Top Banner

of 25

4 Meth for C1BA Preparation

Aug 07, 2018

Download

Documents

kopalko77
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • 8/20/2019 4 Meth for C1BA Preparation

    1/25

    Methodology for CBA preparationSOP Environment

    Programming Meeting for water and wastewater projectsin the period 2008-2009

    Mamaia, 10-13th July 2008

    Massimo Marra

    JASPERS Regional Office for Romania and Bulgaria

  • 8/20/2019 4 Meth for C1BA Preparation

    2/25

    2

    JASPERS activities

    ‘Joint Assistance to Support Projects in European Regions’ Advisory services to MAs and Final Beneficiaries – EC/EIB/EBRD

    √ Objectives: increase the capacity of beneficiary countries, supportthem to make best use of EU funding, improve/speed up fundabsorption

    JASPERS concentrates on Major Projects :

    - Transport and other sectors  €50 M > capital cost- Environment €25 M > capital cost

    JASPERS priorities are :

    - large projects supported by Cohesion Fund and ERDF- other Cohesion Fund projects- other ERDF projects

    Horizontal Issues covering more than one country/sector (as CBA)

  • 8/20/2019 4 Meth for C1BA Preparation

    3/25

    3

    What does JASPERS offer?

    Assistance from early stages of project through to thedecision to grant assistance

    Preparatory work required to deliver a mature project e.g. Advice on conceptual development and project structuring

    Advice on project preparation e.g. cost-benefit analysis, financial

    analysis, environmental issues, procurementplanning.

    Review of documentation: feasibility studies, technicaldesign, tender documents.

    Advice on compliance with EU law (environmental,competition and others) and conformity with EU policies

  • 8/20/2019 4 Meth for C1BA Preparation

    4/25

  • 8/20/2019 4 Meth for C1BA Preparation

    5/25

    5

    National CBA Guidelines

    Being developed jointly by Romanian Authorities (MESD – MEF)and JASPERS

    National CBA Guidelines to be consistent with EC and Romanianrequirements (HG 28/2008)

    Valid for ALL projects co-financed by Structural Funds

    General CBA Guidance document Rationale and objectives

    What is a CBA and why/when perform it (small projects) General methodological Approach (discount rates, reference period, etc.)

    Macroeconomic assumptions and data to be used

    Valid for all sectors

    To be formally embedded in national approval process

    Sectoral CBA Guidelines for Water, Transport, SW and Energy Strategic approach and definition of objectives Project identification and demand assessment

    Feasibility and Option Analysis

    Financial Projections

    Economic Analysis

    Risk and Sensitivity analysis

    Conclusions and presentation of results

  • 8/20/2019 4 Meth for C1BA Preparation

    6/25

    6

    STRUCTURE OF CBASTRUCTURE OF CBASTRUCTURE OF CBASTRUCTURE OF CBA

    1. Option and Feasibility Analysis1. Option and Feasibility Analysis1. Option and Feasibility Analysis1. Option and Feasibility AnalysisHow can an objective be achieved? Are the selected optionsfeasible?

    2. Financial Analysis2. Financial Analysis2. Financial Analysis2. Financial AnalysisDoes the project need cofinancing?Does the project need cofinancing?Does the project need cofinancing?Does the project need cofinancing? How much money isnecessary to implement the option selected?

    3. Economic Analysis3. Economic Analysis3. Economic Analysis3. Economic Analysis

    Is the project worth cofinancing?Is the project worth cofinancing?Is the project worth cofinancing?Is the project worth cofinancing? What is the impact on thearea where the project is going to be implemented?

    4. Risk Analysis4. Risk Analysis4. Risk Analysis4. Risk AnalysisWhich are the most likely financial and economic results?

    CBA mainelementsCBA mainelements

    General CBA Structure

  • 8/20/2019 4 Meth for C1BA Preparation

    7/25

    7

    Sequence of CBA – Water/WW projects

      Strategic approach and definition of objectives 

      Project identification and Option Analysis 

      Financial Projections 

      Economic Analysis 

      Risk and Sensitivity analysis 

      Conclusions and presentation of results 

  • 8/20/2019 4 Meth for C1BA Preparation

    8/25

    8

    Strategic approach

    Main strategic drivers

    Compliance with EC Directives

    Improvement of water resource management(Regionalisation)

    Expected impact on regional development

    Project must be consistent with National policy,

    NSRF and SOP priority areas

    Project to support the achievement of SOPobjectives

  • 8/20/2019 4 Meth for C1BA Preparation

    9/25

    9

    Definition of Project Objectives

    Objective 1 Provide adequate water and sewerage services, at accessible tariffs

    Objective 2 Provide adequate drinking water quality in all urban agglomerations

    Objective 3 Improve the purity of watercourses

    Objective 4 Improve of the level of WWTP sludge management

    Objective 5 Create innovative and efficient water management structures

    SOP Objectives – Priority Axis 1

    Example Project Objectives

    Specific Objective Values without project Expected value after

    completion

    1. Increase in coverage of waterand sewerage services

    % of population connected towater supply and sewerage

    systems

    % of population connected towater supply and sewerage

    systems

    2. Improvement of quality of

    drinking water to meet EU

    standards (98/83/EC)

    % of population with drinking

    water meeting EU standards

    % of population with drinking

    water meeting EU standards

    3. Increase of coverage ofwastewater treatment to meet

    Urban WWT Directive

    Number of agglomerations withadequate wastewater treatment

    Number of agglomerations withadequate wastewater treatment

    4. Establish efficient operators

    and associated structures

    (ROCs, IDAs)

    Number of ROC/IDA with

    adequate set up and capacity to

    manage water/ww systems

    Number of ROC/IDA with

    adequate set up and capacity to

    manage water/ww systems

  • 8/20/2019 4 Meth for C1BA Preparation

    10/25

    10

    Option Analysis and Selection

    Assessment of existinginfrastructures

    Identification of problems

    (How/Why objectives are not met)

    Identification of options(What can we do to meet

    objectives)

    First screening and shortlistMulticriteria analysis

    Comparison of retained options(technical and economic)

    Selection ofpreferred option

    ProjectObjectives

    Nationalpolicy and

    SOPObjectives

  • 8/20/2019 4 Meth for C1BA Preparation

    11/25

    11

    Financial Analysis

    To establish the level of financial self-sufficiency, financialperformance and sustainability of the project

    Projections of financial flows of the project for without(baseline) and with project scenarios:

    Total planned investment (including residual value)

    Revenues (demand evolution and tariff increases)

    Operating and maintenance costs (also estimate costsavings)

    In local currency and then translation into euros

    Reference period typically 30 years Financial discount rate set at 5%

    Project impact = Difference between with and withoutscenario

  • 8/20/2019 4 Meth for C1BA Preparation

    12/25

    12

    Establishing scenarios

    With Project Without project

    Macroeconomic data   Shall be valid for all projects (NSRF)

    Population dynamics   Same in both scenarios 

    Service levels

    Connections and metering rate

    Water consumption (domestic&not)

    Physical losses & infiltration

    O&M costs

    Financial performance

    EBITDA & EBIT

    Cash flows and reserves

    Debt service coverage (DSCR)

    Tariff development and Affordability

    Tariff increase steps   Polluter pays Principle!! 

    Affordability constraints   Equity considerations!! 

  • 8/20/2019 4 Meth for C1BA Preparation

    13/25

    13

    Project profitability indicators

    Incremental cash flows used to determine financialperformance indicators before and after EU grant “before” FNPV/C needs to be

  • 8/20/2019 4 Meth for C1BA Preparation

    14/25

    14

    Only for revenue generating projects (as per Art. 55 ofRegulation 1083/2006

    If project revenues do not cover O&M costs, then theproject is not revenue-generating

    Calculation based on incremental revenues and costs,and normally using constant euros

    Depreciation and contingencies not to be included

    See details in Working Document 4: Guidance on the

    Methodology for Carrying Out Cost-Benefit Analysis, preparedby the Commission in August 2006

    Funding Gap (1)

  • 8/20/2019 4 Meth for C1BA Preparation

    15/25

    15

    Funding gap rate: DIC 

     DNR DIC  R

      −

    =

    Funding

    gap

    The “funding gap” is the part of the investment cost

    which is not going to be paid back by the project netrevenue. The funding-gap rate is the complementaryto 100% of the gross self-financing margin.

    * Discounted net revenue = + discounted revenue

     – discounted operating costs + discounted residual value

    DIC: Discounted Investment cost

    DNR: Discounted Net Revenue*

    Funding gap

    R%

    Gross self-financingmargin

    (100-R)%

    Funding Gap (2)

  • 8/20/2019 4 Meth for C1BA Preparation

    16/25

    16

    Factors to consider in establishing FG

    Article 55(2):  “Eligible expenditure on revenue-generating projects shall not exceed the

    current value of the investment cost less the current value of the net revenue from the

    investment over a specific reference period (…)

    In the calculation, the managing authority shall take account of the reference period

    appropriate to the category of investment concerned, the category of project, the

    profitability normally expected of the category of investment concerned, the  application

    of the polluter-pays principle, and, if appropriate,   considerations of equity linked to

    the relative prosperity of the Member State  concerned.”

    Polluter pays principle: Scenario for tariffs should reflect the correct application ofthe Polluter Pays Principle. For Water: WFD 2000/60/EC -  Article 9. – “Member States shall take account of the  principle of recovery of the costs of water services,including environmental and resource costs , (…) in accordance in particular with the polluter pays principle.” 

    Affordability (equity): WFD 2000/60/EC - Article 9. – “Member States may in so doing have regard to the social, environmental and economic effects of the recovery […] ". Practically, total charges paid by the users for water and wastewater servicesshould not exceed certain commonly accepted thresholds.

  • 8/20/2019 4 Meth for C1BA Preparation

    17/25

    17

    Tariff setting and Affordability

    MESD policy on Affordability: 4% of income for the poorest 10% of households @ per capita 75 litres/day.

    Higher tariffs may be required if financial sustainability of ROC isendangered. In these cases, special measures to reduce the financial

    burden on the poorest households

    Total cost to

    be coveredby tariffs(Polluter

    Pays)

    Rationalefor

    FundingGap

    Affordability Limit

  • 8/20/2019 4 Meth for C1BA Preparation

    18/25

  • 8/20/2019 4 Meth for C1BA Preparation

    19/25

    19

    Economic Analysis

    Identifying benefits

    Benefits from improved access to drinking water Benefits from improved quality of bathing and surface waters

    (use and non use values)

    Resource costs savings

    Other benefits difficult to monetise

    Adjusting costs

    Fiscal corrections

    Converting financial prices into economic prices

    Add negative externalities

  • 8/20/2019 4 Meth for C1BA Preparation

    20/25

    20

    Project benefits and Negative Externalities

    Project Benefits

    Type Base for calculation Monetary value Comments

    Access to drinking water Nr. Of households inproject service area

    148 Euro/household/year(2008 value)

    Values for following years ofprojection to be increased byreal GDP growth

    Improvement of water bodies

    (use value)

    Nr. Of people living in the

    project service area

    20.4 Euro/person/year

    (2008 value)

    Values for following years of

    projection to be increased byreal GDP growth

    Improvement of water bodies(non use value)

    Nr. Of households inproject service area

    0.004 – 0.011

    Euro/household/year/KMriver

    See Annex

    Cost savings to customers   –private well

    Nr. Of households newlyconnected

    315 Euro/household/year

    Cost savings to customers   –sewage disposal

    Nr. Of households newlyconnected

    348 Euro/household/year

    Cost savings to operator  – waterabstraction

    Incremental watersavings (in m3)

    Water abstraction fee(Apele Romane)

    To be detailed in technical FS

    Cost savings to operator – energyconsumption

    CO2 emission savings (intonnes)

    From 25 Euro/tonne in 2010 to45 Euro/tonne in 2030

    To be detailed in technical FS.

    Negative Externalities

    Type Base for calculation Monetary value Comments

    Increase in CO2 emission   –sludge digestion

    CO2 emission (in tonnes) From 25 Euro/tonne in 2010 to45 Euro/tonne in 2030

    To be detailed in technical FS.

    Increase in CO2 emission   –

    sludge transportation

    CO2 emission (in tonnes) From 25 Euro/tonne in 2010 to

    45 Euro/tonne in 2030

    To be detailed in technical FS.

  • 8/20/2019 4 Meth for C1BA Preparation

    21/25

    21

    Adjusting Costs

    Economic costs (conversion factors):

  • 8/20/2019 4 Meth for C1BA Preparation

    22/25

    22

    Sensitivity and Risk Analysis (1)

    Purpose is to assess the robustness of the projectfinancial and economic profitability indicators (FRR/C,FNPV/C, ERR, ENPV)

    First, identification of key variables and their impact interms of changes in the profitability indicators

    Second, calculate “switching values” for those variablesfor which a variation of 1% results in a variation of more

    than 5% in the profitability indicators

  • 8/20/2019 4 Meth for C1BA Preparation

    23/25

    23

    Sensitivity and Risk Analysis (2)

    Finally, estimate probability distributions for theprofitability indicators based on the probabilitydistribution of all the key variables (Monte Carlo)

  • 8/20/2019 4 Meth for C1BA Preparation

    24/25

    24

    CBA Conclusions

    Standard format for presenting CBA results(Application Form info requirements)

    Does the project needs co-financing??

    Financial analysis FNPV/C

  • 8/20/2019 4 Meth for C1BA Preparation

    25/25

    25

    THANK [email protected]