DAFTAR UPAH PEKERJA
UPAH PEKERJA H A R G A
M a n d o r @ Rp. 85,000 / hariP e k e r j a @ Rp. 55,000 / hariTukang kayu @ Rp. 75,000 / hariTukang cat @ Rp. 75,000 / hariTukang batu @ Rp. 70,000 / hariTukang gali @ Rp. 70,000 / hariTukang politur / Melamik @ Rp. 75,000 / hariUpah Kerja Besi Beton @ Rp. 75,000 / kgBiaya Fabrikasi Baja @ Rp. 600 / kgBiaya Erection Baja @ Rp. 900 / kgBiaya Cat Zinkromate Baja @ Rp. 500 / kgBiaya Pemadatan Tanah @ Rp. 15,000 / m3Upah Kerja Beton @ Rp. 30,000 / m3Sewa Pompa Beton @ Rp. 3,700,000 / 8 jam
DAFTAR HARGA BAHAN
BAHAN / MATERIAL H A R G A
BATU : Batako @ Rp. 2,500 / buah
Bata Merah @ Rp. 545 / buahBESI / BAJA :
Besi Beton @ Rp. 9,000 / kg BAJA WF @ Rp. 9,800 / kg
BAJA CNP @ Rp. 9,000 / kg
BETON : Ready Mix K.300 @ Rp. 780,000 / m3
Floor Deck Tebal 1 mm ex. Cahaya Deck @ Rp. 150,000 / m2
Kayu Bekisting @ Rp. 2,800,000 / m3Kawat beton @ Rp. 13,600 / kgKeramik 30x30 putih @ Rp. 42,000 / m2
VALVE (Kitz, Toyo, Versa) : Gate Valve dia 20 mm @ Rp. / buah Gate Valve dia 40 mm @ Rp. / buah Gate Valve dia 80 mm @ Rp. / buah Ball Valve dia 20 mm @ Rp. / buah Ball Valve dia 40 mm @ Rp. / buah
Strainer dia 80 mm @ Rp. / buah Check Valve dia 80 mm @ Rp. / buah
Foot Valve dia 80 mm @ Rp. / buah Press Gauge @ Rp. / buah
Pipa GIP Medium : Dia 150 mm ( 6" ) @ Rp. / m1 Dia 100 mm ( 4" ) @ Rp. / m1 Dia 80 mm ( 3" ) @ Rp. / m1 Dia 50 mm ( 2" ) @ Rp. / m1 Dia 40 mm ( 1,5" ) @ Rp. / m1 Dia 20 mm ( 3/4" ) @ Rp. / m1
Pipa PPR PN 10 : Dia 80 mm ( 3" ) @ Rp. / m1 Dia 50 mm ( 2" ) @ Rp. / m1 Dia 40 mm ( 1,5" ) @ Rp. / m1 Dia 20 mm ( 3/4" ) @ Rp. / m1
Pipa PVC AW : Dia 200 mm ( 8" ) @ Rp. / m1 Dia 150 mm ( 6" ) @ Rp. / m1 Dia 100 mm ( 4" ) @ Rp. / m1 Dia 80 mm ( 3" ) @ Rp. / m1 Dia 65 mm ( 2,5" ) @ Rp. / m1 Dia 50 mm ( 2" ) @ Rp. / m1
DATA RENCANA ANGGARAN BIAYA (RAB)
PROJECT : HOTEL GRAND PRIMA CIREBON LOCATION : JL. SILIWANGI 105 - 107, CIREBON 45124 LINGKUP PEKERJAAN : PONDASI - STRUKTUR - PLUMBING
NO. WORK ITEMS PENAWARAN HARGA
BOBOT % UNIT PRICE AMOUNT
I PEKERJAAN PERSIAPAN DAN TANAH 1,186,646,400 6.5316
II PEKERJAAN STRUKTUR 14,939,503,456 II. 1 PEKERJAAN TIANG PANCANG 1,902,820,500 10.4736 II. 2 PEKERJAAN PONDASI DAN STRUKTUR LANTAI DASAR 3,760,105,817
A PEKERJAAN GALIAN DAN URUGAN 79,238,125 0.4361B PEKERJAAN PILE CAP 553,012,481 3.0439C PEKERJAAN PLAT LANTAI 922,814,640 5.0794D PEKERJAAN TIE BEAM (SLOOF) 1,018,265,489 5.6048E PEKERJAAN TANGGA 70,416,832 0.3876F PEKERJAAN KOLOM 995,110,161 5.4773G PEKERJAAN PITLIFT 121,248,088 0.6674
II. 3 PEKERJAAN STRUKTUR LANTAI 1 1,667,547,368 A PEKERJAAN BALOK 788,608,682 4.3407B PEKERJAAN KOLOM 309,187,284 1.7018C PEKERJAAN PLAT BETON DAN TANGGA 569,751,402 3.1361D PEKERJAAN BAJA (KANOPI DEPAN) - -
II. 4 PEKERJAAN STRUKTUR LANTAI MEZZANINE 1,932,514,102 10.637 II. 5 PEKERJAAN STRUKTUR LANTAI DUA 1,580,314,004
A PEKERJAAN BALOK 795,607,830 4.3792B PEKERJAAN KOLOM 216,696,341 1.1928C PEKERJAAN PLAT BETON DAN TANGGA 568,009,833 3.1265D PEKERJAAN CANOPY - -
II. 6 PEKERJAAN STRUKTUR LANTAI 3 1,394,142,726 A PEKERJAAN BALOK 675,941,718 3.7206B PEKERJAAN KOLOM 214,428,451 1.1803C PEKERJAAN PLAT BETON DAN TANGGA 503,772,557 2.7729
II. 7 PEKERJAAN STRUKTUR LANTAI PH 1,360,853,891 A PEKERJAAN BALOK 662,635,786 3.6473B PEKERJAAN KOLOM 194,450,601 1.0703C PEKERJAAN PLAT BETON DAN TANGGA 503,767,505 2.7729
II. 8 PEKERJAAN STRUKTUR LANTAI ATAP 1,177,591,693 A PEKERJAAN BALOK 637,024,868 3.5063B PEKERJAAN KOLOM 34,246,224 0.1885C PEKERJAAN PLAT BETON 506,320,601 2.7869
II. 9 PEKERJAAN STRUKTUR DAK ATAP 163,613,354 A PEKERJAAN BALOK 72,354,069 0.3983B PEKERJAAN PLAT BETON 91,259,285 0.5023
IV PEKERJAAN PLUMBING 2,041,633,780 IV. 1 PEKERJAAN DEEP WEEL 441,871,000 2.4322 IV. 2 PEKERJAAN POMPA UTAMA 738,652,000 4.0657 IV. 3 PEMIPAAN & INST. INCLUDE ASSESORIES BERIKUT MATERIAL 451,658,780
A INSTALASI DAN PEMIPAAN RUANG POMPA 45,343,000 0.2496B INSTALASI DAN PEMIPAAN AIR BERSIH 142,934,200 0.7867C INSTALASI DAN PEMIPAAN AIR LIMBAH 65,465,000 0.3603D INSTALASI DAN PEMIPAAN AIR HUJAN 108,216,000 0.5956E INSTALASI DAN PEMIPAAN AIR PANAS 89,700,580 0.4937
IV. 4 PEMIPAAN & INST. STP INCLUDE ASSESORIES BERIKUT MATERIAL BANT 409,452,000 2.2538
A SUB TOTAL 18,167,783,636 100.0000
B JASA KONTRAKTOR (Management Fee) 10% 1,816,778,364
C TOTAL 19,984,562,000
D PPN 10% 1,998,456,200
E GRAND TOTAL (Rounded) 21,983,018,200
PEMBULATAN 21,983,020,000
LAMA WAKTU PEKERJAAN 8 BULAN KALENDER
DATA ANALISIS BIAYA PELAKSANAAN DILAPANGAN
PROJECT : HOTEL GRAND PRIMA CIREBON LOCATION : JL. SILIWANGI 105 - 107, CIREBON 45124 LINGKUP PEKERJAAN : PONDASI - STRUKTUR - PLUMBING
NO. WORK ITEMS PENAWARAN HARGA
BOBOT % UNIT PRICE AMOUNT
I PEKERJAAN PERSIAPAN DAN TANAH 1,207,460,200 6.5316
II PEKERJAAN STRUKTUR 14,231,500,977 II. 1 PEKERJAAN TIANG PANCANG 1,902,820,500 10.4736 II. 2 PEKERJAAN PONDASI DAN STRUKTUR LANTAI DASAR 3,730,875,911
A PEKERJAAN GALIAN DAN URUGAN 70,889,808 0.4361B PEKERJAAN PILE CAP 551,140,576 3.0439C PEKERJAAN PLAT LANTAI 910,873,428 5.0794D PEKERJAAN TIE BEAM (SLOOF) 1,031,941,770 5.6048E PEKERJAAN TANGGA 69,903,202 0.3876F PEKERJAAN KOLOM 976,291,968 5.4773G PEKERJAAN PITLIFT 119,835,159 0.6674
II. 3 PEKERJAAN STRUKTUR LANTAI 1 1,638,944,910 A PEKERJAAN BALOK 775,342,321 4.3407B PEKERJAAN KOLOM 301,080,352 1.7018C PEKERJAAN PLAT BETON DAN TANGGA 562,522,237 3.1361D PEKERJAAN BAJA (KANOPI DEPAN) - -
II. 4 PEKERJAAN STRUKTUR LANTAI MEZZANINE 1,369,875,702 10.637 II. 5 PEKERJAAN STRUKTUR LANTAI DUA 1,557,719,904
A PEKERJAAN BALOK 783,354,804 4.3792B PEKERJAAN KOLOM 212,521,527 1.1928C PEKERJAAN PLAT BETON DAN TANGGA 561,843,572 3.1265D PEKERJAAN CANOPY - -
II. 6 PEKERJAAN STRUKTUR LANTAI 3 1,372,399,066 A PEKERJAAN BALOK 664,699,558 3.7206B PEKERJAAN KOLOM 210,305,463 1.1803C PEKERJAAN PLAT BETON DAN TANGGA 497,394,045 2.7729
II. 7 PEKERJAAN STRUKTUR LANTAI PH 1,339,702,435 A PEKERJAAN BALOK 651,599,078 3.6473B PEKERJAAN KOLOM 190,714,225 1.0703C PEKERJAAN PLAT BETON DAN TANGGA 497,389,132 2.7729
II. 8 PEKERJAAN STRUKTUR LANTAI ATAP 1,158,060,496 A PEKERJAAN BALOK 626,165,609 3.5063B PEKERJAAN KOLOM 33,043,348 0.1885C PEKERJAAN PLAT BETON 498,851,539 2.7869
II. 9 PEKERJAAN STRUKTUR DAK ATAP 161,102,053 A PEKERJAAN BALOK 71,004,099 0.3983B PEKERJAAN PLAT BETON 90,097,954 0.5023
IV PEKERJAAN PLUMBING 2,034,773,780 IV. 1 PEKERJAAN DEEP WEEL 441,871,000 2.4322 IV. 2 PEKERJAAN POMPA UTAMA 731,792,000 4.0657 IV. 3 PEMIPAAN & INST. INCLUDE ASSESORIES BERIKUT MATERIAL 451,658,780
A INSTALASI DAN PEMIPAAN RUANG POMPA 45,343,000 0.2496B INSTALASI DAN PEMIPAAN AIR BERSIH 142,934,200 0.7867C INSTALASI DAN PEMIPAAN AIR LIMBAH 65,465,000 0.3603D INSTALASI DAN PEMIPAAN AIR HUJAN 108,216,000 0.5956E INSTALASI DAN PEMIPAAN AIR PANAS 89,700,580 0.4937
IV. 4 PEMIPAAN & INST. STP INCLUDE ASSESORIES BERIKUT MATERIAL BANT 409,452,000 2.2538
A SUB TOTAL 17,473,734,957 100.0000
B JASA KONTRAKTOR (Management Fee) 10% 1,747,373,496
C TOTAL 19,221,108,453
D PPN 10% 1,922,110,845
E GRAND TOTAL (Rounded) 21,143,219,298
PEMBULATAN 21,143,220,000
LAMA WAKTU PEKERJAAN 8 BULAN KALENDER
BIAYA PELAKSANAAN PROYEK
Biaya Langsung
Biaya Total pada Progress Minggu Ke 50 = Rp -
Biaya Tidak Langsung (Biaya Over Head)
1 Gaji Karyawan dan Staf dilapangan = Rp 32,622,750 / BlnSite Manager 1 OrangSite Engineer 1 OrangEngineer 1 OrangSurveyor 2 OrangSupervisor 3 Orang
2 Keamanan dan Keselamatan Lokasi Proyek = Rp 10,500,000 / BlnSecurity 6 Orang
3 Biaya OperasionalKebutuhan A(Menggunakan Sumb. Air Tanah) = Rp - / BlnKebutuhan Listrik = Rp 4,500,000 / BlnKebutuhan Telpon = Rp 850,000 / Bln
4 Perumahan Tenaga KerjaKostan Karyawan = Rp 4,500,000 / Bln
5 Pengurusan Izin dan Pajak PPN, PPh(Owner) = Rp - / Bln
6 Pengurusan Keanggotaan Jamsostek = Rp 21,534,562 / Thn
Maka Biaya Over Head Total = Rp 54,767,297 / Bln
REKAP LAP. PROGRES MINGGUAN
PROJECT : HOTEL GRAND PRIMA CIREBON LOCATION : JL. SILIWANGI 105 - 107, CIREBON 45124 LINGKUP PEKERJAAN : PONDASI - STRUKTUR - PLUMBING
NO. WORK ITEMS UNIT PRICE BOBOT % Mg Ke-1 Mg Ke-2 Mg Ke-3 Mg Ke-4
BOBOT % BIAYA Rp BOBOT % BIAYA Rp BOBOT % BIAYA Rp BOBOT % BIAYA Rp
I PEKERJAAN PERSIAPAN DAN TANAH 1,186,646,400 6.5316 0.1000 18,167,775 0.1000 18,167,775 0.1000 18,167,775 0.1000 18,167,775
II PEKERJAAN STRUKTUR II. 1 PEKERJAAN TIANG PANCANG 1,902,820,500 10.4736 - - - - - - 1.1600 210,746,236 II. 2 PEKERJAAN PONDASI DAN STRUKTUR LANTAI DASAR 3,760,105,817 20.6965 - - - - - - - -
A PEKERJAAN GALIAN DAN URUGAN 79,238,125 0.4361B PEKERJAAN PILE CAP 553,012,481 3.0439C PEKERJAAN PLAT LANTAI 922,814,640 5.0794D PEKERJAAN TIE BEAM (SLOOF) 1,018,265,489 5.6048E PEKERJAAN TANGGA 70,416,832 0.3876F PEKERJAAN KOLOM 995,110,161 5.4773G PEKERJAAN PITLIFT 121,248,088 0.6674
II. 3 PEKERJAAN STRUKTUR LANTAI 1 1,667,547,368 9.1786 - - - - - - - - A PEKERJAAN BALOK 788,608,682 4.3407B PEKERJAAN KOLOM 309,187,284 1.7018C PEKERJAAN PLAT BETON DAN TANGGA 569,751,402 3.1361D PEKERJAAN BAJA (KANOPI DEPAN) - -
II. 4 PEKERJAAN STRUKTUR LANTAI MEZZANINE 1,932,514,102 10.637 - - - - - - - - II. 5 PEKERJAAN STRUKTUR LANTAI DUA 1,580,314,004 8.6985 - - - - - - - -
A PEKERJAAN BALOK 795,607,830 4.3792B PEKERJAAN KOLOM 216,696,341 1.1928C PEKERJAAN PLAT BETON DAN TANGGA 568,009,833 3.1265D PEKERJAAN CANOPY - -
II. 6 PEKERJAAN STRUKTUR LANTAI 3 1,394,142,726 7.6738 - - - - - - - - A PEKERJAAN BALOK 675,941,718 3.7206B PEKERJAAN KOLOM 214,428,451 1.1803C PEKERJAAN PLAT BETON DAN TANGGA 503,772,557 2.7729
II. 7 PEKERJAAN STRUKTUR LANTAI PH 1,360,853,891 7.4905 - - - - - - - - A PEKERJAAN BALOK 662,635,786 3.6473B PEKERJAAN KOLOM 194,450,601 1.0703C PEKERJAAN PLAT BETON DAN TANGGA 503,767,505 2.7729
II. 8 PEKERJAAN STRUKTUR LANTAI ATAP 1,177,591,693 6.4817 - - - - - - - - A PEKERJAAN BALOK 637,024,868 3.5063B PEKERJAAN KOLOM 34,246,224 0.1885C PEKERJAAN PLAT BETON 506,320,601 2.7869
II. 9 PEKERJAAN STRUKTUR DAK ATAP 163,613,354 0.9006 - - - - - - - - A PEKERJAAN BALOK 72,354,069 0.3983B PEKERJAAN PLAT BETON 91,259,285 0.5023
IV PEKERJAAN PLUMBING IV. 1 PEKERJAAN DEEP WEEL 441,871,000 2.4322 - - - - - - - - IV. 2 PEKERJAAN POMPA UTAMA 738,652,000 4.0657 - - - - - - - - IV. 3 PEMIPAAN & INST. INCLUDE ASSESORIES BERIKUT MATERIAL 451,658,780 2.4859 - - - - - - - -
A INSTALASI DAN PEMIPAAN RUANG POMPA 45,343,000 0.2496B INSTALASI DAN PEMIPAAN AIR BERSIH 142,934,200 0.7867C INSTALASI DAN PEMIPAAN AIR LIMBAH 65,465,000 0.3603D INSTALASI DAN PEMIPAAN AIR HUJAN 108,216,000 0.5956E INSTALASI DAN PEMIPAAN AIR PANAS 89,700,580 0.4937
IV. 4 PEMIPAAN & INST. STP INCLUDE ASSESORIES BERIKUT MATERIAL BANTU 409,452,000 2.2538 - - - - - - - - SUB TOTAL 18,167,783,635
AKTUAL PRESTASI SETIAP MINGGU 0.1000 0.1000 0.1000 1.2600 AKUMULASI AKTUAL PRESTASI SETIAP MINGGU 0.1000 0.2000 0.3000 1.5600
TOTAL 18,167,775 18,167,775 18,167,775 228,914,011
PROJECT : HOTEL GRAND PRIMA CIREBON LOCATION : JL. SILIWANGI 105 - 107, CIREBON 45124 LINGKUP PEKERJAAN : PONDASI - STRUKTUR - PLUMBING
NO. WORK ITEMS UNIT PRICE BOBOT % Mg Ke-1 Mg Ke-2 Mg Ke-3 Mg Ke-4
BOBOT % BIAYA Rp BOBOT % BIAYA Rp BOBOT % BIAYA Rp BOBOT % BIAYA Rp
I PEKERJAAN PERSIAPAN DAN TANAH 1,186,646,400 6.5316 0.1685 30,612,701 1.6016 290,975,086 0.0640 11,627,376 0.0655 11,899,893
II PEKERJAAN STRUKTUR II. 1 PEKERJAAN TIANG PANCANG 1,902,820,500 10.4736 - - - - - - - - II. 2 PEKERJAAN PONDASI DAN STRUKTUR LANTAI DASAR 3,760,105,817
A PEKERJAAN GALIAN DAN URUGAN 79,238,125 0.4361 - - - - - - - - B PEKERJAAN PILE CAP 553,012,481 3.0439 - - - - 0.1351 24,544,823 - - C PEKERJAAN PLAT LANTAI 922,814,640 5.0794 - - - - - - - - D PEKERJAAN TIE BEAM (SLOOF) 1,018,265,489 5.6048 - - - - - - - - E PEKERJAAN TANGGA 70,416,832 0.3876 - - - - - - - - F PEKERJAAN KOLOM 995,110,161 5.4773 - - - - 0.0909 16,514,617 0.0290 5,268,690 G PEKERJAAN PITLIFT 121,248,088 0.6674 - - - - - - - -
II. 3 PEKERJAAN STRUKTUR LANTAI 1 1,667,547,368 - - - - - - A PEKERJAAN BALOK 788,608,682 4.3407 - - - - - - - - B PEKERJAAN KOLOM 309,187,284 1.7018 - - - - - - - - C PEKERJAAN PLAT BETON DAN TANGGA 569,751,402 3.1361 - - - - - - - - D PEKERJAAN BAJA (KANOPI DEPAN) - - - - - - - - - -
II. 4 PEKERJAAN STRUKTUR LANTAI MEZZANINE 1,932,514,102 10.637 - - - - - - 0.1936 35,172,956 II. 5 PEKERJAAN STRUKTUR LANTAI DUA 1,580,314,004
II. 6 PEKERJAAN STRUKTUR LANTAI 3 1,394,142,726 A PEKERJAAN BALOK 675,941,718 3.7206 - - - - - - - - B PEKERJAAN KOLOM 214,428,451 1.1803 - - - - - - - - C PEKERJAAN PLAT BETON DAN TANGGA 503,772,557 2.7729 - - - - - - - -
II. 7 PEKERJAAN STRUKTUR LANTAI PH 1,360,853,891 A PEKERJAAN BALOK 662,635,786 3.6473 - - - - - - - - B PEKERJAAN KOLOM 194,450,601 1.0703 - - - - - - - - C PEKERJAAN PLAT BETON DAN TANGGA 503,767,505 2.7729 - - - - - - - -
II. 8 PEKERJAAN STRUKTUR LANTAI ATAP 1,177,591,693 A PEKERJAAN BALOK 637,024,868 3.5063 - - - - - - - - B PEKERJAAN KOLOM 34,246,224 0.1885 - - - - - - - - C PEKERJAAN PLAT BETON 506,320,601 2.7869 - - - - - - - -
II. 9 PEKERJAAN STRUKTUR DAK ATAP 163,613,354 A PEKERJAAN BALOK 72,354,069 0.3983 - - - - - - - - B PEKERJAAN PLAT BETON 91,259,285 0.5023 - - - - - - - -
IV PEKERJAAN PLUMBING IV. 1 PEKERJAAN DEEP WEEL 441,871,000 2.4322 - - - - - - - - IV. 2 PEKERJAAN POMPA UTAMA 738,652,000 4.0657 - - - - - - - - IV. 3 PEMIPAAN & INST. INCLUDE ASSESORIES BERIKUT MATERIAL 451,658,780
A INSTALASI DAN PEMIPAAN RUANG POMPA 45,343,000 0.2496 - - - - - - - - B INSTALASI DAN PEMIPAAN AIR BERSIH 142,934,200 0.7867 - - - - - - - - C INSTALASI DAN PEMIPAAN AIR LIMBAH 65,465,000 0.3603 - - - - - - - - D INSTALASI DAN PEMIPAAN AIR HUJAN 108,216,000 0.5956 - - - - - - - - E INSTALASI DAN PEMIPAAN AIR PANAS 89,700,580 0.4937 - - - - - - - -
IV. 4 PEMIPAAN & INST. STP INCLUDE ASSESORIES BERIKUT MATERIAL BANTU 409,452,000 2.2538 - - - - - - - - SUB TOTAL 18,167,783,635
AKTUAL PRESTASI SETIAP MINGGU 0.1685 1.6016 0.2900 0.2881 AKUMULASI AKTUAL PRESTASI SETIAP MINGGU 0.1685 1.7701 2.0601 2.3482
TOTAL 30,612,701 290,975,086 52,686,816 52,341,538
PROJECT : HOTEL GRAND PRIMA CIREBON LOCATION : JL. SILIWANGI 105 - 107, CIREBON 45124 LINGKUP PEKERJAAN : PONDASI - STRUKTUR - PLUMBING
NO. WORK ITEMS UNIT PRICE BOBOT % Mg Ke-1 Mg Ke-2 Mg Ke-3 Mg Ke-4
BOBOT % BIAYA Rp BOBOT % BIAYA Rp BOBOT % BIAYA Rp BOBOT % BIAYA Rp
I PEKERJAAN PERSIAPAN DAN TANAH 1,207,460,200 6.5316 0.1685 31,149,648 1.6016 296,078,795 0.0640 11,831,320 0.0655 12,108,617
II PEKERJAAN STRUKTUR II. 1 PEKERJAAN TIANG PANCANG 1,902,820,500 10.4736 - - - - - - - - II. 2 PEKERJAAN PONDASI DAN STRUKTUR LANTAI DASAR 3,730,875,911
A PEKERJAAN GALIAN DAN URUGAN 70,889,808 0.4361 - - - - - - - - B PEKERJAAN PILE CAP 551,140,576 3.0439 - - - - 0.1351 24,461,740 - - C PEKERJAAN PLAT LANTAI 910,873,428 5.0794 - - - - - - - - D PEKERJAAN TIE BEAM (SLOOF) 1,031,941,770 5.6048 - - - - - - - - E PEKERJAAN TANGGA 69,903,202 0.3876 - - - - - - - - F PEKERJAAN KOLOM 976,291,968 5.4773 - - - - 0.0909 16,202,315 0.0290 5,169,055 G PEKERJAAN PITLIFT 119,835,159 0.6674 - - - - - - - -
II. 3 PEKERJAAN STRUKTUR LANTAI 1 1,638,944,910 - - - - - - A PEKERJAAN BALOK 775,342,321 4.3407 - - - - - - - - B PEKERJAAN KOLOM 301,080,352 1.7018 - - - - - - - - C PEKERJAAN PLAT BETON DAN TANGGA 562,522,237 3.1361 - - - - - - - - D PEKERJAAN BAJA (KANOPI DEPAN) - - - - - - - - - -
II. 4 PEKERJAAN STRUKTUR LANTAI MEZZANINE 1,369,875,702 10.637 - - - - - - 0.1936 24,932,588 II. 5 PEKERJAAN STRUKTUR LANTAI DUA 1,557,719,904
II. 6 PEKERJAAN STRUKTUR LANTAI 3 1,372,399,066 A PEKERJAAN BALOK 664,699,558 3.7206 - - - - - - - - B PEKERJAAN KOLOM 210,305,463 1.1803 - - - - - - - - C PEKERJAAN PLAT BETON DAN TANGGA 497,394,045 2.7729 - - - - - - - -
II. 7 PEKERJAAN STRUKTUR LANTAI PH 1,339,702,435 A PEKERJAAN BALOK 651,599,078 3.6473 - - - - - - - - B PEKERJAAN KOLOM 190,714,225 1.0703 - - - - - - - - C PEKERJAAN PLAT BETON DAN TANGGA 497,389,132 2.7729 - - - - - - - -
II. 8 PEKERJAAN STRUKTUR LANTAI ATAP 1,158,060,496 A PEKERJAAN BALOK 626,165,609 3.5063 - - - - - - - - B PEKERJAAN KOLOM 33,043,348 0.1885 - - - - - - - - C PEKERJAAN PLAT BETON 498,851,539 2.7869 - - - - - - - -
II. 9 PEKERJAAN STRUKTUR DAK ATAP 161,102,053 A PEKERJAAN BALOK 71,004,099 0.3983 - - - - - - - - B PEKERJAAN PLAT BETON 90,097,954 0.5023 - - - - - - - -
IV PEKERJAAN PLUMBING IV. 1 PEKERJAAN DEEP WEEL 441,871,000 2.4322 - - - - - - - - IV. 2 PEKERJAAN POMPA UTAMA 731,792,000 4.0657 - - - - - - - - IV. 3 PEMIPAAN & INST. INCLUDE ASSESORIES BERIKUT MATERIAL 451,658,780
A INSTALASI DAN PEMIPAAN RUANG POMPA 45,343,000 0.2496 - - - - - - - - B INSTALASI DAN PEMIPAAN AIR BERSIH 142,934,200 0.7867 - - - - - - - - C INSTALASI DAN PEMIPAAN AIR LIMBAH 65,465,000 0.3603 - - - - - - - - D INSTALASI DAN PEMIPAAN AIR HUJAN 108,216,000 0.5956 - - - - - - - - E INSTALASI DAN PEMIPAAN AIR PANAS 89,700,580 0.4937 - - - - - - - -
IV. 4 PEMIPAAN & INST. STP INCLUDE ASSESORIES BERIKUT MATERIAL BANTU 409,452,000 2.2538 - - - - - - - - SUB TOTAL 17,473,734,957
AKTUAL PRESTASI SETIAP MINGGU 0.1685 1.6016 0.2900 0.2881 AKUMULASI AKTUAL PRESTASI SETIAP MINGGU 0.1685 1.7701 2.0601 2.3482
TOTAL 31,149,648 296,078,795 52,495,376 42,210,260
Biaya Aktual di lapangan pada Minggu ke-50dengan Progres Pekerjaan = 75.337 % x Rp 17,473,734,957 = Rp13,164,187,704.56
Prakiraan sisa Biaya Pekerjaan (ETC)Sisa Progres Pekerjaan = 24.663 % x Rp 17,473,734,957 = Rp 4,309,547,252 Biaya Over Head = 8 Bln x Rp 54,767,296.83 /Bln = Rp 438,138,375
Rp 4,747,685,627
`Biaya yang diperlukan sampai Pekerjaan PSP selesai adalah EAC = Rp17,911,873,331.67