.3500 or Tukang batu 75,000.00 26,250.00 26,250.00 0.7000 or Pekerja 55,000.00 38,500.00 38,500.00 0.0350 or Kepala tukang 80,000.00 2,800.00 2,800.00 0.0350 or Mandor 90,000.00 3,150.00 3,150.00
Jumlah 70,700.00 101,599.80 172,299.80
NO. NAMA PEKERJAAN HARGA SATUAN UPAH BAHAN JUMLAH HARGA
10.0000 kg Semen Pc 50 kg 1,342.00 13,420.00 13,420.00 1.5000 kg Semen warna 11,000.00 16,500.00 16,500.00 0.3500 or Tukang batu 75,000.00 26,250.00 26,250.00 0.7000 or Pekerja 55,000.00 38,500.00 38,500.00 0.0350 or Kepala tukang 80,000.00 2,800.00 2,800.00 0.0350 or Mandor 90,000.00 3,150.00 3,150.00
Jumlah 70,700.00 99,732.00 170,432.00 I.3 1 m2 Lantai keramik 40 x 40
10.0000 kg Semen Pc 50 kg 1,342.00 13,420.00 13,420.00 1.5000 kg Semen warna 11,000.00 16,500.00 16,500.00 0.3500 or Tukang batu 75,000.00 26,250.00 26,250.00 0.7000 or Pekerja 55,000.00 38,500.00 38,500.00 0.0350 or Kepala tukang 80,000.00 2,800.00 2,800.00 0.0350 or Mandor 90,000.00 3,150.00 3,150.00
Jumlah 70,700.00 118,092.83 188,792.83 I.4 1 m2 Lantai keramik 60 x 60
10.0000 kg Semen Pc 50 kg 1,342.00 13,420.00 13,420.00 1.5000 kg Semen warna 11,000.00 16,500.00 16,500.00 0.3500 or Tukang batu 75,000.00 26,250.00 26,250.00 0.7000 or Pekerja 55,000.00 38,500.00 38,500.00 0.0350 or Kepala tukang 80,000.00 2,800.00 2,800.00 0.0350 or Mandor 90,000.00 3,150.00 3,150.00
Jumlah 70,700.00 99,382.75 170,082.75 I.5 1 m2 Lantai keramik anti slip 20 x 20
26.5000 bh Keramik anti slip 20 x 20 2,464.00 65,296.00 65,296.00 0.0450 m3 Pasir pasang 100,600.00 4,527.00 4,527.00
10.4000 kg Semen Pc 50 kg 1,342.00 13,956.80 13,956.80 1.6200 kg Semen warna 11,000.00 17,820.00 17,820.00 0.3500 or Tukang batu 75,000.00 26,250.00 26,250.00 0.7000 or Pekerja 55,000.00 38,500.00 38,500.00 0.0350 or Kepala tukang 80,000.00 2,800.00 2,800.00 0.0350 or Mandor 90,000.00 3,150.00 3,150.00
Jumlah 70,700.00 101,599.80 172,299.80 I.6 1 m2 Lantai keramik anti slip 30 x 30
10.0000 kg Semen Pc 50 kg 1,342.00 13,420.00 13,420.00 1.5000 kg Semen warna 11,000.00 16,500.00 16,500.00 0.3500 or Tukang batu 75,000.00 26,250.00 26,250.00 0.7000 or Pekerja 55,000.00 38,500.00 38,500.00 0.0350 or Kepala tukang 80,000.00 2,800.00 2,800.00 0.0350 or Mandor 90,000.00 3,150.00 3,150.00
Jumlah 70,700.00 99,732.00 170,432.00 I.7 1 m2 Lantai keramik anti slip 40 x 40
1.0000 dos Keramik 40 x 40 80,300.00 80,300.00 80,300.00 0.0190 m3 Pasir pasang 100,600.00 1,911.40 1,911.40 0.1920 zak Semen Pc 50 kg 67,100.00 12,883.20 12,883.20 0.0140 kg Semen warna 11,000.00 154.00 154.00 0.2500 or Tukang batu 75,000.00 18,750.00 18,750.00 0.5000 or Pekerja 55,000.00 27,500.00 27,500.00 0.0250 or Kepala tukang 80,000.00 2,000.00 2,000.00 0.0250 or Mandor 90,000.00 2,250.00 2,250.00
Jumlah 50,500.00 95,248.60 145,748.60 L.8 1 m2 Lantai Papan Ulin diketam tanpa celah
0.0234 m3 Papan kayu ulin 5,500,000.00 128,700.00 128,700.00 0.1609 kg Paku ulin 22,000.00 3,539.80 3,539.80 0.6000 or Tukang kayu 75,000.00 45,000.00 45,000.00 0.3000 or Pekerja 55,000.00 16,500.00 16,500.00 0.0600 or Kepala tukang 80,000.00 4,800.00 4,800.00 0.0150 or Mandor 90,000.00 1,350.00 1,350.00 1.0000 ls Alat bantu (ketam listrik) 3,000.00 3,000.00 3,000.00
Jumlah 67,650.00 135,239.80 202,889.80 L.9 1 m2 Lantai jembatan titian ulin dengan celah
0.0234 m3 Papan ulin 5,500,000.00 128,700.00 128,700.00 0.1609 kg Paku ulin 22,000.00 3,539.80 3,539.80 0.3750 or Tukang kayu 75,000.00 28,125.00 28,125.00 0.0375 or Kepala tukang 80,000.00 3,000.00 3,000.00 0.0125 or Mandor 90,000.00 1,125.00 1,125.00 0.1250 or Pekerja 55,000.00 6,875.00 6,875.00 1.0000 ls Alat bantu (ketam listrik) 3,000.00 3,000.00 3,000.00
Jumlah 39,125.00 135,239.80 174,364.80
NO. NAMA PEKERJAAN HARGA SATUAN UPAH BAHAN JUMLAH HARGA
( Rp ) ( Rp ) ( Rp ) ( Rp ) J. Pekerjaan PlapondJ.1 1 m2 Memasang langit-langit tripleks (120 x 240) cm,
tebal 3.6 mm0.3750 lbr Plywood 3.6 mm 55,000.00 20,625.00 20,625.00 0.0300 kg Paku plywood 27,500.00 825.00 825.00 0.1000 or Tukang kayu 75,000.00 7,500.00 7,500.00 0.1000 or Pekerja 55,000.00 5,500.00 5,500.00 0.0100 or Kepala tukang 80,000.00 800.00 800.00 0.0050 or Mandor 90,000.00 450.00 450.00
Jumlah 14,250.00 21,450.00 35,700.00 J.2 1 m2 Memasang langit-langit tripleks (120 x 240) cm,
tebal 4 mm0.3750 lbr Plywood 4 mm 60,500.00 22,687.50 22,687.50 0.0300 kg Paku plywood 27,500.00 825.00 825.00 0.1000 or Tukang kayu 75,000.00 7,500.00 7,500.00 0.1000 or Pekerja 55,000.00 5,500.00 5,500.00 0.0100 or Kepala tukang 80,000.00 800.00 800.00 0.0050 or Mandor 90,000.00 450.00 450.00
Jumlah 14,250.00 23,512.50 37,762.50 J.3 1 m2 Memasang langit-langit tripleks (120 x 240) cm,
tebal 6 mm0.3750 lbr Plywood 6 mm 100,100.00 37,537.50 37,537.50 0.0300 kg Paku plywood 27,500.00 825.00 825.00 0.1000 or Tukang kayu 75,000.00 7,500.00 7,500.00 0.1000 or Pekerja 55,000.00 5,500.00 5,500.00 0.0100 or Kepala tukang 80,000.00 800.00 800.00 0.0050 or Mandor 90,000.00 450.00 450.00
Jumlah 14,250.00 38,362.50 52,612.50 J.4 1 m2 Memasang langit-langit calsiboard (120 x 240) cm,
tebal 4.5 mm0.3750 lbr Calsiboard 4.5 mm 59,950.00 22,481.25 22,481.25 0.0300 kg Paku plywood 27,500.00 825.00 825.00 0.1000 or Tukang kayu 75,000.00 7,500.00 7,500.00 0.1000 or Pekerja 55,000.00 5,500.00 5,500.00 0.0100 or Kepala tukang 80,000.00 800.00 800.00 0.0050 or Mandor 90,000.00 450.00 450.00
Jumlah 14,250.00 23,306.25 37,556.25 J.5 1 m2 Memasang langit-langit lambreziring kayu tebal 9 mm
0.0150 m3 Papan kayu lumbriziring tebal 9 3,025,000.00 45,375.00 45,375.00 0.0100 kg Paku kayu 16,500.00 165.00 165.00 0.8000 or Tukang kayu 75,000.00 60,000.00 60,000.00 0.8000 or Pekerja 55,000.00 44,000.00 44,000.00 0.0800 or Kepala tukang 80,000.00 6,400.00 6,400.00 0.0400 or Mandor 90,000.00 3,600.00 3,600.00
Jumlah 114,000.00 45,540.00 159,540.00 j.6 1 m' Memasang list langit-langit kayu profil
1.0500 m' List kayu profil 4,125.00 4,331.25 4,331.25 0.0100 kg Paku kayu 16,500.00 165.00 165.00 0.0500 or Tukang kayu 75,000.00 3,750.00 3,750.00 0.0500 or Pekerja 55,000.00 2,750.00 2,750.00 0.0050 or Kepala tukang 80,000.00 400.00 400.00 0.0030 or Mandor 90,000.00 270.00 270.00
Jumlah 7,170.00 4,496.25 11,666.25 J.7 1 m2 Plapond calsiboard 3,5 mm + rangka
0.3819 lbr Calsiboard 3,6 mm 57,750.00 22,054.73 22,054.73 0.0201 m3 Kayu meranti 2,640,000.00 53,064.00 53,064.00 0.1000 kg Paku 16,500.00 1,650.00 1,650.00 0.5000 or Tukang kayu 75,000.00 37,500.00 37,500.00 0.2500 or Pekerja 55,000.00 13,750.00 13,750.00 0.0500 or Kepala tukang 80,000.00 4,000.00 4,000.00 0.0125 or Mandor 90,000.00 1,125.00 1,125.00
Jumlah 56,375.00 76,768.73 133,143.73 J.8 1 m1 Kusen pintu, jendela, ventilasi kayu ulin
(pekerjaan memasang kusen jadi)1.0000 m1 Kusen kayu ulin 74,800.00 74,800.00 74,800.00 0.0750 or Tukang kayu 75,000.00 5,625.00 5,625.00 0.1500 or Pekerja 55,000.00 8,250.00 8,250.00 0.0075 or Kepala tukang 80,000.00 600.00 600.00 0.0075 or Mandor 90,000.00 675.00 675.00
Jumlah 15,150.00 74,800.00 89,950.00 J.9 1 m2 Memasang rangka langit-langit (60 x 60) cm,
kayu klas II atau III 0.0163 m3 Kayu balok 5/7 cm 2,640,000.00 43,032.00 43,032.00 0.2500 kg Paku kayu 7 s/d 10 cm 16,500.00 4,125.00 4,125.00 0.3000 or Tukang kayu 75,000.00 22,500.00 22,500.00 0.2000 or Pekerja 55,000.00 11,000.00 11,000.00 0.0300 or Kepala tukang 80,000.00 2,400.00 2,400.00 0.0100 or Mandor 90,000.00 900.00 900.00
Jumlah 36,800.00 47,157.00 83,957.00
NO. NAMA PEKERJAAN HARGA SATUAN UPAH BAHAN JUMLAH HARGA
( Rp ) ( Rp ) ( Rp ) ( Rp )
J.10 1 m2 Memasang rangka langit-langit (50 x 100) cm, kayu klas II atau III
0.0154 m3 Kayu balok 5/7 cm 2,640,000.00 40,656.00 40,656.00 0.2000 kg Paku kayu 7 s/d 10 cm 16,500.00 3,300.00 3,300.00 0.3000 or Tukang kayu 75,000.00 22,500.00 22,500.00 0.1500 or Pekerja 55,000.00 8,250.00 8,250.00 0.0300 or Kepala tukang 80,000.00 2,400.00 2,400.00 0.0750 or Mandor 90,000.00 6,750.00 6,750.00
Jumlah 39,900.00 43,956.00 83,856.00 K. Pekerjaan KusenK.1 1 m3 Membuat dan memasang kusen pintu dan jendela,
kayu klas I 1.1000 m3 Balok kayu klas I 5,500,000.00 6,050,000.00 6,050,000.00 1.2500 kg Paku 10 cm 22,000.00 27,500.00 27,500.00 1.0000 kg Lem kayu 20,250.00 20,250.00 20,250.00
21.0000 or Tukang kayu 75,000.00 1,575,000.00 1,575,000.00 7.0000 or Pekerja 55,000.00 385,000.00 385,000.00 2.1000 or Kepala tukang 80,000.00 168,000.00 168,000.00 0.3500 or Mandor 90,000.00 31,500.00 31,500.00
Jumlah 2,159,500.00 6,097,750.00 8,257,250.00 K.2 1 m3 Membuat dan memasang kusen pintu dan jendela,
kayu klas II atau III 1.2000 m3 Balok kayu klas II atau III 3,520,000.00 4,224,000.00 4,224,000.00 1.2500 kg Paku 10 cm 22,000.00 27,500.00 27,500.00 1.0000 kg Lem kayu 20,250.00 20,250.00 20,250.00
18.0000 or Tukang kayu 75,000.00 1,350,000.00 1,350,000.00 6.0000 or Pekerja 55,000.00 330,000.00 330,000.00 1.8000 or Kepala tukang 80,000.00 144,000.00 144,000.00 0.3000 or Mandor 90,000.00 27,000.00 27,000.00
Jumlah 1,851,000.00 4,271,750.00 6,122,750.00 K.3 1 m2 Membuat dan memasang daun pintu panel,
kayu klas I0.0400 m3 Papan kayu klas I 6,600,000.00 264,000.00 264,000.00 0.5000 kg Lem kayu 20,250.00 10,125.00 10,125.00 3.0000 or Tukang kayu 75,000.00 225,000.00 225,000.00 1.0000 or Pekerja 55,000.00 55,000.00 55,000.00 0.3000 or Kepala tukang 80,000.00 24,000.00 24,000.00 0.0500 or Mandor 90,000.00 4,500.00 4,500.00
Jumlah 308,500.00 274,125.00 582,625.00 K.4 1 m2 Membuat dan memasang daun pintu panel,
kayu klas II 0.0400 m3 Papan kayu klas II 3,850,000.00 154,000.00 154,000.00 0.5000 kg Lem kayu 20,250.00 10,125.00 10,125.00 3.0000 or Tukang kayu 75,000.00 225,000.00 225,000.00 1.0000 or Pekerja 55,000.00 55,000.00 55,000.00 0.3000 or Kepala tukang 80,000.00 24,000.00 24,000.00 0.0500 or Mandor 90,000.00 4,500.00 4,500.00
Jumlah 308,500.00 164,125.00 472,625.00 K.5 1 m2 Membuat dan memasang pintu dan jendela kaca,
kayu klas I 0.0240 m3 Papan kayu klas I 6,600,000.00 158,400.00 158,400.00 0.3000 kg Lem kayu 20,250.00 6,075.00 6,075.00 2.4000 or Tukang kayu 75,000.00 180,000.00 180,000.00 0.8000 or Pekerja 55,000.00 44,000.00 44,000.00 0.2400 or Kepala tukang 80,000.00 19,200.00 19,200.00 0.0400 or Mandor 90,000.00 3,600.00 3,600.00
Jumlah 246,800.00 164,475.00 411,275.00 K.6 1 m2 Membuat dan memasang pintu dan jendela kaca,
kayu klas II 0.0240 m3 Papan kayu klas II 3,850,000.00 92,400.00 92,400.00 0.3000 kg Lem kayu 20,250.00 6,075.00 6,075.00 2.4000 or Tukang kayu 75,000.00 180,000.00 180,000.00 0.8000 or Pekerja 55,000.00 44,000.00 44,000.00 0.2400 or Kepala tukang 80,000.00 19,200.00 19,200.00 0.0400 or Mandor 90,000.00 3,600.00 3,600.00
Jumlah 246,800.00 98,475.00 345,275.00 K.7 1 m2 Membuat dan memasang pintu dan jendela jalusi,
kayu klas I0.0640 m3 Papan kayu klas I 6,600,000.00 422,400.00 422,400.00 0.5000 kg Lem kayu 20,250.00 10,125.00 10,125.00 3.0000 or Tukang kayu 75,000.00 225,000.00 225,000.00 1.0000 or Pekerja 55,000.00 55,000.00 55,000.00 0.3000 or Kepala tukang 80,000.00 24,000.00 24,000.00 0.0500 or Mandor 90,000.00 4,500.00 4,500.00
Jumlah 308,500.00 432,525.00 741,025.00
NO. NAMA PEKERJAAN HARGA SATUAN UPAH BAHAN JUMLAH HARGA
( Rp ) ( Rp ) ( Rp ) ( Rp )
K.8 1 m2 Membuat dan memasang pintu dan jendela jalusi,kayu klas II
0.0640 m3 Papan kayu klas II 3,850,000.00 246,400.00 246,400.00 0.5000 kg Lem kayu 20,250.00 10,125.00 10,125.00 3.0000 or Tukang kayu 75,000.00 225,000.00 225,000.00 1.0000 or Pekerja 55,000.00 55,000.00 55,000.00 0.3000 or Kepala tukang 80,000.00 24,000.00 24,000.00 0.0500 or Mandor 90,000.00 4,500.00 4,500.00
Jumlah 308,500.00 256,525.00 565,025.00 K.9 1 m2 Memasang jalusi kusen, kayu klas I
0.0600 m3 Papan kayu klas I 6,600,000.00 396,000.00 396,000.00 0.1500 kg Paku 1 s/d 2.5 cm 20,250.00 3,037.50 3,037.50 2.0000 or Tukang kayu 75,000.00 150,000.00 150,000.00 0.6700 or Pekerja 55,000.00 36,850.00 36,850.00 0.2000 or Kepala tukang 80,000.00 16,000.00 16,000.00 0.3350 or Mandor 90,000.00 30,150.00 30,150.00
Jumlah 233,000.00 399,037.50 632,037.50 K.10 1 m2 Memasang jalusi kusen, kayu klas II
0.0600 m3 Papan kayu klas II 3,850,000.00 231,000.00 231,000.00 0.1500 kg Paku 1 s/d 2.5 cm 20,250.00 3,037.50 3,037.50 2.0000 or Tukang kayu 75,000.00 150,000.00 150,000.00 0.6700 or Pekerja 55,000.00 36,850.00 36,850.00 0.2000 or Kepala tukang 80,000.00 16,000.00 16,000.00 0.3350 or Mandor 90,000.00 30,150.00 30,150.00
Jumlah 233,000.00 234,037.50 467,037.50 L. Pekerjaan AtapL.1 1 m3 Kuda-kuda bentang lebih dari 7 meter
(atap pelana tdk byk jurai/atap sekolah dasar)1.1000 m3 Kayu meranti 2,640,000.00 2,904,000.00 2,904,000.00 3.0000 kg Paku kayu 16,500.00 49,500.00 49,500.00
17.3611 or Tukang kayu 75,000.00 1,302,082.50 1,302,082.50 11.0480 or Pekerja 55,000.00 607,640.00 607,640.00 1.7361 or Kepala tukang 80,000.00 138,888.00 138,888.00 0.5524 or Mandor 90,000.00 49,716.00 49,716.00 1.0000 ls Alat bantu (bor listrik, dll) 20,000.00 20,000.00 20,000.00
Jumlah 2,098,326.50 2,973,500.00 5,071,826.50 L.2 1 m3 Kuda-kuda bentang lebih dari 7 meter
(atap perisai/byk jurai/atap rumah agak rumit)1.2000 m3 Kayu meranti 2,640,000.00 3,168,000.00 3,168,000.00 3.6000 kg Paku kayu 16,500.00 59,400.00 59,400.00
20.8330 or Tukang kayu 75,000.00 1,562,475.00 1,562,475.00 13.2576 or Pekerja 55,000.00 729,168.00 729,168.00 2.0833 or Kepala tukang 80,000.00 166,664.00 166,664.00 0.6629 or Mandor 90,000.00 59,661.00 59,661.00 1.0000 ls Alat bantu (bor listrik, dll) 20,000.00 20,000.00 20,000.00
Jumlah 2,517,968.00 3,247,400.00 5,765,368.00 L.3 1 m3 Kuda-kuda bentang lebih dari 7 meter
(atap bentuk sulit dgn bentuk arsitektur rumit)1.3000 m3 Kayu meranti 2,640,000.00 3,432,000.00 3,432,000.00 3.9000 kg Paku kayu 16,500.00 64,350.00 64,350.00
22.5694 or Tukang kayu 75,000.00 1,692,705.00 1,692,705.00 14.3624 or Pekerja 55,000.00 789,932.00 789,932.00 2.2569 or Kepala tukang 80,000.00 180,552.00 180,552.00 0.7181 or Mandor 90,000.00 64,629.00 64,629.00 1.0000 ls Alat bantu (bor listrik, dll) 20,000.00 20,000.00 20,000.00
Jumlah 2,727,818.00 3,516,350.00 6,244,168.00 L.4 1 m3 Kuda-kuda bentang kurang dari 7 meter
(atap pelana tdk byk jurai/atap sekolah dasar)1.1000 m3 Kayu meranti 2,640,000.00 2,904,000.00 2,904,000.00 3.0000 kg Paku kayu 16,500.00 49,500.00 49,500.00 6.9444 or Tukang kayu 75,000.00 520,830.00 520,830.00
13.8889 or Pekerja 55,000.00 763,889.50 763,889.50 0.6944 or Kepala tukang 80,000.00 55,552.00 55,552.00 0.6944 or Mandor 90,000.00 62,496.00 62,496.00 1.0000 ls Alat bantu (bor listrik, dll) 20,000.00 20,000.00 20,000.00
Jumlah 1,402,767.50 2,973,500.00 4,376,267.50 L.5 1 m3 Kuda-kuda bentang kurang dari 7 meter
(atap perisai/byk jurai/atap rumah agak rumit)1.2000 m3 Kayu meranti 2,640,000.00 3,168,000.00 3,168,000.00 3.6000 kg Paku kayu 16,500.00 59,400.00 59,400.00
16.6667 or Tukang kayu 75,000.00 1,250,002.50 1,250,002.50 8.3330 or Pekerja 55,000.00 458,315.00 458,315.00 1.6667 or Kepala tukang 80,000.00 133,336.00 133,336.00 0.4167 or Mandor 90,000.00 37,503.00 37,503.00 1.0000 ls Alat bantu (bor listrik, dll) 20,000.00 20,000.00 20,000.00
Jumlah 1,879,156.50 3,247,400.00 5,126,556.50
NO. NAMA PEKERJAAN HARGA SATUAN UPAH BAHAN JUMLAH HARGA
( Rp ) ( Rp ) ( Rp ) ( Rp )
L.6 1 m3 Kuda-kuda bentang kurang dari 7 meter(atap bentuk sulit dgn bentuk arsitektur rumit)
1.3000 m3 Kayu meranti 2,640,000.00 3,432,000.00 3,432,000.00 3.9000 kg Paku kayu 16,500.00 64,350.00 64,350.00
18.0556 or Tukang kayu 75,000.00 1,354,170.00 1,354,170.00 9.0277 or Pekerja 55,000.00 496,523.50 496,523.50 1.8056 or Kepala tukang 80,000.00 144,448.00 144,448.00 0.4514 or Mandor 90,000.00 40,626.00 40,626.00 1.0000 ls Alat bantu (bor listrik, dll) 20,000.00 20,000.00 20,000.00
Jumlah 2,035,767.50 3,516,350.00 5,552,117.50 L.7 1 m1 Kuda-kuda diketam halus, konsul kayu bengkirai
1.0000 m1 Kayu bengkirai 3,520,000.00 3,520,000.00 3,520,000.00 3.0000 kg Paku 16,500.00 49,500.00 49,500.00 0.0511 or Tukang kayu 75,000.00 3,832.50 3,832.50 0.0682 or Pekerja 55,000.00 3,751.00 3,751.00 0.0051 or Kepala tukang 80,000.00 408.00 408.00 0.0034 or Mandor 90,000.00 306.00 306.00 1.1000 m3 Pek. Gergajian 5,000.00 5,500.00 5,500.00
Jumlah 8,297.50 3,575,000.00 3,583,297.50 L.8 1 m3 Gording, kayu klas II
1.1000 m3 Balok kayu klas II 2,640,000.00 2,904,000.00 2,904,000.00 15.0000 kg Besi strip tebal 5 mm 12,533.69 188,005.39 188,005.39 3.0000 kg Paku 12 cm 16,500.00 49,500.00 49,500.00 7.2000 or Tukang kayu 75,000.00 540,000.00 540,000.00 2.4000 or Pekerja 55,000.00 132,000.00 132,000.00 0.7200 or Kepala tukang 80,000.00 57,600.00 57,600.00 0.1200 or Mandor 90,000.00 10,800.00 10,800.00
(atap perisai/byk jurai/atap rumah agak rumit)0.0146 m3 Kayu meranti 2,640,000.00 38,544.00 38,544.00 0.0567 kg Paku kayu 16,500.00 935.55 935.55 0.1170 or Tukang kayu 75,000.00 8,775.00 8,775.00 0.0780 or Pekerja 55,000.00 4,290.00 4,290.00 0.0117 or Kepala tukang 80,000.00 936.00 936.00 0.0039 or Mandor 90,000.00 351.00 351.00
(atap bentuk sulit dgn bentuk arsitektur rumit)0.0157 m3 Kayu meranti 2,640,000.00 41,448.00 41,448.00 0.0610 kg Paku kayu 16,500.00 1,006.50 1,006.50 0.1260 or Tukang kayu 75,000.00 9,450.00 9,450.00 0.0840 or Pekerja 55,000.00 4,620.00 4,620.00 0.0126 or Kepala tukang 80,000.00 1,008.00 1,008.00 0.0042 or Mandor 90,000.00 378.00 378.00
Jumlah 15,456.00 42,454.50 57,910.50 L.12 Atap seng gelombang BJLS 20
(atap pelana/perisai sederhana/atap sekolahan)0.8929 lbr Seng BJLS 20 42,900.00 38,305.41 38,305.41 0.0482 kg Paku seng 27,500.00 1,325.50 1,325.50 0.0750 or Tukang kayu 75,000.00 5,625.00 5,625.00 0.0375 or Pekerja 55,000.00 2,062.50 2,062.50 0.0075 or Kepala tukang 80,000.00 600.00 600.00 0.0018 or Mandor 90,000.00 162.00 162.00
Jumlah 8,449.50 39,630.91 48,080.41 L.13 Atap seng gelombang BJLS 20
(atap perisai yang banyak jurai)1.1688 lbr Seng BJLS 20 42,900.00 50,141.52 50,141.52 0.0540 kg Paku seng 27,500.00 1,485.00 1,485.00 0.0975 or Tukang kayu 75,000.00 7,312.50 7,312.50 0.0488 or Pekerja 55,000.00 2,684.00 2,684.00 0.0098 or Kepala tukang 80,000.00 784.00 784.00 0.0023 or Mandor 90,000.00 207.00 207.00
Jumlah 10,987.50 51,626.52 62,614.02
NO. NAMA PEKERJAAN HARGA SATUAN UPAH BAHAN JUMLAH HARGA
( Rp ) ( Rp ) ( Rp ) ( Rp ) L.15 1 m' Bubungan seng datar/ Jurai dalam
1.0000 m' Seng plat BJLS 20 15,950.00 15,950.00 15,950.00 0.0500 kg Paku seng 27,500.00 1,375.00 1,375.00 0.0088 m3 Papan kayu meranti 2,695,000.00 23,716.00 23,716.00 0.0750 or Tukang besi 75,000.00 5,625.00 5,625.00 0.0750 or Pekerja 55,000.00 4,125.00 4,125.00 0.0075 or Kepala tukang 80,000.00 600.00 600.00 0.0038 or Mandor 90,000.00 342.00 342.00
Jumlah 10,692.00 41,041.00 51,733.00 L.16 1 m2 Atap genteng metal mutu klas I
(atap pelana/perisai sederhana/atap sekolahan)1.3000 lbr Genteng metal 0.4mm 79,750.00 103,675.00 103,675.00 0.0300 kg Paku genteng 27,500.00 825.00 825.00 0.0536 or Tukang kayu 75,000.00 4,020.00 4,020.00 0.0321 or Pekerja 55,000.00 1,765.50 1,765.50 0.0054 or Kepala tukang 80,000.00 432.00 432.00 0.0016 or Mandor 90,000.00 144.00 144.00
Jumlah 6,361.50 104,500.00 110,861.50 L.17 1 m2 Atap genteng metal mutu klas I
(atap perisai yang banyak jurai)1.3000 lbr Genteng metal 0.4mm 79,750.00 103,675.00 103,675.00 0.0300 kg Paku genteng 27,500.00 825.00 825.00 0.0577 or Tukang kayu 75,000.00 4,327.50 4,327.50 0.0346 or Pekerja 55,000.00 1,903.00 1,903.00 0.0058 or Kepala tukang 80,000.00 464.00 464.00 0.0017 or Mandor 90,000.00 153.00 153.00
Jumlah 6,847.50 104,500.00 111,347.50 L.18 1 m2 Atap genteng metal mutu klas II
(atap pelana/perisai sederhana/atap sekolahan)1.3000 lbr Genteng metal 0.3 mm 46,200.00 60,060.00 60,060.00 0.0300 kg Paku genteng 27,500.00 825.00 825.00 0.0536 or Tukang kayu 75,000.00 4,020.00 4,020.00 0.0321 or Pekerja 55,000.00 1,765.50 1,765.50 0.0054 or Kepala tukang 80,000.00 432.00 432.00 0.0016 or Mandor 90,000.00 144.00 144.00
Jumlah 6,361.50 60,885.00 67,246.50 L.19 1 m2 Atap genteng metal mutu klas II
(atap perisai yang banyak jurai)1.3000 lbr Genteng metal 46,200.00 60,060.00 60,060.00 0.0300 kg Paku genteng 27,500.00 825.00 825.00 0.0577 or Tukang kayu 75,000.00 4,327.50 4,327.50 0.0346 or Pekerja 55,000.00 1,903.00 1,903.00 0.0058 or Kepala tukang 80,000.00 464.00 464.00 0.1700 or Mandor 90,000.00 15,300.00 15,300.00
Jumlah 21,994.50 60,885.00 82,879.50 L.20 1 m' Nok genteng metal model U panjang 110 cm
1.0000 bh Nok model U 28,600.00 28,600.00 28,600.00 0.0750 kg Paku genteng 27,500.00 2,062.50 2,062.50 0.0375 or Tukang kayu 75,000.00 2,812.50 2,812.50 0.0375 or Pekerja 55,000.00 2,062.50 2,062.50 0.0038 or Kepala tukang 80,000.00 304.00 304.00 0.0019 or Mandor 90,000.00 171.00 171.00
Jumlah 5,350.00 30,662.50 36,012.50 L.21 1 M1 Nok genteng metal model C panjang 40 cm
3.0000 bh Nok model C 30,800.00 92,400.00 92,400.00 0.0750 kg Paku genteng 27,500.00 2,062.50 2,062.50 0.0375 or Tukang kayu 75,000.00 2,812.50 2,812.50 0.0375 or Pekerja 55,000.00 2,062.50 2,062.50 0.0038 or Kepala tukang 80,000.00 304.00 304.00 0.0019 or Mandor 90,000.00 171.00 171.00
Jumlah 5,350.00 94,462.50 99,812.50 L.23 1 m' Nok samping genteng metal 110 cm
1.0000 bh Nok samping genteng metal 25,300.00 25,300.00 25,300.00 0.0750 kg Paku genteng 27,500.00 2,062.50 2,062.50 0.0375 or Tukang kayu 75,000.00 2,812.50 2,812.50 0.0375 or Pekerja 55,000.00 2,062.50 2,062.50 0.0038 or Kepala tukang 80,000.00 304.00 304.00 0.0019 or Mandor 90,000.00 171.00 171.00
Jumlah 5,350.00 27,362.50 32,712.50 L.24 1 m' List plank 3/20 cm, kayu klas I
0.0108 m3 Papan kayu klas I 5,500,000.00 59,400.00 59,400.00 0.1000 kg Paku 5 s/d 7 cm 22,000.00 2,200.00 2,200.00 0.2000 or Tukang kayu 75,000.00 15,000.00 15,000.00 0.1000 or Pekerja 55,000.00 5,500.00 5,500.00 0.0200 or Kepala tukang 80,000.00 1,600.00 1,600.00 0.0050 or Mandor 90,000.00 450.00 450.00
Jumlah 22,550.00 61,600.00 84,150.00
NO. NAMA PEKERJAAN HARGA SATUAN UPAH BAHAN JUMLAH HARGA
( Rp ) ( Rp ) ( Rp ) ( Rp )
L.25 1 m' List plank 3/20 cm, kayu klas I I0.0108 m3 Papan kayu klas II 3,465,000.00 37,422.00 37,422.00 0.1000 kg Paku 5 s/d 7 cm 22,000.00 2,200.00 2,200.00 0.2000 or Tukang kayu 75,000.00 15,000.00 15,000.00 0.1000 or Pekerja 55,000.00 5,500.00 5,500.00 0.0200 or Kepala tukang 80,000.00 1,600.00 1,600.00 0.0050 or Mandor 90,000.00 450.00 450.00
Jumlah 22,550.00 39,622.00 62,172.00 L.26 1 m1 Les penutup teras papan ulin 2/20
0.0044 m3 Papan kayu ulin 5,500,000.00 24,200.00 24,200.00 0.0250 kg Paku 22,000.00 550.00 550.00 0.0750 or Tukang kayu 75,000.00 5,625.00 5,625.00 0.0750 or Pekerja 55,000.00 4,125.00 4,125.00 0.0075 or Kepala tukang 80,000.00 600.00 600.00 0.0038 or Mandor 90,000.00 342.00 342.00 1.0000 ls Pemakaian ketam, bor, dll 500.00 500.00 500.00
Jumlah 10,692.00 25,250.00 35,942.00 L.27 1 m1 Les penutup papan ulin 3/20
0.0060 m3 Papan kayu ulin 5,500,000.00 33,000.00 33,000.00 0.0250 kg Paku 22,000.00 550.00 550.00 0.0750 or Tukang kayu 75,000.00 5,625.00 5,625.00 0.0750 or Pekerja 55,000.00 4,125.00 4,125.00 0.0075 or Kepala tukang 80,000.00 600.00 600.00 0.0038 or Mandor 90,000.00 342.00 342.00 1.0000 ls Pemakaian ketam, bor, dll 500.00 500.00 500.00
Jumlah 10,692.00 34,050.00 44,742.00 M. Pekerjaan Cat-catanM.1 1 m2 Mengikis/mengerok cat tembok cara manual
0.0500 bh Kapek 20,000.00 1,000.00 1,000.00 0.1500 or Pekerja 55,000.00 8,250.00 8,250.00 0.0080 or Mandor 90,000.00 720.00 720.00
Jumlah 8,970.00 1,000.00 9,970.00 M.2 1 m2 Mencuci bidang permukaan tembok lama dengan sabun
0.0500 kg Sabun 15,000.00 750.00 750.00 0.0800 or Pekerja 55,000.00 4,400.00 4,400.00 0.0040 or Mandor 90,000.00 360.00 360.00
Jumlah 4,760.00 750.00 5,510.00 M.3 1 m2 Lapis plamir pada tembok
0.1000 kg Plamir tembok 25,300.00 2,530.00 2,530.00 0.0500 bh Kapek 20,000.00 1,000.00 1,000.00 0.5000 lbr Ampelas 3,850.00 1,925.00 1,925.00 0.0300 or Tukang cat 75,000.00 2,250.00 2,250.00 0.0200 or Pekerja 55,000.00 1,100.00 1,100.00 0.0030 or Kepala tukang 80,000.00 240.00 240.00 0.0010 or Mandor 90,000.00 90.00 90.00
Jumlah 3,680.00 5,455.00 9,135.00 M.4
0.1000 kg Plamir 25,300.00 2,530.00 2,530.00 0.1000 kg Cat dasar 16,500.00 1,650.00 1,650.00 0.2600 kg Cat tembok biasa (penutup 2x ) 15,400.00 4,004.00 4,004.00 0.0630 or Tukang cat 75,000.00 4,725.00 4,725.00 0.0200 or Pekerja 55,000.00 1,100.00 1,100.00 0.0063 or Kepala tukang 80,000.00 504.00 504.00 0.0025 or Mandor 90,000.00 225.00 225.00
Jumlah 6,554.00 8,184.00 14,738.00 M.5 1 m2 Mengecat dinding / plapond (anti jamur/klas A)
0.4250 kg Cat tembok (klas A) 54,000.00 22,950.00 22,950.00 0.0750 kg Tukang cat 75,000.00 5,625.00 5,625.00 0.1500 lbr Pekerja 55,000.00 8,250.00 8,250.00 0.0075 or Kepala tukang 80,000.00 600.00 600.00 0.0075 or Mandor 90,000.00 675.00 675.00
Jumlah 1,275.00 36,825.00 38,100.00 M.6
0.2000 kg Cat meni 25,850.00 5,170.00 5,170.00 0.1500 kg Plamir 25,300.00 3,795.00 3,795.00 0.1700 kg Cat dasar 16,500.00 2,805.00 2,805.00 0.2600 kg Cat kilap penutup 2x 49,500.00 12,870.00 12,870.00 0.0900 or Tukang cat 75,000.00 6,750.00 6,750.00 0.0700 or Pekerja 55,000.00 3,850.00 3,850.00 0.0060 or Kepala tukang 80,000.00 480.00 480.00 0.0025 or Mandor 90,000.00 225.00 225.00
1 m2 Mengecat bidang kayu baru (1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup)
NO. NAMA PEKERJAAN HARGA SATUAN UPAH BAHAN JUMLAH HARGA
( Rp ) ( Rp ) ( Rp ) ( Rp )
M.7 1 m2 Pengecatan bidang tembok lama 2 lapis dengan kuas
0.2400 kg Cat tembok (klas A) 54,000.00 12,960.00 12,960.00 0.0150 bh Kuas 17,050.00 255.75 255.75 0.0500 or Tukang cat 75,000.00 3,750.00 3,750.00 0.0600 or Pekerja 55,000.00 3,300.00 3,300.00 0.0050 or Kepala tukang 80,000.00 400.00 400.00 0.0030 or Mandor 90,000.00 270.00 270.00
Jumlah 7,720.00 13,215.75 20,935.75 M.8 1 m2 Pengecatan bidang tembok lama 2 lapis dengan roll
0.4700 kg Cat tembok (klas A) 54,000.00 25,380.00 25,380.00 0.0100 bh Roll 27,500.00 275.00 275.00 0.0300 or Tukang cat 75,000.00 2,250.00 2,250.00 0.0400 or Pekerja 55,000.00 2,200.00 2,200.00 0.0030 or Kepala tukang 80,000.00 240.00 240.00 0.0020 or Mandor 90,000.00 180.00 180.00
Jumlah 4,870.00 25,655.00 30,525.00 M.9
0.1000 kg Plamir 25,300.00 2,530.00 2,530.00 0.2400 kg Cat tembok biasa 15,400.00 3,696.00 3,696.00 0.5000 lbr Ampelas 3,850.00 1,925.00 1,925.00 0.0150 bh Kuas 17,050.00 255.75 255.75 0.0500 bh Kapek 20,000.00 1,000.00 1,000.00 0.0600 or Tukang cat 75,000.00 4,500.00 4,500.00 0.0800 or Pekerja 55,000.00 4,400.00 4,400.00 0.0060 or Kepala tukang 80,000.00 480.00 480.00 0.0040 or Mandor 90,000.00 360.00 360.00
Jumlah 9,740.00 9,406.75 19,146.75 M.10 1 M2 Mengecat dasar / meni
0.0840 kg Cat meni 25,850.00 2,171.40 2,171.40 0.0440 ltr Minyak cat 16,500.00 726.00 726.00 0.0600 or Tukang cat 75,000.00 4,500.00 4,500.00 0.0300 or Pekerja 55,000.00 1,650.00 1,650.00 0.0060 or Kepala tukang 80,000.00 480.00 480.00 0.0015 or Mandor 90,000.00 135.00 135.00
Jumlah 6,765.00 2,897.40 9,662.40 M.11
0.1000 kg Plamir 25,300.00 2,530.00 2,530.00 0.4700 kg Cat tembok biasa 15,400.00 7,238.00 7,238.00 0.5000 lbr Ampelas 3,850.00 1,925.00 1,925.00 0.0100 bh Roll 27,500.00 275.00 275.00 0.0500 bh Kapek 20,000.00 1,000.00 1,000.00 0.0400 or Tukang cat 75,000.00 3,000.00 3,000.00 0.0600 or Pekerja 55,000.00 3,300.00 3,300.00 0.0040 or Kepala tukang 80,000.00 320.00 320.00 0.0030 or Mandor 90,000.00 270.00 270.00
Jumlah 6,890.00 12,968.00 19,858.00 M.12 1 m2 Pasang waterproofing
0.4250 kg Waterproofing 27,500.00 11,687.50 11,687.50 0.0750 or Tukang cat 75,000.00 5,625.00 5,625.00 0.1500 or Pekerja 55,000.00 8,250.00 8,250.00 0.0075 or Kepala tukang 80,000.00 600.00 600.00 0.0075 or Mandor 90,000.00 675.00 675.00
Jumlah 15,150.00 11,687.50 26,837.50 N. Pekerjaan Pipa dan SaniterN.1 1 m1 Memasang pipa PVC AW Ø 1/2 inchi
1.2000 m Pipa PVC AW Ø 1/2 inchi 5,225.00 6,270.00 6,270.00 35% Harga pipa ls Perlengkapan 1,828.75 1,828.75 1,828.75
0.0600 or Tukang pipa 75,000.00 4,500.00 4,500.00 0.0360 or Pekerja 55,000.00 1,980.00 1,980.00 0.0060 or Kepala tukang 80,000.00 480.00 480.00 0.0018 or Mandor 90,000.00 162.00 162.00
Jumlah 7,122.00 8,098.75 15,220.75 N.2 1 m1 Memasang pipa PVC AW Ø 3/4 inchi
1.2000 m Pipa PVC AW Ø 3/4 inchi 6,325.00 7,590.00 7,590.00 35% Harga pipa ls Perlengkapan 2,213.75 2,213.75 2,213.75
0.0600 or Tukang pipa 75,000.00 4,500.00 4,500.00 0.0360 or Pekerja 55,000.00 1,980.00 1,980.00 0.0060 or Kepala tukang 80,000.00 480.00 480.00 0.0018 or Mandor 90,000.00 162.00 162.00
Jumlah 7,122.00 9,803.75 16,925.75
1 m2 Pengecatan langit-langit 2 lapis dengan cat tembok, menggunakan kuas termasuk plamur
1 m2 Pengecatan langit-langit 2 lapis dengan cat tembok, menggunakan roll termasuk plamur
NO. NAMA PEKERJAAN HARGA SATUAN UPAH BAHAN JUMLAH HARGA
( Rp ) ( Rp ) ( Rp ) ( Rp )
N.3 1 m1 Memasang pipa PVC AW Ø 1 inchi1.2000 m Pipa PVC AW Ø 1 inchi 7,975.00 9,570.00 9,570.00
35% Harga pipa ls Perlengkapan 2,791.25 2,791.25 2,791.25 0.0600 or Tukang pipa 75,000.00 4,500.00 4,500.00 0.0360 or Pekerja 55,000.00 1,980.00 1,980.00 0.0600 or Kepala tukang 80,000.00 4,800.00 4,800.00 0.0018 or Mandor 90,000.00 162.00 162.00
Jumlah 11,442.00 12,361.25 23,803.25 N.4 1 m1 Memasang pipa PVC AW Ø 2 inchi
1.2000 m Pipa PVC AW Ø 2 inchi 18,700.00 22,440.00 22,440.00 35% Harga pipa ls Perlengkapan 6,545.00 6,545.00 6,545.00
0.0900 or Tukang pipa 75,000.00 6,750.00 6,750.00 0.0540 or Pekerja 55,000.00 2,970.00 2,970.00 0.0090 or Kepala tukang 80,000.00 720.00 720.00 0.0027 or Mandor 90,000.00 243.00 243.00
Jumlah 10,683.00 28,985.00 39,668.00 N.5 1 m1 Memasang pipa PVC AW Ø 4 inchi
1.2000 m Pipa PVC AW Ø 4inchi 53,350.00 64,020.00 64,020.00 35% Harga pipa ls Perlengkapan 18,672.50 18,672.50 18,672.50
0.1350 or Tukang pipa 75,000.00 10,125.00 10,125.00 0.0810 or Pekerja 55,000.00 4,455.00 4,455.00 0.0135 or Kepala tukang 80,000.00 1,080.00 1,080.00 0.0041 or Mandor 90,000.00 369.00 369.00
1.0000 bh Closed jongkok teraso 132,000.00 132,000.00 132,000.00 0.0100 m3 Batu bata 500,000.00 5,000.00 5,000.00 6.0000 kg Semen Pc 50 kg 1,342.00 8,052.00 8,052.00 0.0100 m3 Pasir pasang 100,600.00 1,006.00 1,006.00 1.5000 or Tukang batu 75,000.00 112,500.00 112,500.00 1.0000 or Pekerja 55,000.00 55,000.00 55,000.00 0.3000 or Kepala tukang 80,000.00 24,000.00 24,000.00 0.1100 or Mandor 90,000.00 9,900.00 9,900.00
Jumlah 201,400.00 146,058.00 347,458.00 N.8 1 bh Memasang closed duduk/monoblock
1.0000 bh Closed duduk/monoblock 2,200,000.00 2,200,000.00 2,200,000.00 6% Harga Closed ls Perlengkapan 132,000.00 132,000.00 132,000.00
1.1000 or Tukang batu 75,000.00 82,500.00 82,500.00 3.3000 or Pekerja 55,000.00 181,500.00 181,500.00 0.0010 or Kepala tukang 80,000.00 80.00 80.00 0.1600 or Mandor 90,000.00 14,400.00 14,400.00
Jumlah 278,480.00 2,332,000.00 2,610,480.00 N.9 1 bh Memasang urinoir
1.0000 bh Urinoir 880,000.00 880,000.00 880,000.00 30% Harga Urinoir ls Perlengkapan 264,000.00 264,000.00 264,000.00
6.0000 kg Semen Pc 50 kg 1,342.00 8,052.00 8,052.00 0.0100 m3 Pasir pasang 100,600.00 1,006.00 1,006.00 1.0000 or Tukang batu 75,000.00 75,000.00 75,000.00 1.0000 or Pekerja 55,000.00 55,000.00 55,000.00 0.1000 or Kepala tukang 80,000.00 8,000.00 8,000.00 0.1000 or Mandor 90,000.00 9,000.00 9,000.00
Jumlah 147,000.00 1,153,058.00 1,300,058.00 N.10 1 bh Memasang wastafel keramik
1.0000 bh Wastafel keramik 286,000.00 286,000.00 286,000.00 12% Harga Westafel ls Perlengkapan 34,320.00 34,320.00 34,320.00
6.0000 kg Semen Pc 50 kg 1,342.00 8,052.00 8,052.00 0.0100 m3 Pasir pasang 100,600.00 1,006.00 1,006.00 1.4500 or Tukang batu 75,000.00 108,750.00 108,750.00 1.2000 or Pekerja 55,000.00 66,000.00 66,000.00 0.1500 or Kepala tukang 80,000.00 12,000.00 12,000.00 0.1000 or Mandor 90,000.00 9,000.00 9,000.00
Jumlah 195,750.00 329,378.00 525,128.00 N.11 1 bh Memasang bak cuci piring stainless steel (1 lobang)
1.0000 bh Bak cuci stainless steel (1 lobang) 286,000.00 286,000.00 286,000.00 1.0000 set Water drain+accessories 34,100.00 34,100.00 34,100.00 0.3000 or Tukang batu 75,000.00 22,500.00 22,500.00 0.0300 or Kepala tukang 80,000.00 2,400.00 2,400.00
Jumlah 24,900.00 320,100.00 345,000.00
NO. NAMA PEKERJAAN HARGA SATUAN UPAH BAHAN JUMLAH HARGA
( Rp ) ( Rp ) ( Rp ) ( Rp )
N.12 1 bh Memasang bak cuci piring stainless steel (2 lobang)1.0000 bh Bak cuci stainless steel (2 lobang) 484,000.00 484,000.00 484,000.00 1.0000 set Water drain+accessories 34,100.00 34,100.00 34,100.00 0.3000 or Tukang batu 75,000.00 22,500.00 22,500.00 0.0300 or Kepala tukang 80,000.00 2,400.00 2,400.00
Jumlah 24,900.00 518,100.00 543,000.00 N.13 1 bh Memasang kran air Ø 1/2 inchi (stainless steel)
1.0000 bh Kran air Ø 1/2 inchi (stainless steel 38,500.00 38,500.00 38,500.00 0.0250 rol Seal tape 4,950.00 4,950.00 4,950.00 0.1000 or Tukang pipa 75,000.00 7,500.00 7,500.00 0.0100 or Kepala tukang 80,000.00 800.00 800.00
Jumlah 8,300.00 43,450.00 51,750.00 N.14 1 bh Memasang kran air Ø 3/4 inchi (stainless steel)
1.0000 bh Kran air Ø 3/4 inchi (stainless steel 39,600.00 39,600.00 39,600.00 0.0250 rol Seal tape 4,950.00 4,950.00 4,950.00 0.1000 or Tukang pipa 75,000.00 7,500.00 7,500.00 0.0100 or Kepala tukang 80,000.00 800.00 800.00
Jumlah 8,300.00 44,550.00 52,850.00 N.15 1 bh Memasang kran air Ø 1/2 inchi (galvanis)
1.0000 bh Kran air Ø 1/2 inchi (galvanis) 22,000.00 22,000.00 22,000.00 0.0250 rol Seal tape 4,950.00 4,950.00 4,950.00 0.1000 or Tukang pipa 75,000.00 7,500.00 7,500.00 0.0100 or Kepala tukang 80,000.00 800.00 800.00
Jumlah 8,300.00 26,950.00 35,250.00 N.16 1 bh Memasang kran air Ø 3/4 inchi (galvanis)
1.0000 bh Kran air Ø 3/4 inchi (galvanis) 26,400.00 26,400.00 26,400.00 0.0250 rol Seal tape 4,950.00 4,950.00 4,950.00 0.1000 or Tukang pipa 75,000.00 7,500.00 7,500.00 0.0100 or Kepala tukang 80,000.00 800.00 800.00