    Keith Henning, Marc Van Wonderen Halliburton

    Jason Smith and Eric Ladbrook Shell EPE

    12th SPE ICoTA European Well Intervention Round Table

    Use of Mobile HWU in Multi-Platform Workover Operations in

    the North Sea

  • 8/10/2019 8 Keith Henning - Halliburton.pdf

    2/21

    Introduction An HWU in the North Sea provided long-term workover

    operations as an alternative to standard drilling

    equipment and personnel.

    Various challenges were encountered in facilitating themobile workover operation around five offshoreinstallations during 2005/6.

    Show how the HWU was adapted to operate in two

    operating environments through existing platformderrick packages and as a stand-alone towerencapsulated HWU.

    Lessons learned from these operations.

  • 8/10/2019 8 Keith Henning - Halliburton.pdf

    3/21

  • 8/10/2019 8 Keith Henning - Halliburton.pdf

    4/21

    Why an HWU Was Considered

    Economically more attractive Number of available drilling personnel limited

    Eliminate the need to upgrade existing drilling rig

    equipment

    HWU could provide

    Flexibility and mobility to adapt to each installation Specialist crews

  • 8/10/2019 8 Keith Henning - Halliburton.pdf

    5/21

    Planning and Preparation

    Setting Up a Dedicated Project Team

    A dedicated onshore and offshore team was identifiedto manage the HWU as it moved within the offshoreassets

    Onshore

    Offshore

  • 8/10/2019 8 Keith Henning - Halliburton.pdf

    6/21

  • 8/10/2019 8 Keith Henning - Halliburton.pdf

    7/21

    Planning and Preparation

    The HWU :

    1. Perform cleanup operations.2. Pull/run tubulars up to 9 5/8-in. casing.

    3. Sufficient margins to perform any over-

    pulls at depths of up to15,000 ft.4. Increase tripping speeds by working in

    three weight modes: 200, 400, and

    600K.

    5. Provide a 20K ft/lbs. HWU rotating head.

  • 8/10/2019 8 Keith Henning - Halliburton.pdf

    8/21

    Planning and Preparation

    Platform Surveys

    Standalone or thru

    Derrick.

    Facilities available. Crane

    Additions to Standard

    HWU package

  • 8/10/2019 8 Keith Henning - Halliburton.pdf

    9/21

    Project team meetings

    Installation of the HWU on the platform.

    Installation of the completion components

    Structural verification

    HAZID

    CWOP

    Onshore trials Mobilization

    Planning and Preparation

  • 8/10/2019 8 Keith Henning - Halliburton.pdf

    10/21

    Operational Challenges HWU rig-up environment

    Two rig-up modes Tower rig-up

    Available deck space

    Skid & Pipe

    Availability of crane Heavy crane lifts

    Multiple lifts

    Visual perception on arrival

    Derrick rig-up

  • 8/10/2019 8 Keith Henning - Halliburton.pdf

    11/21

    Operational Challenges HWU rig-up environment

    Two rig-up modes Tower rig-up

    Derrick rig-up

    BOPs below drill floor

    HWU on drill floor Heavy lifts in confined space

    Top Drive Tracks

    HWU Basket level

    Multiple lifts to assemble Escape Methods

  • 8/10/2019 8 Keith Henning - Halliburton.pdf

    12/21

    Operational Challenges HWU rig-up environment

    Two rig-up modes Tower rig-up

    Derrick rig-up

    BOPs below drill floor

    HWU on drill floor Heavy lifts in confined space

    Top Drive Tracks

    HWU Basket level

    Multiple lifts to assemble Escape routes

  • 8/10/2019 8 Keith Henning - Halliburton.pdf

    13/21

    Operational Challenges Limited bed space

    Crews multi-skill Personnel movements closely managed

    Limited deck space

    Up to 450m2 required (equipment + pipe) Sharing with platform activities

    Shutdowns and Construction

    Platform Electrical and Air

  • 8/10/2019 8 Keith Henning - Halliburton.pdf

    14/21

    Completion Design Challenges

    Removal/install. of 13 5/8-in. hanger

    Problem HWU Jack and Slip Window 11

    Full Joint below Hanger

    Solution

    Cut below hanger & lay down

    Fish tubing at surface

    Install short joint for RIH

  • 8/10/2019 8 Keith Henning - Halliburton.pdf

    15/21

    Completion Design Challenges Install ASV

    Problem

    Wellbore ASV ~42 ft long.

    HWUs 10-ft hydraulic jack cylinder stroke

    Could not be deployed with crane

    ASV had control line pre-installed Solution

    Assy. had to be walked through the HWU

    Used multiple points to set slips

    Removed from 3 wells and installed into 2

  • 8/10/2019 8 Keith Henning - Halliburton.pdf

    16/21

    ASV assembly walked thru HWU

  • 8/10/2019 8 Keith Henning - Halliburton.pdf

    17/21

    Completion Design Challenges

    Install Dual Hanger

    Problem

    2 3/8-in ASV on the short string for gasinjection.

    Could not be installed into the std. 10ft

    work window.

    Solution The 10-ft HWU access window was

    extended with 4-ft ext. legs

    Stationary slip window bottom plate was

    modified to 20 3/4-in. Final length let dual assemblies be tailed in

    thru the work window

  • 8/10/2019 8 Keith Henning - Halliburton.pdf

    18/21

    Dual hanger trials

  • 8/10/2019 8 Keith Henning - Halliburton.pdf

    19/21

    Results of the Workover Program

    Auk AA01 ESP workover with

    HWU in derrick

    30 36

    Gannet GA10 Workover due to

    tubing leak with HWU

    in tower

    36 40

    Tern TA22 Well Intervention dueto tubing leak with

    HWU in derrick

    50 43

    Brent Bravo

    BB27

    Workover due to

    TRSSV failure with

    HWU in tower

    45 45

    Brent Charlie

    BC23

    Workover due to

    failed gas lift with

    HWU in derrick

    47 60

    Activity Description Actual TimePlan Time

  • 8/10/2019 8 Keith Henning - Halliburton.pdf

    20/21

    Conclusions HWU program a successful alternative to drilling

    pkgs.

    HWU offered flexibility: mobile and adaptable to the

    restrictions of each installation.

    Dedicated project team onshore successful in

    Liaising with various offshore platform teams.

    Program benefited from keeping dedicated lead

    offshore personnel.

    HWU crews able to integrate into different

    platform systems.

    Twelve months without a reportable HSEincident.