    Solar Park:

    Utility Scale Solar Power ProjectDevelopment

    A S M Alamgir KabirChairman, BPDB

    20 September, 2011

  • 7/28/2019 66762248 ASM Alamgir Kabir Solar Projects in Bangladesh

    2/34

    2

    Bangladeshs Power Sector: At a Glance(FY 2010)

    Electricity Growth : 10 % in FY-2010 (Av. 7 % since 1990)

    Generation Capacity : 6984 MW(16 August, 2011)

    Total Consumers : 12.5 Million

    Transmission Lines : 8,600 km Distribution Lines : 2,75,000 km

    Per Capita Generation : 251 kWh (incl. Captive)

    Access to Electricity : 50 %

  • 7/28/2019 66762248 ASM Alamgir Kabir Solar Projects in Bangladesh

    3/34

    3

    Demand Supply Situation

    Generation on Jan 6, 2009: 3268 MW(Capacity- 4931 MW)

    Generation: 5000 5300 MW(Capacity- 6984 MW)

    Highest so far: 5244 MW( August 29, 2011)

    Gas shortage causes 400 - 600 MWless Power Generation

    Peak Demand: 6000 MW(with DSM)

    Load shedding up to800 MWduring hot summer days (with DSM)

    Shortage and unreliable power supply has constrainedeconomic growth

  • 7/28/2019 66762248 ASM Alamgir Kabir Solar Projects in Bangladesh

    4/34

    44444

    Power Generation Projects up to 2016Calendar Year Wise Projects Completion (From 2010 to 2016)

    YEAR

    2010

    (MW)Commissioned

    2011(MW)

    2012(MW)

    2013(MW)

    2014(MW)

    2015(MW)

    2016(MW)

    TOTAL(MW)

    Public 2 5 5 1 1 0 7 5 8 2 1 0 4 0 1 2 7 0 4 5 0 1 5 0 0 6 2 0 4

    Private2 7 0 1 0 5 1 3 1 9 1 1 3 4 1 0 5 3 1 9 0 0 1 3 0 0 7 0 8 1

    QuickRental 2 5 0 1 2 3 8 1 4 8 8

    Total 775 2450 1901 2174 2323 2350 2800 14,773

    Public Sector : 6204 MW (comm: 360 MW, u/c: 1629 MW, Tender: 1425 MW); (42%)

    Private Sector : 8569 MW (comm:1463 MW, u/c: 1667 MW, Tender: 2639 MW); (58%)

    January, 2011

  • 7/28/2019 66762248 ASM Alamgir Kabir Solar Projects in Bangladesh

    5/34

    55555

    Gen Addition Jan 09 Dec 09 : 356 MW

    Gen Addition Jan 10 Dec 10 : 775 MW

    Gen Addition Jan 11 Aug 11 : 1048 MW

    Total Gen. Addition (Jan 09 Aug 11): 2179 MW

    Power Generation Addition From Jan 09 to Aug. 11

  • 7/28/2019 66762248 ASM Alamgir Kabir Solar Projects in Bangladesh

    6/34

    6

    Successful Contract Signed since Jan 2009

    Sl.

    No.

    Descript

    ion

    No. of

    Contract

    No. of

    Plant

    Capacity

    (MW)

    Commis

    . (MW)

    01. PrivateSector

    25 27 3020 1353

    02. PublicSector

    17 17 1734 105

    Total 42 44 4754 1458

    Out of 4754 MW, 1458 MW (18 Plants) already commissioned. 26 Projects with capacity 3296 MW under construction.

  • 7/28/2019 66762248 ASM Alamgir Kabir Solar Projects in Bangladesh

    7/34

    7

    Projects Under Tendering Process: Contract within Next 6Months

    Sl.

    No Description No. of Projects Capacity(MW)

    01. Public Sector 5 1425

    02. Private Sector(IPPs)

    23 2639

    Total 28 4064

  • 7/28/2019 66762248 ASM Alamgir Kabir Solar Projects in Bangladesh

    8/34

    8

    Renewable Energy Policy envisions 5% of total power,i.e. at least 800 MW from renewable sources by 2015.

    Solar energy is the most proven source till date

    Private sector is the engine of growth in power sectordevelopment of Bangladesh

    Solar Park is the concept through which utility scale

    solar power project is to be developed through privatesector

    Renewable Energy Development in Bangladesh

  • 7/28/2019 66762248 ASM Alamgir Kabir Solar Projects in Bangladesh

    9/34

    9

    Policy, Incentives and Security

    Mechanism for Investment inPrivate Power Projects

  • 7/28/2019 66762248 ASM Alamgir Kabir Solar Projects in Bangladesh

    10/34

    10

    Private Sector Power Generation Policy

    Tariff based bidding

    Sovereign guarantee from the Government for

    obligations of Government entities through

    Implementation Agreement (IA)

    Assistance in getting clearances from various agencies

    Attractive incentive packages

  • 7/28/2019 66762248 ASM Alamgir Kabir Solar Projects in Bangladesh

    11/34

    11

    Exemption from corporate income tax for a period of 10years.

    Plant and equipment (full value) and spare parts (10% oforiginal plant cost) without payment of customs duties, VATand any other surcharges.

    Repatriation of equity along with dividends.

    Cont

    Major Incentives for IPPs

  • 7/28/2019 66762248 ASM Alamgir Kabir Solar Projects in Bangladesh

    12/34

    12

    Major Incentives for IPPs..contd.

    Tax exemption and repatriation facilities on royalties,technical know how and technical assistance fees

    Avoidance of double taxation on the basis of bilateral

    agreements

    The Bangladeshi currency, Taka is freely convertible for

    FDI

    Duty Exemption for Solar Panel

  • 7/28/2019 66762248 ASM Alamgir Kabir Solar Projects in Bangladesh

    13/34

    13

    Payment Guarantee

    Implementation Agreement (IA) and PPA will ensure fair andreasonable risk allocation, and payment by the Purchaser is

    guaranteed by GOB

    Payments under the PPA will continue in the event of

    dispatch failure

    Payment under the PPA will be ensured by Letter of Credit

    Payment to Escrow Account ensures lenders re - payment

  • 7/28/2019 66762248 ASM Alamgir Kabir Solar Projects in Bangladesh

    14/34

    14

    Why invest in Bangladesh SolarPark ?

    Projects will implemented on BOO basis

    IPPsare operating about 50 % of total generation and makingprofit;

    IPPsand BPDB have met their obligations under the PPA without

    problems or controversy and no conflict or major problems/issueshave arisen

    Independent Regulation to protect Industry and Consumers

    interests

    Local engineers, technician and skill workers are available

  • 7/28/2019 66762248 ASM Alamgir Kabir Solar Projects in Bangladesh

    15/34

    1515

    Solar Park

    Solar Park Demonstration Projects will be in non-

    agricultural lands

    Two types of Land will be used:

    - Government owned land- Railway owned Land.

    Power generated will be directly fed into the Grid oncommercial basis

    Primarily 8 potential sites have been identified

    Estimated Development Target: 135 MW

  • 7/28/2019 66762248 ASM Alamgir Kabir Solar Projects in Bangladesh

    16/34

    16

    Solar Park at Govt. Land

    Sl. No. Project Location Land available Est. Gen.

    Capacity1. Rajabarihat, Rajshahi 52 Acres 15-20 MW

    2. PGCB Grid Sub-station

    Compound, Ishwardi, Pabna

    18 Acres 5-6 MW

    3. Rajshahi (Char area at theriver Padma)

    500 Acres 150-160 MW

    4. Adjacent area near Bangabandhu Bridge 150 Acres 30-40 MW

    TOTAL 200-226 MW

  • 7/28/2019 66762248 ASM Alamgir Kabir Solar Projects in Bangladesh

    17/34

    1717

    Solar Park at Railway Land

    Sl. No. Location Land available Est. Gen. Capacity

    1. Azampur Railway Station,Dhaka

    52 Acres 12-15 MW

    2. Halishahar RTA, Chittagong 42 Acres 8-10 MW

    3. Pahartoli Railway Station,Chittagong

    25 Acres 5-7 MW

    4. Kumira Railway Station,Chittagong 30 Acres 6-8 MW

    TOTAL 31-40 MW

  • 7/28/2019 66762248 ASM Alamgir Kabir Solar Projects in Bangladesh

    18/34

    18

    Implementation

    To be implemented on BOO basis

    Contract period shall be 15-20 years

    IPP Operator will be selected through Competitive

    Bidding Power Purchase Agreement (PPA) between BPDB and

    IPP Operator

    Land Lease Agreement with IPP Operator

  • 7/28/2019 66762248 ASM Alamgir Kabir Solar Projects in Bangladesh

    19/34

    1919

    BPDB

    Technical

    Assist.

    Select

    s

    Implementation Model: Government Land

    ADB & other DPs

    Solar Park IPP[Equity Participation]

    PRG

    PCG

    BPDB

    Guarantee

    Fee

    Tariff

    15Yrs

    PPA

  • 7/28/2019 66762248 ASM Alamgir Kabir Solar Projects in Bangladesh

    20/34

    2020

    BPDB

    Technical

    Assist.

    Select

    s

    Implementation Model: Railway Land

    ADB & other DPs

    Solar Park IPP[Equity Participation]

    LowI

    nterestCredit

    BPDB

    LoanRepaym

    ent

    Tariff

    15Yrs

    PPA

    RAILWAY

    LandLease

    Fee

    15Yrs

    LLA

  • 7/28/2019 66762248 ASM Alamgir Kabir Solar Projects in Bangladesh

    21/34

    21

    Summary of Project Financing

    Sl.

    No.

    Types Est.

    Capacity(MW)

    Est. Invest.

    Req.Mil. US$

    Est. Loan

    Mil. US$

    Est. Equity

    Mil. US$

    1 Solar Park at Govt. Land 115 546 382

    (70%)

    164

    (30%)

    2 Solar Park at Railway Land 20 95 66.5

    (70%)

    28.5

    (30%)

    Sub-total 135 MW 641 448.5

    (70%)

    192.5

    (30%)

  • 7/28/2019 66762248 ASM Alamgir Kabir Solar Projects in Bangladesh

    22/34

    22

    .

    Site Details

  • 7/28/2019 66762248 ASM Alamgir Kabir Solar Projects in Bangladesh

    23/34

    23

    Rajabarihat, Rajshahi

    Land available : 52 Acres- .

    Land Status:- Land is under Ministry of

    Fisheries and Livestock- Land uncultivated since 1988- Land available in a single plot- High Land and ready to use- Land transfer under process

  • 7/28/2019 66762248 ASM Alamgir Kabir Solar Projects in Bangladesh

    24/34

    24

    PGCB Grid Substation Compound,

    Ishwardi, Pabna

    Land available :

    Spot 1- Near Grid Control Room: 3 acres

    Spot 2- North side of Rest House: 3 acres

    Spot 3- Play ground & adjacent area:7 acres

    Spot 4- About 5 acres

    Total area available: 18 Acres (Approx.)

  • 7/28/2019 66762248 ASM Alamgir Kabir Solar Projects in Bangladesh

    25/34

    2525

    PGCB Grid Substation Compound,

    Ishwardi, Pabna Contd.

  • 7/28/2019 66762248 ASM Alamgir Kabir Solar Projects in Bangladesh

    26/34

    26

    PGCB Grid Substation Compound,

    Ishwardi, Pabna Contd .

    Spot: 1 Spot: 2

    Spot: 3 Spot: 4

  • 7/28/2019 66762248 ASM Alamgir Kabir Solar Projects in Bangladesh

    27/34

    27

    Rajshahi

    Char area in the river Padma

    Prospective Locations:

    Char Mazerdiar: 200 acres (50-60MW) Char Ashariadah: 300 acres (80-100MW)

    - Sub-station and Transmission System is to be

    developed- River crossing Power evacuation system isnecessary

    Ch a r i s a St r i p o f Sa n d y L an d r i s i n g o u t o f a r i v e r b e d .

  • 7/28/2019 66762248 ASM Alamgir Kabir Solar Projects in Bangladesh

    28/34

    28

    Chak Asharia

  • 7/28/2019 66762248 ASM Alamgir Kabir Solar Projects in Bangladesh

    29/34

    29

    Char Mazerdiar

    Chak Asharia

  • 7/28/2019 66762248 ASM Alamgir Kabir Solar Projects in Bangladesh

    30/34

    30

    Adjacent area near

    Bangabandhu Bridge, Sirajgonj

    Land available for Solar PV System :

    East Side of Banghabondhu Bridge (Towards North) : about30 acres

    - Prospective location for 10 MW East side of Banghabondhu Bridge (Towards South) : about

    10 acres- Prospective location for 3MW

    West Side of Banghabondhu Bridge (Towards North) besidesEcopark : about 50 acres

    - Prospective location for 15 MW Sirajgonj embankment adjacent area (paikpara) : about 20

    acres- Prospective location for 7MW

    Area adjacent to NWZPGCL Grid sub-station: 25-30 acres -Prospective location for 10 MW

    Total area available: 150 Acres (Approx.)

  • 7/28/2019 66762248 ASM Alamgir Kabir Solar Projects in Bangladesh

    31/34

    3131

    Adjacent area near

    Bangabandhu Bridge, Sirajgonj

  • 7/28/2019 66762248 ASM Alamgir Kabir Solar Projects in Bangladesh

    32/34

    32

    East Side

    West Side

    Paikpara Near NWPGCL

  • 7/28/2019 66762248 ASM Alamgir Kabir Solar Projects in Bangladesh

    33/34

    33

    Expected Intervention from ADB and

    other Development Partners

    Technical Assistance :- Comprehensive Feasibili ty Study- Project Design- Preparation of Standard Procurement Documents

    - Capacity Building

    Low Interest Credit Support Partial Risk Guarantee Partial Credit Guarantee

    Technical SupportTechnical Support

    Financial SupportFinancial Support