Top Banner
Draft Initial Environmental Examination (Main Report Part 1 of 2) Project Number: 54035-001 February 2020 IND: Gujarat Solar Power Project Prepared by AECOM India Private Limited for Electro Solaire Private Limited and the Asian Development Bank. This initial environmental examination is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
71

54035-001: Gujarat Solar Power Project

Apr 11, 2023

Download

Documents

Khang Minh
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: 54035-001: Gujarat Solar Power Project

Draft Initial Environmental Examination (Main Report – Part 1 of 2)

Project Number: 54035-001 February 2020

IND: Gujarat Solar Power Project

Prepared by AECOM India Private Limited for Electro Solaire Private Limited and the Asian

Development Bank.

This initial environmental examination is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Page 2: 54035-001: Gujarat Solar Power Project

Environment and Social Impact Assessment

200 MW Solar Power Project in Radhanesda Solar Power Park, Gujarat, India Electro Solaire Private Limited

DRAFT REPORT

February 27, 2020

Page 3: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

AECOM

Quality information

Prepared by Checked by Verified by Approved by

Revision History

Revision Revision date Details Authorized Name Position

05

Distribution List # Hard Copies PDF Required Association / Company Name

No Yes ESPL

Page 4: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

AECOM

Prepared for: Electro Solaire Private Limited 1st Floor, Orchid Centre

Sector 53 Golf Course Road Gurugram - 122002 Haryana, India

Prepared by:

AECOM India Private Limited

19th Floor Building No.5

Tower C

Cyber City

Gurgaon 122002

Haryana

India

CIN: U74210KA2005PTC037770

T: +91 124 4682700/800

aecom.com

© 2020 AECOM India Private Limited. All Rights Reserved.

This document has been prepared by AECOM India Private Limited (“AECOM”) for sole use of our client (the “Client”) in accordance with generally accepted consultancy principles, the budget for fees and the terms of reference agreed between AECOM and the Client. Any information provided by third parties and referred to herein has not been checked or verified by AECOM, unless otherwise expressly stated in the document. No third party may rely upon this document without the prior and express written agreement of AECOM.

Page 5: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

AECOM

Table of Contents

Executive Summary ................................................................................................. 12

List of Abbreviations ................................................................................................. 17

1. Introduction ................................................................................................. 1-19

1.1 Project Background ............................................................................................................... 1-20

1.2 Purpose and Scope of Work .................................................................................................. 1-20

1.3 Approach and Methodology ................................................................................................... 1-21

1.3.1 Delineation of the Study Area/Area of Influence .................................................................... 1-21

1.3.2 Desktop Review ..................................................................................................................... 1-22

1.3.3 Screening and Scoping ......................................................................................................... 1-23

1.3.4 Stakeholder Identification and Analysis ................................................................................. 1-24

1.3.5 Site Survey ............................................................................................................................ 1-24

1.3.6 Socio-Environment Baseline Data collection ......................................................................... 1-24

1.3.7 Stakeholder Consultation ...................................................................................................... 1-25

1.3.8 Impact Assessment ............................................................................................................... 1-25

1.3.9 Environment and Social Management Plan ........................................................................... 1-25

1.3.10 Agencies contacted ............................................................................................................... 1-25

1.4 Limitations ............................................................................................................................. 1-25

1.5 Layout of Report .................................................................................................................... 1-25

2. Project Description ..................................................................................... 2-27

2.1 Project Location ..................................................................................................................... 2-27

2.2 Site Settings .......................................................................................................................... 2-27

2.3 Project Overview ...................................................................................................................... 30

2.3.1 Project Components ................................................................................................................. 30

2.3.1.1 DC Components ....................................................................................................................... 31

2.3.1.2 AC Components ....................................................................................................................... 32

2.3.1.3 Civil Structures ......................................................................................................................... 32

2.3.1.4 Earthing .................................................................................................................................... 33

2.3.1.5 Lighting and Over Voltage Protection ....................................................................................... 33

2.3.1.6 Supervisory Control and Data Acquisition (SCADA) System .................................................... 33

2.3.2 Power Evacuation—Substation and Transmission Line ........................................................... 33

2.3.3 Access Roads ........................................................................................................................... 34

2.4 Status of the Project ................................................................................................................. 34

2.5 Resource Requirement and Procurement ................................................................................ 37

2.5.1 Land requirement and Procurement process............................................................................ 37

2.5.1.1 Project-related land procurement and existing land procurement status .................................. 37

2.5.1.2 Key Issues in Land Procurement .............................................................................................. 38

2.5.2 Land procurement process ....................................................................................................... 38

2.5.3 Manpower requirement ............................................................................................................. 40

2.5.4 Water Requirement................................................................................................................... 40

2.6 Waste Generation ..................................................................................................................... 40

2.6.1 Waste Water ............................................................................................................................. 40

2.6.2 Hazardous Waste ..................................................................................................................... 41

2.6.3 Solid Waste .............................................................................................................................. 41

2.7 Implementation Schedule ......................................................................................................... 41

2.7.1 Construction Activities .............................................................................................................. 41

2.7.2 Operation and Maintenance ..................................................................................................... 42

3. Environment and Social Regulatory Framework ............................................ 43

3.1 Terms of Reference .................................................................................................................. 43

Page 6: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

AECOM

3.2 National and Regional Enforcement Authorities ....................................................................... 48

3.3 Applicable Environment and Social Laws and Regulations ...................................................... 50

3.4 Policy Framework in India ........................................................................................................ 57

3.5 Applicable International Standards and Guidelines .................................................................. 57

3.5.1 FMO Social Sustainability Policy .............................................................................................. 57

3.5.2 IFC Performance Standards ..................................................................................................... 58

3.5.3 IFC EHS Guidelines ................................................................................................................. 60

3.5.4 Equator Principles, 2020 .......................................................................................................... 61

3.5.5 Applicability of ADB SPS and IFC PS ....................................................................................... 63

3.5.6 Applicable International Conventions ....................................................................................... 64

3.6 Categorisation of Project .......................................................................................................... 66

3.6.1 Classification as per MoEF&CC, India ...................................................................................... 66

3.6.2 Classification as per IFC Performance Standards .................................................................... 66

3.6.3 Project categorisation as per ADB SPS .................................................................................... 67

3.7 Applicable Environmental Standards ........................................................................................ 68

3.7.1 Ambient Air Quality ................................................................................................................... 68

3.7.2 Ambient Noise Standards ......................................................................................................... 69

3.7.3 Noise Standards for Occupational Exposure ............................................................................ 69

3.7.4 Water Quality Standards ........................................................................................................... 70

4. Environmental and Socio-Economic Baseline ............................................... 71

4.1 Environmental Baseline ............................................................................................................ 71

4.1.1 Physiography ............................................................................................................................ 73

4.1.2 Geology .................................................................................................................................... 74

4.1.3 Drainage ................................................................................................................................... 74

4.1.4 Land use and Land Cover ........................................................................................................ 77

4.1.5 Soil Types ................................................................................................................................. 80

4.1.6 Hydrogeology ........................................................................................................................... 80

4.1.7 Climate and Meteorology .......................................................................................................... 82

4.1.7.1 Rainfall ..................................................................................................................................... 83

4.1.7.2 Wind Speed .............................................................................................................................. 83

4.1.8 Natural Hazards ........................................................................................................................ 83

4.1.8.1 Wind Hazard ............................................................................................................................. 83

4.1.8.2 Seismicity ................................................................................................................................. 84

4.2 Air, Water, Noise and Soil Baseline .......................................................................................... 85

4.2.1 Ambient Air Quality ................................................................................................................... 85

4.2.2 Ambient Noise Quality .............................................................................................................. 86

4.2.3 Water Quality ............................................................................................................................ 87

4.2.4 Soil Environment ...................................................................................................................... 88

4.2.5 Traffic ........................................................................................................................................ 91

4.3 Biodiversity profile .................................................................................................................... 93

4.3.1 Delineation of the Study Area ................................................................................................... 93

4.3.2 Methodology ............................................................................................................................. 93

4.3.2.1 Primary Data............................................................................................................................. 94

4.3.2.2 Secondary Data ........................................................................................................................ 94

4.3.3 Species Profile of the Study Area ............................................................................................. 95

4.3.3.1 Floristic Species ....................................................................................................................... 95

4.3.3.2 Faunal Species ......................................................................................................................... 99

4.3.3.3 Invasive Alien Species ............................................................................................................ 101

4.3.4 Habitat Profile of the Study Area ............................................................................................. 101

4.3.4.1 Natural Habitats ...................................................................................................................... 104

Page 7: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

AECOM

4.3.4.2 Modified Habitats .................................................................................................................... 104

4.3.4.3 Critical Habitats ...................................................................................................................... 105

4.3.5 Designated Areas ................................................................................................................... 109

4.3.5.1 Legally Protected Areas ........................................................................................................... 111

4.3.5.2 Internationally Recognized Areas ............................................................................................ 111

4.3.6 Ecosystem Services ................................................................................................................ 111

4.3.6.1 Provisioning Services .................................................................. Error! Bookmark not defined. 4.4 Socio-economic Profile ........................................................................................................... 112

4.4.1 Socio-Economic Environment................................................................................................. 112

4.4.2 Approach and Methodology .................................................................................................... 112

4.4.3 Administrative Profile .............................................................................................................. 113

4.4.3.1 State profile: Gujarat ............................................................................................................... 113

4.4.3.2 District profile: Banaskantha ................................................................................................... 114

4.4.3.3 Project Area ............................................................................................................................ 114

4.4.3.4 Study Area .............................................................................................................................. 114

4.4.4 Demographic profile of the Study Area ................................................................................... 114

4.4.4.1 Population level ...................................................................................................................... 115

4.4.4.2 Social stratification: Vulnerable groups, SCs and STs ............................................................ 115

4.4.4.3 Gender Profile ........................................................................................................................ 116

4.4.5 Education level ....................................................................................................................... 117

4.4.6 Occupation and Livelihood ..................................................................................................... 118

4.4.6.1 Land use pattern ..................................................................................................................... 120

4.4.6.2 Irrigation ................................................................................................................................. 120

4.4.6.3 Workforce Participation Rate .................................................................................................. 121

4.4.7 Physical Infrastructure and Civic Amenities ............................................................................ 121

4.4.7.1 Health Profile and Infrastructure ............................................................................................. 121

4.4.7.2 Drinking Water ........................................................................................................................ 122

4.4.7.3 Sanitation ............................................................................................................................... 122

4.4.7.4 Banks, Roads and Post Offices .............................................................................................. 122

4.4.7.5 Electricity supply ..................................................................................................................... 122

4.4.7.6 Cooking Fuel .......................................................................................................................... 122

4.4.7.7 Religious Sites ........................................................................................................................ 122

5. Stakeholder Engagement and Consultation ................................................ 124

5.1 Introduction ............................................................................................................................. 124

5.2 Stakeholder Consultation and Disclosure Requirement for the project ................................... 124

5.3 Stakeholder Categorisation .................................................................................................... 125

5.4 Approach and Methodology of Stakeholder Analysis .............................................................. 125

5.5 Stakeholder Analysis .............................................................................................................. 125

5.6 Stakeholder Consultations and Engagement ......................................................................... 134

5.6.1 Consultations with Mamlatdar (Magistrate Executive), Department of Revenue, Vav Tehsil. . 134

5.6.2 Consultations with Sarpanch (Village Head) of Radhanesda Village Panchayat .................... 135

5.6.3 Consultations with Sarpanch (Village Head) Kundaliya Village Panchayat ............................ 138

5.6.4 Consultations with Opinion Leader of Kundaliya village ......................................................... 141

5.6.5 Consultations with Principal/Teacher, Government Middle School, Radhanesda village, Vav Tehsil ...................................................................................................................................... 141

5.6.6 Consultations with Anganwadi Worker, Kundaliya Village, Vav Tehsil .................................... 143

5.6.7 Consultations with Veterinary Officer, Vav Tehsil .................................................................... 144

5.6.8 Focus Group Discussions with Rabari Community Members ................................................. 145

5.6.9 Consultations with the Gujarat Power Corporation Limited (GPCL) ....................................... 147

6. Analysis of Alternatives ................................................................................ 149

Page 8: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

AECOM

6.1 No Project Scenario ................................................................................................................ 149

6.2 Alternate Location for Project ................................................................................................. 150

6.3 Alternate Source of Power Generation ................................................................................... 150

6.4 Alternate Project Technology .................................................................................................. 151

6.5 Alternate Transmission Line Route ......................................................................................... 153

7. Impact Assessment ..................................................................................... 154

7.1 Impact Assessment Criteria .................................................................................................... 154

7.2 Impact Identification ................................................................................................................ 155

7.3 Environmental Impacts and Mitigation Measures ................................................................... 157

7.3.1 Impacts during the Pre-construction and Construction Phase ................................................ 157

7.3.1.1 Ambient Air Quality ................................................................................................................. 157

7.3.1.2 Soil Quality ............................................................................................................................. 158

7.3.1.3 Impact on Surface and Ground Water Quality ........................................................................ 159

7.3.1.4 Impact on Water Availability .................................................................................................... 160

7.3.1.5 Ambient Noise Quality ............................................................................................................ 160

7.3.1.6 Solid and Hazardous Waste Management ............................................................................. 161

7.3.1.7 Traffic and Transport ............................................................................................................... 163

7.3.1.8 Occupational Health and Safety ............................................................................................. 163

7.3.2 Impacts during Operation Phase ............................................................................................ 165

7.3.2.1 Visual Impacts and Aesthetics ................................................................................................ 165

7.3.2.2 Impact on Soil and Water Quality ........................................................................................... 166

7.3.2.3 Impact on Water Availability .................................................................................................... 167

7.3.2.4 Occupational Health and Safety of Workers ........................................................................... 168

7.3.3 Impacts during Decommissioning Phase ................................................................................ 169

7.3.3.1 Environment and Occupational Health & Safety ..................................................................... 169

7.3.3.2 Impact on Land Due to Improper Waste Disposal .................................................................. 171

7.4 Ecological Impacts and Mitigation Measures .......................................................................... 171

7.4.1 Impacts during the Construction Phase .................................................................................. 172

7.4.2 Impacts during the Operation and Maintenance Phase .......................................................... 174

7.4.3 Impacts during the Decommissioning Phase .......................................................................... 177

7.5 Socio- Economic Impacts and Mitigation Measures ............................................................... 180

7.5.1 Impacts during the pre-construction phase ............................................................................. 180

7.5.1.1 Impact on animal grazing ....................................................................................................... 180

7.5.2 Impacts during the construction and operation phases .......................................................... 180

7.5.2.1 Impacts on Local Economy .................................................................................................... 180

7.5.2.2 Employment opportunities ...................................................................................................... 181

7.5.2.3 Labour Rights and Welfare ..................................................................................................... 181

7.5.2.4 Labour Influx ........................................................................................................................... 182

7.5.3 Impacts during the decommissioning phase ........................................................................... 182

7.5.3.1 Loss of employment opportunities .......................................................................................... 182

7.6 Impact of Climate Change on Solar PV Power Plant .............................................................. 183

7.6.1 Anticipated Impacts ................................................................................................................ 183

7.6.1.1 Construction Phase ................................................................................................................ 183

7.6.1.2 Operational Phase .................................................................................................................. 185

7.6.1.3 Climate Transition Risk. .......................................................................................................... 186

7.7 Cumulative Impact Assessment.............................................................................................. 188

7.7.1 Environmental Impacts ........................................................................................................... 188

7.7.2 Impacts on Biodiversity and Ecosystem Services ................................................................... 189

7.7.2.1 Impact on Biodiversity ............................................................................................................ 189

7.7.2.2 Impact on Ecosystem Services............................................................................................... 189

Page 9: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

AECOM

7.7.3 Socio-economic Impacts ........................................................................................................ 190

7.7.3.1 Impact on land ........................................................................................................................ 190

7.7.3.2 Migrant Workers ..................................................................................................................... 190

7.7.3.3 Impact on Infrastructure .......................................................................................................... 190

7.7.4 Conclusion .............................................................................................................................. 190

8. Environment and Social Management Plan ................................................. 191

8.1 Introduction ............................................................................................................................. 191

8.2 Organizational Structure (Environment, Social, Health and Safety) ....................................... 191

8.3 Roles and Responsibilities ..................................................................................................... 192

8.4 Inspection, Monitoring and Audit ............................................................................................. 196

8.5 Documentation and Record Keeping ...................................................................................... 196

8.6 Training ................................................................................................................................... 197

8.7 Environment and Social Management Plan and Procedures ................................................. 198

8.7.1 Environment and Social Management Plan ............................................................................ 198

8.7.1.1 ESMP during Construction Phase .......................................................................................... 198

8.7.1.2 ESMP during Operation Phase ............................................................................................... 198

8.7.1.3 ESMP during Decommissioning Phase .................................................................................. 198

8.7.2 Waste Management Plan ....................................................................................................... 216

8.7.2.1 Waste Type and Quantity Generated ...................................................................................... 216

8.7.2.2 Waste Management, Handling and Disposal .......................................................................... 217

8.7.3 Storm Water Management Plan ............................................................................................. 217

8.7.4 Occupational Health and Safety Plan ..................................................................................... 217

8.7.4.1 Risk Assessment .................................................................................................................... 218

8.7.4.2 Control Measures ................................................................................................................... 218

8.7.4.3 Training Requirements ........................................................................................................... 218

8.7.4.4 Documentation and Record Keeping ...................................................................................... 219

8.7.5 Contract Worker Accommodation Plan ................................................................................... 219

8.7.5.1 Designed/ Construction standard ........................................................................................... 220

8.7.5.2 Drinking water ......................................................................................................................... 220

8.7.5.3 Toilet/ Washing/ Showering Facilities ...................................................................................... 220

8.7.5.4 Hygiene and housekeeping .................................................................................................... 221

8.7.5.5 First aid/ Medical facilities ....................................................................................................... 221

8.7.5.6 Audit and Inspection ............................................................................................................... 221

8.7.6 Traffic Management Plan ........................................................................................................ 221

8.7.6.1 Management Measures .......................................................................................................... 221

8.7.7 Environment and Social Monitoring Plan ................................................................................ 222

8.7.7.1 Environmental Monitoring Plan ............................................................................................... 222

8.7.7.2 Social and Health and Safety Monitoring Plan........................................................................ 222

8.7.7.3 Monitoring Plan during Decommissioning Phase ................................................................... 223

8.7.8 Emergency Preparedness and Response Plan ...................................................................... 223

8.7.8.1 Responsibilities ....................................................................................................................... 223

8.7.8.2 Identification of Emergencies.................................................................................................. 224

8.7.8.3 Declaration of Emergencies.................................................................................................... 224

8.7.8.4 Emergency Equipment ........................................................................................................... 225

8.7.8.5 Coordination with External Agencies ...................................................................................... 226

8.7.8.6 Emergency Response Team ................................................................................................... 226

8.7.8.7 Emergency Response Procedure ........................................................................................... 227

8.7.8.8 Reporting and Documentation ................................................................................................ 227

9. Conclusions and Recommendations ........................................................... 228

Appendix A Participant list of Stakeholder Consultations ....................................... 230

Page 10: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

AECOM

Appendix B Mammals of the Study Area ................................................................ 231

Appendix C Resident Birds of the Study Area ........................................................ 233

Appendix D Migratory Birds of the Study Area ....................................................... 237

Appendix E Reptiles of the Study Area................................................................... 240

Appendix F Amphibians of the Study Area ............................................................. 242

Appendix G Fishes of the Study Area..................................................................... 243

Figures

Figure 1-1: Map showing physical features of the site and the area of influence ............................................... 1-22 Figure 2-1: Indicative location of Project site in Gujarat, India ........................................................................... 2-27 Figure 2-2: Map showing Project Location in Radhanesda Solar Park ................................................................. 29 Figure 2-3: Overview of Solar PV Plant ................................................................................................................. 30 Figure 2-4: View of the project site ........................................................................................................................ 35 Figure 2-5: Ground water at a depth of 1-2 m below ground at site ...................................................................... 35 Figure 2-6: View of the existing paved access road running parallel to site .......................................................... 35 Figure 2-7: Limda Mata Ki Mandir under renovation at a distance of 1km from site.............................................. 35 Figure 2-8: Map showing the project location and external transmission line ....................................................... 36 Figure 2-9. Land procurement/ allotment process ................................................................................................ 39 Figure 4-1: Map showing Environment and Traffic Monitoring Locations .............................................................. 72 Figure 4-2: Geological Map of Gujarat State ......................................................................................................... 74 Figure 4-3: Map representing Drainage within 5 km radius of site ........................................................................ 76 Figure 4-4: Map showing Landuse within 5 km radius of the Proposed Project site.............................................. 78 Figure 4-5: Map showing Land use of the Proposed Project site .......................................................................... 79 Figure 4-6: Soil Map of Gujarat State .................................................................................................................... 80 Figure 4-7: Hydrogeological map of Banaskantha district ..................................................................................... 82 Figure 4-8: Wind Hazard map of Gujarat state ...................................................................................................... 84 Figure 4-9: Earthquake Hazard Map of Gujarat state ............................................................................................ 85 Figure 4-10: Soil Texture Diagram ......................................................................................................................... 90 Figure 4-11: Hourly Traffic Volumes at TM1 .......................................................................................................... 92 Figure 4-12: Biodiversity Sampling Sites in the Study Area .................................................................................. 94 Figure 4-13: Some Floristic Species recorded in the Study Area .......................................................................... 98 Figure 4-14: Habitat Profile of the Project Site .................................................................................................... 102 Figure 4-15: Habitat Profile of the Transmission Corridor ................................................................................... 103 Figure 4-16: The Central Asian Flyway ............................................................................................................... 107 Figure 4-17: Designated Areas around the Study Area ....................................................................................... 110 Figure 7-1: Flood Scenario in Gujarat State ........................................................................................................ 184 Figure 8-1: Project organization structure ........................................................................................................... 192

Tables

Table 2-1: Components of Solar PV Plant ............................................................................................................. 30 Table 2-2: Technical Details of PV Power Plant ..................................................................................................... 31 Table 3-1: Terms of Reference for the ESIA .......................................................................................................... 44 Table 3-2 Enforcement agencies relevant to the project ...................................................................................... 48 Table 3-3: Applicable Environment and Social Laws and Regulations .................................................................. 51 Table 3-4 National and State Level Policies Applicable to the Project .................................................................. 57 Table 3-5 Applicability of IFC Performance Standards ......................................................................................... 59 Table 3-6: Broad Overview ADB SPS and their applicability to the Project ........................................................... 63 Table 3-123-7: Treated sewage discharge guidelines as per IFC.......................................................................... 70 Table 4-1: Environmental Parameters Monitored for Baseline Data Collection ..................................................... 71 Table 4-2: Environmental Monitoring Locations .................................................................................................... 73

Page 11: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

AECOM

Table 4-3: Landuse classification of Banaskantha district ..................................................................................... 77 Table 4-4: Land use specific to Project Area and Site ........................................................................................... 77 Table 4-5: Average Annual Rainfall (in mm) for Banaskantha District ................................................................... 83 Table 4-6: Results of Ambient Air Monitoring ......................................................................................................... 86 Table 4-7: Results of Ambient Noise level Monitoring ........................................................................................... 86 Table 4-8: Results of Ground Water and Surface Water Quality Analysis ............................................................. 87 Table 4-9: Standard Soil Classification .................................................................................................................. 89 Table 4-10: Results of Soil quality analysis ........................................................................................................... 89 Table 4-11: PCU Factors adopted for Traffic Volume Survey ................................................................................ 91 Table 4-12: Hourly Traffic Volumes ........................................................................................................................ 91 Table 4-13: Floristic Species recorded in the Study Area ...................................................................................... 96 Table 4-14: Invasive Alien Species of Study Area ............................................................................................... 101 Table 4-15: Critically Endangered and Endangered Species .............................................................................. 105 Table 4-16 Demographic Profile of State of Gujarat ............................................................................................ 113 Table 4-17 Villages falling within five (05) kilometre radii. ................................................................................... 114 Table 4-18 Population Level ................................................................................................................................ 115 Table 4-19 Presence of Vulnerable Sections of Community within the study area .............................................. 116 Table 4-20 Gender Profile of the Study Area ....................................................................................................... 116 Table 4-21 Literacy profile of Study Area ............................................................................................................. 117 Table 4-22 Occupational pattern in the Study Area ............................................................................................. 119 Table 4-23 Land Use Pattern of Study Area ........................................................................................................ 120 Table 4-24 Irrigation Pattern in Study Area .......................................................................................................... 120 Table 4-25 Workforce Population in the Study Area ............................................................................................ 121 Table 5-1 Overview of Disclosure and stakeholder consultation requirement ..................................................... 124 Table 5-2 Stakeholder Group Categorisation ...................................................................................................... 125 Table 5-3: Stakeholder Significance and Engagement Requirement .................................................................. 125 Table 5-4: Stakeholder Analysis .......................................................................................................................... 127 Table 5-5 Summary of overall stakeholder influence ........................................................................................... 134 Table 6-1: Anticipated Power Supply position of Gujarat in 2018-2019 ............................................................... 149 Table 6-2: The levels of irradiance at the proposed Project Site (Month wise) .................................................... 149 Table 6-3 Comparative analysis of Various Power Generation Options .............................................................. 151 Table 6-4: Characteristics of some PV Technology Classes................................................................................ 152 Table 7-1: Impact Assessment Criteria ................................................................................................................ 154 Table 7-2: Impact Significance Matrix ................................................................................................................. 155 Table 7-3: Activity- Impact Interaction Matrix – Pre-Construction, Construction, Operation & Decommissioning Phase .................................................................................................................................................................. 155 Table 7-4: Impact Significance – Ambient Air Quality .......................................................................................... 158 Table 7-5: Impact Significance – Soil Quality ...................................................................................................... 158 Table 7-6 Impact Significance – Impact on Surface and Ground Water Quality .................................................. 160 Table 7-7: Impact Significance – Impact on Water Availability ............................................................................. 160 Table 7-8: Impact Significance – Ambient Noise Quality ..................................................................................... 161 Table 7-9: Impact Significance – Waste Storage and Disposal ........................................................................... 162 Table 7-10 Impact Significance – Impact on Traffic and Transport ..................................................................... 163 Table 7-11: Impact Significance – Impact to Occupational Health and Safety of Workers................................... 165 Table 7-12: Impact Significance – Aesthetic and Visual Impacts......................................................................... 166 Table 7-13: Impact Significance – Impacts on Soil Quality .................................................................................. 167 Table 7-14 Impact Significance – Surface Water Quality ..................................................................................... 167 Table 7-15: Impact Significance – Impact on Water Availability ........................................................................... 168 Table 7-16: Impact Significance – Occupational Health and Safety of Workers .................................................. 169 Table 7-17: Impact Significance – Environment Occupational Health and Safety Hazards ................................. 171 Table 7-18 Impact Significance – Impact on Land due to Improper Disposal of Waste ....................................... 171 Table 7-19: Impact Significance – Animal Grazing .............................................................................................. 180 Table 7-20: Impact Significance – Local Economy .............................................................................................. 181 Table 7-21: Impact Significance – Employment Opportunities ............................................................................ 181 Table 7-22: Impact Significance – Labour Rights and Welfare ............................................................................ 182 Table 7-23: Impact Significance – Employment opportunities ............................................................................. 182 Table 7-24: Impact Significance – Climate Change ............................................................................................. 188 Table 7-25: Details of proposed solar projects near project site .......................................................................... 188 Table 8-1: ESMP during Pre-Construction Phase ............................................................................................... 200

Page 12: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

AECOM

Table 8-2: ESMP during Construction Phase ...................................................................................................... 202 Table 8-3: ESMP during Operation Phase........................................................................................................... 208 Table 8-4: ESMP during Decommissioning Phase .............................................................................................. 212 Table 8-5 Environmental Monitoring Plan ............................................................................................................ 222 Table 8-6 Social and Health and Safety Monitoring Plan .................................................................................... 222 Table 8-7 Codification of Siren ............................................................................................................................ 226

Page 13: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

AECOM

Executive Summary Electro Solaire Private Limited (ESPL) has been selected for developing 200 MW solar power project after bidding by Gujarat Urja Vikas Nigam Limited for 700 MW grid connected Solar Photovoltaic Power Projects to be set up at Radhanesda Solar Park in Radhanesda village, Vav Taluka, Banaskantha district in the state of Gujarat (Phase III – R). Gujarat Power Corporation Limited (GPCL) has been appointed as a nodal agency for development of the 700 MW Ultra Mega Solar Power Park under the National Solar Mission by Ministry of New and Renewable Energy (MNRE).

Solairedirect Energy India Private Limited, the Indian subsidiary of Engie Solar India Private Limited has incorporated a Special Purpose Vehicle (SPV) namely M/s Electro Solaire Private Limited (hereinafter referred as ‘Client’/ESPL) for the development of the 200 MW project. The 200 MW solar power plant is proposed to be set up on 380 hectares (~938.06 acres) of land (two [02] land parcels of 190 hectares each) that has been leased by GUVNL for a period of 25 years to ESPL.

The ESIA has been undertaken as per requirements of International Finance Corporation (IFC) Sustainability Framework (Policy and Performance Standards on Environmental and Social Sustainability) 2012 and the associated World Bank Group Environmental Health and Safety Guidelines, ADB’s 2009 Safeguard Policy Statement (SPS), FMO's Social Sustainability Policy and Equator Principles IV (2020).

AECOM India Private Limited (hereinafter referred to as ‘AECOM’) has been appointed by ESPL to undertake the ESIA study to evaluate environment and social risks and impacts associated with the Project.

The overall area covered by the assessment includes the following constituent areas:

• The footprint of the project, hereafter referred to as the ‘Project Site’;

• The area extending 5 km outward from the Project Site boundary (estimated to contain the potential receptors of any project-related environment, social and ecological impacts), hereafter referred to as the ‘Area of Influence’ or ‘AOI’; and

• The alignment of the external transmission line, along with the area extending 500 m on either side of the alignment, hereafter collectively referred to as the ‘Transmission Corridor’.

• The ‘Project Site’, the ‘AOI’ and the ‘Transmission Corridor’ are hereafter collectively referred to as the ‘Study Area’.

Project Description

The proposed project site is spread over an area of ~938.06 acres of land in the Radhanesda village of the state of Gujarat in India. The site can be accessed through State Highway (SH) 127 which passes through the village Kundaliya and connects to Radhanesda village at a distance of 8 km from the site. The road further connects to Limbidya village (Limbiya- Baet road) which is an existing government paved road (~3.5 m wide) and runs parallel towards north of the site.

ESPL is in the process of appointing a lump sum Turnkey contract with an Engineering, procurement and construction (Sub-contractor or EPC) contractor for development of this proposed project.

Power Evacuation

Power generated through PV modules will be stepped up to 33kV and will be pooled to main HT panel using breaker feeder. As per information provided by ESPL, a 33kV/220 kV internal common pooling substation (PSS) which will be constructed by GUVNL near the Project Site for all the Solar Power Developers in the Solar Park and the power will be further evacuated through a 400-kV transmission line of length ~35 km. The transmission line will be connected to the 400/200kV Banaskantha substation in Khimanavas village (Inter-Connection Point/Delivery Point), which is situated at a distance of 35 km from the project site. As per the information available, the transmission line corridor is currently under construction and is expected to be commissioned by March 2020.

Access road

Page 14: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

AECOM

The site can be accessed through State Highway (SH) 127 which passes through village Kundaliya and connects Radhanesda village at a distance of 8 km from the site. The road further connects Limbidya village (Limbiya- Baet road) which is an existing government paved road (~3.5 m wide) and runs parallel towards the north of the site. The road leading to the site is an existing paved village road, and thus, no new road will be required to be developed for the project.

Land Requirement

The project land (380 hectares) allotted on lease basis for a period of 25 years to ESPL, is owned by the Gujarat Power Corporation Limited (GPCL). The said land does not include any private or forest land.

Project Activities

Construction Phase

Construction Labour: As informed, during the peak construction phase, 600-700 workers will be employed for a duration of 2-3 months. While most of the workers in the unskilled and semi-skilled categories will be hired from the neighbouring villages and from within the Banaskantha district, the manpower requirement in the skilled and highly skilled categories will be sourced from outside the state. Approximately 30% of the construction manpower will be migrant workers who will be provided accommodation in houses taken on lease basis by the EPC contractor in the neighbouring villages.

Water requirement: it is estimated that water requirement for the construction phase will be 100 KL (Kilo litres) which includes water requirements for curing works, sprinkling and batching plant). The water will be sourced through a branch of the Sardar Sarovar Narmada Water canal located at a distance of 40 km from the Project Site. Reverse Osmosis (RO) treated packaged drinking water will be provided to the workers at site (~5000L/day) for peak construction period. One labour camp will be constructed, as reported.

Operation and Maintenance Phase

Water Requirement: During the operation phase, Reverse Osmosis (RO) treated packaged drinking water will be provided to the workers at site (~250L/day). Water for domestic requirement at the site will be ~1 KL and will be sourced through Narmada Canal.

As per the information provided by the Client, GPCL will construct a tank of 10 lakh litres capacity inside the solar park for meeting the water requirement for module cleaning for the entire solar park. Water for module cleaning will be sourced by GPCL through a branch of Narmada canal and will be stored in the tank to be constructed by GPCL for the entire solar park. Assuming a minimum of 2.5 litres of water per module, the water requirement for cleaning the whole plant (i.e. ~10 lakh modules) will be approximately 1,666 kilo litres, at one time. With a cleaning schedule of twice a month, it is estimated that approximately 3,332 kilo litres of water will be required for cleaning purpose on a monthly basis.

Analysis of Alternatives

The proposed project is an opportunity to utilize the solar potential of the state for power generation. A “No Project Scenario” will not address the issue of power shortage. An alternative without the project is undesirable, as it would worsen the power supply-demand scenario, which is expected to be a constraint on economic growth.

There are no fuel requirements or large quantities of water required for the operation of the plant. GHG emissions and other environmental pollution (stack emissions, ash management etc.) issues are also limited. Furthermore, there are minimal social issues associated with solar power projects.

The following additional criteria have been considered for site selection:

• The site is located away from major settlements;

• The site does not fall under any reserved or protected forests;

• The land procured for the site mainly comprises of fallow land which is barren in nature and practically unusable for any other purpose; and

• No environmentally sensitive features such as water bodies, forests, archaeological sites are located in the immediate site surroundings.

Page 15: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

AECOM

Environmental Baseline

A study area of 5 km from the proposed project area was considered for the evaluation of environmental and social existing status and potential impacts.

Ambient Air Quality: All of the parameters measured for ambient air quality were noted to be well within the permissible limits of the National Ambient Air Quality Standards, as defined by MoEF&CC at the sampled locations.

Ground Water quality: The pH value of the sample was observed to be within the prescribed range, indicating neutral balance. The hardness and total dissolved solids (TDS) value in the groundwater sample exceeds the permissible limit. Chemical parameters such as chloride and magnesium were noted to be exceeding the permissible limit. Calcium was noted to be exceeding the acceptable limit but is within the permissible limit. Other heavy metal parameters such as Selenium, barium, Fluoride, boron were detected in the groundwater sample but were noted to be within acceptable limit. The groundwater sample does not show the presence of faecal coliforms implying that there is no faecal contamination in the groundwater. All other parameters were observed to be within the acceptable limits as specified in the drinking water standard of IS 10500:2012. It can be inferred from the water quality that groundwater contains high number of dissolved solids and has high hardness and thus is not completely fit for human consumption prior to conventional treatment.

Ambient Noise quality: The ambient noise level at location NQ 1 (near the site boundary) was noted to be exceeding the permissible standards of noise levels prescribed by CPCB for day time and night time. The high noise level can be attributed to vehicular movements, ground levelling work being undertaken nearby the site and high wind movement on the day of monitoring. Ambient noise level at NQ 2 (Radhanesda village road) was noted to be within permissible limits for the day time. However, noise levels were noted to be exceeding slightly above the permissible limits for night time. The ambient noise level at location NQ 3 (empty land parcels near the site) was noted to be exceeding the permissible standards for day time whereas the night time levels were within the permissible limits for noise level. The high noise levels at NQ 2 and NQ 3 can be attributed mainly to the high wind velocity on the day of monitoring and some construction activities being undertaken in the area in and around the Project Site (construction of the boundary wall, shops in the near vicinity, etc.).

Soil Quality: The pH values of the soil samples at the project site (SQ1) and around the site (SQ2) indicate normal to slightly saline soil conditions. Electrical conductivity of soil samples indicate that soil at the project site (SQ1) is injurious to most crops and thus indicates high salinity of soil and the soil around the project site falls under Normal category. The relatively high Sodium concentration in Soil sample at the project site indicates highly sodic soil and indicates that the soil has poor soil structure with low infiltration rate and aeration and thus the soil is not suitable for cultivation of many crops. Iron content in the soil samples were noted to be high. Heavy metals such as chromium, cadmium, Mercury were not detected in the soil samples. Whereas other heavy metals such as lead, nickel and arsenic were observed in the soil samples. The texture of soil sample SQ 1, i.e. the soil at the Project site is “Sandy Loam”, and the texture of soil sample SQ 2 (around the Project site) is “Sandy”.

Traffic Analysis: Out of the total traffic at the Village road, maximum influx and outflux was observed for light vehicles (four wheelers) such as cars, vans (48%), followed by two wheelers (26%). This is followed by Six Wheelers/Heavy Vehicles such as Light Commercial vehicles, Trucks and Buses etc. (24%). Further, cycles amounted for less than 1% of the traffic at the road.

Morning peak hour for maximum traffic influx was noted as 11:00-12:00 hours with 34.1 units. During night, peak traffic was observed at 17:00-18:00 hours with 32.75 units. Daily cumulative traffic movement at the village road was observed to be 335.9 units.

Socio-Economic Baseline

The project area is in Radhanesda village, Vav Tehsil in District of Banas kantha. The project area is spread over 938.06 acres in Radhanesda Village. Radhanesda village falls under the jurisdiction of Radhanesda Village Panchayat. The study area has been further divided into direct impact area (the area where the project will be located) and indirect impact area (within 05 km of the project area). Kundaliya village falls within the 5-kilometre radii of the project.

Biodiversity Baseline:

Page 16: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

AECOM

The Study Area, which includes the estimated areas of influence of both, the Project and its shared facilities, represents a part of the north-eastern fringe of the Little Rann of Kutch. The natural vegetation of the Study Area represents desert thorn scrub forest-type typical to semi-arid tracts of north-western India, including unique edaphic forms, such as Rann Saline Thorn Scrub and Salvadora Scrub. The habitat profile of the Study Area consists of a mosaic of near-natural to slightly modified habitats, with the Project Site containing mainly near-natural habitats, such as saline flats, grassland and scrub, while the Transmission Line Corridor contains mainly modified habitats, such as cultivated or fallow farmland, but also a few natural wetlands. The floristic and faunal profiles of the Study Area are characterized by habitat-specialist species of thorny scrub and wetlands. There is considerable presence of the invasive alien species Prosopis juliflora, throughout the Study Area. At least three (3) designated areas are situated in the vicinity of the Study Area, at distances of 1.5 km to 17 km from the corresponding nearest point on the boundary of the Study Area. The Study Area is situated within the Central Asian Flyway and in proximity to the East Asia – East Africa Flyway. A critical habitat assessment, involving focused monitoring of the Study Area for identified critical habitat trigger species, has concluded that it is improbable that the Project Site represents critical habitat with respect to the concerned species. The Study Area provides priority provisioning ecosystem services to the local pastoral community in terms of fodder for livestock.

Stakeholder Engagement

• Interaction with relevant government stakeholders GPCL, GUVNL, GEDA officials, Revenue officer of Vav Tehsil, Veterinary Officer of Vav Tehsil as well as Village Panchayat (Local Government) heads of Kundaliya and Radhanesda villages were undertaken;

• Consultations with opinion leaders (leader, principal/teacher of Government School, Radhanesda village) was undertaken;

• Focus Group Discussions with the community members of Radhanesda and Kundaliya villages were undertaken; and

• Consultations with members of Rabari Community (OBC) a pastoral nomadic community was also undertaken.

Environmental and Social Impacts

The Project is a renewable energy project which uses solar energy for power generation. Renewable energy projects are considered to be cleaner compared to fossil fuel-based energy projects. The anticipated impacts during the construction, operation and decommissioning phases and after mitigation have been summarized in the Table below:

Impact Description Impact Nature

Significant of Impact

Overall Impact after mitigation

Pre-construction and Construction Phase

Ambient Air Quality Negative Moderate Minor

Soil Quality Negative Moderate Minor

Ambient Noise Quality Negative Moderate Minor

Water resources Quality Negative Moderate Minor

Solid and Hazardous Waste Management Negative Moderate Minor

Impact on Traffic and Transport Negative Moderate Minor

Impact to Occupational Health and Safety of Workers Negative Moderate Minor

Biodiversity and Ecosystem Services (Project) Negative Moderate Minor

Biodiversity and Ecosystem Services (Transmission Line) Negative Moderate Minor

Operational Phase

Aesthetic and Visual Impacts Negative Minor Minor

Soil Quality Negative Moderate Insignificant

Water Availability Negative Major Moderate

Occupational Health and Safety Hazards Impact Negative Moderate Minor

Page 17: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

AECOM

Impact Description Impact Nature

Significant of Impact

Overall Impact after mitigation

Biodiversity and Ecosystem Services (Project) Negative Moderate Minor

Biodiversity and Ecosystem Services (Transmission Line) Negative Major Moderate

Employment Opportunities Negative Minor Moderate

Impact on local economy Negative Minor Moderate

Labour Rights and Welfare Negative Minor Moderate

Decommissioning Phase

Environment and Occupational Health and Safety Impact Negative Moderate Minor

Impact on Land Due to Improper Waste Disposal Major Moderate

Biodiversity and Ecosystem Services (Project) Negative Moderate Minor

Biodiversity and Ecosystem Services (Transmission Line) Negative Moderate Minor

Employment Opportunities Negative Minor Moderate

Based on the above impact assessment matrix, impacts due to Project and transmission line has been identified and all the impacts identified can be managed through mitigation measures. Mitigation measures for each identified impact have been provided, along with the overall significance of the impact, before and after application of the mitigation measures.

An Environmental and Social Management and Monitoring Plan (ESMMP) has been developed to ensure that social and environmental impacts, risks and liabilities identified during the ESIA process are effectively managed during the operation and closure of the proposed project. The ESMP delineates the monitoring and management measures to avoid and/or minimize the identified impacts by allocating management responsibility and suggesting skill requirement for implementation of these measures.

Page 18: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

AECOM

List of Abbreviations SNo. Abbreviation Extension

1. AECOM AECOM India Private Limited

2. AC Alternate Current

3. AAQ Ambient Air Quality

4. AoI Area of Influence

5. CGWA Central Ground Water Authority

6. CPCB Central Pollution Control Board

7. CPR Common Property Resource

8. CTE Consent to Establish

9. CTO Consent to Operate

10. CSR Corporate Social Responsibility

11. CR Critically Endangered

12. DPR Detailed Project Report

13. DG Diesel Generator

14. DC Direct Current

15. ESPL Electro Solaire Private Limited

16. ERT Emergency Response Team

17. EN Endangered

18. EPC Engineering, Procurement and Construction

19. EPA Environment (Protection) Act, 1986

20. EAP Environment Action Plan

21. ESIA Environment and Social Impact Assessment

22. ESMP Environment and Social Management Plan

23. ESMS Environment and Social Management System

24. EMS Environment Management System

25. EHS Environment, Health and Safety

26. FGD Focus Group Discussions

27. GoG Government of Gujarat

28. GP Gram Panchayat

29. GHG Green House Gases

30. GSS Grid Sub -Station

31. GRM Grievance Redress Mechanism

32. GPCB Gujarat Pollution Control Board

33. GPCL Gujarat Power Corporation Limited

34. GUVNL Gujarat Urja Vikas Nigam Limited

35. HSE Health, Safety and Environment

36. ISA Implementation and Support Agreement

37. IMD Indian Meteorological Department

38. IP Indigenous People

39. IFC International Finance Corporation

Page 19: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

AECOM

40. IUCN International Union for Nature and Natural Resources

41. MW Mega Watt

42. MoEF&CC Ministry of Environment, Forest and Climate Change

43. MNRE Ministry of New and Renewable Energy

44. NOC No Objection Certificate

45. O&M Operations and Maintenance

46. PRI Panchayati Raj Institution

47. PPE Personal Protective Equipment

48. PV Photo Voltaic

49. PUC Pollution Under Control

50. PSS Pooling Sub-station

51. PPA Power Purchase Agreement

52. PIC Prior Informed Consent

53. SC Scheduled Caste

54. ST Scheduled Tribe

55. SPPD Solar Power Park Developer

56. SPV Special Purpose Vehicle

57. TL Transmission Line

58. VU Vulnerable

59. WMP Waste Management Plan

60. WPA Wildlife Protection Act

Page 20: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

AECOM

1. Introduction Government of Gujarat vide resolution (G.R. No. SLR – 11-2015-2442 B) dated 13 August 2015, has notified the Gujarat Solar Power Policy 2015 which shall remain operational for the period up to 31 March 2021. The Gujarat Solar Power Policy 2015 stipulates that the obligated entities may purchase solar power to fulfil their renewable purchase obligation (RPO) at the tariff determined through competitive bidding. Subsequently, the Ministry of Power, vide Resolution (No. 23/27/2017 – R&R) dated 03 August 2017 notified the Guidelines for Tariff Based Competitive Bidding Process for Procurement of Power from grid connected Solar Photo Voltaic (PV) Power Projects.

Based on the above, Gujarat Urja Vikas Nigam Limited (GUVNL), vide request for selection (RFS) [No. GUVNL/700 MW/Solar (Phase III-R)] dated 06 March 2019, had floated tender for purchase of power through Competitive Bidding Process (followed by reverse e-auction) from 700 MW grid connected Solar Photovoltaic Power Projects to be set up at Radhanesda Solar Park in Gujarat (Phase III – R). The Radhanesda Solar Park/Radhanesda Ultra Mega Solar Park is located at Radhnesada village, Taluka Vav, Banaskantha district in the state of Gujarat. After successful bidders were announced for development of Solar Power Projects in the Radhanesda Solar Park, Government of Gujarat (GoG) appointed as a nodal agency for development of the 700 MW Ultra Mega Solar Power Project in the Radhanesda Solar Park under the National Solar Mission by Ministry of New and Renewable Energy (MNRE) vide its guidelines for Development of Solar Parks issued in June 2015 and its amendments thereon. GPCL has thus been designated as Solar Power Park Developer (SPPD)/ Solar Park Implementing Agency (SPIA) by Government of Gujarat. The entire solar park has been divided into seven (07) number of plots of 190 hectares each which has been allotted to different power producers by GPCL.

Engie is one of the largest solar power producing companies in France and Belgium. As of April 2018, the company has commissioned 1,849 MW of solar power across India, China and Thailand in Asia; Italy, Czech Republic, Netherlands, United Kingdom, Belgium, France and Spain in Europe; Brazil, Chile, Peru and Panama in South America; the United States of America and Canada in North America; South Africa in Africa and New Caledonia, Wallis and Futuna and Vanuatu in Oceania.

In 2015, Engie acquired 95% stake in Solaire Direct (now, Engie Solar SAS, France), a Europe based company which develops, installs and operates a broad array of solar photovoltaic (“PV”) power plants ranging from 1.5 kWp to tens of MWp in capacity. The Indian arm of Engie Solar SAS, France named as Solairedirect Energy India Private Limited was incorporated in 2010 with the primary objective to tap the solar power potential in the Indian market. Solairedirect Energy India Private Limited is amongst the leading solar power developers in India with platform of about 462 MWp under operation and construction.1

For the purpose of executing the 200 MW Radhanesda Solar Power Project, Solairedirect Energy India Private Limited incorporated a Special Purpose Vehicle (SPV) namely M/s Electro Solaire Private Limited (hereinafter referred as ‘Client’/ESPL). ESPL has been declared as one of the successful bidders, pursuant to Letter of Award (LoA) dated 28 May 2019 for development of Solar Power Project of 200 MW capacity (100 MW X 2 plots) and sale of entire of electrical energy, so produced, for commercial purposes from such power plant to GUVNL. The Power Purchase Agreement (PPA) was signed between ESPL and GUVNL on 26 August 2019 for a period of twenty-five (25) years. ESPL has been allotted Plot D (100 MW) and Plot E (100 MW) for development of solar plants within the Radhanesda Solar Park at Radhanesda village, Taluka Vav, Banaskantha district in the state of Gujarat (hereafter referred to as the “Site” or “Project Site”).

The 200 MW solar power plant (also referred to as the solar power project) in Gujarat is proposed to be set up on 380 hectares (~938.06 acres) of land (two [2] land parcels of 190 hectares each) that has been leased by GUVNL for a period of 25 years to ESPL through a competitive bidding in March 2019.

As per the Implementation and Support Agreement (ISA) for Grid Connected Solar Photo Voltaic Projects in Radhanesda Ultra Mega Solar Park (700 MW) signed between GPCL and ESPL dated 22 October 2019, GPCL will identify and acquire the land required for setting the power plant, obtain necessary permits and clearances

1 Detailed Project Report (DPR) for Development of 200 MW Solar Power Project at Radhanseda Ultra Solar Park, Banaskantha Gujarat (December 2019).

Page 21: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

AECOM

required for development and will develop various infrastructure like internal transmission system, water supply, road connectivity, drainage system etc. for the solar power project.

The ESIA has been undertaken as per requirements of International Finance Corporation (IFC) Sustainability Framework (Policy and Performance Standards on Environmental and Social Sustainability) 2012 and the associated World Bank Group Environmental Health and Safety Guidelines, ADB’s 2009 Safeguard Policy Statement (SPS), FMO's Social Sustainability Policy and Equator Principles IV (2020).

AECOM India Private Limited (hereinafter referred to as ‘AECOM’) has been appointed by ESPL to undertake the ESIA study to evaluate environment and social risks and impacts associated with the Project. The ESIA study comprised of a reconnaissance survey, baseline environmental monitoring, primary ecological survey, data analysis and consultations and discussions with relevant stakeholders.

1.1 Project Background ESPL intends to develop a 200 MW capacity solar power project in Radhanesda village, Vav Taluka,

Banaskantha district in the state of Gujarat, India (hereinafter referred as ‘Project’).

The project will be based on Solar Photo Voltaic technology using Multi/Poly Crystalline Silicon PV modules for power generation. The 200 MW solar power plant in Gujarat is proposed to be set up on 380 hectares (~938.06 acres) of land (two land parcels of 190 hectares each) that has been leased by GUVNL for a period of 25 years to ESPL.

A solar power plant is a cleaner option for power generation in comparison to non-renewable fossil fuels. Ministry of Environment, Forest and Climate Change (MoEF&CC) in its Office Memorandum No. J-11013/41/2006-IA-II (I) dated 13 May 2011 (as provided in Appendix A) stated that the solar power projects are not covered under the ambit of Environmental Impact Assessment (EIA) Notification, 2006 and therefore does not require prior environmental clearance (EC).

ESPL is in the process of signing a lump sum Turnkey contract with an engineering, procurement and construction (hereafter referred as EPC or ‘Sub-contractor’) contractor for development of the proposed project. The Sub-contractor will be responsible for installation of solar panels, construction of transformers in existing pooling substation and laying of transmission line. Post construction, an operation and maintenance (O&M) contractor for the project will be appointed by ESPL.

The power generated through the project will be fed to the common internal Pooling Substation (PSS), to be set up for all power developers (who would be operating in the Radhanesda Solar Park), which will be constructed by GUVNL near the Project Site and power will be further evacuated through a 400-kV transmission line of ~35 km length. As per the information available, the transmission line corridor is currently under-construction. The transmission line will be connected to the 400/200kV Banaskantha substation in Khimanavas village, which is currently under-construction and is expected to be commissioned by March 2020.

1.2 Purpose and Scope of Work The main purpose of the ESIA study is to identify, evaluate and manage environmental and social impacts that may arise during the development and operation of the project. This study is being undertaken as per the requirements of the IFC Performance Standards (PS) 2012, ADB Safeguard Policy Statement 2009 (SPS) and other lenders (as shared in the Terms of Reference – ToR), to understand the environmental and social compliance of the Project vis-à-vis the reference framework. The objectives of the ESIA study have been detailed below:

• Reconnaissance survey and primary site assessment to collect and review baseline environmental and social conditions;

• Collection of additional secondary environmental, social and demographic information;

• Identification and review of the applicable environment and social standards and identification of key issues;

• Assessment of potential environment and social impacts of the project and its components;

Page 22: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

AECOM

• Undertaking cumulative environmental and social impacts assessment from other existing, planned or reasonably defined developments;

• Identifying key stakeholders and undertaking stakeholder consultations to assess the influence and impact of the proposed project on them;

• Suggesting mitigation measures and plans to maximize project benefits in consultation with affected communities;

• Preparing an ESIA Report encompassing all components of the baseline study, impacts assessed, documented consultations undertaken and management plans to mitigate the impacts assessed; and

• Developing an Environmental and Social Management Plan (ESMP) based on the impacts identified including monitoring aspects of the mitigation measures suggested.

1.3 Approach and Methodology The approach and methodology applied for the execution of the impact assessment study is as provided:

• The relevant project documents and detailed project report were reviewed to understand the project requirements;

• Regulatory review was undertaken to understand the applicable, local and national legislation and regulatory frameworks;

• A detailed social and environmental assessment of the site and surrounding areas was undertaken through the following:

─ Reconnaissance surveys to understand site specific issues;

─ Discussions with the local community and identification of key issues;

─ Collation of secondary information on social aspects of the site, supplemented by consultations with the local communities to understand community perception with regard to the project and its activities;

─ Stakeholder mapping and Identification;

─ Focused group consultations with selected land losers and other impacted groups;

─ Field surveys and data compilation;

─ Group/Community Consultations: Group meetings and consultations with local and community representatives; and

• Assessment of impacts based on understanding of the project activities and existing baseline status;

• Preparation of an Environment and Social Management Plan (ESMP).

1.3.1 Delineation of the Study Area/Area of Influence A case study approach was adopted to understand the various criteria for delineation of the study area or area of influence. IFC categorises the project primarily according to the significance and nature of its impacts. IFC defines the project's area of influence as the primary project site(s) and related facilities that the client (including its contractors) develops or controls; shared facilities that are not funded as part of the project (funding may be provided separately by a client or a third party including the government), and whose viability and existence depend exclusively on the project and whose goods or services are essential for the successful operation of the project; areas potentially impacted by cumulative impacts from further planned development of the project and areas potentially affected by impacts from unplanned but predictable developments caused by the project that may occur later or at a different location. The area of influence does not include potential impacts that would occur without the project or independent of the project.

IFC Sustainability Framework and Performance Standards (PS), World Bank EHS Guidelines and sector-specific (as applicable) environmental, health and safety guidelines as well as national regulatory requirements suggest that primary baseline data is to be collected so that it reflects the pollutants of concern associated with project processes. Since the proposed project is a renewable energy project and is located in the barren region of Radhanesda village, Banaskantha district in Gujarat and is devoid of much habitation, industrial activity or other

Page 23: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

AECOM

pollution sources, hence, primary impacts from the proposed solar power project have been assessed in and around a radius of 2 kilometres (km) around the Project Site and secondary impacts have been assessed in and around a radius of 5 km around the Project Site.

Therefore, for the purpose of the ESIA study, an area of 5 km (aerial distance) radius has been considered as the Area of Influence (AoI) for identification and assessment of potential environmental and social impacts around the proposed project.

• Direct Impact Zone (Core Components): The area covering the Project Site, internal transmission line corridor and direct access road to the project is designated as the area under the direct influence of the project for environmental, ecological and social impacts.

• Indirect Impact Zone (Shared Facilities): Area outside the direct impact zone of the project, up to a radius of 5 km, is considered as the indirect influence zone for the project for environmental, ecological and social impacts.

All the baseline environmental profiling, including environmental monitoring, socio-economic studies and public consultations, have been carried out within the AoI of 5 km.

In order to include the farthest anticipated direct receptors of biodiversity-related impacts, AoI for the biodiversity studies was delineated as the proposed Project Site, along with the area extending outward up to a radius of 5 km from the Project Site boundary. The map showing the physical features of the Project Site is provided below in Figure 1-1.

Figure 1-1: Map showing physical features of the site and the area of influence

1.3.2 Desktop Review

AECOM carried out a desk-based review of the information shared by the client prior to mobilizing for the site visit for undertaking the Impact assessment. As part of the review, the proposed project area was screened using Google Earth. Based on the review of satellite imagery, the environmental and social sensitivities to be covered as part of the site visit were assessed and subsequently scoped in.

Page 24: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

AECOM

The desk-based review was primarily focussed on but was not limited to the following documents:

• Detailed project report (DPR);

• Site layout plan;

• Evacuation Approval;

• Power purchase agreement (PPA);

• Solar radiation report;

• Various land related documents;

• Organizational chart; and

• Other Project related documents.

1.3.3 Screening and Scoping

At the initial stage of the impact assessment, a preliminary level screening and scoping assessment of the project and its components, including an appraisal of the higher-level environment and social (E&S) risks, screening of the project site and shared facilities (including the access roads, transmission lines, substation, sources of raw material etc.) was undertaken. The screening and scoping study was conducted to identify the likely impacts that the development of the project will have on environment, biodiversity and social conditions in the AoI, to establish an understanding of the various linkages between the lifecycle phases of the project and the associated environmental, social and ecological aspects and development of the activity-impact matrix for the project, to identify the various stakeholders to be consulted for the ESIA study and develop a forward-going approach and methodology to be adopted including E&S baseline development, stakeholder engagement, impact assessment and development of the Environment and Social Management Plan (ESMP).

The screening and scoping assessment was undertaken based on the understanding of the objective and scope of work and AECOM’s experience of working on renewable energy projects, especially the solar energy sector.

The AECOM team, comprising of one (1) EHS expert, one (1) Social expert and one (1) bio-diversity expert undertook a site visit to the project location between 30 - 31 October 2019 and 04-07 November 2019. As part of the site visit, the following key activities were undertaken:

• Meeting with the on-site project representative;

• Site walk through the two land parcels (measuring 190 hectares each) purchased/ earmarked for the project;

• Site walk through the proposed site for the Pooling Substation (PSS) of the solar power park;

• Visit to the under-construction 400/220 kV Banaskantha Grid Substation (GSS) to which power from the project as well as other players operating in the power plant would be evacuated. The proposed GSS is located at a distance of 35 kms from the power park in Khimanavas village;

• Consultations with members of local communities from the Radhanesda village;

• Consultations with the local Sarpanch;

• Consultations with the Gujarat Power Development Corporation;

• Preliminary biodiversity screening for the presence of critical habitats (CH); and

• Photo documentation of the existing land use, structures close to the site, access roads, village structures etc.

The critical habitat screening (undertaken as part of the E&S Scoping) indicated that the Study Area (including the Project Site) is part of the reported ranges of certain potential CH trigger species, as defined by IFC PS 6. Thereafter, a Critical Habitat Assessment (CHA) to assess the area coinciding with the proposed Project Site, as well as, the areas coinciding with the shared facilities of the Project, namely the pooling sub-station, the external transmission line corridor and the main sub-station, for the presence of Critical Habitat (hereafter referred to as ‘CH’), as defined by the applicable reference frameworks, namely the IFC Performance Standard 6 (PS6), 2012 and the ADB Safeguard Policy Statement (SPS), 2009 was undertaken.

Page 25: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

AECOM

The relevant preliminary findings of the CHA study are reported as part of the biodiversity baseline of the ESIA report.

1.3.4 Stakeholder Identification and Analysis

On the basis of the understanding developed in the initial stages, the potential stakeholders for the project were identified and the individual concerns, expectations and influences of the stakeholders on the project were identified. The purpose of such an understanding was to allow for a proper assessment and mitigation of the impacts. On the basis of this understanding, an exercise of stakeholder mapping was undertaking, the purpose of which was to:

• Identify each stakeholder group;

• Study their profile and nature of stakes;

• Understand each groups’ specific issues, concerns and expectations from projects in the area; and

• Gauge their influence on the project.

1.3.5 Site Survey

AECOM team conducted a site survey in two phases i.e. from the 1-3 January and 7-10 January 2020. The following activities were undertaken during this visit:

• Undertake environmental assessments to gain an understanding of the following and consultations with site representatives:

─ Site setting assessment of 5 km study area for the project site;

─ Site setting assessment of transmission line corridor;

─ Study of key environmental receptors such as large water bodies, forest area, man-made sensitivities such as schools, colleges, hospitals etc.

• Undertake environmental monitoring and collection of baseline environmental data;

• Undertake social assessments and consultations in the form of individual interviews and focussed group discussions (FGDs) with the following key stakeholder groups:

─ Local stakeholders; and

─ Institutional stakeholders/government departments.

• Undertake biodiversity assessment including collection of biodiversity baseline data and key stakeholder consultations (Forest department, local community, etc.).

1.3.6 Socio-Environment Baseline Data collection

Environmental baseline data was collected through primary monitoring and reconnaissance surveys of the study area (5 km distance around the project site). Secondary information through literature surveys was also collected for the study area. The baseline study included the following:

• Primary environmental baseline data collection within the study area. The primary environmental and social baseline data was collected with respect to ground water, ambient air quality (AAQ), ambient noise level, soil quality, traffic survey and socio-economics profile. The ecology and biodiversity data were also collected as part of the primary data collection;

• The GIS mapping of the study area was done to present details on land use pattern, forest/ vegetation cover, settlements, water bodies, drainage pattern, spot heights and contours; and

• Information on geology, meteorological conditions, water and ecological resources, socio-economic status etc. was collected from secondary sources.

Page 26: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

AECOM

1.3.7 Stakeholder Consultation

During the site visit for ESIA, following groups of stakeholders were consulted with the objective of collecting baseline data/information and to understand concerned issues:

• Institutional Stakeholders: Representative of GPCL, Mamlatdar (Magistrate Executive) of Vav tehsil, Veterinary officer of Vav tehsil were consulted;

• Local communities: Consultations with village heads (Sarpanch) of Kundaliya and Radhanesda village, Opinion leaders of the Kundaliya and Radhanesda village and Anganwadi worker of Kundaliya village were consulted; and

• ESPL site representative: Consultations were undertaken with the ESPL site team during visit.

1.3.8 Impact Assessment Impact identification and prediction are undertaken on the basis of environmental and social baseline data collected. The major processes involved are:

• Identification – to define the impacts associated with different phases of the project and the activities undertaken;

• Prediction – to forecast the nature, magnitude, type, duration, extent, scale, frequency likelihood and sensitivity of the major impacts identified; and

• Evaluation – to determine the significance of residual impacts i.e. taking into account how mitigation will reduce a predicted impact.

Professional judgement, experience and knowledge of similar projects were used for impact analysis. The extent and potential consequences of the impacts have been compared against applicable reference framework. Mitigation measures have been suggested for each of the identified adverse impacts.

1.3.9 Environment and Social Management Plan

This section delineates the roles and responsibility and timeline for implementing mitigation measures to prevent the significant impacts arising from activities during different phases of the project.

1.3.10 Agencies contacted

The agencies consulted by AECOM team during the ESIA study include the following:

• Tehsil Revenue Department, Vav;

• GPCL, Gandhinagar;

• Animal Husbandry department, Vav;

• Office of the Deputy Conservator of Forest (DCF), Wild Ass Sanctuary, Dhrangadhra

• Range Forest Office, Tharad; and

• Divisional Forest Office, Palanpur.

1.4 Limitations The ESIA study of the project is limited to project information made available by the client, discussion with ESPL representative, primary monitoring, secondary data collected, consultation with local community and observations made during site survey. Professional judgement and interpretation of facts has been applied for presenting inference from the collected information.

1.5 Layout of Report The current ESIA Report has been arranged under the following chapters:

Page 27: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

AECOM

1. Chapter One: Introduction (This chapter provides a background of the project and the current Report, the objectives with which the study has been undertaken, the scope of work, etc.)

2. Chapter Two: Project description (This chapter provides details of the project location, key project components and utilities, land requirements, power purchase agreement, current project status, etc.)

3. Chapter Three: Environment and Social Regulatory framework (This chapter encompasses the national administrative requirements, applicable permits, licences, approvals and consents and project categorisation as per Reference Framework)

4. Chapter Four: Environmental and socio-economic baseline (This chapter illustrates the environmental baseline, socio-economic baseline and Ecology baseline)

5. Chapter Five: Analysis of alternatives (This section presents the analysis of alternatives for the proposed solar project)

6. Chapter Six: Impact Assessment (This chapter highlights the impact assessment criteria, key environmental risks and key social risks)

7. Chapter Seven: Environment and Social Management Plan (This chapter highlights the organization structure, training, Inspection monitoring and audit and Documents and record keeping)

8. Chapter Eight: Conclusion and Recommendations

Page 28: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

AECOM

2. Project Description

2.1 Project Location The proposed Project Site is located in Radhanesda Ultra-Mega Solar Park (700 MW) situated in Radhanesda village, Vav Taluka, Banskantha district in the state of Gujarat, India. The site can be accessed through State Highway (SH) 127 which passes through the village Kundaliya and connects to Radhanesda village at a distance of 8 km from the site. The road further connects to Limbidya village (Limbiya- Baet road) which is an existing government paved road (~3.5 m wide) and runs parallel towards north of the site. The Site is situated at a level of ~3 m below the access road. Ahmedabad airport is the nearest airport to the site at a distance of 271 km towards northwest of the site. Radhanesda village is the nearest habitation to the site at a distance of ~4 km. International border with Pakistan is at a distance of about 28 km from the site. There is no solar power plant or any industry within 5 km radius of the project site.

The Indicative proposed project site location has been depicted in the Figure 2-1 below.

Figure 2-1: Indicative location of Project site in Gujarat, India

2.2 Site Settings The Project Site comprises of two (2) adjoining plots i.e. Plot D and Plot E, each measuring 190 hectares (~469.03 acres) and is located in the south western portion of the Radhanesda Solar Park. Towards north west of the Site is the land parcel measuring 68 hectares (167.96 acres), which has been designated for grazing purposes by the Government of Gujarat and the proposed Pooling Substation (PSS), to be constructed by GUVNL. The Southern boundary of the Site is also the boundary of the solar park towards that side. The Project

Page 29: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

AECOM

Site is surrounded by other solar power developers towards the east and west side. The PSS, to be constructed in the northern portion of the solar park, will cater to all the power developers operating within the Radhanesda solar power park. The site is generally flat and is situated at an elevation of 6 m above mean sea level. The entire land parcel comprising the Radhanesda Solar Power Park (including the Project Site) is owned by the Government of Gujarat (GoG) and does not involve any private or forest land.

A major proportion (approximately 80%) of the site constitutes natural or near-natural habitats represented by saline mudflats, thorn scrub and thorn forest and the remaining site constitutes modified habitats represented by farmland, salt-pans and embankments. No physical structures were noted at the site during the site visit.

It was noted that the soil at the project site has high salinity and accumulation of salt was noted throughout the land parcels. Also, the soil needs to be compacted prior to commencing any work on the site.

Ground water was noted to be at a depth of 1-2 m below ground level (bgl) at the site and the same was confirmed by the village Sarpanch. However, the ground water was reported to be extremely saline and thus unsuitable for drinking or domestic purposes. It is proposed that underground cables will be laid at the site for evacuation of the power generated through the project. It was informed by the project proponent that rain water gets accumulated at the site during precipitation.

The access road running parallel to the site is an existing paved road (~3.5 m wide) and is well connected to nearby cities. Thus, no access road needs to be constructed for the project. The map representing the location of project in Radhanesda Solar Park has been shown in the Figure 2-2 below.

Page 30: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

AECOM

Figure 2-2: Map showing Project Location in Radhanesda Solar Park

Page 31: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

AECOM

2.3 Project Overview

2.3.1 Project Components

The project components for a solar power plant include Solar PV array, transformer, inverter, substation, transmission line and shared infrastructures (office building, control room, guard room, etc.).

Solar power is trapped through the PV cells in the modules, which are connected to form an array to produce higher voltage. Since the power generated through the solar panels is a Direct Current (DC) and electrical appliances use the Alternating Current (AC), inverters are used to convert DC to AC generated in the solar farms. Transformers are then connected with the AC to step up the voltage to 33 kV for transmission to pooling substation and there it steps up 220 kV level to feed into the grid substation.

Details on components of PV solar plant are presented in Table 2-1 and schematic diagram of a functional solar power plant with project components is depicted in Figure 2-3 below.

Figure 2-3: Overview of Solar PV Plant

Source: Utility-Scale Solar Photovoltaic Power Plants by IFC (World Bank Group)

Table 2-1: Components of Solar PV Plant

S. No. Component Description

1. Solar PV modules These convert solar radiation directly into electricity through the photovoltaic effect in a silent and clean process that requires no moving parts. The PV effect is a semiconductor effect whereby solar radiation falling onto the semiconductor PV cells generates electron movement. The output from a solar PV cell is direct current (DC) electricity. A PV power plant contains many cells connected in modules and many modules connected in strings2 to produce the required DC power output.

2 Modules may be connected together in a series to produce a string of modules. When connected in a series the voltage increases. Strings of modules connected in parallel increase the current output.

Page 32: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

AECOM

S. No. Component Description

2. Inverters These are required to convert the DC electricity to alternating current (AC) for connection to the utility grid. Many modules in series strings and parallel strings are connected to the inverters.

3. Module mounting (or tracking) systems

These allow PV modules to be securely attached to the ground at a fixed tilt angle, or on sun-tracking frames.

4. Step-up transformers

The output from the inverters generally requires a further step-up in voltage to reach the AC grid voltage level. The step-up transformer takes the output from the inverters to the required grid voltage (for example 33kV and 230 kV depending on the grid connection point and country standards).

5. Grid connection interface

This is where the electricity is exported into the grid network. The substation will also have the required grid interface switchgear such as circuit breakers (CBs) and disconnects for protection and isolation of the PV power plant, as well as metering equipment. The substation and metering point are often external to the PV power plant boundary.

Apart from the above basic components, the project system will consist of a main control room (MCR) and a switch yard within the project boundary.

As per the information provided by the Client, the 250 MW (AC)/200 MW (DC) solar power project will be based on Multi-crystalline silicon (c-Si) Solar Photo Voltaic technology using 380Wp/435Wp) with with 72 cells each for power generation. The proposed power plant will have an AC/DC ratio of 1.50 / 1.40 (DC Overloading).

The salient features of the project components have been presented in Table 2-2 below and the details have been provided in subsequent sections.

Table 2-2: Technical Details of PV Power Plant

Parameter Make

Solar PV Modules 380/435 Wp (789473/666666)

Module mounting structure Fixed type

Tilt- 19 deg for 2P29/ Pitch 8.0 M for 435 Wp

Tilt- 18 deg for 2P30/ Pitch 7.5 M for 380 Wp

String Combiner Box (SCB) 16 Inputs / 1 Output- with 380 Wp design

24 inputs/ 1 output- with 435 Wp design

Cables as per design DC 3.3KV XLPE Armored Cable

Cables as per design AC XLPE with HDPE outer Sheath & water saleable tape

Invertors Capacity 6.40 MW Block with String Inverter (160 kW, 185 KTL Huawei)

3125 kVA

Number of Invertor 64

Invertor Transformer Make 6.40 MVA for String Inverter & 12.5 MVA (16 nos.) for Central Inverter

option

Outdoor HT Panel make and Rating 33KV VCB Indoor type at MCR

Source: Detailed Project Report (DPR)

2.3.1.1 DC Components

PV Module

All solar PV modules mandatorily have to adhere to International Electrotechnical Commission (IEC) specifications given in IEC 61215 for Crystalline Silicon modules. The solar PV modules for the project must be tested and certified by an independent international testing laboratory. For optimum energy generation Crystalline Silicon 380 Wp and 435 Wp modules will be used for this project.

Module Mounting Structure

Fixed tilt ground mounted structures with uniform loading will be used for this project. PV modules are directly mounted on the module support members. The aluminum frame of each solar module is galvanically isolated

Page 33: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

AECOM

from the steel supporting beam to prevent localized corrosion and high-quality stainless-steel fixings are used throughout.

The mounting structure is designed for holding the designated number of modules in series. The frames and leg assemblies of the array structures are made of structural steel sections. The composition of steel conforms to IS 2062, suitable for welding purposes.

The structure will be designed to allow easy replacement of any module to support solar PV modules at a given orientation, absorb and transfer the mechanical loads to the ground properly. The legs of the structures with appropriate strength are fixed in the foundation columns as per design based on site soil condition.

Inverters

Inverters/ Power Conditioning Units (PCU) act as the interface between the PV array and the Grid. As the PV array output varies with the solar radiation, the inverter has to effectively interface with the grid to remain synchronized. Main functions of Inverters are:

• Convert the incoming DC received from PV modules into AC with suitable power quality.

• The inverter also has to act as a protective device of the system. It needs to trip if the voltage, current or frequency goes outside acceptable ranges

For the project, 160 kW (185 KTL) of Huawei make will be used for 6.40 MW block and for 12.5 MW Block with

Central Inverter (3.125 MW outdoor Inverter) will be selected.

2.3.1.2 AC Components

The AC subsystem commences from the output of the inverters and comprises of the transformers, the associated switchgear, metering and protection circuits and terminates at the two-pole structure from where the transmission lines would start.

Transformer

Outdoor oil-type 6.40 MVA for String Inverter & 12.5 MVA for Central Inverter option with Voltage 33KV (as per design) with three (03) winding for String Inverter and five (05) winding for Central Inverter option will be used for the project.

HT Panel

The HT panel is an interface between the transformers and grid providing the protection required for the system. The switchgear contains all equipment viz. Circuit breakers, CTs, PTs, relays and associated equipment. 33 kV Switchgear with16 ITS station and 2 number for MCR will be used.

Metering

The metering arrangement is compatible with the Availability-Based-Tariff (ABT) mechanism along with a check meter with Modbus arrangement and facility to provide remote monitoring. The meter has web communication facility and is visible at the State Load Dispatch Centre (SLDC).

AC Auxiliary System

The AC auxiliary supply of single/three phase is required for periphery lighting, security cabin and control room lighting etc.

2.3.1.3 Civil Structures

Inverter room and Control Room The inverter rooms are pre-fabricated FRP structures and control room is the standard RCC framed structures.

Boundary Wall

The complete plant boundary covering module yard, control room, switchgear room and switch-yard, security cabin, etc. is provided with a compound wall made of pre-cast slabs.

Page 34: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

AECOM

Security Cabin

The security cabin made of FRP (Fiber-reinforced plastic) is provided near the site entry gate.

Transformer Foundation

The power transformer has been placed on gravel filled foundation and placed on the ground/ raised foundation.

Pile Foundation

Pile foundation design has depended upon soil conditions, geographical condition, regional wind speed, bearing capacity, slope stability, etc.

Internal Roads

Internal roads T3 traffic category with 3.5 m width will be constructed 250 mm above floor level. Peripheral roads around the boundary will be constructed as per IRC 37 with at least 3 m width.

2.3.1.4 Earthing

There will be dedicated earthing stations for transformer, MV switch boards and high voltage panels. Maintenance free earthing stations are considered preferable for the design due to long-term trouble-free performance in comparison to conventional pipe earthing. All the modules will be appropriately earthed in accordance to the NEC (National Electrical Code). Grounding of the modules will be done as recommended by the manufacturer.

2.3.1.5 Lighting and Over Voltage Protection

The MV stations comprising of transformers, inverters, etc. will be provided with adequate lightning protection. Similarly, the entire main control room building, and four pole structure arrangement will be protected as per IS standards. Necessary concrete foundation for holding the lightning conductor in position will be made after giving due consideration to the maximum wind speed (47 m/sec) and maintenance requirement at site in future. Each lightning conductor will be fitted with individual separate earth pit as per required Standards including accessories and provided with iron cover plate having a lock arrangement, watering pipe using charcoal or coke and salt as per required provisions of Indian Standards (IS).

2.3.1.6 Supervisory Control and Data Acquisition (SCADA) System

The entire solar PV power plant will be integrated with Supervisory Control and Data Acquisition (SCADA) system which communicates with all the inverters and monitoring boxes (SMB) for displaying parameters mentioned below. The integrated SCADA has the feature to be used either locally via a local computer or also remotely via the Web using either a standard modem or a GSM / WIFI modem and broadband. SCADA have provision of tracking the status of breakers and relays. Following parameters will be shown in the SCADA system:

• Data from weather station;

• PV module back surface temp;

• Line and phase currents;

• Cumulative energy exported;

• Power at 220 kV terminal;

• AC and DC side power of each inverter;

• Voltage of the HT Side; and

• Current and voltage of each sub-array/string.

2.3.2 Power Evacuation—Substation and Transmission Line

Power generated through PV modules will be stepped up to 33kV and will be pooled to main HT panel using breaker feeder. As per information provided by ESPL, a 33kV/220 kV internal common pooling substation (PSS)

Page 35: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

AECOM

which will be constructed by GUVNL near the Project Site for all the Solar Power Developers in the Solar Park and the power will be further evacuated through a 400-kV transmission line of length ~35 km.

As per the information available, the transmission line corridor is currently under construction and is expected to be commissioned by March 2020. The transmission line will be connected to the 400/200kV Banaskantha substation in Khimanava village (Inter-Connection Point/Delivery Point), which is situated at a distance of 35 km from the project site.

As per the DPR, SPPD has secured connectivity from Central Transmission Utility (CTU) for the Solar Park. ESPL after being selected in the bidding, entered into Implementation and Support Agreement (ISA) for connecting their project with grid through internal Pooling Sub-station. ESPL shall connect their project to Internal PSS by laying 33 kV cable up to low voltage bus bar of Pooling Sub-station at its own cost. All the line losses up to Inter-connection point will be on account of the Solar Power Developer.

Metering point shall be at 220 kV side of 400/220 kV Banaskantha substation of Power Grid Corporation of India Limited (PGCIL), i.e. the CTU. However, one more metering system shall be installed at 33 kV side of Internal Pooling Sub-station where power from the Solar Power Project is injected for measuring export / import from each project.

It is to be noted that the transmission line component of the project is a shared facility common to all the solar power producers operating/ proposed to operate within the Power Park. Consequently, ESPL does not have any control over the procedure being employed towards obtaining RoW, payment of compensation to owners of private land parcels towards loss of land located between the foot legs of the transmission and restricted land use along the RoW corridor. However, consultations with communities inhabiting within proximity of the proposed transmission line route indicated that the proponent will pay one-time compensation to land owners for loss of standing crops and trees.

2.3.3 Access Roads

The main entrance to the site is proposed to be from the eastern side. The site can be accessed through State Highway (SH) 127 which passes through the village Kundaliya and connects to Radhanesda village at a distance of 8 km from the site. The road further connects to Limbidya village (Limbiya- Baet road) which is an existing government bitumen road (~3.5 m wide) and runs parallel to the site.

Since, the road is paved thus, no new road will be required to be developed for the project. Consultations with the project proponent suggested that project-related construction material, equipment and machinery are envisaged to be transported through the access road connecting the site.

2.4 Status of the Project For the purpose of the environmental and social impact assessment, a site visit was undertaken in January 2020. As on the day of site visit, the project was noted to be in pre-construction phase, and it was noticed that fencing work to demarcate the site boundary was being undertaken at the proposed project site. As per the information provided, land procurement is under the purview of GPCL. A Power Purchase Agreement (PPA) was signed between GUVNL and ESPL on 26 August 2019 for purchase of power generated from the proposed project for a period of 25 years. As per the information shared by the client, the Engineering, Procurement and Construction (EPC) Contractor for the project is in the process of being finalised. A hydrological study for understanding the flooding and drainage aspects of the entire solar power park was undertaken by IIT, Roorkee in August 2016. The Right of Way (RoW) for the transmission line will be obtained by the GPCL. Evacuation Approval for the entire solar park of capacity 700 MW to be set up in Radhanesda village was obtained by GPCL from Power Grid Corporation of India Limited (PGCIL) through letter dated 13 October 2019.

Page 36: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

AECOM

Figure 2-6: View of the existing paved access road running

parallel to site

Figure 2-7: Limda Mata Ki Mandir under renovation at a

distance of 1km from site

The Figure 2-8 represents the project site along with the PSS and external transmission line.

Figure 2-4: View of the project site Figure 2-5: Ground water at a depth of 1-2 m below

ground at site

Page 37: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

AECOM

Figure 2-8: Map showing the project location and external transmission line

Page 38: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

AECOM

2.5 Resource Requirement and Procurement 2.5.1 Land requirement and Procurement process

The following project components were identified for which land was required during the construction and/ or operation phase;

• Installation of Solar Modules;

• Site office;

• Invertor room;

• Stock yard; and

• Transmission line

The above information on the project components has been drawn based on discussions with the site representatives of ESPL, consultations with institutional stakeholders such as the Gujarat Urja Vikas Nigam Limited (GUVNL), Gujarat Power Development Corporation (GPDC) and Gujarat Energy Development Agency (GEDA) and review of land-related documents shared by ESPL.

2.5.1.1 Project-related land procurement and existing land procurement status

The land required to be used for solar modules is approximately 4 acres/ MW and total 200 MW will be installed in this project. Hence, the total land requirement for installing the 200 MW solar power plant with site office, inverter room, transmission line and other associated structures is approximately 380 hectares (~ 938.06 acres). The Project Site comprises of two (2) adjoining plots i.e. Plot D and Plot E, each measuring 190 hectares (~469.03 acres) and is located in the south western portion of the Radhanesda Solar Park. The land parcel of 68 hectares (167.96 acres), earmarked for grazing purposes, and the proposed PSS, that will be common for all solar power operators which will be operating within the solar power park, are located towards north west of the Project Site.

Details and existing land procurement status for the project is as follows:

• Extent of land: As per the site representatives, the concerned land parcels are mostly saline, sandy and uncultivable land measures and fall within the Radhanesda Solar Power Park located in the Radhanesda village under Vav tehsil in Banaskantha district. ESPL has also undertaken a title search for the project land through representatives from the head office in Pune.

• Mode of procurement: The entire land measuring ~ 938.06 acres has been allotted on lease basis by the GPCL to Electro Solaire Private Limited (ESPL) for a period of 25 years.

• Current procurement status: The lease deed has already been executed between GPCL and ESPL. However, ESPL was yet to take physical possession of the land at the time of the ESIA study.

• Farming and irrigation: The entire project land was observed to be sandy and unfit for farming. Moreover, poor fertility and lack of irrigation facilities for cultivation of the concerned land parcels were reported during community consultations. Consequently, no farming activities were observed or reported during the site visit.

• Access road: The site can be accessed through State Highway (SH) 127 which passes through village Kundaliya and connects Radhanesda village at a distance of 8 km from the site. The road further connects Limbidya village (Limbiya- Baet road) which is an existing government paved road (~3.5 m wide) and runs parallel towards the north of the site. The site is situated at a level of ~3 m below the access road. Consultations with the site representative revealed that at least 2-3 meters of land on either side of the existing road is there (owned by the Government) that can be used to widen the road. Hence, no land is required for widening of the access road.

• Transmission line: Power generated from the project will be fed to the common Pooling Substation (PSS), which will be constructed by GUVNL adjacent to north western portion of the Project Site and power will be further evacuated through a 400-kV transmission line measuring ~35 km. As per the information available, the transmission line corridor is currently under construction. The transmission line will be connected to the 400/200kV Banaskantha substation in Khimanivas village, which is currently

Page 39: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

AECOM

under construction and is expected to be commissioned by March 2020. The transmission line corridor is mostly passing through agricultural land parcels, however, the right of way (RoW) of the transmission line is yet to be finalised.

• Grazing within and around the project site: Grazing activities were observed in a land parcel measuring approximately 68 hectares (167.96 acres) situated adjacent to the north western portion of the Project Site. The land parcel, originally owned by the government, has been handed over to the Radhanesda Gram Panchayat (GP) as a goodwill gesture to the local communities for animal grazing purpose. Consequently, the said land parcel measuring 68 hectares has been excluded from the solar power park. Though the same is located within the boundary of the solar power park, however, it has been excluded from allotment to any developer and is connected by an access road measuring approximately 5-6 meters.

• No appropriation through the tools of acquisition: It is to be noted that no appropriation of land using the tools of acquisition have been involved for the project. Consequently, the project does not have any impacts that are involuntary in nature.

2.5.1.2 Key Issues in Land Procurement

As indicated earlier, land for the concerned solar power park, including the two (2) plots that have been allotted to ESPL for setting up their power project, is owned by the Government of Gujarat. Hence, no procurement of land from private parties has been done for the project. The land in question has been allotted by the Government of Gujarat through the GPCL to individual solar power producers on a lease basis for a period of 25 years. The position of the project/ land procurement vis-à-vis key socio-economic issues are as follows:

• Schedule V Area and Tribal Land: The Project area does not fall under Schedule V areas as defined in the Indian Constitution under Article 342. The land identified for the project does not comprise of any tribal land/ land parcels owned by members belonging to the Indigenous Peoples (IP). Moreover, the project does not have any impacts on IPs. It is to be noted that according to the 2011 Census, Banaskantha has 9.1 % tribal population residing within the district.

• Forest land: The project will be developed on Government-owned sandy, saline, barren and uncultivable waste land. As reported, no forest land will be used for the project.

• Common Property Resources (CPR): No CPRs were reported on the allotted land parcels. As indicated earlier, within the boundary of the solar park, one land parcel measuring 68 hectares (167.96acres) has been allotted by the Government as a goodwill gesture to local communities for grazing purposes.

• No Objection Certificate (NOC) from Panchayat: The State of Gujarat does not require solar power projects to take a NOC from the Gram Panchayat of the impacted villages prior to initiation of construction activities. However, the project proponent reported that prior to commencement of construction activities at site, a NOC will be obtained from the Radhanesda Gram Panchayat.

• Landlessness: As the entire project land is owned by GPCL and the same has been leased to ESPL for a period of 25 years, there is no possibility for landlessness caused by the project.

• Encumbrance on Land/ Economic Impact: No encumbrance or encroachment on the project land could be observed at site or reported during stakeholder consultations. Similarly, no agricultural activities were observed at site. Hence, based on the general site conditions – sandy/ uncultivable nature of land, lack of rains and the limited farming being undertaken around the proposed project land, no significant economic impacts of the project are envisaged.

• Cultural Heritage sites: ‘Limda Mata Ki Mandir’ – a temple was observed at approximately 1 km from the project. The existing temple was being renovated during the site visit. The project will have no bearing/ impact on the temple. Consultations with the local communities and the Sarpanch, Radhanesda indicated that the temple has been existing in the same location since generations and that its origin/ circumstances surrounding its origin is not known.

2.5.2 Land procurement process

As indicated earlier, the project land allotted on lease basis for a period of 25 years to ESPL, is owned by the Gujarat Power Corporation Limited (GPCL). The said land does not include any private or forest land. The

Page 40: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

AECOM

procedure used for procurement/ allotment of the said land by the GPCL on lease basis to ESPL has been highlighted in Figure 2-9.

Figure 2-9. Land procurement/ allotment process

The key aspects of the lease of the concerned land parcels between GPCL and ESPL that were reviewed in the lease document include the following:

• The Land is located in the old survey no- 121 and has two (2) new blocks – Survey no-125 and Survey no-128;

• The nature of land use is non-agricultural;

• The extent of land in the old survey no. i.e. 121 is 1407.06.98 acres and the same was confirmed through a remeasurement applied by the Talati cum Mantri of Kundaliya Village;

• The lease period is for 25 years;

• The lease rate is to be Rs. 10,000 per hectare per year with a provision for increase in the lease rate by 15 % every three years; and

• Review of the land allotment genesis suggests that the concerned parcels were allotted as per the officer’s order on 24/4/1965 (name of the allotted person is not clearly mentioned) and again on 9/4/1966. Therefore, there is change in allotment and the government has allotted the same land at Radhanesda to a new person (name of the allotted person is not clearly mentioned).

Based on review of the lease deed shared by ESPL, consultations with the revenue department officials, the ESPL representatives and the local Sarpanch, it can be confirmed that the land procurement for the project is being done through the land lease process.

Page 41: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

AECOM

2.5.3 Manpower requirement Procurement of land for the project was already completed at the time of the site visit. However, no project-related construction activities had started. The EPC contractor for the project was yet to be appointed at the time of site visit. However, it was reported that during the peak construction phase, approximately 600-700 workers will be employed for a duration of 2-3 months. Some of the key activities to be undertaken at site during the construction phase includes foundation work, civil construction work, electrical and structural work etc. While most of the workers in the unskilled and semi-skilled categories will be hired from the neighbouring villages and from within the Banaskantha district, the manpower requirement in the skilled and highly skilled categories will be sourced from outside the state. It was revealed by the site representative of ESPL that approximately 30 % of the construction manpower will be migrant workers who will be provided accommodation in houses taken on lease basis by the EPC contractor in the neighbouring villages. It was also confirmed that the one labour camp will be constructed near the project site during the construction phase. The manpower requirement during the operations phase was reportedly between 6 – 8 people who will be engaged through contractors mostly for housekeeping, security, gardening etc. The ESPL manpower to be engaged during the construction and operations phases was reported to be between 10 – 15 (during construction) and 4 (during operations) respectively.

2.5.4 Water Requirement Construction Phase

In the proposed plant almost all the buildings and structures will be prefabricated type and all the equipment will be packed and shifted in completely assembled or partially assembled form. The installation of the equipment will not require water in any form, as reported. As per the information shared by the Client, water requirement for the construction phase will be 100 KL (Kilo litres) that will be required for piling, foundation works and other construction activities. The water will be sourced through a branch of the Sardar Sarovar Narmada Water canal located at a distance of 40 km from the Project Site. Reverse Osmosis (RO) treated packaged drinking water will be provided to the workers at site (~5000L/day) for peak construction period. One labour camp will be constructed, as reported.

Operation Phase

Conventionally, the water requirements for the plant in operation phase are predominantly for washing of solar PV modules periodically to remove bird droppings, dust and other dirt and for domestic use.

During the operation phase, Reverse Osmosis (RO) treated packaged drinking water will be provided to the workers at site (~250L/day). Water for domestic requirement at the site will be ~1 KL and will be sourced through Narmada Canal as informed by the Client.

As per the information provided by the Client, GPCL will construct a tank of 10 lakh litres capacity inside the solar park for meeting the water requirement for module cleaning for the entire solar park. Water for module cleaning will be sourced by GPCL through a branch of Narmada canal and will be stored in the tank to be constructed by GPCL for the entire solar park. Assuming a minimum of 2.5 litres of water per module3, the water requirement for cleaning the whole plant (i.e. ~10 lakh modules) will be approximately 1,666 kilo litres, at one time. With a cleaning schedule of twice a month, it is estimated that approximately 3,332 kilo litres of water will be required for cleaning purpose on a monthly basis.

2.6 Waste Generation

2.6.1 Waste Water During construction phase, adequate number of portable toilets will be provided by the EPC contractor at site and a septic tank with soak pit will be provided for disposal of domestic wastewater generated. Wastewater from construction activity will be limited to cleaning and washing activities.

3 As per the details shared by Client, ~2.5 liters of water will be required for cleaning of one module.

Page 42: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

AECOM

During the operation phase, domestic wastewater will be limited to domestic wastewater discharged from the site office. Toilets with a septic tank and soak pit will be provided for disposal of domestic wastewater generated at the site office.

2.6.2 Hazardous Waste

During construction phase, hazardous waste such as used oil from diesel generator (DG) sets, oil-soaked cotton, oil lined containers, paints etc. will be generated at the site. The hazardous waste will be disposed through a Gujarat Pollution Control Board (GPCB) authorized hazardous waste recycler within 90 days of generation.

During operation phase, no DG set is proposed to be installed at the site and thus the hazardous waste generation will be limited to used oil from transformer. The oil will be reused after filtration and the waste oil will be disposed through a GPCB approved hazardous waste recycler.

2.6.3 Solid Waste

Solid waste generation during the construction phase will consist primarily of scrapped building materials, excess concrete and cement, rejected components and materials, packing and shipping materials (pallets, crates, Styrofoam, plastics etc.). The waste will be disposed by the EPC contractor by following designated solid waste management practices.

During operation phase, the waste generated will be limited to paper, plastic waste and food waste from the site office. The waste shall be collected in designated bins at site and disposed at a regular interval by the O&M contractor.

2.7 Implementation Schedule ESPL has undertaken site assessment based on solar radiation data available, identification of land and land procurement for the proposed project. The entire project land has been allotted to ESPL by the GPCL on lease basis for a period of 25 years.

ESPL will engage an EPC contractor on turnkey basis for undertaking construction works by the end of January 2020. The construction works will comprise of carrying out geotechnical investigations, foundation works, installation of switch yard, array yard installation, SCADA system, inverters modules and equipment installation.

Once construction of the project is over, the project will be handed over to an Operation and Maintenance Contractor (O&M) which is yet to be finalised by ESPL. However, the O&M contract will be for a period of twenty-five (25) years. As part of the O&M, the O&M contractor will be the in-charge of project management which includes financial and administrative control, overall project co-ordination, manpower selection for operation and maintenance etc.

As per the information shared by the Client, the construction of the solar power plant is expected to be initiated by January 2020 and the construction period is expected to last for eleven (11) months. The expected date of commissioning of the 200 MW power plant is November 2020. The construction of the internal PSS has been initiated by GUVNL. The PSS is located at a distance of ~200 m from the site and is expected to be commissioned by June 2020.

2.7.1 Construction Activities

Site Development

The site development activities for the proposed project will entail the following:

• soil investigations;

• site clearing;

• site levelling;

• construction of access roads;

• fencing of site; and

Page 43: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

AECOM

• laying of foundations.

All construction activities shall occur within the site boundary limits with the exception of those activities related to the interconnections between the site and the common infrastructures, which will be performed by the ESPL outside the boundary wall of the site. ESPL shall only be responsible for site clearing and grading of the site as required for construction, operation, and maintenance of the plant.

2.7.2 Operation and Maintenance

The solar photovoltaic system requires least maintenance among all power generation facilities due to the absence of fuel, intense heat, rotating machinery, waste disposal, etc. However, keeping the photovoltaic panels in good condition, monitoring and correcting faults in the connected equipment and cabling are still required in order to get maximum energy from the plant. The maintenance functions of a typical solar PV power plant can be categorized as below.

1) Scheduled or preventative maintenance – Planned in advance and aimed at preventing faults from occurring, as well as keeping the plant operating at its optimum level.

2) Breakdown maintenance – carried out in response to failures.

Maintenance Requirement

The main objective of the plant maintenance is to keep the plant running reliably and efficiently as long as possible. Efficient operation implies close control not only over the cost of production but also over the cost of maintenance. There are two components in maintenance cost: one is the direct cost of maintenance, (i.e. the material and labour), and the other is the cost of production loss.

Routine Maintenance

Several maintenance activities need to be completed at regular intervals during the lifetime of the system. The energy yield of the plant will be monitored using the remote data acquisition system connected to each inverter. Significant reduction in energy yield will trigger specific maintenance requirements, such as inverter servicing or module replacement. Typical activities required are described below:

1) General maintenance: Vegetation will need to be cut back if it starts to cause a fire risk or introduce shading;

2) Modules: Visual inspection and replacement of damaged modules will be required. Cleaning of the module glass surface during long dry periods may be considered. Module cleaning needs to be carried out periodically to remove dust, bird dropping etc.;

3) Wiring and junction box: Visual inspection for corrosion, damage such as chafing and damage by rodents and birds and for overheating of cables and connections;

4) Inverter Servicing: Inverter faults are the most common cause of system downtime in PV power plants and therefore, the scheduled maintenance of inverters should be treated as a centrally important part of the O&M strategy. The preventive maintenance of inverters includes visual inspection, cleaning/replacing cooling fan filters, removal of dust from electronic components, tightening of any loose connections etc.

Breakdown Maintenance

Breakdowns can occur due to lack of routine or preventive maintenance, bad climatic conditions, disturbance in

utility grid etc. As breakdowns affect energy generation and hence revenue generation, these kind of faults needs

to be immediately corrected. Breakdown can occur at any part of the system between solar PV modules to

substation end.

Page 44: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

AECOM

3. Environment and Social Regulatory Framework

This section highlights the environmental and social regulations applicable to the proposed solar power project. The section broadly focuses on the institutional framework, national administrative/ regulatory requirements, applicable environment, health and safety and social legislative requirements, ADB Policies, Strategies and Operations Manuals, FMO policies and IFC Performance Standards, relevant to the proposed project.

3.1 Terms of Reference Scoping exercise for the project was undertaken in November 2019. Based on the scoping, Terms of Reference (ToR) for the ESIA study are illustrated in Table 3-1.

Page 45: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

Electro Solaire Private Limited

AECOM

Table 3-1: Terms of Reference for the ESIA

S. N. Section Particulars Description of the Content

1. Executive Summary - The section will provide a brief summary of the project, ESIA process and methodology adopted, environment and social baseline conditions, significant project related aspects and identified impacts and mitigation.

2. Introduction • Project Background

• Purpose and Scope of Work

• Approach and Methodology

• Agencies Contacted

• Limitations

• Report Layout

The section will provide description of project background with objectives, purpose and scope and approach & methodology adopted for the ESIA study.

3. Project Description

• Site Settings

• Project Layout

• Project Components

• Power Evacuation System

• Land Requirement

• Status of the Project as on date of Site visit

• Resource requirement

This section will present project details such as layout, land details, site settings, project components etc. This will

also include the description of the infrastructural development as a part of project life cycle during construction and

operation phase and resources required.

4. Environmental and Social Regulatory Framework

• Introduction

• Enforcement Agencies

• Applicable Environment and Social Laws, Regulations and Policies

• IFC Performance Standards

• UN Guiding principles on Business and Human Rights

• Applicable Environmental Standards

• Applicable International Conventions

This section will provide information on Policy, Legal and Administrative framework applicable to the proposed solar

farm project as well reference to the International conventions and Clients Guidance documents. The section will also

define the applicability of IFC Performance Standards of the proposed project.

5. Environment and Socio-Economic Baseline

• Introduction

• Physiography

• Geology and Soil

• Drainage

• Ground Water Resources

• Water Quality

• Climate and Meteorology

• Natural hazards

• Ambient Air Quality

• Ambient Noise

This section will illustrate the baseline settings of the environmental aspects, ecological profile and socio-economic

status of the project area.

Environmental Aspects:

Results of the primary environmental monitoring conducted will also be analysed against the legal as well as

international standards and presented under this section. The following parameters will be assessed:

Micro-meteorology: Available information on meteorology for the area representative of the site will be collected

from Meteorology Department. Setting up an automatic micro-meteorological station with data logging facility at the

site for continuous monitoring for micro-meteorological parameters like ambient temperature, wind direction, wind

speed, relative humidity, cloud cover and rainfall for twelve (12) weeks.

Page 46: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

Electro Solaire Private Limited

AECOM

• Biodiversity

• Socio-economic Environment

Air Quality: Information on Air quality will be collected through monitoring of ambient air quality for one (01) weeks

per location for parameters such as Particulate Matter (PM-10), PM-2.5, Oxides of Nitrogen (NOx), Sulphur Dioxide

(SO2), etc.

Surface and Ground Water: Surface and ground water samples will be collected for analyses of following

parameters:

• Organoleptic and Physical Parameters: Colour, Odour, pH, Taste, Turbidity, Total Dissolved Solids

• General Parameters: Biological Oxygen Demand (BOD), Chemical Oxygen Demand (COD), Aluminium (as Al), Ammonia (as total ammonia-N), Anionic detergents (as MBAS), Barium (as Ba), Boron (as B), Calcium (as Ca), Chloramines (as Cl2), Chloride (as Cl), Copper (as Cu), Fluoride (as F), Free residual chlorine, Iron (as Fe), Magnesium (as Mg), Manganese (as Mn), Nitrate (as NO3), Phosphorus (as P), Selenium (as Se), Silver (as Ag), Sulphate (as SO4), Sulphide (as H2S), Total alkalinity as calcium carbonate, Total hardness (as CaCO3), Zinc (as Zn), Cadmium (as Cd), Cyanide (as CN), Lead (as Pb), Mercury (as Hg), Molybdenum (as Mo), Nickel (as Ni), Pesticides, Polychlorinated biphenyls, Total arsenic (as As), Total chromium (as Cr).

• Bacteriological Parameters: E. coli bacteria, Total coliform bacteria

Soil Quality: Soil samples will be collected and analysed for the following parameters:

• Physical Parameters: Particle Size Distribution, Texture, pH, and Permeability, Porosity, Electrical Conductivity,

etc.

• Chemical Parameters: Nitrites, Nitrates, Phosphates, TPH, Heavy Metals such as Fe, Pb, Mn, Ni, Ba, Zn, Cu,

Cd, Cr, As and Hg, Total Hydrocarbons, Cation Exchange Capacity, Trace Metal, Organic Matter, etc.

Ambient noise quality will be monitored to determine hourly equivalent noise levels. The noise sampling will be done

once during the study period continuously for 24 hours, selected on the basis of the site sensitivities within the study

area. The results of the findings will be analysed to work out Leq hourly, Leq day and Leq night.

Biodiversity Aspects:

Methodology and duration of the biodiversity study would be provided. Further, specific details on the following

biodiversity aspects would be provided:

• Floristic Profile – based on reported Forest Types and recorded floristic species

• Faunal Profile – based on reported and recorded species of mammals, birds (resident and migratory), reptiles, amphibians and fishes

• Invasive Alien Species

• Habitat Profile (Natural and Modified Habitats)

• Potential Critical Habitats – based on PS6-stipulated criteria/thresholds

• Designated Areas (Legally Protected Areas and Internationally Recognized Sites)

• Ecosystem Services (Provisioning, Regulating, Supporting and Cultural)

Page 47: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

Electro Solaire Private Limited

AECOM

Social Aspects:

The socio-economic and demographic details of the study area encompassing villages within a radius of 5 kms will be

provided on the following parameters: -

• Education and literacy;

• Occupation and livelihood;

• Rural infrastructure and civic amenities; and

• Road, communication and transport.

The ESIA will also assess the land procurement status and process.

The performance of the state, district and block vis-à-vis key socio-economic and demographic indicators will also be

sketched.

Further, assessment of socio-economic impact associated with the right of way and land procurement of any shared or related facilities (for example access road, transmission line, etc.) will be undertaken.

6. Stakeholder Engagement and Consultation

• Introduction

• Objective and Scope

• Engagement Mapping and Analysis

• This section will highlight the requirements of the IFC with respect to stakeholder consultations and disclosure. Key stakeholder groups of the project will be identified and mapped in this section basis which engagement measures can be proposed.

7. Analysis of Alternatives

• Introduction

• No Project Scenario

• Alternative Site Location

• Alternate Source of Power Generation

• Alternate Routes of Transmission Line

• Conclusion

This section will present the analysis of alternatives for the proposed solar project considering no project scenario,

alternate methods for power generation and technology and alternate routes for transmission line.

8. Evaluation of Impacts

• Introduction

• Summary of Project Activities

• Impact Evaluation Criteria

• Impact Significance Criteria

• Impact Assessment

This section will describe the Environmental, Ecological and Social impacts associated with the pre-construction,

construction and operation, and decommissioning phase of the project and suggests specific mitigation measures to

avoid/reduce the identified impacts.

The exercise will cover impacts on areas of high biodiversity, protected areas or threatened species, disturbance of ecological systems and local communities through alteration of ambient air quality, noise levels, soil, surface and underground water quality resulting from Project activities; efficiency of energy use and opportunities of technology improvement; increased risk of natural resource degradation and alteration from significant use by the Project; acceptability of labour and working conditions during the construction and operation of the project, impacts on erosion and sediment discharge to surface waters etc.

The ESIA will also assess cumulative impacts with respect to construction, water usage, biodiversity etc., in detail and assess if the impacts are in line with the reference framework. The Impact assessment exercise will also include assessment of Climate Physical and Transition Risks, resulting from

climate change, which involve event-drive (acute) or longer-term shifts (chronic) in climate patterns.

Page 48: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

Electro Solaire Private Limited

AECOM

9. Environmental and Social Management Plan (ESMP)

• Introduction

• Organizational Structure (Environment, Social, Health and safety)

• Roles and responsibilities

• Monitoring and Audit

• Documentation and record keeping

• Training

Social Management Plans:

• Stakeholder Engagement Plan (inclusive of Monitoring mechanism)

• Grievance Redressal Mechanism (inclusive of Monitoring mechanism)

Environment Monitoring and Management Plan

• Waste Management Plan

This section will provide recommendation for environmental and social management plan aimed at minimizing the

negative environmental and social impacts of the project. Environmental and social monitoring requirements for

effective implementation of mitigating measures during development as well as operation of the project will also be

delineated along with requisite institutional arrangements for their implementation.

10. Conclusion and Categorization of the Project

- This section will conclude the outcomes of the study and categorise the proposed project based on IFC

Categorization. The conclusions and recommendations of the proposed ESIA study will be based on site inspections,

evaluation of impacts identified by specialists and the process of stakeholder consultation.

11. Gap Analysis against the Equator Principles

The section will present the gap analysis of the project against the equator principles and present an E&S Action Plan

to close the gaps identified.

Page 49: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

Electro Solaire Private Limited

AECOM

3.2 National and Regional Enforcement Authorities In India, Ministry of New and Renewable Energy (MNRE) is the nodal agency to manage the upcoming solar power projects and the environmental aspects are governed by Ministry of Environment, Forests and Climate Change (MoEF&CC), Central Pollution Control Board (CPCB), Central Electricity Authority (CEA) and Central Electricity Regulatory Commission (CERC). The social governance aspects at the micro level are addressed by institutions like panchayats and municipal bodies.

All the permissions and the approvals have to be taken from the concerned ministries, line departments and the local civic bodies for any upcoming project in India. The environmental and social governance approach in the country consists of:

1. Regulatory and implementing entities;

2. Legal framework including policies, acts and laws; and

3. Permitting system.

A brief description of the relevant enforcement agencies with respect to the institutional framework is described in Table 3-2 below:

Table 3-2 Enforcement agencies relevant to the project

S. N. Name of the Agency Description

1. MoEF&CC MoEF&CC is the apex body in India which has been formulated to plan, promote, co-

ordinate and oversee the implementation of India's environmental and forestry policies and

programmes. Various acts like The Environment (Protection) Act 1986, as amended in April

2003, The Air (Prevention and Control of Pollution) Act, 1981, amended in 1987 and The

Water (Prevention and Control of Pollution) Act, 1974, amended in 1988 have been

developed. It is the responsibility of the apex body to ensure the compliance under the acts

to maintain stipulated standards and environmental management through various

supporting rules promulgated under the Acts.

2. Central Pollution Control

Board (CPCB)

The CPCB was established in September 1974, for the purpose of implementing provisions

of the Water (Prevention and Control of Pollution) Act, 1974. The executive responsibilities

for the industrial pollution prevention and control are primarily executed by the CPCB at the

Central level, which is a statutory body, attached to the MoEF&CC. CPCB works towards

control of water, air and noise pollution, land degradation and hazardous substances and

waste management. CPCB will direct GPCB in case any violation is undertaken in

complying with the conditions of Hazardous Waste Authorization.

3. Gujarat Pollution Control

Board (GPCB)

GPCB is a statutory authority, constituted as per the provisions under the Water (Prevention

and Control of Pollution) Act, 1974, entrusted to implement environmental laws and rules

within the jurisdiction of the State of Gujarat, India. The Board ensures proper

implementation of the statutes, judicial and legislative pronouncements related to

environmental protection within the State. Solar Farms fall under ‘White Category’ as per Final Document on Revised Classification of Industrial Sectors Under Red, Orange, Green

and White Categories (February 29, 2016) issued by CPCB. There shall be no necessity of

obtaining the Consent to Operate for White category of industries under the Water

(Prevention and Control of Pollution) Act, 1974 and the Air (Prevention and control of

pollution) Act, 1981. Intimation to concerned SPCB / PCC shall suffice. White Category

Units do not require a Hazardous waste authorization from the Board, however, hazardous

and other wastes generated by such industries shall be handed over to the authorised

actual users, waste collectors or disposal facilities.

4. Petroleum and

Explosives Safety

Organisation (PESO)

The PESO is under the Department of Industrial Policy & Promotion, Ministry of Commerce

and Industry, Government of India. The Chief Controller of explosives is responsible to deal

with provisions of: The Explosive Act, 1884 and Rules, 2008, The Petroleum Act, 1934 and

the Rules 2002, The Static and Mobile pressure vessels (Unfired) Rules, 2016 and

amended 2018, and Manufacture, Storage and Import of Hazardous Chemical Rules, 1989

and amendment 2000.

Page 50: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

Electro Solaire Private Limited

AECOM

S. N. Name of the Agency Description

The site will store a small quantity of fuel during construction phase. However, in case fuel

storage exceeds the limit as stipulated in the Act, the project is required to obtain a license

from PESO.

5. Director Industrial

Safety and Health

(DISH)

The main objective of the DISH is to ensure safety, health, welfare and working conditions

of workers working in factories and in construction works by effectively enforcing the

provisions of the Factories Act, 1948 the Building & Other Construction Workers Act 1996

and other labour legislations. It is also to ensure the protection of rights of workers and to

redress their grievances.

Factory license is required as ‘factory’ means ‘any premises having ten or more workers

involved in a manufacturing process’. Factory License from the State Government or Chief Inspectorate of Factories, Gujarat is required to be obtained for the project. Project

proponent/ Construction contractor shall comply with all requirements of Gujarat Factories

Rules 1963 and participate in periodic inspection. It is also to be ensured that no child

labour is engaged during construction or operation phases of the project.

6. Ministry of New and

Renewable Energy

(MNRE)

The MNRE is the nodal ministry of Government of India for all matters related to new and

renewable energy. The broad aim is to develop and deploy new and renewable energy for

supplementing the energy requirements of the country as stated on its website. The role of

MNRE has been assuming importance in recent times with growing concerns of energy

security. Energy self-sufficiency was identified as the major driver for new and renewable

energy in the wake of the two oil shocks of 1970.

7. Gujarat Energy

Development Agency

(GEDA)

Gujarat Energy Development Agency (GEDA) is shouldering the responsibility of a state

nodal agency (SNA) for the Ministry of New and Renewable Energy Sources (MoNRE) and

the state designated agency (SDA) for Bureau of Energy Efficiency (BEE). It aims to provide

a platform to utilization of sustainable energy (renewable energy and energy efficient)

technologies on mass scale to make them techno-economically and socio-culturally viable

in the context of Gujarat’s energy scenario.

8. Central Electricity

Authority

CEA is a Statutory Body constituted under the erstwhile Electricity (Supply) Act, 1948,

thereafter replaced by the Electricity Act, 2003, where similar provisions exist, the office of

the CEA is an "Attached Office" of the Ministry of Power. The CEA is responsible for the

technical coordination and supervision of programmes and is also entrusted with a number

of statutory functions.

9. Central Electricity

Regulatory Commission

The Commission intends to promote competition, efficiency and economy in bulk power

markets, improve the quality of supply, promote investments and advise government on the

removal of institutional barriers to bridge the demand supply gap and thus foster the

interests of consumers.

10. Central Ground Water

Authority (CGWA)

CGWA was constituted under Sub-section (3) of Section 3 of the Environment (Protection)

Act, 1986 for the purposes of regulation and control of ground water development and

management. As per CGWA's guidelines effective from 01 June 2019, NOC is required for

ground water withdrawal for all infrastructure projects drawing/proposing to draw ground

water through an energised means. (with effect from 16.11.2015).

For the proposed project (falling in “Saline“ category) NOC is required for ground water,

abstraction, NOC may be provided that the fresh water resources are not affected through

such abstraction. No disposal of brine/contaminated ground water shall be allowed in the

premise. In case there are any overlain/underlain by fresh water aquifers, NOC will only be

granted after submission of a hydrogeological study, undertaken by a NABET accredited

consultant.

11. Gram Panchayat Gram Sabha or the Panchayats are the local bodies which have been defined by the 73rd

Constitutional Amendment Act, 1992. Panchayats have to be consulted before acquiring

land in the Scheduled Areas for development projects and before re-settling or rehabilitating

persons affected by such projects in the Scheduled Areas. The responsibilities that have

been entrusted upon Panchayats comprises of the preparation of plans for economic

development and social justice and the implementation of such schemes for economic

development and social justice, as may be assigned to them.

12. Office of the Deputy

Conservator of Forest

If the project site is a part of the Protected Area or Eco sensitive Zone of the Wild Ass

Sanctuary, which lies in close proximity to the project site, then an application for approval

Page 51: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

Electro Solaire Private Limited

AECOM

S. N. Name of the Agency Description

(DCF), Wild Ass

Sanctuary, Dhrangadhra

from the National Board for Wildlife (NBWL) will have to be submitted to the DCF, Wild Ass

Sanctuary, Dhrangadhra

13. Office of the Range

Forest Officer, Tharad

If any project infrastructure, activities or personnel are likely to occur in any area falling in

the jurisdiction of the Tharad forest range, application for approval will have to be submitted

to the Range Forest Officer, Tharad.

3.3 Applicable Environment and Social Laws and Regulations

Table 3-3 summarizes the key regulations that are relevant to the project across its lifecycle. This table should be used to update/develop a comprehensive legal register for the Project.

Page 52: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

Electro Solaire Private Limited

AECOM

Table 3-3: Applicable Environment and Social Laws and Regulations

S. No.

Aspect Relevance Applicable Legislation Agency Responsible

Applicable Permits and Requirements

EHS Laws, Acts, Rules and Regulations

1. Environmental Protection

• Construction activities will generate air, water and noise emissions; and

• Scattering of debris and construction material can contaminate the soil, water and surroundings.

• The Environment (Protection) Act 1986, as amended in April 2003; and

• EPA Rules 1986, as amended in 2002.

GPCB As per Section 7 of Environment Protection Act, 1986 and Rule 3 of the Environment Protection Rule, 1986, no person carrying on any industry, operation and process shall discharge or emit any environmental pollutant in excess of prescribed standards. Compliance under the rules to maintain stipulated standards and environmental management through various supporting rules promulgated under the Act.

ESPL and the EPC contractor are required to ensure that Project implementation adheres to the various clauses laid down in the Act

2. Prevention and Control of Water Pollution

Waste water generation during construction and operation of the Plant

The Water (Prevention and Control of Pollution) Act, 1974, amended in 1988

GPCB As per the section 24 of the Water (Prevention and Control of Pollution) Act, 1974, amended in 1988 no person shall knowingly cause or permit any poisonous, noxious or polluting matter into any stream or well or sewer or on land.

3. Prevention and Control of Air Pollution

Movement of vehicles, operation of diesel generators for power at campsite or other construction activities.

The Air (Prevention and Control of Pollution) Act, 1981, amended in 1987.

GPCB As per section 22 of The Air (Prevention and Control of Pollution) Act, 1981, amended in 1987, no person operating any industrial plant, in any air pollution control area shall discharge or cause or permit to be discharged the emission of any air pollutant in excess of the standards laid down by the GPCB.

A solar power plant is clean option for power generation in comparison to non-renewable fossil fuels. Ministry of Environment, Forest and Climate Change (MoEF&CC) in its Office Memorandum No. J-11013/41/2006-IA-II (I) dated 13th May 2011 stated that the solar power projects are not covered under the ambit of EIA Notification, 2006 and therefore does not require prior environmental clearance. In addition to this, CPCB issued notification regarding harmonization of classification of industrial sectors under Red/Orange/Green/White categories which states that ‘solar renewable power plants of all capacities’ is classified as a “White Industry” (Part-A, Serial Number 35) and does not require Consent to Establish and Consent to Operate. Only intimation to the concerned regional officer of State Pollution Control Board (SPCB) shall suffice 4

4 As per latest directions of Central Pollution Control Board, dated March 2016, Final report on revised categorization of industrial sectors under Red/ Orange/ Green/ White, solar power projects have been classified under White category of industries. As per the CPCB’s direction to SPCB/PPCs, “there shall be no necessity of obtaining Consent to Operate for White Category of industries and intimation to the concerned SPCB/PPC shall suffice.” And as per GPCB (https://www.gpcb.gov.in/Portal/News/129_1_GREEN_CATEGORY_EXEMPTED_FROM_CTE_CCA.pdf) “white category industries shall not be included in the Consent Mechanism. As per CPCB order dated 18th January 2017, the White category includes Solar Power Plants of all capacities. (http://kredlinfo.in/scrollfiles/exemption%20from%20pollution%20board.pdf)

Page 53: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

Electro Solaire Private Limited

AECOM

S. No.

Aspect Relevance Applicable Legislation Agency Responsible

Applicable Permits and Requirements

4. NOC And Consent to Establish and Operate for Batching Plant

Batching plant operation would lead to emission of fugitives. It also envisages waste water generation which could lead to contamination of land and water resources. In addition, there would be generation of noise disturbance to the neighbouring villages.

The Water (Prevention and Control of Pollution) Act, 1974;

The Air (Prevention and Control of Pollution) Act, 1981 &

The Noise Pollution (Regulation and Control) Rules, 2000 and subsequent amendments.

GPCB Applicable.

Needs to be obtained before the construction work is commenced.

5. License under Factories Act, 1948

Factory license is required as the project is generating, transforming or transmitting power.

Chapter I of The Factories Act, 1948 Directorate, Industrial Safety and Health, Government of Gujarat

As per the section 6 of The Factories Act, 194, ESPL would have to obtain registration of the power plant from the State Government or Chief Inspectorate of Factories, Gujarat if 10 or more workers are engaged, triggering the applicability of the Factories Act.

6. Noise Emissions Noise generated from operation of construction machinery

• The Noise (Regulation & Control) Rules, 2000 as amended in October 2002; and

• As per the Environment (Protection) Act (EPA) 1986 the ambient noise levels are to be maintained as stipulated by CPCB for different categories of areas like, commercial, residential and silence zones etc.

GPCB

As per the Rules 3 and 4 of the Noise (Regulation & Control) Rules, 2000 as amended in October 2002, noise emissions in the project area should not exceed standards specified in the Schedule.

7. Hazardous Wastes Management

• The proposed project will generate waste oil from diesel generator during construction phase and used transformer oil during operation phase;

• Solvents and chemicals used or cleaning etc.; and Management of damaged solar modules.

Hazardous and Other Wastes (Management and Trans boundary Movement) Rules, 2016 as amended in 2019

GPCB As per the Hazardous Waste and Other Wastes (Management and Trans boundary Movement) Rules 2016 and its amendment in 2019 the Rule 6 after sub-rule (1) states that: 5 An occupier shall not be required obtain an authorisation under this rule, from the State Pollution Control Board, in case the consent to establish or consent to operate, is not required from the State Pollution Control Board or Pollution Control Committee under the Water (Prevention and Control of Pollution) Act, 1974 (25 of 1974) and Air (Prevention and Control of Pollution) Act, 1981 (21 of 1981); Provided that the hazardous and other wastes generated by the occupier shall be given to the actual user, waste collector or operator of the disposal facility, in accordance with the Central Pollution Control Board guidelines. However, as per the Rules 4, 6, 8, 17, 18, 19 and 20 of the Hazardous and Other Wastes (Management and Transboundary Movement) rules following compliances are to be ensured by ESPL:

5 https://kspcb.gov.in/Hazardous%20and%20Other%20Wastes%20Amendment%20Rules,%202019_25-03-2019.pdf

Page 54: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

Electro Solaire Private Limited

AECOM

S. No.

Aspect Relevance Applicable Legislation Agency Responsible

Applicable Permits and Requirements

• Authorization for collection, reception, storage, transportation and disposal of hazardous wastes;

• Liability of the occupier, transporter and operator of a facility: The occupier, transporter and operator of a facility shall be liable for damages caused to the environment resulting due to improper handling and disposal of hazardous waste listed in schedules to the Rules; and

The occupier and operator of a facility shall also be liable to reinstate or restore damaged or destroyed elements of the environment.

8. Construction and Demolition Waste

Collection, segregation, storage and disposal of construction and demolition (C&D) waste at construction phase of the project.

Construction and Demolition Waste Management Rules, 2016

Gram Panchayat As per the Construction and Demolition Waste Management Rules, 2016, if waste more than 20 tons or more in one day or 300 tons per project in a month is generated then ESPL shall submit waste management plan and get appropriate approvals from the local authority before starting construction or demolition work. ESPL should also ensure responsible collection, store and disposal of the C&D waste.

9. Electricity Distribution License

Private sector projects to obtain distribution Licenses from the State Electricity Regulation Committee and to have open access to the transmission lines

• The Electricity Act 2003; and

• The, Central Electricity Authority (Measures relating to Safety and Electricity Supply) Regulations, 2010

Gujarat Electricity Regulatory Commission

As per section 14 of The Electricity Act, 2003, ESPL shall obtain license under the act.

Under rules 12 and 7, ESPL and the Contractors to ensure preventive measures for health and safety of humans and plant.

10. Storage of Petroleum products

There will be storage of Diesel at site for operation of generators during construction phase.

• The Petroleum Act 1934, as amended in August 1976

• The Petroleum Rules 1976, as amended in March 2002.

PESO (Chief Controller of Explosives)

As per Section 3 of The Petroleum Act 1934 and Rule 116 of The Petroleum Rules 1976, ESPL will be required to obtain a license from PESO, if the quantity of the fuel stored exceeds two thousand and five hundred litres and/ or is stored in a receptacle exceeding one thousand litres in capacity.

11. Surface Transportation

Movement of construction vehicles and other vehicles for transportation of workers

• The Motor Vehicles Act 1988, as amended by Motor Vehicles (Amendment) Act 2000, dated 14th August 2000.

• The Central Motor Vehicles Rules 1989, as amended through 20th October 2004 by the Central Motor Vehicles (Fourth Amendment) Rules 2004.

State Transport Authority

ESPL to ensure compliance of the Section 39, Motor Vehicle Act, 1988 as amended in 2017 and Rule 47, Motor Vehicle Rule, 1989.

Biodiversity related laws

Page 55: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

Electro Solaire Private Limited

AECOM

S. No.

Aspect Relevance Applicable Legislation Agency Responsible

Applicable Permits and Requirements

12. Forest Protection Presence of legally protected forest areas in proximity to the project site

The Indian Forest Act, 1927 Gujarat State Forest Department

Approval of the Forest Department is required if project-related infrastructure, activities or personnel occur within a legally protected forest area.

13. Wildlife Conservation

Presence of wildlife habitats, including those of Schedule I species, in and around the project site

The Wildlife (Protection) Act, 1972 National Board for Wildlife

Approval of the National Board for Wildlife is required if project-related infrastructure, activities or personnel occur within national parks and sanctuaries.

14. Forest Conservation

Presence of legally protected forest areas in proximity to the project site

The Forest (Conservation) Act, 1980 Gujarat State Forest Department

Approval of the Forest Department is required if the project uses legally protected forest land for any non-forest purpose.

Social and labour-related Laws, Regulations and Acts

15. Labour Engagement of workers for construction and operation of the plant

The Factories Act, 1948 and Gujarat Factories Rules, 1963

Department of Labour, Government of Gujarat

ESPL / EPC Contractor shall comply with all requirements of Factories Rules and participate in periodic inspection.

16. Contract Workers Engagement of contract workers The Contract Labour (Regulation and Abolition) Act, 1970 as amended in 2017

Department of Labour, Government of Gujarat

As per Section 12 of the Contract Labour (Regulation and Abolition) Act, 1970 a contractor executing any contract work by engaging 20 or more contract labourers has to obtain a licence under the Act.

17. Child Labour Engagement of Child Labour at site The Child Labour (Prohibition and Regulation) Act, 1986

Department of Labour, Government of Gujarat

Section 3 under the Child Labour (Prohibition and Regulation) Act, 1986 (CLA, 1986) including amendment in 2016. No child below the age of 14 years shall be employed in any establishment mentioned in Schedule Part A and Part B of the CLA, 1986.

18. Bonded Labour Engagement of Bonded Labour at site Bonded Labour (Abolition) Act 1976 Department of Labour, Government of Gujarat

Rule 4 of the Bonded Labour System (Abolition) Act, 1976 specifies "After the commencement of this Act, no person shall-

• make any advance under, or in pursuance of, the bonded labour system, or compel any person to render any bonded labour or other form of forced labour."

19. Payment of Wages

Provision of wages to labour engaged at the site

Minimum Wages Act, 1948 Department of Labour, Government of Gujarat

Section 12 of the Minimum Wages Act, 1948: The employer shall pay to every employee engaged in a scheduled employment under him wages at a rate not less than the minimum rate of wages fixed by the appropriate Government Authority for that class of employees in that employment without any deductions except as may be authorized within such time and subject to such conditions as may be prescribed.

Every employer shall be responsible for the payment to persons employed by him of all wages required to be paid under this Act.

20. Payment of Wages.

Equal wages to male and female workers at site

Equal Remuneration Act 1976 Department of Labour,

It is the duty of an employer to pay equal remuneration to men and women workers for same work or work of a similar nature.

Page 56: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

Electro Solaire Private Limited

AECOM

S. No.

Aspect Relevance Applicable Legislation Agency Responsible

Applicable Permits and Requirements

Government of Gujarat

21. Payment of Wages

Engagement of Labour at site Workmen's Compensation Act, 1923 Department of Labour, Government of Gujarat

Requires if personal injury is caused to a workman by accident arising out of and in the course of his employment, his employer shall be liable to pay compensation in accordance with the provisions of this Act.

22. Women at Workplace

Engagement of Female Labour at site Maternity Benefit Act, 1961 Department of Labour, Government of Gujarat

Section 4 of the Maternity Benefit Act, 1961 including amendment as in Maternity Benefit (Amendment) Act, 2017: -

• "No employer shall knowingly employ a woman in any establishment during the six weeks immediately following the day of her delivery or her miscarriage;

• No woman shall work in any establishment during the six weeks immediately following the day of her delivery or her miscarriage; and

• Without prejudice to the provisions of section 6, no pregnant woman shall, on a request being made by her in this behalf, be required by her employer to do during the period specified in sub- section (4) any work which is of an arduous nature or which involves long hours of standing, or which in any way is likely to interfere with her pregnancy or the normal development of the foetus, or is likely to cause her miscarriage or otherwise to adversely affect her health."

Section 5 of the Maternity Benefit Act, 1961 including as amended in 2017. "As per the amendment in 2017,

• Subject to the provisions of this Act, every woman shall be entitled to, and her employer shall be liable for, the payment of maternity benefit at the rate of the average daily wage for the period of her actual absence, that is to say, the period immediately preceding the day of her delivery, the actual day of her delivery and any period immediately following that day;

• No woman shall be entitled to maternity benefit unless she has actually worked in an establishment of the employer from whom she claims maternity benefit, for a period of not less than eighty days in the twelve months immediately preceding the date of her expected delivery;

• The maximum period for which any woman shall be entitled to maternity benefit shall be twenty-six weeks of which not more than eight weeks shall precede the date of her expected delivery;

• A woman who legally adopts a child below the age of three months or a commissioning mother shall be entitled to maternity benefit for a period of twelve weeks from the date the child is handed over to

Page 57: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

Electro Solaire Private Limited

AECOM

S. No.

Aspect Relevance Applicable Legislation Agency Responsible

Applicable Permits and Requirements

the adopting mother or the commissioning mother, as the case maybe; and

In case where the nature of work assigned to a woman is of such nature that she may work from home, the employer may allow her to do so after availing of the maternity benefit for such periods and on such conditions as the employer and the woman may mutually agree."

23. Contractor Labour License

Contractors or third parties to be involved in the construction works for the proposed project, if required, will also be engaged only subject to availability of valid registration.

Building and Other Construction Workers (Regulation of Employment and Conditions of Service) Act, 1996 and Contract Labour (Regulation and Abolition) Act, 1970.

Department of Labour, Government of Gujarat

Section 7 of the Act mandates the registration of establishments. ESPL

should ensure that contractor/ sub-contractors have a valid registration

under the Building and Other Construction Works Act and Contract

Labour (Regulation and Abolition) Act, 1970.

24. Contract Labour Principal Employer registration for engaging contract labour through third party is required.

The Contract Labour (Regulation and Abolition) Act, 1970

Department of Labour, Government of Gujarat

Section 7 of the Act mandates the Principal Employer registration for engaging contract labour through third party.

25. Migrant Workmen Principal Employer registration for engaging migrant labour is required for direct/indirect labour.

The Inter-State Migrant Workmen (Regulation of Employment and conditions of service) Act, 1979

Department of Labour, Government of Gujarat

Section 4 of the Act mandates that the Principal Employer registration should be obtained for engaging migrant labour through third party.

26. Working Conditions

Working conditions of contracted Labour working at the site

Contract Labour (Regulations and Abolition) Act, 1970

Department of Labour, Government of Gujarat

Section 16,17,18,19,20 and 21 of the said Act mandates the provision of the principal employer to ensure that all the contracted workers are provided with condition of services, rate of wages, holidays, hours of work as stipulated in the act and rules.

Page 58: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

Electro Solaire Private Limited

AECOM

3.4 Policy Framework in India Policies with respect to the renewable energy in India and Gujarat, focusing on the solar power, as released by the Government of India and Government of Gujarat from time to time and applicable to the project are discussed briefly in Table 3-4:

Table 3-4 National and State Level Policies Applicable to the Project

S. N. Name of the Policy Description

1. National Electricity

Policy 2005 The National Electricity Policy 2005 states that environmental concerns would be suitably addressed through appropriate advance action by way of comprehensive Environmental Impact Assessment and implementation of Environment Action Plan (EAP). As per the policy, adequate safeguards for environmental protection with suitable mechanism for monitoring of implementation of Environmental Action Plan and R&R Schemes should be put in place. Open access in transmission has been introduced to promote competition amongst the generating companies who can now sell to different distribution licensees across the country. This should lead to availability of cheaper power.

2. National Solar Mission

(JNNSM) The objective of the Jawaharlal Nehru National Solar Mission (JNNSM) under the brand 'Solar India' is to establish India as a global leader in solar energy, by creating the policy conditions for its diffusion across the country as quickly as possible. The Mission has set a target of 20,000 MW and stipulates implementation and achievement of the target in 3 phases (first phase up to 2012-13, second phase from 2013 to 2017 and the third phase from 2017 to 2022) for various components, including grid connected solar power.

The successful implementation of the JNNSM requires the identification of resources to overcome the financial, investment, technology, institutional and other related barriers which confront solar power development in India. The penetration of solar power, therefore, requires substantial support. The policy framework of the Mission will facilitate the process of achieving grid parity by 2022.

3. National Environmental

Policy, 2006 Government of India released the National Environment Policy in 2006. The policy aims at mainstreaming environmental concerns into all developmental activities. It emphasises conservation of resources, and points that the best way to aid conservation is to ensure that people dependent on resources obtain better livelihoods from conservation, than from degradation of the resources.

4. Gujarat Solar Power

Policy 2015 The Government of Gujarat vide G.R. No. SLR-11-2015-2442-B has formulated Gujarat Solar Power Policy 2015 to promote the generation of power from solar energy. Objectives of the policy are: 1) To promote generation of green and clean power in the State using solar energy; 2) To create conditions conducive to the participation of private and public sector as well as PPP in the promotion and setting up of up Solar Energy based power projects in the State; 3) Productive use of wastelands / non – agricultural lands thereby leading to socioeconomic transformation and a reduction in regional disparities in development; 4) Employment generation and skill up gradation of the youth; 5) To put in place an appropriate investment climate that would leverage the benefits of Clean Development Mechanism (CDM) and result in lower Green House Gas (GHG) emissions; 6) Co-creation of Solar Centers of Excellence and pools of technical professionals which would work towards applied research and commercialization of indigenous and cutting edge technologies involving applications of solar energy generation and appliances; 7) Spreading of environmental consciousness among all citizens of the State especially the youth and school going children; and 8) Decentralization and diversification of the energy portfolio and to increase the share of renewable solar power.

3.5 Applicable International Standards and Guidelines

3.5.1 FMO Social Sustainability Policy

FMO's Social Sustainability Policy intends to protect people and the environment impacted by its own operations and its investments and to help clients manage their environmental and social impact and improve their corporate governance. FMO requires, that all clients comply with applicable environmental, social and human rights laws in their home and host countries. In addition, with respect to the management of environmental and social impact, the primary standards that guide FMO’s relationship with clients are the IFC Environmental and Social Performance Standards and the associated World Bank Group Environmental Health and Safety Guidelines.

Page 59: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

Electro Solaire Private Limited

AECOM

3.5.2 IFC Performance Standards

The performance standards stipulate that any proposed project shall meet the following requirements throughout the life of an investment by IFC or other relevant financial institution: -

• Performance Standard 1: Assessment and Management of Environmental and Social Risks and Impacts;

• Performance Standard 2: Labour and Working Conditions;

• Performance Standard 3: Resource Efficiency and Pollution Prevention;

• Performance Standard 4: Community Health, Safety, and Security;

• Performance Standard 5: Land Acquisition and Involuntary Resettlement;

• Performance Standard 6: Biodiversity Conservation and Sustainable Management of Living Natural Resources; s

• Performance Standard 7: Indigenous Peoples; and

• Performance Standard 8: Cultural Heritage

These Performance Standards and guidelines provide ways and means to identify impacts and affected stakeholders and lay down processes for management and mitigation of adverse impacts. The applicability of the Performance Standards is discussed in Table 3-5.

Page 60: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

Electro Solaire Private Limited

AECOM

Table 3-5 Applicability of IFC Performance Standards

S. No.

Performance Standard

Description and Applicability

1. PS1 – Assessment and Management of Environmental and Social Risks and Impacts

APPLICABLE

PS 1 establishes the importance of:

• Integrated assessment to identify the environmental and social impacts, risks, and opportunities of projects;

• Effective community engagement through disclosure of project-related information and consultation with local communities on matters that directly affect them; and

• The project proponent’s management of environmental and social performance throughout the life of the project.

The PS 1 is applicable to projects with environment and/or social risks and/or impacts. The proposed project is a solar power project and will have environmental and social impacts such as stress on existing water resources, construction activities, direct or indirect impact on communities, etc.

2. PS2 – Labour and Working Conditions

APPLICABLE

PS-2 recognizes that the pursuit of economic growth through employment creation and

income generation should be accompanied by protection of the fundamental rights of

workers.

3. PS3 - Resource Efficiency and Pollution Prevention

APPLICABLE

PS3 recognizes that increased economic activity and urbanization often generate increased levels of pollution to air, water, and land, and consume finite resources in a manner that may threaten people and the environment at the local, regional, and global levels.

The objectives of PS 3 are:

• To avoid or minimize adverse impacts on human health and the environment by avoiding or minimizing pollution from project activities.

• To promote more sustainable use of resources, including energy and water.

• To reduce project-related GHG emissions.

The proposed project is a clean energy project and will not have major pollution sources associated with it. The construction works for the development of project will entail generation of wastes like air emissions, wastewater, used oil from DG sets and construction debris. The operation phase will result in generation of minor quantities of waste such as used transformer oil, broken and defunct solar panels and waste water from cleaning of solar panels.

4. PS4 – Community Health, Safety and Security

APPLICABLE

PS 4 recognizes that project activities, equipment, and infrastructure can increase community exposure to risks and impacts. Its main stress is to ensure that the safeguarding of personnel and property is carried out in accordance with relevant human rights principles and in a manner that avoids or minimizes risks to the Affected Communities.

Objectives of PS 4 thus are:

• To anticipate and avoid any adverse impacts on the health and safety of the Affected Community during the project life from both routine and non-routine circumstances.

• To ensure that the safeguarding of personnel and property is carried out in accordance with relevant human rights principles and in a manner that avoids or minimizes risks to the Affected Communities.

The proposed project will involve transportation of construction material and movement of construction machinery which may pose safety risks to the affected communities.

5. PS5 – Land Acquisition and Involuntary Resettlement

NOT APPLICABLE

PS 5 recognizes that project-related land acquisition and restrictions on land use can have adverse impacts on communities and persons that use this land. Its main aim is to anticipate and avoid, or where avoidance is not possible, minimize adverse social and economic impacts from land acquisition or restrictions on land use by providing compensation for loss of assets at replacement cost and ensuring that resettlement activities are implemented with appropriate disclosure of Information, consultation, and the informed participation of those affected.

Page 61: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

Electro Solaire Private Limited

AECOM

S. No.

Performance Standard

Description and Applicability

The PS is not applicable for the project as land for the solar park in question has neither been acquired by the government nor does it involve any privately-owned land. Stakeholder consultations at site also confirmed that there were no economic/ livelihood activities on the concerned land prior to its allotment to players for setting up their solar plant. This is primarily due to the saline and barren nature of the concerned land parcel (comprising the Site) because of which the land was not suitable for any agriculture activities.

6. PS6 – Biodiversity Conservation and Sustainable Management of Living Natural Resources

APPLICABLE

PS 6 recognizes that protecting and conserving biodiversity, maintaining ecosystem services, and sustainably managing living natural resources are fundamental to sustainable development.

The objectives of PS 6 are:

▪ To protect and conserve biodiversity

▪ To maintain the benefits from ecosystem services

▪ To promote the sustainable management of living natural resources through the adoption of practices that integrate conservation needs and development priorities.

The Project Site, as well as, the area of influence of the project contain natural and near-natural habitats, besides modified habitats, as also a potential critical habitat. The Project Site and the area of influence of the project provide important ecosystem services to the local community, including priority provisioning services in the form of water resources and pasture for livestock. The proposed project infrastructure and activities, such as removal of vegetation, levelling of land, laying of access roads, vehicular movement, artificial illumination and installation of solar panelling and power transmission cables, are expected to cause loss or degradation of habitats and ecosystem services, as well as, fragmentation of habitats, and possibly, promote further spread of already introduced invasive alien species. There is no designated area situated within the Project Site, but there are 3 designated areas within close proximity to the area of influence of the Project.

Therefore, PS 6 is applicable to the Project.

7. PS7 – Indigenous People

NOT APPLICABLE

Performance Standard 7 recognizes that Indigenous Peoples, as social groups with identities that are distinct from mainstream groups in national societies, are often among the most marginalized and vulnerable segments of the population. In many cases, their economic, social, and legal status limits their capacity to defend their rights to, and interests in, lands and natural and cultural resources, and may restrict their ability to participate in and benefit from development.

The PS 7 is not applicable to the project as;

• The project is not located in a schedule V area;

• There is no presence of Scheduled Tribes in the block and district in which the project is located;

• No tribal land has been procured for the project;

• No livelihood dependence on the land has been reported of tribal or non-tribal; and

• With regards to ethnic composition, only 3 (0.17 %) out of the total population of 1,732 in Radhanesda village are Scheduled Castes (SC), as per the Census of India Report 2011. No presence of Scheduled Tribes (ST) is recorded in the village.

8. PS8 – Cultural Heritage NOT APPLICABLE

For the purposes of this Performance Standard, cultural heritage refers to tangible forms of cultural heritage, such as tangible moveable or immovable objects, property, sites, structures, or groups of structures, having archaeological (prehistoric), paleontological, historical, cultural, artistic, and religious values.

The PS is not applicable to the project as;

• The land on which the project is being setup does not contain any structures bearing cultural, historical, religious or spiritual significance; and

No sites bearing cultural, historical, religious or spiritual significance has been impacted by the project

3.5.3 IFC EHS Guidelines

IFC has released the following environmental, health and safety guidelines on 30th April 2007:

• Environmental, Health, and Safety General Guidelines

Page 62: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

Electro Solaire Private Limited

AECOM

• Environmental, Health, and Safety Guidelines for Electric Power Transmission and Distribution issued on 30th April 2007.

The key requirements stated in the EHS guidelines have been discussed in below.

ENVIRONMENTAL ATTRIBUTES

• Air Emissions and Ambient Air Quality,

• Energy Conservation,

• Wastewater and Water Quality,

• Water Conservation,

• Hazardous Materials Management,

• Waste Management,

• Noise and

• Contaminated Land

OCCUPATIONAL HEALTH AND SAFETY

• General Facility Design and Operation,

• Communication and Training,

• Physical/Chemical/Biological Hazards,

• Personal Protective Equipment (PPE) and

• Monitoring.

COMMUNITY HEALTH AND SAFETY

• Water Quality and Availability,

• Structural Safety of Project Infrastructure,

• Life and Fire Safety (L&FS),

• Traffic Safety,

• Transport of Hazardous Materials,

• Disease Prevention and

• Emergency Preparedness and Response.

CONSTRUCTION AND DECOMMISSIONING

• Environment Baseline environmental,

• Occupational Health and Safety and

• Community Health and Safety.

3.5.4 Equator Principles, 2020

The Equator Principles Financial Institutions (EPFIs), have adopted the Equator Principles in order to ensure that the Projects financed by them are developed in a manner that is socially responsible and reflects sound environmental management practices. Equator Principles are a set of principles aiming towards promotion of responsible environmental stewardship and socially responsible development, including fulfilling responsibility to respect human rights by undertaking due diligence. The Principles are intended to serve as a common baseline and framework, globally for all sectors. All the Principles were noted applicable to the project. Additionally, a gap analysis for the project has been taken against the Equator Principles to assess the compliance.

Principle 1: Review and Categorisation

Page 63: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

Electro Solaire Private Limited

AECOM

Using categorisation, the EPFI’s environmental and social due diligence is commensurate with the nature, scale and stage of the Project, and with the level of environmental and social risks and impacts. The categories are:

Category A – Projects with potential significant adverse environmental and social risks and/or impacts those are diverse, irreversible or unprecedented;

Category B – Projects with potential limited adverse environmental and social risks and/or impacts that are few in number, generally site-specific, largely reversible and readily addressed through mitigation measures; and

Category C – Projects with minimal or no adverse environmental and social risks and/or impacts.

Principle 2: Environmental and Social Assessment

For all Category A and Category B Projects, the EPFI will require the client to conduct an Assessment process to address, the relevant environmental impacts of the proposed Project. The Assessment documentation should propose measures to minimise, mitigate, and offset adverse impacts in a manner relevant and appropriate to the nature and scale of the proposed Project. The client is expected to include assessments of potential adverse Human Rights impacts and climate change risks as part of the ESIA or other Assessment, with these included in the Assessment Documentation. The client should refer to the UNGPs when assessing Human Rights risks and impacts, and the Climate Change Risk Assessment should be aligned with Climate Physical Risk and Climate Transition Risk categories of the TCFD.

Principle 3: Applicable Environmental and Social Standards

The Assessment process should, in the first instance, address compliance with relevant host country laws, regulations and permits that pertain to environmental and social issues. India being a Non-Designated Country, the Assessment process evaluates compliance with the then applicable IFC Performance Standards on Environmental and Social Sustainability (Performance Standards) and the World Bank Group Environmental, Health and Safety Guidelines (EHS Guidelines).

Principle 4: Environmental and Social Management System and Equator Principles Action Plan

For all Category A and Category B Projects, the EPFI will require the client to develop or maintain an Environmental and Social Management System (ESMS). Further, an Environmental and Social Management Plan (ESMP) will be prepared by the client to address issues raised in the Assessment process and incorporate actions required to comply with the applicable standards.

Principle 5: Stakeholder Engagement

The EPFI will require the client to demonstrate effective Stakeholder Engagement as an on-going process in a structured and culturally appropriate manner for all Category A and Category B Projects. The client will conduct an Informed Consultation and Participation process. The consultation process will be tailored to the risks and impacts of the Project; the Project’s phase of development; the language preferences of the Affected Communities; their decision-making processes; and the needs of disadvantaged and vulnerable groups.

To facilitate Stakeholder Engagement, the client will, commensurate to the Project’s risks and impacts, make the appropriate Assessment Documentation readily available to the Affected Communities, and where relevant Other Stakeholders, in the local language and in a culturally appropriate manner.

Principle 6: Grievance Mechanism

For all Category A Projects, and as appropriate Category B projects the EPFI will require the client, as part of the ESMS, to establish a grievance mechanism designed to receive and facilitate resolution of concerns and grievances about the Project’s environmental and social performance.

Principle 7: Independent Review

For all Category A Projects and as appropriate Category B projects, an Independent Environmental and Social Consultant, not directly associated with the client, will carry out an Independent Review of the Assessment Documentation including the ESMPs, the ESMS, and the Stakeholder Engagement process documentation in order to assist the EPFI's due diligence, and assess Equator Principles compliance.

Principle 8: Covenants

Page 64: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

Electro Solaire Private Limited

AECOM

For all Projects, the client will covenant in the financing documentation to comply with all relevant host country environmental and social laws, regulations and permits in all material respects.

Principle 9: Independent Monitoring and Reporting

For Projects where an Independent Review is required under Principle 7, the EPFI will require the appointment of an Independent Environmental and Social Consultant after Financial Close or require that the client retain qualified and experienced external experts to verify its monitoring information which would be shared with the EPFI.

Principle 10: Reporting and Transparency

For all Category A Projects and as appropriate Category B projects:

• The client will ensure that, at a minimum, a summary of the ESIA is accessible and available online.

• The client will publicly report GHG emission levels during the operational phase for Projects emitting over 100,000 tonnes of CO2 equivalent annually.

• The EPFI will encourage the client to share commercially non-sensitive Project-specific biodiversity data with the Global Biodiversity Information Facility13 (GBIF) and relevant national and global data repositories, using formats and conditions to enable such data to be accessed and re-used in future decisions and research applications.

3.5.5 Applicability of ADB SPS and IFC PS

An overview of ADB’s Safeguard Policy Statement (SPS) and their applicability to the project is provided in the table below.

Table 3-6: Broad Overview ADB SPS and their applicability to the Project

S. No. ADB’s Policy/SPS Overview Applicability to the Project

1. SPS 1: Environment The Environmental safeguards are triggered if a

project is likely to have potential environmental

risks and impacts. The projects are initially

screened to determine the level of assessment

that is required. ADB categorises the projects into

three project categories based on the severity,

sensitivity and the magnitude of its potential

environmental impacts: Category A (if the project

likely to have significant adverse environmental

impacts that are irreversible, diverse, or

unprecedented. An environmental impact

assessment (EIA), including an environmental

management plan (EMP), is required); Category

B (if the project likely to have potential impacts

are less adverse than category A and minor

impacts expected can be mitigated. An initial

environmental examination (IEE), including an

EMP, is required); and Category C (if the projects

likely to have minimal or no adverse

environmental impacts. An EIA or IEE is not

required).

Applicable

This SPS is applicable to

environmental aspects like but not

limited to air emissions, water and

wastewater management, noise

emissions, chemical management,

hazardous material management.

2. SPS 2: Involuntary

Resettlement

The policy is designed to avoid the risk of

impoverishment among those displaced as a

direct result of ADB investment. The policy

recognizes that restoring the incomes and living

standards of the affected people is complex, and

requires a development strategy that

encompasses compensation, resettlement and

Not Applicable.

The entire land on which the

project is located is situated has

been leased from the GPCL.

Procurement of the said land was

done by the GPCL from the

government. During the

Page 65: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

Electro Solaire Private Limited

AECOM

rehabilitation packages to improve, or at least

restore, their social and economic base.

The ADB’s Policy on Involuntary Resettlement

stipulates three important elements in involuntary

resettlement: (i) compensation for lost assets and

loss of livelihood and income, (ii) assistance in

relocation including provision of relocation sites

with appropriate facilities and services, and (iii)

assistance with rehabilitation to achieve at least

the same level of well-being with the project as

before.

consultations, it was reported that

no habitations were present on the

land and the land has been

historically owned only by

government. Thus, it can be

concluded that project specific

land procurement has not resulted

in any involuntary resettlements.

3. SPS 3: Indigenous

People

The Policy on Indigenous Peoples is triggered if a

project directly or indirectly affects the dignity,

human rights, livelihood systems, or culture of

indigenous peoples or affects the territories or

natural or cultural resources that indigenous

peoples own, use, occupy, or claim as an

ancestral domain or asset. The policy on states

that the borrower/ client will ensure (i) that

affected indigenous peoples receive culturally

appropriate social and economic benefits; and (ii)

that when potential adverse impacts on

indigenous peoples are identified, these will be

avoided to the maximum extent possible. Where

this avoidance is not feasible, based on

meaningful consultation with indigenous

communities, the Indigenous Peoples Plan (IPP)

will be prepared which outlines measures to

minimize, mitigate, and compensate for the

adverse impacts.

Not applicable

The region where the project is

located does not fall under the

Schedule V area and does not

have any significant presence of

tribal communities. The same was

confirmed through community

consultations. Based on the above

inferences, it can be presumed

that no indigenous people would

have been affected due to project

activities.

4. Policy on Gender and

Development

ADB’s Policy on Gender and Development (2006) is the guiding framework for gender and

development activities. The policy adopts gender

mainstreaming as the key strategy for promoting

gender equality and women’s empowerment across the ADB funded projects. The Policy on

Gender and Development (GAD) is guiding

document to ensure that their needs and

concerns are addressed and that gender issues in

resettlement are mitigated. The policy adopts

gender mainstreaming as a key strategy for

promoting gender equity, and for ensuring that

women participate and that their needs are

explicitly addressed in the decision-making

process.

Applicable

This policy is applicable to social

aspects such as recruitment and

selection, terms of employment,

equal opportunity and non-

discrimination, parity in salary/

wages etc.

3.5.6 Applicable International Conventions

Environmental problems which migrate beyond the jurisdiction (Trans-boundary) require power to control such issues through international co-operation by either becoming a Contracting Party (CP) i.e. ratifying treaties or as a Signatory by officially signing the treaties and agreeing to carry out provisions of various treaties on environment and social safeguards. The relevant international conventions are as provided in Table 3-7.

Page 66: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

Electro Solaire Private Limited

AECOM

Table 3-7 Relevant International Conventions

S. N. International Conventions Salient Features 1. Montreal Protocol on Substances

That Deplete the Ozone Layer (and subsequent Amendments)

India signed the Montreal Protocol along with its London Amendment on 17-9-1992 and also ratified the Copenhagen, Montreal and Beijing Amendments on 3rd March 2003.

2. Kyoto Protocol The Kyoto protocol was signed by India in August 2002 and ratified in February 2005. The convention pertains to the United Nations framework on Climate Change. The 3rd Conference of the Parties to the Framework Convention on Climate Change (FCCC) in Kyoto in December 1997 introduced the Clean Development Mechanism (CDM) as a new concept for voluntary greenhouse-gas emission reduction agreements between industrialized and developing countries on the project level.

3. International Labour Organization conventions

India has also ratified many of the International Labour Organization

conventions that are relevant to the Project including:

1. C1 Hours of Work (Industry) Convention, 1919 (14:07:1921, ratified);

2. C5 Minimum Age (Industry) Convention, 1919 (09:09:1955, ratified):

3. C11 Right of Association (Agriculture) Convention, 1921 (11:05:1923,

ratified):

4. C14 Weekly Rest (Industry) Convention, 1921 (11:05:1923, ratified);

5. C29 Forced Labour Convention, 1930 (30:11:1954, ratified) & C105

Abolition of Forced Labour Convention, 1957 (18:05:2000, ratified);

6. C100 Equal Remuneration Convention, 1951 (25:09:1958, ratified);

7. C107 Indigenous and Tribal Populations Convention, 1957

8. C111 discrimination (Employment and Occupation) Convention, 1958

(03:06:1960, ratified)

4. UN Guiding principles on Business and Human Right

The United Nations (UN) Guiding Principles on Business and Human Rights

(GPs), which were endorsed by the Human Rights Council (HRC) in June

2011, are built on three pillars: states’ duty to protect human rights, corporate responsibility to respect human rights, and access to effective remedies. All

three pillars of the GPs – especially Pillar 1 and Pillar 3 – require states to

take a number of measures to ensure that business enterprises do not violate

human rights and that effective remedies are available in cases of violation.

The UN Working Group on the issue of human rights and transnational corporations and other business enterprises (UNWG) ‘strongly encourages all states to develop, enact and update’ a national action plan (NAP) on business and human rights (BHR) as part of states’ responsibility to disseminate and implement the GPs. In June 2014, the HRC passed a resolution calling upon states to develop NAPs. As of 29 February 2016, ten states have drawn up NAPs of which India was a party wherein it reaffirms India’s commitments towards realization of human rights and promotion of socially responsible businesses in the country.

5. Convention on Biological Diversity, 1992 (CBD or Rio Convention)

India is a party to CBD since 1994. The objectives of the CBD are the conservation of biological diversity, the sustainable use of its components, and the fair and equitable sharing of the benefits arising from commercial and other utilization of genetic resources. The agreement covers all ecosystems, species, and genetic resources.

6. Convention on the Conservation of Migratory Species of Wild Animals, 1983 (CMS or “Bonn Convention”)

India is a Party to CMS since 1983. CMS is an intergovernmental treaty aimed at conservation and sustainable use of migratory animals and their habitats. It brings together Range States through which migratory animals pass and lays the legal foundation for internationally coordinated conservation measures throughout a migratory range. Parties strive towards protecting migratory species, conserving or restoring the places where they live, mitigating obstacles to migration and controlling other factors that might endanger them.

7. Convention on Wetlands of International Importance especially as Waterfowl Habitat, 1971 (Ramsar Convention)

India is a Contracting Party to the Ramsar Convention since 1982. It is an intergovernmental treaty that provides a framework for the conservation and wise use of wetlands and their resources. It includes all lakes and rivers, underground aquifers, swamps and marshes, wet grasslands, peatlands, oases, estuaries, deltas and tidal flats, mangroves and other coastal areas, coral reefs, and also human-made sites, such as fish ponds, rice paddies, reservoirs and salt pans. Contracting Parties commit to work towards the wise use of all their wetlands, designate suitable wetlands for the list of Wetlands of International Importance (the “Ramsar List”) and ensure their effective management, as well as, cooperate internationally on transboundary wetlands, shared wetland systems and shared species

Page 67: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

Electro Solaire Private Limited

AECOM

S. N. International Conventions Salient Features

8. Convention on International Trade in Endangered Species of Wild Flora and Fauna, 1975 (CITES)

India is a Party to CITES since 1976. It is an international agreement between governments aimed at ensuring that international trade in specimens of wild animals and plants does not threaten the survival of such species. Each CITES Party is expected to adapt its domestic legislation to ensure that the CITES framework is implemented at the national level.

9. Convention Concerning the Protection of World Cultural and Natural Heritage, 1972 (UNESCO World Heritage Convention) (WHC).

India has been a State Party to the WHC since 1977. The WHC aims to identify and protect the world's natural and cultural heritage considered to be of outstanding universal value. State Parties to the WHC are expected to identify and nominate properties on their national territory to be considered for inscription on the World Heritage List, giving details of how a property is protected and providing a management plan for its upkeep. States Parties are also expected to protect the World Heritage values of the properties inscribed.

10. The Rotterdam Convention on the Prior Informed Consent (PIC) Procedure

The Rotterdam Convention on the Prior Informed Consent (PIC) Procedure for Certain Hazardous Chemicals & Pesticides in international Trade was adopted by India at the Conference of Plenipotentiaries at Rotterdam in 1998.

3.6 Categorisation of Project 3.6.1 Classification as per MoEF&CC, India

MoEF&CC had brought out notifications in 1989, with the purpose of prohibition/ restriction of operations of certain industries to protect ecologically sensitive Doon Valley. The notification introduced the concept of categorization of industries as “Red”, “Orange “and “Green” with the purpose of facilitating decisions related to location of these industries. Subsequently, the application of this concept was extended in other parts of the country not only for the purpose of location of industries, but also for the purpose of Consent management and formulation of norms related to surveillance / inspection of industries.

According to the Final Document on Revised Classification of Industrial Sectors under Red, Orange, Green White Categories; February 29,2016; Central Pollution Control Board; Table G-5: Final List of White Category of Industries, Sl. No 79 Solar power generation through solar photovoltaic cell, wind power and mini hydel power has been classified under White Category.

• Newly introduced White category contains 36 industrial sectors which are practically non-polluting; and

• There shall be no necessity of obtaining the Consent to Operate’’ for White category of industries. An intimation to concerned SPCB / PCC shall suffice6.

3.6.2 Classification as per IFC Performance Standards

As part of its review of a project’s expected social and environmental impacts, IFC uses a system of social and environmental categorization. This categorization is used to reflect the size of impacts understood as a result of the client’s social and environmental assessment and to specify IFC’s institutional requirements. The categories used by the IFC are:

1. Category A Projects: Projects with potential significant adverse social or environmental risks or/and impacts

that are diverse, irreversible or unprecedented;

2. Category B Projects: Projects with potential limited adverse social or environmental risks or/and impacts

that are few in number, generally site-specific, largely reversible and readily addressed through mitigation

measures;

3. Category C Projects: Projects with minimal or no adverse social or environmental risks or/and impacts,

including certain financial intermediary (FI) projects with minimal or no adverse risks; and

4. Category FI Projects: All FI projects excluding those that are Category C projects.

IFC therefore categorizes the project primarily according to the significance and nature of its impacts. IFC defines the project's area of influence as the primary project site(s) and related facilities that the client (including its contractors) develops or controls; shared facilities that are not funded as part of the project (funding may be

6 Final Document on Revised Classification of Industrial Sectors under Red, Orange, Green White Categories; February 29,2016; Central Pollution Control Board;

Page 68: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

Electro Solaire Private Limited

AECOM

provided separately by a client or a third party including the government), and whose viability and existence depend exclusively on the project and whose goods or services are essential for the successful operation of the project; areas potentially impacted by cumulative impacts from further planned development of the project; and areas potentially affected by impacts from unplanned but predictable developments caused by the project that may occur later or at a different location. The area of influence does not include potential impacts that would occur without the project or independently of the project.

Applying the criteria stipulated by the IFC Policy on Environmental and Social Sustainability for environmental and social categorization of projects, ESPL's proposed 200 MW solar project may be assigned as ‘Category B’ with respect to environmental and social impacts. This is so basis the primary data available to date which indicates that the environmental and social risks and impacts of the proposed project activities are expected to be few in number, generally site-specific, largely reversible, and readily addressed through mitigation measures, which supports the ‘Category B’ classification.

Additional rationale for the above categorization is as below:

• Solar power project is a clean technology project using solar energy for generation of electricity; • No harmful emissions are expected from the project operations; • The Project Site does not coincide or overlap with any Designated Area; and

• Available data suggests that the construction, operation and decommissioning of the proposed solar project are likely to have limited environmental and social impacts which can be readily addressed with mitigation measures.

3.6.3 Project categorisation as per ADB SPS

Project Category and Requirements

The ADB SPS along with the ADB Environmental Safeguards, A Good Practice Sourcebook, 2012 clarifies the rationale, scope and content of an environmental assessment and supported by technical guidelines (e.g., Environmental Assessment Guidelines, 2003). Projects are initially screened to determine the level of assessment that is required according to the following three environmental categories (A, B, or C).

• Category A is assigned to projects that normally cause significant or major environmental impacts that are irreversible, diverse or unprecedented such as hydroelectric dams (an Environmental Impact Assessment is required).

• Category B projects have potential adverse impacts that are less adverse than those of category A, are site-specific, largely reversible, and for which mitigation measures can be designed more readily than for category A projects (an Initial Environmental Examination is required).

• Category C projects are likely to have minimal or no negative environmental impacts. An environmental assessment for Category C projects is not required but environmental implications need to be reviewed.

The project has been evaluated considering the environmental (SPS1) categorization of ADB. The adverse environmental and social impacts of the project are considered site-specific and reversible. Therefore, it has been classified as Category B in accordance with ADB’s SPS1 (2009). The rationale for categorisation is as follows:

• Solar power project is a clean technology project using solar energy for generation of electricity; • No harmful emissions are expected from the project operations; • The Project Site does not coincide or overlap with any Designated Area; • Available data suggests that the construction, operation and decommissioning of the proposed solar

project are likely to have limited environmental and social impacts which can be readily addressed with mitigation measures.

On the backdrop of the understanding of the categorisation of ADB Projects and based on Involuntary Resettlement impacts and based on the following facts, the proposed Project can be classified as Category C with respect to SPS 2 – Involuntary Resettlement:

• The proposed Project is being set up on land owned by the Government of Gujarat (GoG) and has been leased to the proponent for a period of 25 years;

• The land has not been procured from any private land owners and has been in continuous possession of the GoG for at least a period of more than 60 years i.e. since 1960s;

Page 69: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

Electro Solaire Private Limited

AECOM

• No livelihood activities apart from some grazing was reported or observed on the proposed Project land parcel; and

• No housing structures, habitations or settlements were reported or observed at site during the site visit. The same was confirmed through community consultations and discussions with institutional stakeholders.

On the backdrop of the understanding of the categorisation of ADB Projects and based on impacts of IPs and based on the following facts, the proposed Project can be classified as Category C with respect to SPS 3 – IPs:

• The proposed Project will be set up on land owned by the GoG and no acquisition/ procurement of land from private land owners including land parcels owned by IPs is involved in the Project;

• IPs do not have any livelihood dependence on the proposed Project land or any customary land rights on the concerned land parcels; and

• There are no designated CPRs located within the proposed Project area that are being used by IPs.

3.7 Applicable Environmental Standards

3.7.1 Ambient Air Quality

As per the IFC EHS guidelines (April 2007), “the ambient air quality standards are ambient air quality levels established and published through national legislative and regulatory processes and ambient quality guidelines refer to ambient quality levels primarily developed through clinical, toxicological, and epidemiological evidence (such as those published by the World Health Organization)”. National Ambient Air Quality Standards (NAAQS), as notified under Environment (Protection) Rules 1986 and revised through Environment (Protection) Seventh Amendment Rules, 2009 are given Table 3-8:

Table 3-8: National Ambient Air Quality Standards

Pollutant Time Weighted Average

Concentration in Ambient Air

Industrial, Residential, Rural and other Areas

Ecologically Sensitive Area (notified by Central Government)

Sulphur Dioxide (SO2), µg/m3 Annual* 50 20

24 Hours** 80 80

Nitrogen Dioxide (NO2), µg/m3 Annual* 40 30

24 Hours** 80 80

Particulate Matter (size less than 10 µm) or PM10, µg/m3

Annual* 60 60

24 Hours** 100 100

Particulate Matter (size less than 2.5 µm) or PM 2.5, µg/m3

Annual* 40 40

24 Hours** 60 60

Ozone (O3), µg/m3 8 Hours** 100 100

1 Hour** 180 180

Lead (Pb), µg/m3 Annual* 0.5 0.5

24 Hours** 1 1

Carbon Monoxide (CO), mg/m3 8 Hours** 2 2

1 Hour** 4 4

Ammonia (NH3), µg/m3 Annual* 100 100

24 Hours** 400 400

Benzene (C6H6), µg/m3 Annual* 5 5

Benzo (O) Pyrene (BaP), particulate phase only, ng/m3

Annual* 1 1

Page 70: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

Electro Solaire Private Limited

AECOM

Pollutant Time Weighted Average

Concentration in Ambient Air

Industrial, Residential, Rural and other Areas

Ecologically Sensitive Area (notified by Central Government)

Arsenic (As), ng/m3 Annual* 6 6

Nickel (Ni), ng/m3 Annual* 20 20

*Annual arithmetic mean of minimum 104 measurements in a year taken twice a week, 24 hourly at uniform interval

**24 hourly or 8 hourly or 1 hourly value as applicable shall be complied with 98% of the time in a year. 2% of the time they may

exceed, but not on 2 consecutive days. Note: Whenever and wherever monitoring results on two consecutive days of

monitoring exceed the limits specified above for the respective category, it shall be considered adequate reason to institute

regular or continuous monitoring and further investigation.

3.7.2 Ambient Noise Standards

As per the EHS guidelines of IFC, for residential, institutional and educational area, the one hourly equivalent noise level (Leq hourly) for day time (6.00 a.m. to 10.00 p.m.) is 55 dB (A) while the Leq hourly for night time (10.00 p.m. to 6.00 a.m.) is prescribed as 45 dB (A). Noise standards notified by the MoEF&CC vide gazette notification dated 14th February 2000 based on the A- weighted equivalent noise level (Leq) are as presented in Table 3-9.

Table 3-9: Ambient Noise Standards

Area Code Category of Area Limits in dB(A) Leq

Day time Night Time

A Industrial Area 75 70

B Commercial Area 65 55

C Residential Area 55 45

D Silence Zone* 50 40

*Silence zone is defined as area up to 100 m around premises of hospitals, educational institutions and courts. Use of vehicle

horns, loud speakers and bursting of crackers are banned in these zones.

3.7.3 Noise Standards for Occupational Exposure

Noise standards in the work environment are specified by Occupational Safety and Health Administration (OSHA-USA) which in turn are being enforced by Government of India through model rules framed under the Factories Act.

Table 3-10: Standards for Occupational Noise Exposure

Total Time of Exposure per Day in Hours

(Continuous or Short-term Exposure)

Sound Pressure Level in

dB(A)

8 90

6 92

4 95

3 97

2 100

3/2 102

1 105

¾ 107

½ 110

¼ 115

Page 71: 54035-001: Gujarat Solar Power Project

ESIA of 200 MW Solar Power Project

Electro Solaire Private Limited

AECOM

Total Time of Exposure per Day in Hours

(Continuous or Short-term Exposure)

Sound Pressure Level in

dB(A)

Never >115

No exposure in excess of 115 dB (A) is to be permitted.

For any period of exposure falling in between any figure and the next higher or lower figure as indicated in column (1), the

permissible level is to be determined by extrapolation on a proportionate scale.

3.7.4 Water Quality Standards

The designated best use classification as prescribed by CPCB for surface water is as given in Table 3-11.

Table 3-11: Primary Water Quality Criteria for Designated Best Use Classes

Designated-Best-Use Class Criteria

Drinking Water Source without conventional treatment but after disinfection

A • Total Coliforms Organism MPN/100ml shall be 50 or less

• pH between 6.5 and 8.5

• Dissolved Oxygen 6mg/l or more

• Biochemical Oxygen Demand 5 days 20°C 2mg/l or less

Outdoor bathing (Organised) B • Total Coliforms Organism MPN/100ml shall be 500 or less

• pH between 6.5 and 8.5

• Dissolved Oxygen 5mg/l or more

• Biochemical Oxygen Demand 5 days 20°C 3mg/l or less

Drinking water source after conventional treatment and disinfection

C • Total Coliforms Organism MPN/100ml shall be 5000 or less

• pH between 6 to 9

• Dissolved Oxygen 4mg/l or more

• Biochemical Oxygen Demand 5 days 20°C 3mg/l or less

Propagation of Wild life and Fisheries D • pH between 6.5 to 8.5

• Dissolved Oxygen 4mg/l or more

• Free Ammonia (as N) 1.2 mg/l or less

Irrigation, Industrial Cooling, Controlled Waste disposal

E • pH between 6.0 to 8.5

• Electrical Conductivity at 25°C micro mhos/cm Max.2250

• Sodium absorption Ratio Max. 26

• Boron Max. 2mg/l

Below-E • Not Meeting A, B, C, D & E Criteria

Source: Central Pollution Control Board

As per the IFC EHS guidelines, the treated sewage discharge is required to meet the following guidelines.

Table 3-123-7: Treated sewage discharge guidelines as per IFC

S. No. Parameter Guideline Value

1. pH 6-9

2. BOD 30mg/l

3. COD 125 mg/l

4. Total Nitrogen 125 mg/l

5. Oil and Grease 10 mg/l

6. Total Suspended Solids 50 mg/l

7. Total coliform bacteria 400 MPN/100 ml