WRPC Annual Report 2009-10 25 C H A P T E R - 6 MEETINGS 6.1 MEETINGS OF THE WRP COMMITTEE During the year 2009-10, three meetings of WRP Committee were held wherein, operational, commercial and other technical matters of interest, common to the constituents, were discussed. Technical Co-ordination Committee meetings preceded the WRP Committee meetings. Important decisions taken in the meetings are given below: The 10 th WRP Committee meetings was held on 30th May 2009 at Diu • ULDC project was under extended AMC period up to 31.05.2009 and there was a need for going in for a comprehensive Long Term Service Agreement (LTSA). M/s GE had submitted their offer to take up AMC which broadly covered the scope of SCADA / EMS / DTS software as well as hardware at ten control centers commissioned under the ULDC project. It was agreed to assign the maintenance of sophisticated load dispatch system to OEM so that Real time Data availability by interrupt free maintenance of LD equipment is ensured being utmost important for grid operation. The WRP Committee agreed for LTSA through OEM route and that LTSA be taken up with M/s GE for five years at about Rs. 32.5 crores. Further replacement action for the new system should be initiated before the end of three year period so that the new system could be in place by the end of the LTSA period. • The transmission system associated with Tilaiya Ultra Mega Power Project (4000 MW) in Jharkhand, Nabinagar (1000 MW) of Railways and NTPC, Barh- II (1320 MW), Rihand-III (1000 MW), Vindhyachal-IV (1000 MW) and Mauda (1000 MW) of NTPC, and IPPs in Jharkhand, Orissa, MP, Chhattisgarh, and Maharashtra were discussed and identified in 28 th meeting of the Standing
25
Embed
6E- Chapter 2009-10-Final - Welcome to Western Regional Power …wrpc.gov.in/annualreport0910/chapter6.pdf · · 2011-03-02envisaged that in case of fuel shortage in a thermal generating
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
WRPC Annual Report 2009-10
25
C H A P T E R - 6
MEETINGS 6.1 MEETINGS OF THE WRP COMMITTEE
During the year 2009-10, three meetings of WRP Committee were held wherein,
operational, commercial and other technical matters of interest, common to the
constituents, were discussed. Technical Co-ordination Committee meetings preceded
the WRP Committee meetings. Important decisions taken in the meetings are given
below:
The 10th WRP Committee meetings was held on 30th May 2009 at Diu
• ULDC project was under extended AMC period up to 31.05.2009 and there was
a need for going in for a comprehensive Long Term Service Agreement
(LTSA). M/s GE had submitted their offer to take up AMC which broadly
covered the scope of SCADA / EMS / DTS software as well as hardware at ten
control centers commissioned under the ULDC project. It was agreed to assign
the maintenance of sophisticated load dispatch system to OEM so that Real
time Data availability by interrupt free maintenance of LD equipment is
ensured being utmost important for grid operation. The WRP Committee
agreed for LTSA through OEM route and that LTSA be taken up with M/s GE
for five years at about Rs. 32.5 crores. Further replacement action for the new
system should be initiated before the end of three year period so that the new
system could be in place by the end of the LTSA period.
• The transmission system associated with Tilaiya Ultra Mega Power Project
(4000 MW) in Jharkhand, Nabinagar (1000 MW) of Railways and NTPC, Barh-
II (1320 MW), Rihand-III (1000 MW), Vindhyachal-IV (1000 MW) and Mauda
(1000 MW) of NTPC, and IPPs in Jharkhand, Orissa, MP, Chhattisgarh, and
Maharashtra were discussed and identified in 28th meeting of the Standing
WRPC Annual Report 2009-10
26
Committee on Power System Planning in WR .The transmission scheme were
identified in four groups, viz. (i) generation specific, (ii) system strengthening
common for WR and NR, (iii) system strengthening for WR and (iv) pooling
stations for IPPs in Orissa. WRP Committee agreed to the scheme and stressed
that the actual programme with each of the projects, once finalized, will be
brought forth in the Standing Committee meeting and to WRPC meeting. Also,
any change in the transmission scheme, if any, subsequent to discussion in other
region, will have to be brought to the notice of WRP Committee for its
approval.
• WRP Committee approved the cost estimates of Rs 5.16 crores towards
extending the data communication link from Raipur to Bhilai for pooling in
regional system.
• WRP Committee agreed to the transmission scheme connected with
vindhyachal pooling station and phasing of transmission work as below :-
a) When the initial unit at Vindhyachal stage-IV and Rihand-III generation are
commissioned they could be connected to Vindhyachal Pooling point and the
Vindyachal Pooling-Satna-Gwalior 765 kV link be charged at 400 kV level.
b) LILO of Vindhyachal- Jabalpur 400 kV D/C at Sasan.
c) the Vindyachal Pooling-Satna-Gwalior link can be charged at 765 kV level
along with interconnection of Sasan-Vindyhachal 765 kV S/C.
d) After charging at 765 kV level the LILO of Vindhyachal – Jabalpur 400 kV
D/C line at Sasan could be disconnected with suitable switching arrangements
at Sasan 400 kV switchyard to meet its starting power requirements in future.
• Clause 21(4) of Central Electricity Regulatory Commission (Terms and
Conditions of Tariff) Regulation, 2009, which came into force w.e.f. 1.04.2009,
envisaged that in case of fuel shortage in a thermal generating station, the
generating company might propose to deliver a higher MW during peak-load
hours by saving fuel during off-peak hours. The concerned Load Despatch
Centre may then specify a pragmatic day-ahead schedule for the generating
WRPC Annual Report 2009-10
27
station to optimally utilize its MW and energy capability, in consultation with
the beneficiaries. Average Declared Capacity i.e. DCi in such an event shall be
taken to be equal to the maximum peak-hour ex-power plant MW schedule
specified by the concerned Load Despatch Centre for that day.” WRPC
decided following methodology for computation of payment of capacity
charges for thermal generating station in case of fuel shortage:
a) Peak Hours would generally be worked out by taking into regional load of
previous days or similar day of the previous week.
b) It would be of continuous 5 Hrs. (20 time blocks of 15 minutes)
c) The entire year will be divided in two seasons i.e. April to September as
summer and October to March as winter season.
d) Peak Hours during the month of April to September- 1800 Hrs to 2300 Hrs.
e) Peal Hours during the month of October to March – 1700 Hrs to 2200 Hrs.
f) DCi will be taken equal to maximum ex-power plant MW schedule specified
by the WRLDC continuously during the above defined peak hours for that
day
• WRP committee agreed to Installation of 1 x 125 MVAR bus reactors at Rajgarh
sub-station.
11th WRPC meetings was held on 25th September 2009 at Raipur
• The WR Power Committee approved the implementation of WAMS Project in
WR with TCS, IIT Bombay & Tata Power Company limited as consortium
partners and repayment of the loan from CSIR through UI cap fund. The
estimated cost of the project is Rs. 16.75 Crores. POWERGRID share of total
estimated cost of the project is Rs. 8.76 Crores to be met through UI cap fund.
The POWERGRID Share of project cost is for installation of PMUs,
Hardware/software at WRLDC etc. The data generated by PMUs shall be
available at WRLDC and shall be used by the WRLDC for grid operation as
and when they are commissioned. CSIR shall provide soft loan at an interest
WRPC Annual Report 2009-10
28
rate of 3% for implementation of the project, which shall be repaid over a
period of ten years in annual installments. The Project completion time has been
envisaged as two years for development followed by one year for performance
monitoring. Balance amount of the project cost (Rs 7.99 Crs) would be given by
CSIR to IITB as grant and as loan to TCS and Tata Power. The total project
cost of Rs. 16.75 Crs shall be shared by PCGIL – 8.76 Crs, TCS- 3.77 Crs,
Tata Power, 1.44 Crs. and IIT-B- 2.77 . The main features of the project are
as follows:
(i) Installation of PMUs (Phasor Measurement Units) at around 25 to 30 locations
in Western Region Grid. The data from PMUs shall be acquired at Western
Regional Load Despatch Centre (WRLDC)
(ii) Development of software functions using PMU data.
• Transmission system associated with IPPs located in Orissa, Jharkhand, West
Bengal, Madhya Pradesh and Chhattisgarh, Vindhyachal-IV (1000MW) and
Rihand-III (1000MW) generation projects of NTPC and Mauda (2X500 MW)
generation project of NTPC , which were finalized by the Standing Committee
on transmission planning in Western Region were discussed and WR Power
Committee with a broader approach and in the interest of building up of strong
National grid network gave the concurrence for implementation of the proposed
transmission schemes
• As per the clause 9 of Central Electricity Regulatory Commission (Unscheduled
Interchange charges and related matters) Regulations, 2009, all payments on
account of UI charges including additional UI charges levied under the above
Regulations and the interest received on late payment thereof shall be credited
to a Fund called the “Unscheduled Interchange Pool Account Fund”,
Accordingly from 1st April’2009 onwards the surplus amount generated through
the interest earned through deposit amount for UI in IDBI bank and the residual
interest after payment to UI interest receivables will be kept in the
“Unscheduled Interchange Pool Fund”.
WRPC Annual Report 2009-10
29
Member Secretary, WRPC stated that during TCC meeting held on 24th September
2009, Gujarat, MP, Chhattisgarh and Maharashtra had suggested that planned outages
of 500 MW units should not be taken in the months of October to March of the year
and for the current year.
• The WRP Committee deliberated the issue relating to the power scenario in the
Western Regional grid and endorsed the following action plan recommended by
TCC on 24.09.2009: -
(i) The expected power deficit of Western Region 5500-7600 shall have
to be managed through the requisite load shedding and by
implementing distress load shedding plan in the right earnest and as
recommended by WRLDC.
(ii) AUFLS relays should be ensured to remain in operating condition
and provide load relief as per the expected quantum.
(iii) Planned outages of 500 MW units should not be taken in the months
of October to March of the year
The 12th WRPC meetings was held on 16th January 2010 respectively at Vadodara
• WRPC was informed of successful completion of PSS Tuning activity for WR
under Phase I, in which 12 units for PSS Tuning, namely two units each at Dahanu,
Wanakbori, Nasik, Korba West, Satpura and NTPC Korba were identified was
successfully completed. Further, 14 Units namely three units at Parli, three at NTPC
Korba, four at SGTPS Birsingpur, one at Chhattisgarh and three at Gandhinagar under
PSS Tuning for Phase-II in Part I were also identified and the tuning for six units
namely three units each at Parli and Korba NTPC had already been successfully
completed. In the month of Nov. 2009, PSS tuning of generating units at SGTPS
Birsingpur Unit No. 1 to 4 (210 MW each) and Korba (West) unit No. 2 (210 MW)
was carried out successfully.
• WRPC Committee observed that under the prevailing scenario, the excess
injection of power in the grid or excess drawl by the neighboring regions viz.
WRPC Annual Report 2009-10
30
NR and ER were the contributing factors for causing network congestion
following decisions were taken to ease congestion
a) The progress of ongoing intra-regional and inter-regional transmission
lines under construction shall be discussed and reviewed on quarterly
basis by TCC.
b) PGCIL shall carry out study to access the requirement of additional
inter-regional link
• Considering the importance of timely completion of on going transmission
network etc. the WRPC recommended that progress of intra-regional and inter-
regional transmission lines under construction in the region may be discussed
and reviewed on quarterly basis by TCC in a separate meeting. The meeting
shall be convened by Member Secretary, WRPC with representatives from State
TRANCOS, PGCIL and agencies executing transmission schemes in WR
through IPTC. The outcome of the same will be placed in TCC/WRP
Committee meeting for further deliberations.
• Due to failure of communication link between RLDC and SLDC, it became
difficult for SLDC to assess/monitor their real time drawal. The matter was
deliberated and WRP Committee decided that PGCIL will address the issues
concerning frequent failure of communication between RLDC and SLDC
leading in interruption of real time data communication to SLDC. Also, PGCIL
will discuss the matter with the supplier to check the feasibility of providing an
additional port in the gateway for data communication to SLDC in respect of
substation with automation.
• Budget / Revised estimate of WRPC secretariat for the year 2009-10 & 2010-
11. WRP Committee approved revised budget estimate for the year 2009-10
and proposed budget estimate for 2010-11 as indicated below:
Revised Budget Estimate for the year 2009-10 : Rs. 321 Lakhs
Proposed Budget Estimate for the year 2010-11: Rs. 321 Lakhs
WRPC Annual Report 2009-10
31
6.2 MEETINGS OF OPERATION & CO- ORDINATION COMMITTEE
The Operation & Coordination Committee consisting of System Operation Engineers
of constituent State Electricity Utilities, WRLDC, NTPC, PGCIL, Nuclear Power
Corporation, Tata Electric Cos., Reliance Energy Ltd., Torrent A.E. Company, NCA
etc. reviews the system operation and prepares monthly schedules. The Committee met
regularly every month and dealt with the following activities:
• Reviewing the schedule v/s. actual generation of various power stations, drawn
up in the previous month.
• Estimating the availability of power and energy from each power station and
demand of each State for the current and next month.
• Drawing up coordinated maintenance schedule for generating units and major
transmission lines etc.
• Reviewing norms for the system operational discipline to be observed by WR
constituents.
• Reviewing the operation of Automatic Under-Frequency Relays.
• Discussing system occurrences, if any, during the previous month and
reviewing the programme of implementation of the preventive measures.
• Any other specific issues concerning grid operation.
Important decisions taken in the Operation & Coordination Committee meetings
are given below
• Consequent to Commissioning of 400 kV Kansari-Kankroli D/C line in the
event of tripping of 400 kV Kansari-Soja line to avoid tripping of other 220 kV
feeders to Kansari committee suggested following measures
a) Diverting more power on NR-WR HVDC link
b) Load shedding at Kankroli
c) Opening one of the Feeder of 400 kV Kansari- Kankroli D/C
WRPC Annual Report 2009-10
32
• High voltage Problem at Sipat was deliberated and Committee observed that
automatic switching of unit aux. on station transformer in the event of unit
transformer tripping is a general practice and advised NTPC to approach suppliers of
scheme and find out solution so that 5% voltage restriction for switching is removed.
NTPC agreed to do so.
• It was agreed that all the constituents shall ensure availability of UFRs at
prescribed settings.
• Committee agreed to the needs that planned maintenance be carried out in
accordance with the recommendation of the Kukde Committee. It was stressed that the
constituents should adhere to the planned outage program as already approved. Also,
the progress of work should be closely monitored and time frame should be maintained
as recommended by Kukde Committee.
• The OC sub-Committee noted that Cabinet Sectt. have requested Central Nodal
Ministries / Departments to draw Schedule of Review of Crisis Management Plan
and draw up a schedule of mock drills to verify preparedness for the year 2009-10
• The OCC committee noted the following schedule for implementation of only
restricted governor operation in various types of thermal and hydro units:
Type Category To be implemented by
Software based EHG
system
1.03.2010 KWU & LMZ turbines
for thermal sets of 200
MW and above Hardware based EHG
system where boiler
controls are in “ Auto”
1.06.2010
Hydro units of 10 MW
and above
- 1.03.2010
WRPC Annual Report 2009-10
33
• Trial operation of the generating units ready for FGMO in WR may be carried out
on 02.04.2010
• The Sub-Committee discussed Full load testing of 765 kV / 400 kV
transformers at Seoni S/S and it was agreed that Powergrid may test full
load capacity of the transformers. However, adequate contingency measures
in the event of tripping of transformers shall be taken by
WRLDC/POWERGRID prior to the commencement of the testing so as to
ensure uninterrupted grid operation during the testing period.
6.3 MEETINGS OF COMMERCIAL COMMITTEE
During the year 2009-10, three meetings of the Commercial Committee of WRPC were
held to discuss and resolve commercial matters. The Committee discussed various
commercial issues and also reviewed the payment of weekly UI and reactive energy
charges etc. The Excerpts of the decisions taken in the meetings are:
52nd Commercial Committee meeting held on 9th April 2009, Mumbai
Commercial Committee had decided that the scheduling, monitoring etc. in respect of
Sugen Power Station will be carried out by SLDC, GETCO in line with CERC order
dated 7th May 2008. While granting the open access to Sugen Power station, SLDC,
GETCO, seeks clearance from WRLDC on day-to-day basis. It was noted that
considerable CTU network is used for evacuation of Sugen power and as such it was
necessary for SLDC, GETCO to ascertain if there is any congestion in CTU network.
Committee was requested to consider WRLDC's submission for reviewing the earlier
decision taken during 50th CCM as there is an exit way provided by CERC in case of
any difficulty faced by scheduling agency or RLDC. it was decided that scheduling,
monitoring, accounting etc. to be continued with SLDC, GETCO and in case of any
transmission constraints; generation at Sugen power station should be suitably
regulated.
WRPC Annual Report 2009-10
34
• In term of Central Electricity Regulatory Commission (Terms & Condition of
Tariff) Regulation, 2009, the monthly Energy account (REA) issued by RPC
shall also include a statement specifying the ratio in which transmission charges
for interstate transmission system for that month are to be shared by
transmission users in accordance with regulation 3.3. Also, the bill for
transmission charges (inclusive of incentive) for transmission charges for a
month should be raised by the transmission licensee based on its estimate of
Transmission System Availability Factor (TAFM) for the month and
adjustment, if any, has to be made on the basis of TAFM to be certified by the
Member Secretary of WRPC within 30 days from the last day of the relevant
month. Further as per Clause-32 (3) of Central Electricity Regulatory
Commission (Terms and Conditions of Tariff) Regulations, 2009, the monthly
regional energy account issued by Member Secretary of the Regional Power
Committee should also include a statement specifying the ratio in which
transmission charges for the month are to be shared by the transmission users in
accordance with regulation 33. Accordingly it was agreed that that PGCIL
would make available the details of outages (certified by WRLDC) to all the
beneficiaries by 10th of the following month. Concerned beneficiaries, after
examining these details, should furnish their comments/observations, if any, to
WRPC by the 20th of the following month. In case of non-receipt of the same by
this time period, it will be taken, as no comments. Member Secretary, WRPC,
will certify the TAFM accordingly. PGCIL would raise the transmission
charges bill based on the REA and constituents will make the payment
accordingly.
• In term of Clause 21(4) Of Central Electricity Regulatory Commission (Terms
And Conditions Of Tariff) Regulation, 2009, “In case of fuel shortage in a
thermal generating station, the generating company may propose to deliver a
higher MW during peak-load hours by saving fuel during off-peak hours. The
concerned Load Despatch Centre may then specify a pragmatic day-ahead
schedule for the generating station to optimally utilize its MW and energy
capability, in consultation with the beneficiaries. Average Declared Capacity
WRPC Annual Report 2009-10
35
i.e. DCi in such an event shall be taken to be equal to the maximum peak-hour
ex-power plant MW schedule specified by the concerned Load Despatch Centre
for that day.” following was decided for computation of payment of capacity
charges for thermal generating station:
b) Peak Hours would generally be worked out by taking into regional load of
previous days or similar day of the previous week.
c) It would be of continuous 5 Hrs. (20 time blocks of 15 minutes)
d) The entire year will be divided in two seasons i.e. April to September as
summer and October to March as winter season.
e) Peak Hours during the month of April to September – 1800 Hrs to 2300 Hrs.
f) Peal Hours during the month of October to March – 1700 Hrs to 2200 Hrs.
g) Dci will be taken equal to maximum ex-power plant MW schedule specified by
the WRLDC continuously during the above defined peak hours for that day
53rd Commercial Committee meeting held on 8th September 2009 at , Mumbai.
• Automatic Meter Reading (AMR) solution developed by M/s BPL for
downloading and transmitting the data from remote locations to RLDCs having
main feature of automatically reading from the meter and transmitted to RLDC
was deliberated and the committee members unanimously opined that the above
project may be initially taken at few 3 or 4 locations in the Western Region free
of cost and based on the experience the decision for implementing the same for
all locations will be taken later on, Asoj, Koradi or Kolhapur, Korba(W) and
Bina or Bhopal locations can be initially taken up by M/s BPL to start the
project.
54th Commercial Committee meeting held on10th Dec. 2009 at Mumbai
• The Commercial committee deliberated the existing practice followed in WR
for Utilization of Un-requisitioned power by constituents of WR from NTPC
power stations in WR and its scheduling within the region in detail and
WRPC Annual Report 2009-10
36
suggested that in view of observations made by WRLDC, the matter may be
put up to WRP Committee in its ensuing meeting. However, till such time the
present methodology for scheduling of un-requisitioned power from NTPC
station in WR to the deficit beneficiaries of WR may be continued.
• In accordance with the directions given by the Hon’ble Commission in the order
dated 31.07.2009 in the petition No. 64/2008 and 67/2008, Transmission
charges for use of GETCO transmission system for conveyance of central sector
power to DD and DNH for the period 1.04.09 to 31.03.2010 WRPC Secretariat
had worked out the transmission charges payable to GETCO for conveyance of
Central Sector power to DD & DNH for the period 1.04.09 to 31.03.2010. The
total charges for the year 2009-10 in respect of DD worked out to Rs. 173.41
Lacs whereas in respect of DNH it is Rs. 380.30 Lacs. . The same have been
implemented in the REAs w.e.f. the month of Sept-2009 and for the past period
i.e. April-09 to August-09 and the REAs have accordingly been modified.
6.4 MEETINGS OF PROTECTION COMMITTEE
The Protection Committee constituted by WRP Committee met four times during the
year 2008-09 to review the performance of the protective relaying schemes in the
context of system occurrences which had taken place in the Western Region and to
evolve corrective / preventive measures to enhance grid security. Major
recommendations and issues discussed during above meetings are given below:
105th Protection Committee Meeting held on 18th June 2009 at WRPC Mumbai:
The Committee discussed the system occurrences that occurred in the WR grid during
the period January 2009 to March 2009.
In regards to the system disturbance at 400kV Kharghar S/S, in MSETCL system on 27-
01-2009, Committee observed that tripping of Main bus-II was in order, but operation of
WRPC Annual Report 2009-10
37
Main bus-I was undesirable and felt that the auxiliary contact of the TB isolator might
have operated (mal operation due to interconnection problem) resulting in operation of
Zone-I Bus bar protection. MSETCL, representative told that the high impedance Bus
Bar protection schemes are being replaced with modern numerical Bus Bar protection
schemes at important S/S’s, in a phased manner.
In regard to the system disturbance due to operation of LBB relay at 400 kV Khedamara
S/S in CSPTCL system on 03-02-2009, Committee felt that the 86 relay might have
remained in stuck condition after extending the tripping command to the breaker for
about 200msec. The LBB scheme detected this condition as the stuck breaker condition
and operated. Committee recommended for early replacement of the existing scheme by
phase segregated scheme.
In regards to the system disturbance due to tripping of 220kV Kim-Zagadiya line No. 1
& 2 on Y ph. over current at Kim S/S at 220 kV Kim S/S in GETCO system on 09-02-
2009 leading to tripping of generators at Utran and TPGL, due to non availability of
evacuation, Committee felt that with limitations on the evacuation of power due to
outage of 220kV Kim-Vav 1 & 2 lines, the PS settings of the 220kV Kim-Zagadiya
lines should have been raised to 100% before the outages and also corrective actions
would have been taken to restrict the generation at TPGL, for avoiding the occurrence.
In regards to the system disturbance at 220 kV Uran S/S in MSETCL system on 26-
03-2009, due to busting of the Y-ph line PT resulting in operation of Zone-I bus bar
protection, Committee felt that multiple faults took place over a span of short time at
different locations. The tripping of Bus bar zone1 is in order for a PT fault, which is
covered in this Bus zone. For a transient Y phase to Earth fault on the 220kV Uran-
Apta#2 line the tripping at Apta end on backup protection ahead of DPS zone 2 is
undesirable, and as such the DPS scheme at Apta end should be tested thoroughly. The
backup relay settings of 220kV Uran-HOC-Apta#1 should be reviewed and time
coordinated with the zone-2 timings of the DPS.
WRPC Annual Report 2009-10
38
In regards to system disturbance due to operation of the 220kV Main Bus bar-I
protection scheme, at 220 kV Khaparkheda S/S in MSETCL system on 27-03-2009
Committee observed that the operation of Main Bus 1 Bus Bar protection is in order.
However it was felt that the cause of the bus fault was because of non adherence to the
standard S/S maintenance practices. Maintenance of S/S equipments should be done
strictly as per schedule and earth wire shield between gantry nos 39 & 40 should be
provided at the earliest.
In regards to system disturbance , due to operation of 220kV Main Bus-1 at 400 kV
Chandrapur S/S in MSETCL system on 28-03-2009, Committee observed that the
operation of bus bar protection for TBC (Aux. Bus) and 220kV Main Bus-1 was in order.
However the trippings of 220kV Chandrapur-MIDC and 220kV Chandrapur-Warora
ckt.1 from remote end on DPS Zone 1 is undesirable and the DPS is overreaching.
Committee recommended for through testing of the DPS schemes. MSETCL
representative told that the DPS schemes are proposed to be replaced with numerical
relays.
In regards to the system disturbance, due to multiple tripping of lines and generating
units at KLTPS, SLTPS and ALTPS at 400 kV Chorania S/S in GETCO system on 30-
03-2009, Committee observed that the 400kV Asoj-Chorania line#1 might have tripped
in Zone 1 due to overreach. The power swing blocking and over voltage protection might
have operated due to a sudden throw off of load due to the line trippings.
In regards to the system disturbance due to operation of 220kV Zone-1 Bus Bar
protection at 220 kV Mehsana S/S in GETCO system on 14-01-2009, Committee
observed that the operation of Zone-1 Bus Bar protection scheme was in order.
Committee also felt that regular maintenance/ tightening of the wirings in the relay
panels should be carried out.
WRPC Annual Report 2009-10
39
106th Protection Committee Meeting held on 1st and 2nd September 2009 at WRPC
Mumbai.
The Committee discussed the system occurrences that occurred in the WR grid during
the period April 2009 to June 2009.
In regards to the system disturbance due to non operation of the ABB make RADSS Bus
Bar protection scheme, resulting in tripping of lines from remote ends at 220 kV Tapper
S/S in GETCO system on 02-05-2009, Committee observed that the fault was sensed and
cleared by the remote end relays of the lines connected to the Bus in zone-2, suggesting
that the fault was fed for the zone 2 timings. Further though the fault was of highly
resistive in nature (which would have been confirmed if the fault currents recorded by
the DRs of the remote relays would have been made available), the insensitivity of the
ABB make RADSS Bus Bar Protection scheme to such type of faults needs to be taken
up with the manufacturer.
The Committee further observed that while documenting standard operating procedures,
which are in process, the education of operating staff should be included so as to avoid
such man made mistakes.
In regards to the system disturbance due to non operation of the Areva make numerical
Bus Bar protection scheme because of wrong wirings at 220 kV Wagra S/S in GETCO
system on 31-05-2009, Committee felt that wirings should be checked at the time of
initial commissioning/testing of the Bus Bar protection scheme to avoid such avoidable
failures.
In regards to the System disturbance due to operation of LBB of the T/F-1, while
charging the 220/66 KV 100 MVA T/F -1 on 96 relay at 220kV Vav S/S in GETCO
system on 23-06-2009, Committee felt that the inrush current sustaining for 10cycles is
not a good sign from the point of view of healthiness of the transformer as per the
records of the DR recorded by the relay. Further it was also felt that the transformer
Breaker should have tripped through the TC-2, in the event of failure of the TC-1.
WRPC Annual Report 2009-10
40
In regards to the system disturbance due to operation of the Bus Bar differential
protection of 132 kV Bus A at Sikka TPS in GSECL system on 04-06-2009, Committee
observed that the tripping of feeders connected to Bus-A on operation of the Bus Bar
protection is in order. However tripping of 132kV Dhrol and 132kV Naghedi lines
connected to Bus-B from remote ends in Zone 3 timing is highly undesirable for a Bus
fault of transient nature and in view of the normal test results of the Bus Coupler breaker
timings. It was also pointed out that if PMU data comes into the system such failures
could be precisely detected and rectified.
In regards to the system disturbance due to operation of 220 KV Main-I Bus-bar
protection scheme at 400 KV S/S Nagda in MPPTCL system on 23-05-2009, Committee
observed that the operation of the Bus Bar protection is in order. However the non-
tripping of 220kV Nagda-Ratlam-I feeder at local end and tripping of this feeder from
remote end in Zone 2 is incorrect. The Circuit Breaker control circuit of this feeder at
Nagda end needs to be thoroughly checked.
In regards to the system disturbance due to operation of the 220kV Bus bar Zone-
2protection at 220kV GTPS Uran S/S in MSETCL system on 19-04-2009, Committee
observed that with the operation of the Bus Inter-connector and Bus Zone-2 protection,
all the 220kV feeders connected to the Bus –I should have also tripped (due to clubbing
of Bus Zone-I & II), thereby isolating the fault being fed from remote end sources and
local sources connected to Bus-I. Due to failure of DC supply meant for isolator logic
of GT unit 5,6,7 & 8 and in view of the Bus Inter-connecter operated (thereby blocking
the Bus Coupler trip), the fault was being fed by these generators from Bus-I and from
Bus-II through the Bus Coupler till the backup protection of the GTs cleared the fault.
However the tripping of 220kV Uran-Apta-II in Zone 2 at Apta end is undesirable. The
trip control circuit of this feeder at Uran end should be checked thoroughly in view of
the CB timing test results of the CB were in order. Also the control circuit of extension
of Bus Bar trip command to all the feeders needs to be checked.
In regards to the system disturbance due to snapping of B phase jumper of 220kV Bus
Coupler bay from isolator end at 400kV Karad S/S in MSETCL system on 19-05-2009,
Committee observed that though the fault was out of zone fault for Bus Zone-1, the fault
WRPC Annual Report 2009-10
41
would have been sensed in the Bus zone-II by the Bus Bar protection scheme. The matter
may be taken up with M/s ABB for not sensing the fault, in view of the fault contribution
recorded by the remote end DRs. Also had the earth fault protection been provided to the
Bus Coupler, the fault would have got isolated. Committee also felt that tripping of
400kV lines and 220kV lines from remote ends in Zone 2 is undesirable and ICTs should
be provided with directional back up protection on HV and LV sides.
In regards to the system disturbance due to operation of 220kV Bus Bar-I differential
protection at 2x220MW KAPS ATPS in NPCIL system on 02-04-2009, Committee felt
that the clamping arrangement of Bus post insulator as described by NPCIL
representative is as per the standard practice. The Bus post insulators might have failed
due to mechanical stress and aging of the insulators hence special attention to condition
monitoring of the older equipment needs to be done. Also, NPCIL may examine the need
of increase in number of supports.
In regards to the system disturbance due to operation of Bus-bar protection of Bus-2 at
400kV Jabalpur S/S in PGCIL system on 12-05-2009, Committee observed that the
operation of Bus Bar protection scheme is in order. However the trippings of 400kV
Vindhyachal-Jabalpur#2, 400kV Jabalpur-Itarsi#1&2 on operation of Main-I/Main-II
protection and sensing the fault in reverse direction is incorrect. Also operation of over
voltage stage –I protection of 400kV Vindhyachal-Jabalpur # 3 & 4 and Jabalpur-Itarsi
#3 & 4 lines is undesirable in view of increase in loading on these feeders due to
tripping of other evacuating circuits.
In regard to the system disturbance due to the mal-operation of Bus-bar protection
(because of scheme wiring problem) for through fault at 400kV Rajgarh S/S in PGCIL
system on 17-06-2009, Committee observed that necessary corrective actions have
already been taken to avoid the undesirable tripping. However PGCIL may take up the
matter with the manufacturer for necessary corrections in the Bus Bar differential
scheme.
WRPC Annual Report 2009-10
42
107th Protection Committee Meeting held on19th and 20th November 2009 at
Lonawala.
The Committee discussed the system occurrences that occurred in the WR grid during
the period July 2009 to September 2009.
In regards to the system disturbance due to operation of LBB protection of Generator
Transformer Unit # 2 at Wanakbori TPS in GSECL system on 18-07-2009, Committee
in general felt that the suggestions needs to be looked at depth and may be taken up while
reviewing the protection manual. However the control circuit needs to be checked during
the routine testing of these relays.
In regards to the system disturbance due to operation of LBB Relay of 400kV Indore-Nagda
Feeder at 400 KV S/S Indore in MPPTCL system on 19-04-2009, Committee felt that the
operation of LBB is undesirable. Sensing the fault at Nagda end (400kV Indore-Nagda
feeder) by the distance protection in Zone-2 indicates that the D/T was not sent from Indore
end and/or not received at Nagda end. Committee further recommended for draining of
moisture regularly for pneumatic breakers, since this leads to corrosion of the operating
mechanism resulting in delayed operation/clearing of fault. Committee also felt that due to
non availability of the SOE and DR records it is very difficult to arrive at any conclusion and
suggest remedial measures and insisted that utilities should make available such records
along with the disturbance reports.
In regards to the system disturbance due to operation of 400kV Bus-Bar differential
(Zone 1, Y-ph) protection at 400kV Satpura S/S in MPPGCL system on 27-08-2009,
Committee observed that the operation of Bus Bar differential protection was in order.
However tripping of 400/220kV ICT on instantaneous O/C is undesirable. The need for
providing/enabling the instantaneous/High set feature of O/C, E/F (backup protection)
may be reviewed during the protection manual review.
In regards to the system disturbance due to operation of the Bus Bar Protection Scheme
at Korba STPS in Chhattisgarh system on 13-09- 2009, Committee observed that the
operation of the Bus Bar protection was in order, however due to tripping of 400kV
WRPC Annual Report 2009-10
43
KSTPS-Bhilai#2 from Bhilai end on receipt of spurious PLCC signal, aggravated the
situation. Committee felt that a statistical data of mal operation of PLCC schemes of
various manufacturers needs to be compiled at the RPC level and requested constituents
to submit the data of PLCC (along with make, type & date & time of operation) mal
operations for the last one year to WRPC.
Also Committee felt that the periodicity of thermovision scanning be raised and this
activity be closely monitored at important S/S’s particularly at the Generating Stations.
In regards to the system disturbances due to operation of the Bus Bar protection of Bus
Coupler 1 (between Bus-1 & Bus-2) and the LBB trip protection relay K96 respectively
at 400 kV VSTPS Vindhyachal S/S in NTPC system on 03.10.2009 and 04.10.2009,
Committee felt that the operation of protection scheme on 03.10.09 was in order.
However necessary steps are required to be taken to avoid accumulation of water vapors
on the S/S yard equipments from the near by cooling towers so that such incidences
could be avoided in future. Also the recommendations of the report of the “Study Group
on the disturbance of 22.07.08 at Vindhyachal STPS”, circulated vide letter No.
WRPC/Prot./Vindya/2008-09/5891 Dtd.03.06.09 be followed and the compliance of the
same may be submitted at the earliest. NTPC representative intimated that
recommendations at paras (ii),(iii),(iv) &(v) of the report of the “Study Group on the
disturbance of 22.07.08 at Vindhyachal STPS”, have been implemented and the
recommendation at (vi) would be complied soon. Committee further felt that the
occurrence of 04.10.09 due to operation of LBB protection seems to be logically in
correct, since taking the feeders into service connected to the Bus section without
resetting the LBB relay (which was operated on 03.10.09), is impossible.
108th Protection Committee Meeting held on 25th and 26th March 2010 at Koradi
Nagpur.
The Committee discussed the system occurrences that occurred in the WR grid during
the period October 2009 to December 2009.
WRPC Annual Report 2009-10
44
In regards to the system disturbance due to operation of Local Breaker Back-up (LBB)
protection of GT-5 at Ukai TPS in GSECL system on 17-10-2009, Committee observed
that the operation of LBB operation due to delayed opening of Y pole and operation of
the low forward power relay is in order. The existing LBB scheme having minimum
current setting of 0.2A, be replaced by LBB scheme having minimum setting of less
than or equal to 0.05A for generator units. Committee felt that the LBB timings for
generators and PDR be kept 200msec and 150msec respectively, since time
discrimination of 50msec is available.
In regards to the system disturbance due to operation of Bus Bar protection of Bus-I at
400kV Choraniya S/S in GETCO system on 29.11.2009, Committee observed that as
discussed in the past, Tan-delta alone couldn’t ascertain the health of the CT. However
trend (deterioration in Tan-delta) of the Tan-delta measurements can give a clue about
the health of the CT. The DG analysis is a comprehensive tool to decide the health of
CT, hence constituents may adopt online DGA and Tan-delta measurements at critical
locations, since these online measurement kits are available in market.
In regards to the system disturbance at 400 kV S/S Indore in MPPTCL system on 22-10-
2009, Committee felt that the CT failure of Jetpura line might have initiated from the line
side thereby resulting in a through fault and as seen from the DR the fault was isolated by
DPS in less than 80msec. Further Committee appreciated supplementing of the DR reports
along with the occurrence report and requested the members of the sub-Committee that all
the major occurrences under Item No. 2, be supplemented with relevant DRs, so that the
analysis/review of the protection schemes/settings becomes easier by correlating the recorded
data with the studies data.
In regards to the system disturbance due to failure of B phase CT of 220 kV Bus coupler
bay at 220kV Parli S/S in MSETCL system on 29-11-2009, Committee felt that thermo
vision scanning be carried out regularly at old S/Ss where the equipments are old.
WRPC Annual Report 2009-10
45
Study Group report on system disturbance at 400 kV VSTPS Vindhyachal S/S in
NTPC system on 22-07-2008
A study group comprising of members from WRPC, WRLDC, VSTPS, Powergrid,
GSECL and MSETCL was formed by Member Secretary, WRPC to look into the matter
in detail and analyze the incidence and come up with remedial measures to avoid
reoccurrences of such incidence
The findings and recommendations of the Study Group is as follows,
(i) There is a need for proper monitoring of the S/S equipment healthiness. Best
practices should be adopted. Different utilities follow different practices. A common
minimum maintenance practice, philosophy and periodicity of testing and details of
tests carried on EHV system equipments should be standardized. In particular DCRM,
Dew point measurements, overhaul of CB operating mechanism etc should
compulsorily be carried out at regular intervals. Protection Committee Meeting (PCM)
forum of WRPC may bring out a common minimum maintenance requirement of EHV
system equipments for adoption by utilities.
(ii) Whenever a timing discrepancy is observed in the CB during testing, it should
be attended immediately.
(iii) DPS of Vindhyachal-Satna #1, and Vindhyachal-Satna #2 lines should be
thoroughly checked for mal-operation during this incidence at Vindhyachal STPS on
Zone-2.
(iv) Monitoring equipments such as Event Recorder, Disturbance Recorder, GPS
time clock are to be kept in working conditions. Effective measures needs to be taken
by stations for maintaining these equipments.
(v) During this disturbance efforts were made to save the two generating units by
transferring them to the healthy bus section, when the line breaker had developed
problem. During this process, a bus fault took place due to faulty breaker and resulted
in entire station tripping and also risked the N-E-W Grid. If instead of saving the two
units, the faulty element/section was isolated by opening the bus coupler immediately
(which would have tripped the two units), the damage would have been limited, most
of the generation would have been saved and N-E-W Grid would have been subjected
WRPC Annual Report 2009-10
46
to lesser stress. Therefore the Study Group recommends that an action plan needs to be
developed by all Generating stations and EHV sub-stations to deal with the emergency
situations such that faulty elements/section should be taken out from grid as fast as
possible to avoid cascading effects.
(vi) Separate differential relays are used for protection of each zone, at Vindhyachal
STPP. This Bus Bar protection scheme should be replaced with numerical Bus Bar
protection at Vindhyachal STPP.
6.5 MEETING OF SYSTEM STUDY GROUP
System Study Group of WRPC, comprising the representatives from the constituents of
the Western region, conducted system studies and operational planning studies
concerning the Western Regional Power system. The System Study Group carried out
studies to finalize the requirement of HT shunt capacitor.
WRPC prepared the study cases for the 2008-10 conditions and the conducted studies
keeping the NR, ER and WR systems in synchronous mode as per present
interconnection conditions. The meeting of the Study Committee was held on 20th April
2009. Since there was no significant addition of EHV/HV shunt capacitors during 08-
09 and the EHV Shunt capacitor requirement targets finalized for 08-09 studies were
felt to be adequate hence the targets for the year 08-09 were retained for the year 09-10.
The targets for 09-10 were as below:
S. No Constituent Capacitor targets in MVAR
1 Gujarat 435
2 Maharashtra 375
3 Madhya Pradesh 110
4 Chhattisgarh 90
5 Goa 0
6 TPC 0
7 AECO 0
8 WR 1010
WRPC Annual Report 2009-10
47
6.6 MEETINGS OF LGBR STUDY COMMITTEE
The report of Load Generation Balance covers the anticipated power supply position viz.
month wise station generation, total availability and requirement, anticipated capacity and
energy shortages of the constituents of the Western Region. The anticipated availability of
each constituent has been worked out taking into consideration of installed capacity, new
addition in generation, maintenance schedule, partial and forced outages etc. The LGBR
helps the constituents in initiating advance action for power purchase and for working out
load regulatory measures. During the year 2009-10, the LGBR Study Committee met on
12.06.09 for 1st quarterly review for the year 2009-10, on 11.09.2009 for 2nd quarterly
review for the year 2009-10, and on 11.12.09 for 3rd quarterly review for the year 2009-10
wherein maintenance programme for the Annual LGBR for the year 2010-11 were finalized.
The Committee met on 12.03.10 to discussed and finalized the requirement details for
the year 2010-11.
Special Meeting to discuss the technical details of the proposed Wide Area
Measurement Systems (WAMS):
A meeting was held on 17.9.2009 at WRLDC, Mumbai to discuss the technical
details of the proposed WAMS project The brief outcome of the discussions is as
follows:
a) MSETCL representative stated that Maharshtra is already implementing a
project of installing PMU / WAMS in their system.
b) GETCO, MPPTCL and CSPTCL representatives were of the view that the
implementation of WAMS should be done at a regional level as proposed by
POWERGRID.
c) So far as the proportionate sharing of the cost of Rs 8.76 cr by Maharshtra is
concerned, Maharashtra stated that they will not be able to share the same as
they are already implementing the WAMS project in their system.
d) Regarding installation of PMUs in MSETCL system under the proposed
regional WAMS project and utilization of the MSETCL installed WAMS PMU
WRPC Annual Report 2009-10
48
data in Maharashtra system, MSETCL representative stated that they would
revert back.
e) Constituents suggested that the expenditure of Rs 8.76 cr for the above project
may be met from the UI cap fund as the project is for system improvement.
WRLDC clarified that this will be subject to the approval of CERC.
f) It was suggested to form a PMU study group at RPC level comprising of
representatives of Protection groups from all the constituents of WR, that will
look into the analysis of correct/incorrect operation of the protection relays
during line trippings and other grid disturbances using inputs from WAMS data
which is in milliseconds time frame, study of stability related issues by study
group etc. At present the data routing was envisaged at RLDC levels. Hence the
data routing should be such that the WAMS PMU data is available to the
Protection and Study groups both at the State as well as RPC level. The
necessary details of data routing to the SLDC/WRLDC/Protection and PMU
Study group can be finalized accordingly.
g) It was also suggested that Task force from the representatives of WR
constituents may be formed which would monitor the progress of the
implementation of the proposed WAMS project.
h) Constituents felt that the continuous real time data (24 x 7) should not be
provided in view of the commercial implications. POWERGRID representative
agreed to discuss the same with IIT-B and revert back. The data sharing by IIT-
B in the above pattern may be done during the project implementation period
only.
Meeting to discuses issues related to synchronization of first unit (330 MW) of
Mundra Thermal power station of M/s. Adani Power Ltd. and its connectivity to
the grid was held at WRPC office Mumbai on 9th April 2009
• The issues concerning synchronization of first unit of 330 MW of Mundra
Thermal Power Station along with its dedicated 400kV Mundra-Sami-Dehgam
transmission line with WR grid was deliberated where in the following was
agreed:
WRPC Annual Report 2009-10
49
a) Initial synchronization of 330 MW 1st Unit of Mundra, TPS of Adani Power
Limited will be through 220 kV Mundra-Nani Khakhar line as this is the only
available link for start up power.
b) Thereafter 400 kV Mundra-Sami-Dehgam line will be charged as per the
charging instructions issued by the CTU (POWERGRID) in coordination with
WRLDC.
c) To enable initial synchronization through Nani Khakhar M/s. Adani Power
Limited (M/s APL) shall coordinate the activities with GETCO authorities in
consultation with SLDC, GETCO, Vadodara.
d) M/s. APL will ensure that all the requisite metering arrangements etc. are in
place before synchronization and connectivity of the lines with grid in
consultation with WRTS-II, PGCIL, Vadodara / WRLDC.
e) WRLDC pointed out that the SEMs (APEX meters of M/s Secure) presently
provided by M/s APL are not compatible with software available at WRLDC.
M/s APL was requested to ensure that compatible meters are provided before
synchronization. If needed, they may request WRTS-II PGCIL, Vadodara for
providing the required meters at Mundra end on payment basis. M/s APL also
to provide SEMs (4 Nos.) on 220 kV Mundra-Nani Khakhar D/C line.
f) M/s APL would confirm in writing the readiness of 400 kV Mundra-Sami-
Dehgam D/c lines after completing pending works.
g) M/s APL would ensure PLCC communication on Mundra-Sami-Dehgam
sections after getting clearance/approval for frequency from relevant authorities.
h) M/s. APL will take prompt action for providing speech, telemetry and data
communication to WRLDC in accordance with IEGC.
6.7 MEETINGS HELD DURING THE YEAR 2009-10
List of WRPC and other Committee Meetings held during the year 2009-10 is given in