-
1096 IEEE SYSTEMS JOURNAL, VOL. 8, NO. 4, DECEMBER 2014
Voltage Variation on Distribution Networks WithDistributed
Generation: Worst Case Scenario
M. A. Mahmud, Member, IEEE, M. J. Hossain, Senior Member, IEEE,
and H. R. Pota
AbstractThis paper presents an analytical approach to estab-lish
a relationship between the voltage variation and
distributedgeneration (DG) integration for the planning and
operation ofdistribution networks with DG. The proposed approach is
mainlybased on the derivation of a voltage variation formula for
distri-bution networks with DG and the consideration of the worst
casescenario, which establishes a relationship between the amount
ofvoltage variation and maximum permissible DG. Some
recommen-dations are presented based on the worst case voltage
variationformula and DG integration to counteract the voltage
variationeffect. The relationship between the connection cost and
voltagelevel is also presented in this paper. The feasibility of
the proposedapproach is validated by comparing the voltage profile
obtainedfrom the derived formula to that with the existing power
systemsimulation software.
Index TermsDistributed generation (DG), distributionsystems,
voltage variation, worst case scenario.
I. INTRODUCTION
T RADITIONALLY, distribution networks are passive net-works
where the flow of both real and reactive poweris from a higher to a
lower voltage level. The integration ofa small- and medium-sized
generation into distribution net-works is increasing as these types
of generating units offer anumber of technical, environmental, and
economical benefitsfor the utilities along with consumers due to
their locationnear to customers [1][3]. Beside these benefits, the
integrationof distributed generation (DG) units significantly
changes thebehavior of the distribution network operation, e.g.,
passivedistribution networks with a unidirectional power flow
areconverted into active distribution networks with a
bidirectionalpower flow. From the technical point of view, these
changeshave negative impacts along with positive impacts to
bothdistribution network service providers (DNSPs) and
customers.
To provide the maximum benefit and alleviate the limit
ongeneration capacity, an active network management (ANM)
ofdistribution networks or other novel approaches are needed tobe
considered, which allow the connection of more DG unitsinto the
existing distribution network [4]. An ANM in the form
Manuscript received September 30, 2011; revised June 12, 2012
and July 29,2012; accepted October 7, 2012. Date of publication
June 12, 2013; date ofcurrent version November 20, 2014.
M. A. Mahmud is with the Future Grid Research Centre, Department
of Elec-trical and Electronic Engineering, The University of
Melbourne, Melbourne,Vic. 3010, Australia (e-mail:
[email protected]).
M. J. Hossain is with Griffith School of Engineering, Griffith
University,Gold Coast, Qld. 4222, Australia (e-mail:
[email protected]).
H. R. Pota is with the School of Engineering and Information
Technology,The University of New South Wales at the Australian
Defence Force Academy,Canberra, A.C.T. 2600, Australia (e-mail:
[email protected]).
Digital Object Identifier 10.1109/JSYST.2013.2265176
of centralized control is introduced in [5] to increase the
DGconnection capacity. A centralized distribution managementsystem
controller, similar to that used in transmission networks,is
presented in [6] and [7] to maximize the DG penetration usinga
wide-area voltage control and reactive power managementapproach
where state estimations are employed to assess thevoltage level.
However, the centralized approaches presentedin [5] and [7] require
significant investment in sensors andcommunication assets, which
make their application difficult toincrease the DG penetration.
There are several alternative approaches, which include toensure
the maximum DG capacity with minimal voltage im-pacts in the
distribution network. A distributed voltage con-trol approach is
introduced in [8] to limit the voltage risein distribution feeders
by considering continuously distributedloads and generation. Some
other distributed active manage-ment approaches are presented in
[9][11] to accommodatemore DG units by controlling the power factor
rather than thevoltage control to counteract the effect of the DG
integration.However, these approaches are similar to fit-and-forget
mannerthat accommodate the full DG capacity without encounteringany
voltage or thermal issues [12].
There is significant ongoing research interest for evaluatingthe
DG capacity with a wide range of methods, objectives,
andconstraints within two broad approaches. The first approachis to
accommodate DG units with distributed and prespecifiedcapacities at
the best locations by using evolutionary computa-tions such as
genetic algorithms (GAs) [13], [14] and the parti-cle swarm
optimization (PSO) [15], which are able to handle thedistributed
formulations. However, the distributed formulationof the DG
capacity will not provide a truly optimal solution.Moreover, the
use of multiple capacities extends the searchspace significantly.
The other approach requires the networklocations of interest to be
prespecified with algorithms guidingthe DG capacity growth within
network constraints. In this case,these methods are not capable of
solving the continuous func-tions of the capacity. To solve these
continuous functions, linearprogramming [16], gradient search [17],
or optimal power flow(OPF) [18][23] methods are employed. A major
drawbackof this approach is that the perceived optimal solution
maycontain a number of sites with very small available
capacitieswhen a large number of locations are searched. Moreover,
therequirement of prespecifying locations is another major
issuewith this approach as this involves a significant effort
beyondthe feasibility of manual searches even for a small
distributionnetwork. To overcome some of these limitations, a
hybridmethod (the combination of GA and OPF) is presented in
[24]where the GA is used to search a large range of
combinations
1932-8184 2013 IEEE. Personal use is permitted, but
republication/redistribution requires IEEE permission.See
http://www.ieee.org/publications_standards/publications/rights/index.html
for more information.
-
MAHMUD et al.: VOLTAGE VARIATION ON DISTRIBUTION NETWORKS WITH
DG: WORST CASE SCENARIO 1097
of locations and an OPF is used to define the available
capacityfor each combination. However, this method also requires
thenumber of DG units to be prespecified. Another hybrid method(the
combination of PSO and OPF) is introduced in [25] todo the same
task as presented in [24] and obtain a betterperformance, but this
method also suffers from the limitationof prespecifying DG
units.
The majority of the optimization techniques are complexand
involve more mathematical computations. Moreover, thesetechniques
have the problem of long convergence time, prema-ture convergence,
and no performance guarantee. To overcomethese difficulties,
analytical approaches can be adopted to en-hance the power quality
of distribution feeders in terms of thenode voltage profile
improvement, which, in turn, reduces thepower loss. Various
analytical methods have been presented in[26][30] for the placement
of optimal DG units in distributionnetworks. Most of the analytical
approaches as presented in[26][30] are mainly based on the network
sensitivity approach.
From the existing literature on the DG planning and opera-tion,
it can be summarized that the main purpose of integratingDG units
is to deliver a portion of real and/or reactive powerinto the
network to enhance the voltage profile of distributionnetworks
along with the reduction in distribution losses andinvestment
costs. However, most of the approaches are mainlybased on the
consideration of real power available from the DGunit although the
consideration of reactive power available fromthe DG unit has
gained attraction in some recent investigations[11], [29][31]. The
reactive power from DG units can helpimprove the voltage profile
and reduce the energy loss. The lackof attention to the reactive
power capability exhibited by DGunits at the planning stage may
lead to the potential increasein investment costs and improper
allocation of DG units. Itis of vital importance that the reactive
capability limit of DGunits is accounted in distribution system
planning and operationproblems to quantify the associated
benefits.
The worst case scenario of a system is very important forthe
planning and operation as it captures all unusual conditionsof the
system. In distribution networks planning and operation,the worst
case scenario is essential to demonstrate the relation-ship between
the voltage variation and DG connected to thedistribution network
and to ensure that distribution networksand customers will not be
adversely affected. The aim of thispaper is to establish a
relationship between the voltage variationand DG integration in a
distribution network by considering theworst case scenario and to
provide some solutions to the voltagevariation and connection
costs. Finally, simulation results arepresented for the
justification of the proposed approach.
II. VOLTAGE VARIATION IN CONVENTIONALDISTRIBUTION NETWORK
Since distribution networks have high resistance to
reactanceratio, as compared to transmission networks, the
percentagevoltage drop in distribution networks is more than that
intransmission networks. To get an understanding of the voltagedrop
in distribution networks, the amount of the voltage dropis first
calculated for a two-bus distribution system, as shownin Fig.
1.
Fig. 1. Conventional two-bus distribution system.
In Fig. 1, DS and OLTC stand for the distribution substationand
on-load tap-changer, respectively; VS is the sending-endvoltage; VR
is the receiving-end voltage; P and Q are thereal and reactive
power flowing through the distribution line,respectively; and PL
and QL are the real and reactive powerof the load, respectively.
The voltage at the sending end can bewritten as [32]
VS = VR +P jQ
V S(R+ jX)
= VR +RP +XQ
V S+ j
XP RQV S
.
Therefore, the voltage drop between the sending and receiv-ing
ends can be written as
V = VS VR = RP +XQV S
+ jXP RQ
V S.
Since the phase difference between the sending-end voltageand
the receiving-end voltage is very small, the voltage drop
isapproximately equal to the real part of the drop [33], and if
thesending-end bus is considered as the reference bus, the angleof
this voltage is 0, i.e., V S = |VS | = VS . Therefore, the
aboveequation can be approximated as
V RP +XQVS
. (1)
If the sending-end voltage of the system is considered as
thebase voltage, in per unit, VS can be considered as one and
(1)can be written as follows:
V RP +XQ. (2)
The amount of voltage variation in a large distribution net-work
can be also determined by using a similar approach. InFig. 2, an
n-bus system is considered. The voltage drop betweenthe ith and jth
buses can be written as
Vij RijPij +XijQijVi
, i, j = 1, 2, 3, . . . , n, i = j(3)
where Vij is the variation of voltage between the ith and
jthbuses, Rij is the resistance between the ith and jth buses,
Xijis the reactance between the ith and jth buses, Vi is the
voltageat the ith bus, and Pij and Qij are the active and reactive
powerflowing from the ith to the jth bus, respectively.
The derivation of voltage variation formula for
distributionnetworks with DG based on the derived voltage variation
for-mula as aforementioned is presented in the following
section.
-
1098 IEEE SYSTEMS JOURNAL, VOL. 8, NO. 4, DECEMBER 2014
Fig. 2. Conventional n-bus large distribution system.
Fig. 3. Two-bus distribution system with DG.
III. VOLTAGE VARIATION IN DISTRIBUTIONNETWORK WITH DG
When generators are connected to the distribution system,the
power flow and the voltage profile are affected. In order toexport
power, a generator is likely to operate at a higher voltage,as
compared to other nodes where it is supplying power. In thiscase,
receiving-end voltage VR will be
VR VS +RP +XQ (4)as the direction of the power flow is reversed.
Thus, the voltageat the point of connection of the generator will
rise above thesending-end voltage, which can be clarified through
Fig. 3.
In Fig. 3, a distributed energy resource (DER) is connectedwhere
the voltage is VGEN; PG and QG are active and reactivepower
generated by the DG, respectively; PL and QL are theactive and
reactive power of the load, respectively; and QC isreactive power
of the shunt compensator. This DER with loadsand compensators is
connected to the distribution system via anoverhead distribution
line with impedance R+ jX and throughan OLTC. The voltage variation
along the distribution network,as shown in Fig. 3, can be written
as follows:
V = VGEN VS RP +XQVGEN
(5)
where P = (PG PL), and Q = (QC QL QG). IfVGEN is considered as
base voltage and expressed in terms ofper unit, then (5) can be
written as
V = VGEN VS R(PG PL) +X(QC QL QG).(6)
DERs always export active power (+PG) and may exportor import
reactive power (QG), whereas the load consumesboth active PL and
reactive QL power and the compen-sators may supply or absorb only
reactive power QC . Thereactive power capability of DERs depends on
the nature ofDERs connected to distribution networks. The present
trend isto integrate synchronous machine-based combined heat
power
Fig. 4. n-bus large distribution system with DG.
(CHP) generators, induction machine-based wind generators,and
voltage source inverter-based photovoltaic (PV) generatorsinto
distribution networks, which have different reactive
powercapabilities. For example, if there is a synchronous
machine-based CHP unit within distribution systems, it can
providereactive power to the system as it possesses the
capabilityof controlling reactive power output by adjusting the
fieldexcitation. However, if a wind generator is connected to
thedistribution network as DG, it is essential to provide
somereactive power to the system to maintain the voltage
stabilityas its induction generator requires a source of reactive
power tooperate. Again, if a PV generator is connected to the
system, itcannot provide any reactive power as it needs to operate
at unitypower factor in order to deliver maximum power into the
grid.
The voltage variation in large distribution networks withDG can
be obtained in a similar way to that in conventionaldistribution
networks as discussed before. If we integrate a DGunit at the jth
bus, as presented in Fig. 4, the voltage variationVji at the point
of the DG connection, i.e., at the jth bus of aradial distribution
feeder, can be written as
Vji Rij(PGj PLj) +Xij(QGj QLj)Vj
(7)
where PGj is the active power supplied by the DG unit con-nected
to the jth bus, QGj is the reactive power of the DG unitconnected
to the jth bus, and PLj and QLj are the active andreactive power of
the load connected to the jth bus, respectively.Now, if a shunt
compensator with reactive power QCj is con-nected at the jth bus,
(7) can be written as
Vji Rij(PGj PLj) +Xij(QGj QCj QLj)Vj
. (8)
In per unit, (8) can be written as
Vji Rij(PGj PLj) +Xij(QGj QCj QLj).
These voltage variation formulas can be used to determinethe
relationship between the voltage variation and DG inte-gration,
which may suggest possible solutions to mitigate thevoltage
variation. In this paper, the worst case scenario of
thedistribution network is considered to investigate the
relationshipbetween the voltage variation and DG integration, which
isnot considered in [32]. The worst case scenario of
distributionnetworks with DG is discussed in the following
section.
-
MAHMUD et al.: VOLTAGE VARIATION ON DISTRIBUTION NETWORKS WITH
DG: WORST CASE SCENARIO 1099
IV. ESTIMATION OF VOLTAGE VARIATION ANDDG CAPACITY USING WORST
CASE SCENARIO
DERs are connected to the distribution system due to
thetechnological innovations and changes in the economic
andregulatory environment, as well as to meet the increased
loaddemand. From (6), we can write
PG VGEN VS +RPL X(QC QL QG)R
(9)
and for a large distribution network
PGj Vj Vi +RijPLj Xij(QCj QLj QGj)Rij
.
From (9), it is clear that the level of DG connected to
thedistribution system depends on the voltage at the primary DS,the
voltage level of the receiving end, the size of the conductorsand
the distance from the primary DS, the load demand on thesystem, and
the other generation on the system.
DNSPs should consider the worst case operating scenariosto
demonstrate the relationship between the voltage variationand the
amount of DG integration so that their networks andcustomers will
not be adversely affected. Generally, these worstcase scenarios
are:
1) minimum load maximum generation;2) maximum load minimum
generation;3) maximum load maximum generation.Since the aim of this
paper is to find out the maximum
amount of DG units that can be integrated into the
distributionnetwork under the worst condition, the minimum load
max-imum generation scenario is considered in this paper as
theworst case scenario. Under the considered worst case
scenario
PL = 0 QL = 0 PG = PGmax.
Now, for the sake of simplicity, if we consider that the
systemis operating at unity power factor, QG and QC will be zero.In
this case, the worst case voltage variation for a
two-busdistribution network can be obtained from (6) and written
inthe following form:
Vworst = VGENmax VS RPGmax. (10)For a large system, the worst
case voltage variation is
Vworstji = Vjmax Vi RijPGjmax.From (10), it is clear that the
voltage variation depends on theresistance of the distribution line
and the power supplied byDERs. If the resistance of the
distribution line is constant, thenwe can write
Vworst PGmax (11)and that for a large system is
Vworstji PGjmax.Therefore, the voltage variation in the
distribution network withDG is directly proportional to the amount
of active power
supplied by DERs. Since there is a linear relationship
betweenthe voltage variation and the amount of active power
suppliedby DERs, the voltage variation is more onerous when there
isno demand on the system as the generation is exported backto the
primary distribution system. The voltage variation in
thedistribution system also limits the amount of DG units that
canbe integrated into the distribution network, and this can be
seenin the following equation, which is obtained from (6):
PGmax VGENmax VSR
. (12)
The capacity of the DG unit that can be accommodated in
theexisting system is clearly limited by the maximum voltage atthe
point of DG connection, which can be written as
PGmax VGENmax VSR
(13)
and for a large distribution system, it can be written as
PGjmax Vjmax ViRij
.
Therefore, from the worst case scenario, it is seen that
theresistance of the line, as well as the voltage variation within
thesystem, is critical for the DG integration. From the worst
casescenario of distribution networks with DG, possible solutions
tothe voltage variation due to the integration of the maximum
DGunit can be obtained easily, which is presented in the
followingsection.
V. MITIGATION OF VOLTAGE VARIATION BASED ONWORST CASE
SCENARIO
The integration of DERs may cause an excessive voltagevariation.
Traditionally, the DS is equipped with an over- orundervoltage
protection relay to protect it. The voltage protec-tion scheme may
permanently disconnect DERs, or it may evendisconnect the DS from
the main grid, which may cause seriouseconomical damage for
customers and DNSPs. The voltagevariation on the DS can be
mitigated through the followingapproaches:
1) by using the resistance reduction;2) by regulating primary DS
voltage VS ;3) by using the generation curtailment;4) by using the
reactive power compensation.
A. Mitigation of Voltage Variation by Using theResistance
Reduction
If the amount of the DG connected to a distribution system
isconstant, from (10), we can write
Vworst R. (14)From (14), it is seen that the worst case voltage
variation thatconsiders the maximum DG penetration is directly
proportionalto the resistance of the line. Therefore, the voltage
variationin distribution networks can be reduced by decreasing the
lineresistance. The resistance of a line can be reduced by
increasing
-
1100 IEEE SYSTEMS JOURNAL, VOL. 8, NO. 4, DECEMBER 2014
the conductor size for which it is essential to change the
in-frastructure of the existing distribution network
infrastructure,which is very difficult in practice. Therefore,
before construct-ing a new distribution system, i.e., for the
future planning andoperation of a distribution network, DNSPs
should consider thereduced value of the line resistance to make
provisions for alarger amount of DG units.
B. Mitigation of Voltage Variation by Using the ReactivePower
Compensation
If we consider the worst case scenario with DERs andcompensators
are operating at a power factor other than unity,(6) can be
rewritten as
Vworst RPGmax +X(QGmax QC). (15)
From (15), it is seen that the voltage variation can be
mitigatedby adjusting the reactive power of DERs and
compensators.
As previously discussed, a DG unit may export or importpower
into or from the grid. When a DG unit exports power,(15) can be
written as
Vworst RPGmax +X(+QGmax QC) (16)
and that for large systems
Vworstji RijPGmaxj +Xij(+QGmaxj QCj). (17)
From (16) and (17), it is seen that the second part of the
rightside of these equations needs to be negative to mitigate
thevoltage rise problem, and in this case, the compensator
mustabsorb reactive power that should be greater than the
maximumreactive power supplied by the generator. However, if there
is avoltage dip within the network, the compensator should
supplyreactive power to the system to keep the voltage within
thespecified limit.
Again, if a DG unit imports reactive power, (15) can bewritten
as
Vworst RPGmax +X(QGmax QC) (18)
and for large systems, it can be written as
Vworstji RijPGmaxj +Xij(QGmaxj QCj). (19)
From (18) and (19), it can be said that if there is a voltage
risewithin the system and the reactive power absorbed by DG isnot
sufficient, it is essential to absorb more reactive power andthe
compensator should absorb reactive power to mitigate thevoltage
rise problem. In case of a voltage dip, reactive powerneeds to be
supplied from the compensator to compensate thereactive power
absorbed by the DG unit.
C. Mitigation of Voltage Variation by Regulating the PrimaryDS
Voltage VS
In conventional passive distribution networks, it is a
commonpractice for DNSPs to maintain the primary DS voltage
above
Fig. 5. Mitigation of voltage variation by regulating primary DS
voltage.
the nominal voltage to ensure that the voltage profile of
thesystem remains within the specified voltage limit. As we
know
Vworst = VGENmax VS .The voltage variation can be mitigated by
regulating thesending-end voltage VS , i.e., the primary DS
voltage. Thiscan easily be done by using OLTCs connected to
distributionnetworks, as shown in Fig. 5, from where it is seen
that theprimary voltage can be regulated by using an automatic
voltagecontroller. The controller senses the voltage variation
betweenthe two buses. If the voltage variation is within the
permissiblelimit, the controller does not work, but if the voltage
varia-tion exceeds the permissible limit, the controller
automaticallyregulates the voltage and thus reduces the voltage
variation.However, in a more complex network, the value of this
voltageand the corresponding tap position of the OLTC would have
tobe optimized.
D. Mitigation of Voltage Variation by Using theGeneration
Curtailment
It is important to observe that the probability of the worstcase
scenario in distribution networks is generally low, andhence, it
may be beneficial to accommodate a larger DER andcurtail it when
the voltage at the busbar where it is connectedvaries outside the
specified limit. The effect of the generationcurtailment on the
voltage variation can be obtained from thefollowing equation:
PGmax PGcur + VGENmax VSR
. (20)
Equation (19) can be rewritten asVworst RPGmax RPGcur. (21)
From (21), it is seen that the voltage rise can be reduced
throughthe generation curtailment. The likelihood of the
coincidenceof the minimum load with maximum generation will
determinethe total annual energy that needs to be curtailed. As the
priceof electricity is primarily driven by the load demand and
thegeneration curtailment occurs typically during the period of
lowload, the value of this energy to be curtailed is relatively
low.However, this approach is not suitable when there is a
voltagedrop within the system.
VI. VOLTAGE LEVEL AND DG CONNECTION COST
From the analysis of the worst case voltage variation, it isseen
that the voltage level at the point of the DG connection isvery
important as it has a great impact on the overall profitabil-ity of
both consumers and DNSPs. If a DG unit is connected to a
-
MAHMUD et al.: VOLTAGE VARIATION ON DISTRIBUTION NETWORKS WITH
DG: WORST CASE SCENARIO 1101
TABLE IVOLTAGE LEVEL AND DG CONNECTION COST
higher voltage level, there is less chance of the voltage
variationwithin the network close to the customers. However, if a
DGunit is connected to the vicinity of the customer, the
voltagevariation due to the DG integration may affect the
customersappliances. Therefore, the voltage level and the effect of
voltagevariation have an inverse relationship.
The connection cost of a device into the existing
distributionnetwork is also very important. These costs are
determinedbased on the network access charge (NAC). Energy
Australiadefines the NAC as a fixed charge (cents/day) applied to
eachenergized connection point at which Energy Australias
energy/demand is measured or recorded. Energy Australias NACunder
different voltage levels and network categories is shownin Table I
[34].
In Table I, the voltage levels are categorized as follows:
lowvoltage (LV): nominally 240/415 V; high voltage (HV): nomi-nally
5, 6.6, 11, or 22 kV; and subtransmission (ST): nominally33 kV or
above. From Table I, it is seen that the NAC is more forthe higher
voltage level, which indicates the higher connectioncost. Due to
this reason, DNSPs main target is to connect a DGunit into the LV
level but this might cause the voltage variationwithin the system.
On the other hand, the connection of a DGunit at a higher voltage
level has a lower impact on the perfor-mance of the network in
terms of the steady-state voltage profileand power quality. These
two conflicting objectives need to bebalanced appropriately.
VII. SIMULATION RESULTS
The voltage level at each connection point of the load
andgeneration is very important for the quality of the supply.Since
there are no internationally agreed rules that define theallowed
steady-state voltage range, the maximum permittedvoltage variation
on each busbar is defined by some technicalregulations or specific
contracts. DNSPs should maintain thevoltage variation in
distribution networks within the permissiblelimit fixed by national
and international standards to guaranteereliable and economic
service to customers. In most cases, theallowable voltage variation
along distribution networks is 6%[35] but it may vary depending on
rules and regulations ofeach country. In this paper, the allowed
voltage variation at thecustomer end is considered as 6% in order
to demonstratethe effect of the DG integration into distribution
networkswith the derived voltage variation formula. In order to
validatethe derived voltage variation formula, the voltage profile
of adistribution network is obtained from the derived formula
andcompared with that of the existing power system
simulationsoftware.
In this paper, a 15-bus Kumamoto, Japanese distributionsystem is
considered, which is shown in Fig. 6. The base power
Fig. 6. Fifteen-bus Kumamoto, Japanese distribution system.
Fig. 7. Voltage profile of the 15-bus distribution system
without DG: (solidline with star) PSSE; (solid line with circle)
derived formula; and (two dottedlines) allowable range of voltage
variation.
Fig. 8. Voltage profile of the 15-bus distribution system with
DG: (solid linewith star) PSSE; (solid line with circle) derived
formula; and (two dotted lines)allowable range of voltage
variation.
of this distribution system is 10 MVA and the base voltage is6.6
kV; the total load on the system is 6.301 MW, 0.446 MVAr.The test
system data with the distribution of loads in differentnodes can be
seen in [36].
-
1102 IEEE SYSTEMS JOURNAL, VOL. 8, NO. 4, DECEMBER 2014
The voltage profile of the 15-bus test system is shown inFig. 7
from where it is seen that the voltages at buses 6, 15,and 11 are
below the considered specified limit 6% becausethese buses are far
away from the main grid supply point. Atthis point, no DERs are
connected to the distribution network.The voltage profile obtained
from a widely used simulation toolin power industry, called PSSE,
is shown by the solid line withstars in Fig. 7. The voltage profile
of this test system shouldbe similar or close to that of obtained
through PSSE when thederived voltage variation formula will be
used. With the derivedvoltage variation formula, the voltage
profile of the 15-bus testsystem is also shown in Fig. 7 by the
solid line with circles,which is very close that of obtained from
PSSE.
Now, if a 6-kW synchronous generator is connected at bus4, a
2-kW PV generator is connected at bus 13, and a 3-kWwind generator
is connected at bus 10, the voltage profile ofthe distribution
network is shown in Fig. 8. In this case, thereshould be a voltage
rise, as compared with the distributionnetwork without DG at buses
4 and 13, as well as their adjacentbuses and a voltage drop at bus
10 and its adjacent buses. Thishappens as the synchronous generator
supplies both active andreactive power and the PV generator
supplies active power tothe system. Moreover, this portion of the
system has enoughreactive power to supply loads. On the other hand,
the region atwhich the wind generator is connected is far from the
main grid,and the reactive power available in this portion is not
sufficientto meet the load demand. Moreover, the wind generator
alsoconsumes reactive power, and this is why the voltage at bus
11,which is adjacent to bus 10, falls down outside the
specifiedlimit. In Fig. 8, it is shown that the voltage profile
obtainedfrom the derived formula is very close to that of obtained
fromPSSE when DERs are integrated into the distribution system.
VIII. CONCLUSION
The voltage variation for a small and a large
distributionnetwork has been estimated through an analytical
approach, andthe derived voltage variation formula is accurate for
performingthe analysis as it provides very similar results to that
of theexisting power system simulation software. The worst
casescenario of the distribution network is considered based on
thederived formula in order to build up a relationship between
thevoltage variation and maximum DG capacity. The relationshipamong
voltage level, voltage variation, and DG connection costis built
using an example. The approach presented in this paperis useful for
the future planning and operation of distributionnetworks, as well
as for the voltage control of the existingdistribution network with
DG. Future works will deal with thedetailed analysis of the voltage
control with different types ofDG such as CHP, wind generators, and
PV.
REFERENCES[1] P. Chiradeja and R. Ramakumar, An approach to
quantify the technical
benefits of distributed generation, IEEE Trans. Energy Convers.,
vol. 19,no. 4, pp. 764773, Dec. 2004.
[2] A. G. Tsikalakis and N. D. Hatziagyriou, Environmental
benefits ofdistributed generation with and without emissions
trading, Energy Policy,vol. 35, no. 6, pp. 33953409, Jun. 2007.
[3] H. A. Gill and G. Joos, Models for quantifying the economic
benefitsof distributed generation, IEEE Trans. Power Syst., vol.
23, no. 2,pp. 327335, May 2008.
[4] J. A. P. Lopes, N. Hatziargyriou, J. Mutale, P. Djapic, and
N. Jenkins,Integrating distributed generation into electric power
systems: A reviewof drivers, challenges and opportunities, Elect.
Power Syst. Res., vol. 77,no. 9, pp. 11891203, Jul. 2007.
[5] S. Liew and G. Strbac, Maximising penetration of wind
generation inexisting distribution networks, Proc. Inst. Elect.
Eng.Gener., Transm.Distrib., vol. 149, no. 3, pp. 256262, May
2002.
[6] A. Shafiu, T. Bopp, I. Chilvers, and G. Strbac, Active
management andprotection of distribution networks with distributed
generation, in Proc.IEEE Power Eng. Soc. Gen. Meet., Jun. 2004, pp.
10981103.
[7] T. Bopp, A. Shafiu, I. Cobelo, I. C. Jenkins, N. Jenkins, G.
Strbac,H. Li, and P. Crossley, Commercial and technical integration
of dis-tributed generation into distribution networks, presented at
the 17th Int.Conf. Electricity Distribution (CIRED), Barcelona,
Spain, 2003, Paper 45.
[8] M. H. J. Bollen and A. Sannino, Voltage control with
inverter-baseddistributed generation, IEEE Trans. Power Del., vol.
20, no. 1, pp. 519520, Jan. 2005.
[9] C. M. Hird, H. Leite, N. Jenkins, and H. Li, Network voltage
controllerfor distributed generation, Proc. Inst. Elect.
Eng.Gener., Transm. Dis-trib., vol. 151, no. 2, pp. 150156, Mar.
2004.
[10] A. E. Kiprakis and A. R. Wallace, Maximizing energy capture
fromdistributed generators in weak networks, Proc. Inst. Elect.
Eng.Gener.,Transm. Distrib., vol. 151, no. 5, pp. 611618, Sep.
2004.
[11] P. M. S. Carvalho, P. F. Correia, and L. A. F. M. Ferreira,
Distributedreactive power generation control for voltage rise
mitigation in distribu-tion networks, IEEE Trans. Power Syst., vol.
23, no. 2, pp. 766772,May 2008.
[12] A. Keane, L. F. Ochoa, E. Vittal, C. J. Dent, and G. P.
Harrison, Enhancedutilization of voltage control resources with
distributed generation, IEEETrans. Power Syst., vol. 26, no. 1, pp.
252260, Feb. 2011.
[13] G. Celli, E. Ghiani, S. Mocci, and F. Pilo, A
multiobjective evolutionaryalgorithm for the sizing and siting of
distributed generation, IEEE Trans.Power Syst., vol. 20, no. 2, pp.
750757, May 2005.
[14] L. F. Ochoa, A. Padilha-Feltrin, and G. P. Harrison,
Time-series-basedmaximization of distributed wind power generation
integration, IEEETrans. Energy Convers., vol. 23, no. 3, pp.
968974, Sep. 2008.
[15] A. M. El-Zonkoly, Optimal placement of multi-distributed
generationunits including different load models using particle
swarm optimisation,IET Gener., Transm. Distrib., vol. 5, no. 7, pp.
760771, Jul. 2011.
[16] A. Keane and M. OMalley, Optimal allocation of embedded
genera-tion on distribution networks, IEEE Trans. Power Syst., vol.
20, no. 3,pp. 16401646, Aug. 2005.
[17] N. S. Rau and Y. H. Wan, Optimum location of resources in
dis-tributed planning, IEEE Trans. Power Syst., vol. 9, no. 4, pp.
20142020,Nov. 1994.
[18] G. P. Harrison and A. R. Wallace, Optimal power flow
evaluation of dis-tribution network capacity for the connection of
distributed generation,Proc. Inst. Elect. Eng.Gener., Transm.
Distrib., vol. 152, no. 1, pp. 115122, Jan. 2005.
[19] P. N. Vovos, G. Harrison, A. R. Wallace, and J. W. Bialek,
Optimal powerflow as a tool for fault level constrained network
capacity analysis, IEEETrans. Power Syst., vol. 20, no. 2, pp.
734741, May 2005.
[20] P. N. Vovos and J. W. Bialek, Direct incorporation of fault
level con-straints in optimal power flow as a tool for network
capacity analysis,IEEE Trans. Power Syst., vol. 20, no. 4, pp.
21252134, Nov. 2005.
[21] L. F. Ochoa, C. J. Dent, and G. P. Harrison, Distribution
network capacityassessment: Variable DG and active networks, IEEE
Trans. Power Syst.,vol. 25, no. 1, pp. 8795, Feb. 2010.
[22] C. J. Dent, L. F. Ochoa, G. P. Harrison, and J. W. Bialek,
Efficient secureAC OPF for network generation capacity assessment,
IEEE Trans. PowerSyst., vol. 25, no. 1, pp. 575583, Feb. 2010.
[23] C. J. Dent, L. F. Ochoa, and G. P. Harrison, Network
distributed gen-eration capacity analysis using OPF with voltage
step constraints, IEEETrans. Power Syst., vol. 25, no. 1, pp.
296304, Feb. 2010.
[24] G. P. Harrisona, A. Piccolo, P. Siano, and A. R. Wallacen,
HybridGA and OPF evaluation of network capacity for distributed
genera-tion connections, Elect. Power Syst. Res., vol. 78, no. 3,
pp. 392398,Mar. 2008.
[25] M. Gomez-Gonzaleza, A. Lopez, and F. Jurado, Optimization
of dis-tributed generation systems using a new discrete PSO and
OPF, Elect.Power Syst. Res., vol. 84, no. 1, pp. 174180, Mar.
2012.
[26] C. Wang and M. H. Nehrir, Analytical approaches for optimal
placementof distributed generation sources in power systems, IEEE
Trans. PowerSyst., vol. 19, no. 4, pp. 20682076, Nov. 2004.
-
MAHMUD et al.: VOLTAGE VARIATION ON DISTRIBUTION NETWORKS WITH
DG: WORST CASE SCENARIO 1103
[27] N. Acharya, P. Mahat, and N. Mithulananthan, An analytical
approachfor DG allocation in primary distribution network, Int. J.
Elect. PowerEnergy Syst., vol. 28, no. 10, pp. 669678, Dec.
2006.
[28] T. Gozel and M. H. Hocaoglu, An analytical method for the
sizing andsiting of distributed generators in radial systems,
Elect. Power Syst. Res.,vol. 79, no. 6, pp. 912918, Jun. 2009.
[29] D. Q. Hung, N. Mithulananthan, and R. C. Bansal, Analytical
expressionsfor DG allocation in primary distribution networks, IEEE
Trans. EnergyConvers., vol. 25, no. 3, pp. 814820, Sep. 2010.
[30] D. Q. Hung, N. Mithulananthan, and R. Bansal, Multiple
distributedgenerators placement in primary distribution networks
for loss reduction,IEEE Trans. Ind. Electron, vol. 60, no. 4, pp.
17001708, Apr. 2013.
[31] K. Zou, A. P. Agalgaonkar, K. M. Muttaqi, and S. Perera,
Distributionsystem planning with incorporating DG reactive
capability and systemuncertainties, IEEE Trans. Sustain. Energy,
vol. 3, no. 1, pp. 112123,Jan. 2012.
[32] M. L. Doumbia and K. Agbossou, Voltage variation analysis
in inter-connected electrical networkDistributed generation, in
Proc. IEEECanada Elect. Power Conf., 2007, pp. 525530.
[33] W. H. Kersting, Distribution System Modeling and Analysis,
2nd ed.London, U.K.: CRC Press, 2007.
[34] Report Network pricing list, Energy Australia, Melbourne,
VIC,Australia, 2010.
[35] C. L. Masters, Voltage rise: The big issue when connecting
embeddedgeneration to long 11 kV overhead lines, Power Eng. J.,
vol. 16, no. 1,pp. 512, Feb. 2002.
[36] F. M. Gonzalez-Longatt, Impact of distributed generation
over powerlosses on distribution system, in Proc. 9th Int. Conf.
Elect. Power Qual.Utilisation, Oct. 2007, pp. 16.
M. A. Mahmud (S10M13) received the Bache-lors degree (with
honours, first class first position) inelectrical and electronic
engineering from RajshahiUniversity of Engineering and Technology
(RUET),Rajshahi, Bangladesh, in 2008 and the Ph.D. de-gree (with
best thesis award) in electrical engi-neering from The University
of New South Wales,Canberra, Australia, in 2012.
He served as a Radio Network Planning Engineerat Huawei
Technologies (BD) Ltd. After that, he be-came a Lecturer at Khulna
University of Engineering
and Technology, Khulna, Bangladesh, and in the Department of
Electricaland Electronic Engineering, RUET. He is currently a
Research Fellow atThe University of Melbourne, Melbourne,
Australia. His research interests aredynamic stability of power
systems, renewable energy integration, smart grids,nonlinear
control theory, and electrical machine.
M. J. Hossain (M11SM13) received the B.Sc.and M.Sc.Eng. degrees
from Rajshahi Universityof Engineering and Technology (RUET),
Rajshahi,Bangladesh, in 2001 and 2005, respectively, and thePh.D.
degree from The University of New SouthWales, Canberra, Australia,
in 2010, all in electricaland electronic engineering.
He served as a Research Fellow in the School ofInformation
Technology and Electrical Engineering,The University of Queensland,
Brisbane, Australia.He was also an Assistant Professor and a
Lecturer
at RUET for six years. He is currently a Lecturer in Griffith
School ofEngineering, Griffith University, Gold Coast, Australia.
His research interestsare power systems, renewable energy
integration and stabilization, voltagestability, microgrids, robust
control, electrical machine, flexible alternatingcurrent
transmission system devices, and energy storage systems.
H. R. Pota received the B.E. degree from SardarVallabhbhai
Regional College of Engineering andTechnology, Surat, India, in
1979; the M.E. degreefrom the Indian Institute of Science,
Bangalore,India, in 1981; and the Ph.D. degree from The Uni-versity
of Newcastle, Callaghan, Australia, in 1985,all in electrical
engineering.
He is currently an Associate Professor at TheUniversity of New
South Wales at the AustralianDefence Force Academy, Canberra,
Australia. Hehas held visiting appointments at the University
of
Delaware, Newark, DE, USA; Iowa State University, Ames, IA, USA;
KansasState University, Manhattan, KS, USA; Old Dominion
University, Norfolk, VA,USA; the University of California at San
Diego, La Jolla, CA, USA; and theCentre for Artificial Intelligence
and Robotics, Bangalore. He has a continuinginterest in the area of
power system dynamics and control and modeling andcontrol of
mechanical systems such as flexible structures, acoustical
systems,and unmanned aerial vehicles.
/ColorImageDict > /JPEG2000ColorACSImageDict >
/JPEG2000ColorImageDict > /AntiAliasGrayImages false
/CropGrayImages true /GrayImageMinResolution 300
/GrayImageMinResolutionPolicy /OK /DownsampleGrayImages true
/GrayImageDownsampleType /Bicubic /GrayImageResolution 300
/GrayImageDepth -1 /GrayImageMinDownsampleDepth 2
/GrayImageDownsampleThreshold 1.50000 /EncodeGrayImages true
/GrayImageFilter /DCTEncode /AutoFilterGrayImages false
/GrayImageAutoFilterStrategy /JPEG /GrayACSImageDict >
/GrayImageDict > /JPEG2000GrayACSImageDict >
/JPEG2000GrayImageDict > /AntiAliasMonoImages false
/CropMonoImages true /MonoImageMinResolution 1200
/MonoImageMinResolutionPolicy /OK /DownsampleMonoImages true
/MonoImageDownsampleType /Bicubic /MonoImageResolution 600
/MonoImageDepth -1 /MonoImageDownsampleThreshold 1.50000
/EncodeMonoImages true /MonoImageFilter /CCITTFaxEncode
/MonoImageDict > /AllowPSXObjects false /CheckCompliance [ /None
] /PDFX1aCheck false /PDFX3Check false /PDFXCompliantPDFOnly false
/PDFXNoTrimBoxError true /PDFXTrimBoxToMediaBoxOffset [ 0.00000
0.00000 0.00000 0.00000 ] /PDFXSetBleedBoxToMediaBox true
/PDFXBleedBoxToTrimBoxOffset [ 0.00000 0.00000 0.00000 0.00000 ]
/PDFXOutputIntentProfile (None) /PDFXOutputConditionIdentifier ()
/PDFXOutputCondition () /PDFXRegistryName () /PDFXTrapped
/False
/Description > /Namespace [ (Adobe) (Common) (1.0) ]
/OtherNamespaces [ > /FormElements false /GenerateStructure
false /IncludeBookmarks false /IncludeHyperlinks false
/IncludeInteractive false /IncludeLayers false /IncludeProfiles
false /MultimediaHandling /UseObjectSettings /Namespace [ (Adobe)
(CreativeSuite) (2.0) ] /PDFXOutputIntentProfileSelector
/DocumentCMYK /PreserveEditing true /UntaggedCMYKHandling
/LeaveUntagged /UntaggedRGBHandling /UseDocumentProfile
/UseDocumentBleed false >> ]>> setdistillerparams>
setpagedevice