4D bim construction scheduling on the 1885 St. James pl. project

Apr 12, 2017

Download

Real Estate

Dat Lien
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: 4D bim construction scheduling on the 1885 St. James pl. project
Page 2: 4D bim construction scheduling on the 1885 St. James pl. project

4D BIM Construction Scheduling on the 1885 St. James Pl. Project

● Dat Lien, President, Axoscape● Xavier Loayza, BIM Specialist, Axoscape

Page 3: 4D bim construction scheduling on the 1885 St. James pl. project
Page 4: 4D bim construction scheduling on the 1885 St. James pl. project

AgendaThe Project4D BIM IntroductionThe BIM modelThe ScheduleThe workflowOutputs

Page 5: 4D bim construction scheduling on the 1885 St. James pl. project

Nelson Murphree Legacy Partners15-story boutique office tower165,146-square-foot buildingNine floors of office spacesix levels of parkingUSGBC: LEED SilverArchitect: Jackson & RyanGC: Tellepsen BuildersBIM Consultant: Axoscape

1885 St. James Pl

Page 6: 4D bim construction scheduling on the 1885 St. James pl. project

The ProblemLimited SpaceExpensive Mast ClimbersComplex ScheduleCommunication

Page 7: 4D bim construction scheduling on the 1885 St. James pl. project

Mast Climber Layout

Floors 1 - 15

Floors 7 - 13

Page 8: 4D bim construction scheduling on the 1885 St. James pl. project

4D BIM for Pre-Construction Planning 3D + Time

Page 9: 4D bim construction scheduling on the 1885 St. James pl. project

BIM Model•Arch model(str+exterior+ext blockwall+ext stone + drywall model/framing•Dry-wall model 3d

Page 10: 4D bim construction scheduling on the 1885 St. James pl. project

BIM model and ScheduleLevel Of Detail (BIM) ≈ Level Of Detail (Schedule)

Page 11: 4D bim construction scheduling on the 1885 St. James pl. project

The SchedulerSelecting the Activities to perform

Page 12: 4D bim construction scheduling on the 1885 St. James pl. project

The ScheduleBuild on Critical path Method (CPM) base

Input by Linear Scheduling Method (LSM)

Sub-contractor Input (rates)

Page 13: 4D bim construction scheduling on the 1885 St. James pl. project

The Schedule: Activity Flow

Page 14: 4D bim construction scheduling on the 1885 St. James pl. project

The SchedulerCrew sizing

Page 15: 4D bim construction scheduling on the 1885 St. James pl. project

The Workflow

Page 16: 4D bim construction scheduling on the 1885 St. James pl. project

The Workflow1. Create Selection Sets 2. Create Activities from

Selection Sets

Page 17: 4D bim construction scheduling on the 1885 St. James pl. project

The Workflow3. Export Timeliner to MS Project

Page 18: 4D bim construction scheduling on the 1885 St. James pl. project

The Workflow4. Build the schedule based on the activities created in Navisworks

Page 19: 4D bim construction scheduling on the 1885 St. James pl. project

The Workflow5. Link the New schedule to Navisworks

6. Map the Activities to the Selection Sets

Page 21: 4D bim construction scheduling on the 1885 St. James pl. project

Q & A