This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
MBP
COCHRANE and OTHER CABLE-STAYED BRIDGES ANALYZED BY MBP
COCHRANE and OTHER CABLE-STAYED BRIDGES ANALYZED BY MBP
• Client: Harbert International, Birmingham, ALAClient: Harbert International, Birmingham, ALA• Claim/Mediation/Trial over delays, inefficiencies and LDs• Eight-year pause in MBP’s work between 1997 and 2005• Jury TrialJury Trial• Complex issues including Engineering of Balanced Cantilever• Successful outcome for Client
Key-words in Construction…“Wh t i P t t i i ?”“What is Post tensioning …?”
• A method of applying external force to pp y gload a structure: usually with high strength steel bars or cables often referred to as tendons.
• Extensively used in Concrete: multi-story buildings and Bridges.
• Also used heavy construction (tiebacks).y ( )
Post-tensioning ConcreteConcrete is strong in compression and weak in tension.
When loaded, a concrete beam will sag or deflect causing the bottom of the beam to elongate and crack.g
Tensile forces tend to pull apart the bottom of a beam as it bends.
Steel reinforcing – rebar - is embedded in concrete as tensile reinforcement to minimize/control cracking.g
The Cochrane Bridge Projectg j• Complete the project after termination of a
previous Contractor.previous Contractor.
• Two Contracts: Main Span & Approaches
• Main Span: mid-span and two back-spans are Cable StayedCable-Stayed
• Approaches: Box Girders cast-on-ground and pp glifted and cast in position. Lifting Equipment provided by Owner.
• Delays & inefficiencies on both contracts
Cochrane Bridge Layoutg y
The Main Spanp
• 1500 ft Main Span over Mobile River.• Three spans: 360, 780 and 360 ftp 360, 80 360• Cast-in-place concrete segments placed in
Balanced Cantilever procedurep• 96 Cable Stays
The Main Span
The Approaches
• Three five-span continuous sections each sideThree five span continuous sections each sideof main span. Typical spans 195 ft.
• 29 Piers each side and two abutments.
• Concrete Superstructure Girders Cast on the Ground cured Post-tensioned then Lifted intoGround, cured, Post tensioned, then Lifted intopermanent position (lifting equipment provided by ADOT).
Background• S.J. Groves was the original contractor
• Terminated for default when Main Span was 45% and• Terminated for default when Main Span was 45% andapproaches 55% complete
• ADOT re-bid completion of the project.
• Existing Structure and Temporary Equipment inspected• Existing Structure and Temporary Equipment inspectedby ADOT and turned over to Harbert, MBP Client.
• NTP to Harbert 7/19/89.
• Construction duration of each contract was 450 days• Construction duration of each contract was 450 days.
MBP Involvement1994 MBP t i d b S i & H lli th• 1994: MBP was retained by Spriggs & Hollingsworth(John Bond), Attorneys for Harbert to:– Analyze construction delays.– Provide expert opinion as to causation, responsibility
and quantification of Delays and Costs.
• 1997: Mediation in Atlanta (Buck Griffin) did not settle.
• 1997 to 2005: Litigation over right to sue State of Alabama; Harbert won.
• February 2005: MBP rehired by Doug Patton for trial preparation and expert testimony on schedule and costs.
Step 1: Verify As-Planned Schedule. Correct Any Absolute Errors,
Omissions.
Step 2: Prepare Detailed As-Built Schedule.
Step 3: Analyze Critical Path Delays by Comparison and Evaluation
of As-Planned and As-Built Performance.of As Planned and As Built Performance.
Analyze Delays and Concurrency with Detailed F t
As-Planned vs. As-BuiltSchedule AnalysisSchedule Analysis
Step 1
AS-PLANNED SCHEDULE
Foundations
Structure
InteriorInterior
Milestone 3
Milestone 2
COMPLETE
Milestone 1
COMPLETEFOUNDATION
21 Days Late
Step 2
COMPLETEPROJECT
56 Days Late
COMPLETESTRUCTURE
36 Days Late
McDonough Bolyard Peck Schedulegraphc
AS-BUILT SCHEDULE
Schedule AnalysisStep 1
AS-PLA N NED SCH EDU LE
Foundations
Step 1
Structure
InteriorInterior
Milestone 3
COMPLETE
Milestone 2
COMPLETESTRUCTURE
Milestone 1
COMPLETEFOUNDATION
21 Days Late
Step 2PROJECT
56 Days Late36 Days Late
Step 3 AS-BUILT SCHEDULE
3RESPONSIBILITY DAYS
OWNERCONTRACTOR
812
6 713 33
16
OTHER 73 4
A n a l y z e D e l a y s
T O T A L 56
OTHER 73 4
McDonough Bolyard Peck Schedulegraphc
IssuesMAIN SPAN:
– Tie-down Drilling Delays Due to AHD’s Stoppagesg y pp g– Formwork adjustments Due to AHD Pier Segment
Defects– Traveler advance: Rear Anchorage Delay Due to g y
Reinforcement Interferences – AHD Elevation Error – Unnecessary Balance of Stay StressingUnnecessary Balance of Stay Stressing– Inadequate Stay Pipe Delays to Cable Stay Stressing– Added Sandblasting Vertical Face of Segments