Page 1: 5-Apr-11 Sprint MMBS Installation Guide1

Confidential

MMBS Installation GuideMMBS Installation GuideMMBS Installation Guide< Sprint >

MMBS Installation Guide< Sprint > Sprint Sprint

2011 3 252011 3 252011. 3. 25

H/W Infra Lab.

2011. 3. 25

H/W Infra Lab.

Annotation) This data could be revised while designing in detail.

Page 2: 5-Apr-11 Sprint MMBS Installation Guide1

Confidential

1. System DescriptionConfidential

Items Specification

System Type MMBS Outdoor

Frequency 800MHz, 1.9GHz, 2.5GHz, 2.5GHz @ RRU

Sector Max. 4 RRU/ sector (Total 12 RRU max)

Channel BW (MHz) 7MHz (800M) 65MHz(1 9G) 20MHz(2 5G)Channel BW (MHz) 7MHz (800M), 65MHz(1.9G), 20MHz(2.5G)

Weight BBU Cabinet : - (kg) w/o DU shelf

- (kg) with 4 DU shelfBattery Cabinet : - (kg) w/o battery

- (kg) with battery

Network Interface T1 or M/W or optic

Physical Dimensions(H W D) 1800x700x1018(820) mm / 70.8in x 29.5in x 40.1(37.0)in(HxWxD) 800 00 0 8(8 0) / 0 8 9 5 0 (3 0)

Power Consumption220VAC (22A,max) @ w/o battery,Only CDMA220VAC (36A,max) @ w/o battery,CDMA/LTE/WiMAX220VAC (40A,max) @ with battery, Only CDMA 220VAC (80A ma ) @ ith batter CDMA/LTE/WiMAX220VAC (80A,max) @ with battery, CDMA/LTE/WiMAX

DU-RU Interface CPRI 4.0 specification (Optic)

Note Recommended NFB Capacit 100A ma 1EA

1

Note. Recommended NFB Capacity 100A,max. 1EA

Page 3: 5-Apr-11 Sprint MMBS Installation Guide1

Confidential Confidential

Items Specification

Rectifier module Specification

Voltage Range 185~275VAC

Frequency 45~66 Hz(50/60 Hz)

O t t V lt 53 5 VDCOutput Voltage -53.5 VDC

Output Voltage Range -43.5~-57.6VDC

Efficienty 96% @ 2kW Output,moduley % @ p ,

Maximum Output Power 2,000W x 7 @ 25 ℃

Weight 1.950 kg (4.3lbs)

2

Page 4: 5-Apr-11 Sprint MMBS Installation Guide1

Confidential Confidential Battery

3

Page 5: 5-Apr-11 Sprint MMBS Installation Guide1

Confidential

1.1 System configurationConfidential

BBU cabinet Battery cabinet

BatteryRectifier

PDP

Battery

TD-LTE/FDD LTEWiMAX

CDMA/FDD LTECDMA

Old version

Battery

User SpaceUser

CDMA/FDD LTE

BatteryUser Spacespace

BatteryCabling Space

Cabling Space

4[BBU Cabinet] [Battery Cabinet]

Page 6: 5-Apr-11 Sprint MMBS Installation Guide1

ConfidentialConfidential

<66Block>- Maker :

GPS portMaker :

- P/N :

Mudroom <Comseal>- Maker : Roxtec

P/N : ComSeal 16/16

2” Conduit

- P/N : ComSeal 16/16

5 4 3 2 1 0

2 Conduit

[Mudroom]

<GPS Splitter>- Maker : Symmetricom- P/N : 58536A

5Note. This data could be revised while designing in detail.[Back side of the BBU cabinet]

Page 7: 5-Apr-11 Sprint MMBS Installation Guide1

Confidential

1.2 System DimensionConfidential

BBU Cabinet

00.0

1,80

1 018 0700 0

300.

0

433.

0

[Front View] [Left View]

1,018.0

6

700.0

[Rear View]

Page 8: 5-Apr-11 Sprint MMBS Installation Guide1

ConfidentialConfidential Battery Cabinet

,800

.0

Old version Old version

11 022 3700 0

742.5

[Front View] [Left View]7

1,022.3700.0

Page 9: 5-Apr-11 Sprint MMBS Installation Guide1

Confidential

1.3 Floor LayoutConfidential

min. distance for no colision opening

cabinets

60

1225

.5 959.

8

1,460min

8

Page 10: 5-Apr-11 Sprint MMBS Installation Guide1

ConfidentialConfidential

9.5

2,20

9

959.

8 60

9

1,460 min

1,739.8 min

Page 11: 5-Apr-11 Sprint MMBS Installation Guide1

ConfidentialConfidential

067

0.0

/ C

630.0

10

[Power/Battery Cabinet Anchor Location]

Page 12: 5-Apr-11 Sprint MMBS Installation Guide1

Confidential

1.4 Service Area700 0700 0 60 0 Confidential700.0700.0 60.0

076

2.

Mudroom

System

61.0

743.

0

60Battery

209.

5

1,44

7.5

136 2,

11

760.01,123.4

Page 13: 5-Apr-11 Sprint MMBS Installation Guide1

Confidential

1.5 Environment Control Module & SensorConfidential

Fire SensorDoor Switch

Lamp

Fire SensorDoor Switch

LampLamp

User SpaceUser Space

Cabling SpaceFlood sensor

Flood sensor

12[BBU Cabinet] [Batery Cabinet]

Page 14: 5-Apr-11 Sprint MMBS Installation Guide1

Confidential

1.6 External I/F Cable(BBU cabinet)1.6 External I/F Cable(BBU cabinet)

Confidential

Item Cable Connector Terminal name Q’t Provider

Power(AC)

1P3W, L1/L2 /N AWG 2

NFB terminal L1,L2,N Conduit #1 1 STA(AC) L1/L2 /N : AWG 2

Black/Red/White

Battery Power #0a(Battery)

AWG 1/0Black/Blue

Compression terminal,1H, M8

Battery switch Conduit #0 2 Eltek

CAN bus #0(Battery) SFTP,4p RJ-45 Conduit #0 1 Eltek

DC Power #0b(Battery) AWG 12 Ferrule Conduit #0 1 Eltek

Battery Power #1a(Battery)

AWG 1/0Black/Blue

Compression terminal,1H, M8

Battery switch Conduit #5 2 Eltek( y) , ,

CAN bus #1(Battery) SFTP,4p RJ-45 Conduit #5 1 Eltek

DC Power #1b(Battery) AWG 12 Ferrule Conduit #5 1 Eltek

RRU cable Hybrid, Option Power,bare wire - Conduit # 2,3,4

3 HQ

Optic,LC

Backhaul(T1) Shield type RJ-45, wire Surge protector Mudroom, C l

16max STAComsealUser Define Alarm Shield type Bare wire 66 block 1 STA

GPS LMR-400 N-Male or N-Female GPS arrestor 1 STA

Ground AWG 2 Compression terminal 2H M6 L5/8”

Ground bus bar Conduit #1 1 STA

13

terminal,2H, M6, L5/8

Page 15: 5-Apr-11 Sprint MMBS Installation Guide1

Confidential

1.7 I/F Port PositionConfidential

BatteryPowerterminal

RRU DC P

AC terminal

Battery

User Space

RRU DC Power

RRU Optic

operating power terminal

User Space

CAN BUS

CAN BUS

Cabling Space

Ground

14[BBU Cabinet] [Batery Cabinet]

Page 16: 5-Apr-11 Sprint MMBS Installation Guide1

ConfidentialConfidential

GPS portUDA,Backhaul

Mudroom < Comseal >- Maker : Roxtec

P/N : ComSeal 16/16

2” Conduit

- P/N : ComSeal 16/16

5 4 3 2 1 0

2 Conduit

[Mudroom]

UDA or Link cableGPS cable

Note. This data could be revised while designing in detail. 15

[Back side of the BBU cabinet]

Page 17: 5-Apr-11 Sprint MMBS Installation Guide1

Confidential

1.8 Power BlockdiagramConfidential

System Power Blockdiagram

16PE

Page 18: 5-Apr-11 Sprint MMBS Installation Guide1

Confidential Confidential Battery Cabinet Power Blockdiagram

17Check power supply TN-C in USA 1P3,can it use 2 SPD(L to N) ?

Page 19: 5-Apr-11 Sprint MMBS Installation Guide1

Confidential Confidential Load Breaker

No

F1

F2

F3

F4

F5

F6

F7

F8

F9

F10

F11

F12

F13

F14

F15

F16

F17

F18

F19

F20

F21

F22

F23

F24

Ca

16

16

16

16

16

16

16

16

16

20

16

16

16

20

16

16

16

20

4A

4A

2A

2A

2Aa

pacity

6A

6A

6A

6A

6A

6A

6A

6A

6A

0A

6A

6A

6A

0A

6A

6A

6A

0A

AUX UADU RRU

LLabel

AU

X0

AU

X1

DU

#0

DU

#1

DU

#2

DU

#3

RR

U#0

RR

U#1

RR

U#2

RR

U#3

RR

U#4

RR

U#5

RR

U#6

RR

U#7

RR

U#8

RR

U#9

RR

U#10

RR

U#11

FAN

#1

FAN

#2

Sm

oke

Light

EAIU

1.9

1.9

1.99GH

z

9GH

z

9GH

z

LVLD

LVBD

Coldstart contactor

18

Page 20: 5-Apr-11 Sprint MMBS Installation Guide1

Confidential

Ref. Power distribution system at USRef. Power distribution system at USConfidential

19

Page 21: 5-Apr-11 Sprint MMBS Installation Guide1

Confidential

2.1 SOW 2.1 SOW Confidential

Lightning rod

GPS Antenna

BBUCabinet

RRU

BackhaulMud-roomAux. Equip. UDA

AC Power Distribution

Panel

AC220VGround

BatteryCabinet

Ground

Tower

20

Page 22: 5-Apr-11 Sprint MMBS Installation Guide1

Confidential

2.2 Material List 2.2 Material List Confidential

To be defined.

21

Page 23: 5-Apr-11 Sprint MMBS Installation Guide1

Confidential

3. Installation Process3. Installation ProcessConfidential

Ground Cable Backhaul CableMaterial Check DU Installation

AC Power Cable UDA Cable(Option)

Ground Buss Installation

EAIU Installation

Backup Battery CableBBU Cabinet

AnchoringGPS Cable

GPS Arrestor&Splitter

RRU Cable

Check

Battery CabinetAnchoring

AUX Installation(Option)

CheckRRU

Installation

22

Page 24: 5-Apr-11 Sprint MMBS Installation Guide1

ConfidentialConfidentialAntenna

Frame Ground Cable

RF Antenna

Cable

RRU

OpticGPS

PowerDC CableOptic Cable

GPSAntenna

Cable

User Space

Cabling Main Ground BarAC Distribution Panel

Power Cable(FR-8 25 mm2 × 3C, 1ea)

g Space Ground Cable(GV 25 mm2×1C)

23

Page 25: 5-Apr-11 Sprint MMBS Installation Guide1

ConfidentialConfidential

Rectifier

PDP

Rectifier

PDP

TD-LTE/FDD LTE

WiMAX

CDMA/FDD LTECDMA

User Space

CDMA/FDD LTE

User Space

Cabling Space

Battery cable

AC cable

24[Front View]

hybrid cable

AC cable

Page 26: 5-Apr-11 Sprint MMBS Installation Guide1

ConfidentialConfidential

Conduit No. Usage

0 Battery #0

1 AC/Ground

[Mudroom]

UDA or Link cable

GPS cable

1 AC/Ground

2 RRU Alpha

3 RRU Beta

4 RRU Gamma5 4 3 2 1 0

To RRU

25

5 Battery #1

[Rear View]

To RRU

Page 27: 5-Apr-11 Sprint MMBS Installation Guide1

Confidential

3.1 AnchoringConfidential

670.

0

630.0

26

[Power/Battery Cabinet Anchor Location]

Page 28: 5-Apr-11 Sprint MMBS Installation Guide1

ConfidentialConfidential

NutAnchor Bolt

Spring Washer

Plane Washer

Floor

2.76”

C f(M10 Anchor-Bolt) Completion of Anchoring(M10 Anchor-Bolt)

Each equipment requires specific bolting pattern Verify that you have the right bolt patternEach equipment requires specific bolting pattern. Verify that you have the right bolt pattern.

27

Page 29: 5-Apr-11 Sprint MMBS Installation Guide1

Confidential

3.2 Ground Cable3.2 Ground CableConfidential

(Front view)

25 mm2 Pressure Terminal(ST, M6,2hole, Dist: 5/8”)User

Space

C bli

28

Cabling Space

Page 30: 5-Apr-11 Sprint MMBS Installation Guide1

Confidential

3.3 AC Power Cable3.3 AC Power CableConfidential

AC(Front view)

100A, 1P3W

P C bl

L1/L2/N

Power CableAC : L1/L2/N (BLACK/RED/WHITE)

1) Through the conduit #12) Connect Ferrule to wire and Fix the cable with switch screw .

User Space

C bli

29

2) Connect Ferrule to wire and Fix the cable with switch screw . Cabling Space

Page 31: 5-Apr-11 Sprint MMBS Installation Guide1

Confidential

3.4 Backup Battery Cable3.4 Backup Battery CableConfidential

Battery power switch

Batter

Routing path : Left,rear edge

Battery operating power

Battery

User Space

power terminal

(Front view)

Battery

CAN User Space

BatteryCAN BUS

CAN BUS

Cabling SpaceUser Space

C bli

Battery

30[BBU Cabinet]

Cabling Space

[Battery Cabinet]

Page 32: 5-Apr-11 Sprint MMBS Installation Guide1

ConfidentialConfidential

(Front view)

User Space

C bli

31

Cabling Space

Page 33: 5-Apr-11 Sprint MMBS Installation Guide1

Confidential

3.5 UADU installation3.5 UADU installationConfidential

1) Install DU shelf support bracket at 20U with cage nut(M6)cage nut(M6)

2) Install DU shelf upper side of bracket stackable

3) Tag the DU shelf label 4) Connect DU shelf cable

(power GPS Backhaul Alarm)Power switch (power,GPS,Backhaul,Alarm)

UADU

User Space

(Front view) DU shelf bracketBracket

User Space

User Space

Cabling

Cabling Space

Cabling Space

32[BBU Cabinet]

Page 34: 5-Apr-11 Sprint MMBS Installation Guide1

ConfidentialConfidentialStep.1 DU Blank bracket Install

Example .

1) Fix the bracket at 20U from bottom Mounting frame with M6 Cage nuts

33

1) Fix the bracket at 20U from bottom Mounting frame with M6 Cage nuts

Page 35: 5-Apr-11 Sprint MMBS Installation Guide1

ConfidentialConfidentialStep.2 UADU Install

Step 2-1 UADU Ground cable connection

DU Unit backsideM6 SEMS

Detail ‘A’

Step.2-1 UADU Ground cable connection

4 mm2 Pressure Terminal(d2: 16 mm, 2Hole)

Ground Cable

Heat Shrink Tube (Green)

Detail ‘B’

Ground Cable(AWG10, GV 4 mm2 × 1C)

※ first connect the Ground cable before install DU unit

1) Connect ground cable backside of UADU

34

) g2) Fix the UADU upper DU blank bracket with M6 floating nuts3) Connect the other ends of ground cable at ground bar of the cabinet left bottom .

Page 36: 5-Apr-11 Sprint MMBS Installation Guide1

ConfidentialConfidential

Step.2-2 UADU install

M6SEMS

Cage nut

Step.2-3 Ground cable - frame

Heat Shrink Tube(Green)

Ground Cable(AWG10, GV 4 mm2 × 1C)

4 mm2 Pressure Terminal(LUg Type, 2Hole)

M6 Hex. Nut

Heat Shrink Tube(Green)

Ground Bar

35

Page 37: 5-Apr-11 Sprint MMBS Installation Guide1

ConfidentialConfidential Power Cable SPEC. from Rectifier to UADU

A2: RTN

A1: -48 VDCD-Sub Plastic hood

SPEC Wire Color Maker

Cable Power Cable Color

( )

A1(-48VDC: blue)

( )(CV 2.5 mm2 × 1C-2) A2(RTN: red)

Connector D-Sub Connector(2W2C)-302W2CPXX42A10X & Hood

- CONEC

36

Page 38: 5-Apr-11 Sprint MMBS Installation Guide1

Confidential

3.6 EAIU4-U Installation3.6 EAIU4-U InstallationConfidential

UDA

Ethernet

(Front view)

Switch

Ethernet

User Space

Cabling1) Re-assemble the wing brackets of EAIU as picture. 2) Fix EAIU at the right frame with M6 SEMS 2ea as picture

PowerUDE

37

Cabling Space

2) Fix EAIU at the right frame with M6,SEMS 2ea as picture

Page 39: 5-Apr-11 Sprint MMBS Installation Guide1

ConfidentialConfidential Cable SPEC. from Rectifier to EAIU

SPEC Wire Color Maker

Cable UL2464 AWG20 2C BLK Black Korea Maker

SEC CODE : EP39-01736A

Cable UL2464, AWG20, 2C BLK Black Korea Maker

Connector 51067-0300 - MOLEX

38

Page 40: 5-Apr-11 Sprint MMBS Installation Guide1

Confidential

3.7 Surge protector Installation3.7 Surge protector InstallationConfidential

GPS arrestorGPS splitter

(Rear view)

[Mudroom]

Roxtec ComsealMudroom

39Note. It will add the surge protector for T1 .

Page 41: 5-Apr-11 Sprint MMBS Installation Guide1

Confidential

3.8 Auxillary Unit Installation3.8 Auxillary Unit InstallationConfidential

* To be defined.

Power switch

UADU

User Space

(Front view) DU shelf bracketBracket

User Space

User Space

Cabling

Cabling Space

Cabling Space

40[BBU Cabinet]

Page 42: 5-Apr-11 Sprint MMBS Installation Guide1

Confidential

3.9 Backhaul – When T13.9 Backhaul – When T1Confidential

GPS arrestor66 Block GPS splitter

(Rear view)

[Mudroom]

Roxtec ComsealUDA or Link cableMudroom

41Note. It will add the surge protector for T1 .

Page 43: 5-Apr-11 Sprint MMBS Installation Guide1

ConfidentialConfidential

Note. BH did not Final Confirmed

(Front view)BH

T1 (from Cell Site Router. Install at User space )User

Space

Cabling1) Link the cable from UDE port of UADU to CSR. 2) Link T1 cable from CSR to surge protector at mudroom

42

Cabling Space

2) Link T1 cable from CSR to surge protector at mudroom.

Page 44: 5-Apr-11 Sprint MMBS Installation Guide1

ConfidentialConfidential T1 cable SPEC. from DU to CSR

RJ45 PLUGShield type

S-FTP

Pin No.

Pair Description COLOR MAP

1 Tip Rx+WHITE

* Pin MAP

1 Tip Rx+/ORANGE

2 Ring Rx- ORANGE

3WHITE/GREEN

4 Ti T BLUE4 Tip Tx+ BLUE

5 Rimg Tx-WHITE/BLUE

6 GREENWHITE

7WHITE/BROWN

8 BROWN

SPEC Wire Color Maker

Cable S-FTP, CAT5e - -

C t RJ45 PLUG (Shi ld)

SEC CODE : EP39-

Connector RJ45 PLUG (Shield) - -

43

Page 45: 5-Apr-11 Sprint MMBS Installation Guide1

Confidential

3.10 UDA cable3.10 UDA cableConfidential

UDA_EAIU ALARM_CABINET

66 Block

(Rear view)

[Mudroom]

Roxtec ComsealUDA or Link cableMudroom

44

1) Pin map is not defined.2) T1 surge protector spec. is not confirmed.

Page 46: 5-Apr-11 Sprint MMBS Installation Guide1

ConfidentialConfidential

SMART PACK RECSMART PACK_REC

Mudroom

UDE

UDE

(Front view)

UDE

UDE

User Space

Cabling

UDE2A_PDP

[EAIU4-U]Cabling Space

45

Page 47: 5-Apr-11 Sprint MMBS Installation Guide1

ConfidentialConfidential

Conne Pin Primary Color Map Secondary Pin Primary Color Map Secondary

66 Block Pin Map

ctor No. Primary Color Map Secondary No. Primary Color Map Secondary

1 262 273 284 294 295 306 317 328 339 34

66Block

9 3410 3511 3612 3713 38

To be defined.

Block 14 3915 4016 4117 4218 4318 4319 4420 4521 4622 4723 4823 4824 4925 50

46

Page 48: 5-Apr-11 Sprint MMBS Installation Guide1

ConfidentialConfidential Cable SPEC. from EAIU to 66 block

SPEC Wire Color Maker

Cable UL2919 AWG24 20PR - -

47SEC CODE : EP39-01555A

Cable UL2919, AWG24, 20PR

②Connector 10136-3000ve - 3M

Page 49: 5-Apr-11 Sprint MMBS Installation Guide1

ConfidentialConfidential Cable SPEC. from DU to EAIU/SpartPack

RJ45 PLUGShield type

S-FTP

Pin No. Pair Description COLOR MAP

WHITE

* Pin MAP

1 TX0+ Ethernet TX Positive signalWHITE/ORANGE

2 TX0- Ethernet TX Negative signal ORANGE

3 RX0+ Ethernet RX Positive signalWHITE/GREEN

4 TX1+ Ethernet TX Positive signal(Gigabit) BLUE

5 TX1- Ethernet TX Negative signal(Gigabit)WHITE/BLUE

6 RX0- Ethernet RX Negative signal GREENWHITE

7 RX1+ Ethernet RX Positive signal(Gigabit)WHITE/BROWN

8 RX1- Ethernet RX Negative signal(Gigabit) BROWN

SPEC Wire Color Maker

Cable S-FTP, CAT5e - -

48SEC CODE : EP39-01342B

Cable S FTP, CAT5e

Connector RJ45 PLUG (Shield) - -

Page 50: 5-Apr-11 Sprint MMBS Installation Guide1

ConfidentialConfidential Cable SPEC. from SpartPack to Mudroom

Pin No. Pair Description COLOR MAP

1

* Pin MAP

1

2

3

455

6

7

8

To be defined

SPEC Wire Color Maker

Cable S-FTP, CAT5e - -

49SEC CODE : EP39-

Cable S FTP, CAT5e

Connector - - -

Page 51: 5-Apr-11 Sprint MMBS Installation Guide1

Confidential

3.11 GPS Cable3.11 GPS CableConfidential

GPS arrestorGPS plitter

(Rear view)

[Mudroom]

Roxtec ComsealMudroom

50

1) GPS surge protector spec. is not confirmed.

Page 52: 5-Apr-11 Sprint MMBS Installation Guide1

ConfidentialConfidential GPS Cable at UADU

WiMAX Only

LTE Only

(Front view)

CDMA Only

CDMA + LTE

User Space

Cabling

CDMA LTE

Cabling Space

51

1) Cable route GPS Splitter from Mudroom

Page 53: 5-Apr-11 Sprint MMBS Installation Guide1

ConfidentialConfidential Cable SPEC. from GPS Arrestor to Splitter

To be defined

SPEC Wire Color Maker

Cable - -

Connector - -

Cable SPEC. from Splitter to UADU

Connector

SEC CODE : EP39-A

To be defined

SPEC Wire Color Maker

Cable - -

SEC CODE : EP39-A

Cable

Connector - -

52

Page 54: 5-Apr-11 Sprint MMBS Installation Guide1

Confidential

3.12 RRU Cable3.12 RRU CableConfidential

RRU Power(Lab. Certi.)

2 5GHz 2 5GHz 800MHz 1 9GHz

Table. Pin map2.5GHz 2.5GHz 800MHz 1.9GHz

gam

-48V

RTN

-48V

RTN

-48V

RTN

-48V

RTN

beta

-48V

RTN

-48V

RTN

-48V

RTN

-48V

RTN

-48V

(Front view)

a V N V N V N V N

ahph

-48V

RTN

-48V

RTN

-48V

RTN

-48V

RTN

Power Cable(AWG 6~10)-48V : Blue

User Space

Cabling

-48V : BlueRTN : Black

1) Through the conduit #2, #3, #42) Connect Ferrule to wire and Fix the cable with switch screw.Cabling

Space

53

2) Connect Ferrule to wire and Fix the cable with switch screw.

Page 55: 5-Apr-11 Sprint MMBS Installation Guide1

ConfidentialConfidential

Table. Pin map

RRU Modified Power Cable (FIT&Commercial)

2.5GHz

2.5GHz

800MHz

1.9GHz

2.5GHz

2.5GHz

800MHz

1.9GHz

2.5GHz

2.5GHz

800MHz

1.9GHz

-48V

RTN

-48V

RTN

-48V

RTN

-48V

RTN

-48V

RTN

-48V

RTN

-48V

RTN

-48V

RTN

-48V

RTN

-48V

RTN

-48V

RTN

-48V

RTN

p

alpha beta gamma

Power Cable(AWG 6~10)-48V : BlueRTN : Black

(Front view)

Move SPD positionChanging

DC SPD Block

Changing..

User Space

Cabling

DC SPD Block

Cabling Space

54

1) Through the conduit #2, #3, #42) Connect Ferrule to wire and Fix the cable with switch screw

Page 56: 5-Apr-11 Sprint MMBS Installation Guide1

ConfidentialConfidential Optic cable

WiMAX Only

LTE Only

(Front view)

CDMA Only

CDMA + LTE

User Space

CablingCabling Space

55

1) Through the conduit #2, #3, #42) Connect suitable optic cable

Page 57: 5-Apr-11 Sprint MMBS Installation Guide1

Confidential

Ref. Conduit finishing methodRef. Conduit finishing methodConfidential

[Optic cable storage box]

It can use storage box when the Optic cable is long

If Power cable is long , Cut the power cable. And Connect Ferrule to wire

Cable glandor Butyl

2” Conduitor Butyl

< 1m

Power cable

Optic cable

Hybrid cable

56

[BBU Cabinet Right view] Flexible pipe length can be changeable. It is why waterproof .

Page 58: 5-Apr-11 Sprint MMBS Installation Guide1

Confidential

Ref. Hybrid cable type (sort by length)Ref. Hybrid cable type (sort by length)Confidential

T 1 T 2 T 3

Table. Cable TypeType 1 Type 2 Type 3

Total Length ~40m ~70m ~120m(requirement is 300feet = 91.4m)

H b id P C bl AWG 8 1 i AWG 6 1 i AWG 4 1 iHybrid Power Cableconfiguration

AWG 8 1 pair,AWG 10 3 pair

AWG 6 1 pair,AWG 8 3 pair

AWG 4 1 pair,AWG 6 3 pair

Cable diameter 32mm 32mm 36mm

Bending radius 800mm 800mm 900mm

Optic cable LC/PC-to-LC/PCSingle mode

LC/PC-to-LC/PCSingle mode

LC/PC-to-LC/PCSingle mode

BBU cabinet (power cable terminal max

size AWG 6 )

- - AWG 4 -> AWG 6 conversion kit need

RRU Power cable Spec AWG 10, 4 pair AWG 10, 4 pair AWG 10, 4 pair

Non use Power and optic cable protection

2 pair power and optic cable With PE pipe

2 pair power and optic cable With PE pipe

2 pair power and optic cable With PE pipe

57

Note. SAMSUNG FIBEROPTICS.

Page 59: 5-Apr-11 Sprint MMBS Installation Guide1

Confidential

[Type 1] 30m Hybrid Cable

Confidential[1.9Mhz] Power cable AWG #8, 2C

Optic cable LC/PC * 4ea + spare 1ealength : 2.5m 1900MHzAWG #8

AWG #10

Max : 41mm 5 core optic

5.5mm

AWG #10

800MHz& 2.5GhzTo BBU

CabinetAWG #10

Break out pointC bl AWG #6 #8

800MHz& 2.5Ghz[800Mhz & 2.5Ghz]

Power cable : AWG #10 , 2C

Cable AWG #6, #8converte AWG #10

800MH

Optic cable : LC/PC * 4ea + spare 1ea

[Future Used]

Water-proof C 800MHz

& 2.5Ghz

[Future Used]

length : 5m

Cap

[ Cable AWG convertor] All Power cable : AWG #10 , 2C * 4ea

Page 60: 5-Apr-11 Sprint MMBS Installation Guide1

Confidential

[Type 2] 60m Hybrid Cable

Confidential

length : 2.5m 1900MHz

[1.9Mhz] Power cable AWG #6, 2COptic cable LC/PC * 4ea + spare 1ea

AWG #6AWG #10

5 core optic Max : 41mm

5.5mm

AWG #10

800MHz& 2.5GhzTo BBU

CabinetAWG #8

Break out pointC bl AWG #6 #8

[800Mhz & 2.5Ghz] Power cable : AWG #8 , 2C

800MHz& 2.5Ghz

Cable AWG #6, #8converte AWG #10

Water-proof C

Optic cable : LC/PC * 4ea + spare 1ea

800MH

[Future Used]

Cap

length : 5m

800MHz& 2.5Ghz

[Future Used]

[ Cable AWG convertor] All Power cable : AWG #10 , 2C * 4ea

Page 61: 5-Apr-11 Sprint MMBS Installation Guide1

Confidential

[Type 3] 90m Hybrid Cable

Confidential

length : 2.5m 1900MHzAWG #4

AWG #4 -> #6ferulle * 2ea [1.9Mhz] Power cable AWG #4, 2C

Optic cable LC/PC * 4ea + spare 1ea

5.5mm

5 core optic Max : 41mm

800MHz& 2.5Ghz

Break out pointC bl AWG #4 #6

To BBUCabinet

AWG #6

x 3[800Mhz & 2.5Ghz]

Power cable : AWG #6 , 2C

Cable AWG #4 , #6converte AWG #10

800MHz& 2.5Ghz

Optic cable : LC/PC * 4ea + spare 1ea

800MH

[Future Used]

Water-proof C

length : 5m

800MHz& 2.5Ghz

[Future Used]

Cap

[ Cable AWG convertor] All Power cable : AWG #10 , 2C * 4ea

Page 62: 5-Apr-11 Sprint MMBS Installation Guide1

Confidential

Ref. Hybrid cable lengthRef. Hybrid cable lengthConfidential

2 t

1sector

2sector

5.0m

Cable length is changed by the RRU location.

Y

2 5m

User Space

3sector

X2

2.5m

Grounding Need the RRU height but Tower

height.

Cabling Space

X1

61Cable length = X1 + X2

Page 63: 5-Apr-11 Sprint MMBS Installation Guide1

Confidential

RRU cable connection (example)Confidential

Unit: mmThere are 3 Type RRU .

RU cabling window Figure differ 3RRU .

Depending RRUs

Depending RRUs

< Cable Gland >D di RRU • Maker : PFLITSCH http://www.pflitsch.de/

• P/N : 22052y, 13 (M20, 13 ~ 9mm)

SHOT BOOT

200(Max)5~6

AWG10

< RRU >

Depending RRUs

Bending radius

Insulator color

“-48V”→( blue )

“GND”→( red )

20(max)insulator

Optic core No. :5

Φ5.5±0.5

=R 20

Φ12±0.5

< Power Cable >Note. This picture is similar sample

< Optic Cable >62

Page 64: 5-Apr-11 Sprint MMBS Installation Guide1

Confidential

Ref. UADUConfidential

WiMAX Only

LTE Only

CDMA Only

CDMA + LTE

63

Page 65: 5-Apr-11 Sprint MMBS Installation Guide1

ConfidentialConfidential

Power

CDMA Only

OPTIC(L0~L5)

GPSUDABH0BH1

OPTICPower

OPTIC(L0 L5)BH1UDE

EDSG

LTE Only

UDABH0

GPSBH2

64

BH1UDE0UDE1

BH1RECEDGB

Page 66: 5-Apr-11 Sprint MMBS Installation Guide1

ConfidentialConfidential

OPTICPower

WiMAX Only

UDABH0BH1

GPSBH2BH1BH1

UDE0UDE1

OPTIC

BH1RECEDGB

Power

CDMA + LTE

GPSUDABH0

65

OPTIC(L0~L5)BH1UDE

EDSG

Page 67: 5-Apr-11 Sprint MMBS Installation Guide1

Confidential

Ref. Single Solution CabinetConfidential

PDP

Battery Circuit Breaker

Rectifier

WiMAXTD LTE/FDD LTETD-LTE/FDD LTE

CDMACDMA/FDD LTE

AC circuit

12 DC Circuit Breaker

User Space

User space

AC circuit breaker

Cabling Space

Cabling Space6 Conduits

66

[BBU Single Cabinet]

Note. This data could be revised while designing in detail.