-
CABLE-NET WALLS; WHERE DO I EVEN START?
Aaron Mazeika PE, Associate Skidmore, Owings & Merrill LLP
San Francisco, California [email protected] For the last seven
years Aaron Mazeika has practiced in the San Francisco office of
Skidmore, Owings & Merrill LLP, where he has led the structural
engineering design team on a number of large scale projects. Recent
projects include: Beijing Finance Street, 700,000m of mixed-use
development including two cable-net faades and three cable-truss
supported glass roofs; and The New Beijing Poly Plaza, a 100,000m
mixed-use tower (office/museum) including a 21 story tall atrium
space enclosed by two cable-net faades, one at 90m tall by 60m wide
is the largest such faade in the world.
Kieran Kelly-Sneed PE ASI Advanced Structures Inc., Los Angeles,
California [email protected] Kieran Kelly-Sneed has several
years of experience in modeling and analysis of cable structures,
beginning during his education at Cal Poly, San Luis Obispo. At
ASI, he has been involved in the design of several cable supported
glass structures and of many other custom faade projects. His role
extends to the job site where he has provided extensive support
during installation of these and other complex structures. Recently
Kieran spent 8 weeks on site at the San Jose Civic Center to
coordinate tensioning of the Rotunda's cable trusses, a complicated
operation due to the flexible steel ribs that anchor them.
Abstract While cable-net supported glass walls remain unusual,
even exotic design solutions for exterior wall enclosures, their
highly transparent nature makes them an attractive option,
particularly for building atria. The behavior of cable-net walls
under lateral loading is conceptually easy to understand, but the
large displacements likely under design wind events bring new
challenges to Architects and Engineers not familiar with the design
of large displacement structures. The design of cable-net wall
systems involves a great deal of coordination between the designers
of the cable-net wall and the designers of the base building
structure (who are often different entities), due to the large
loads transferred across the boundaries of the cable-net, and the
large displacements which need be accounted for in the detailing of
the interface zones. As complex as the design of cable-net walls
can be, this complexity is repeated in the process of installing
the wall. Specialist design-build contractors are typically engaged
to ensure that the installation process is successfully completed.
This paper provides background information on the development of
cable-net wall systems and technologies, and descriptive summaries
of the process of designing and constructing cable-net wall
systems. Different examples of team make-up, and the roles and
responsibilities of the members of the team are described. The
fundamental theory behind the behavior of planar cable-net wall
systems is presented and verified through the application of
parametric analysis studies. By way of a project example, a
detailed description is given of the design of The New Beijing Poly
Plaza, the worlds largest cable-net wall recently completed in
Beijing.
-
STRIVING FOR TRANSPARENCY
Architectural Ambitions Since the dawn of the modernist
movement, architects have challenged engineers with an ambition for
increased transparency in building faade systems. As engineering
technology has evolved, increasingly lightweight structural support
systems have been developed allowing a range of options for the
construction of transparent wall and roof systems. Developments in
structural glass technology have allowed the construction of
all-glass solutions for short-span conditions, but for longer spans
a steel backup system is typically required. The conventional
solution consists of glazing elements spanning between a series of
parallel lightweight steel trusses. Evolutions in the design of
trusses have allowed the use of cable-trusses where the chords of
the truss are replaced by cables, as can be seen in the exterior
wall bracing at the Tokyo International Forum (Rafael Violy
Architects P.C., New York & Structural Design Group, Co. Ltd.,
Tokyo, 1996). Tension is maintained in each chord for all loading
conditions by pre-tensioning the chords against fixed support
points or a single internal compression element. This solution can
be considered as an optimization of the underlying beam and slab
concept. However a paradigm shift was achieved with the conception
and development of the structural solution for the exterior wall of
the Kempinski Hotel at Munich Airport, (Murphy/Jahn, Chicago &
Schlaich, Bergermann und Partner, Stuttgart, 1993). This planar
steel net structure resists lateral loads through catenary action
in the cables, completely eliminating the need for any flexural
beam elements behind the glass faade.
Figure 1. Tokyo International Forum, Tokyo, Japan
Figure 2. Hotel Kempinski, Munich, Germany
Cable-Net Precedents While conceptually simple, due to their
minimal structure and large in-service deflections cable-net
curtain wall systems may still be considered an exotic solution for
the support of glass walls. The completion of several major walls
around the world, however, has established a proven track record of
an achievable scale and level of transparency. Planar two-way cable
systems support and stabilize glass facades through the resistance
to deformation of the two-way pre-tensioned net. Gravitational
loads from the glass elements are carried through the attachment
nodes to the vertical cables, and up to a transfer structure in the
base building above. Lateral deformations due to wind and seismic
loadings are resisted by the tendency of each of the horizontal and
vertical cables to return to its straight line configuration
between supports, while being subject to a perpendicular force. The
flexible nature of a planar cable-net under lateral loading means
that the critical design goal is limiting deflection through
adjusting axial stiffness of the cables, and the cable pre-tension.
In-service deflection limits under a 50-year return wind loading
condition are typically set in the range of L/40 to L/50 (with L
corresponding to the shortest span passing through the considered
point) to protect the integrity of the glass and sealants and to
minimize a perception of movement by the buildings occupants.
Oftentimes the controlling design criterion is the later issue
concerning occupant perception. If well designed and detailed, a
cable-net wall system may be to sustain the design level wind
condition and beyond without structural or sealant failure.
However, if the occupants of the building feel a sense of unease in
the vicinity of the cable-net wall, then the project cannot be
deemed a complete success.
-
Since the construction of the cable-net wall at the Kempinski
Hotel in 1993, several significant cable-net wall systems have been
installed around the world. As additional projects have been
realized, larger and more complex walls have been designed and
constructed, representing an evolution of the original design
concept. Significant milestones in the development of the cable-net
supported wall system include: The Kempinski Hotel in Munich,
Germany, the first application of the planar cable-net concept, is
40m wide by 25m tall and was designed with the principal cable
pre-tension installed in the longer-span horizontal direction. The
22mm diameter cables are spaced at 1500mm on center, and are
pre-tensioned to limit deflections to 900mm. The AOL Time Warner
building on Columbus Circle in New York, USA (Skidmore, Owings
& Merrill LLP, James Carpenter Design Associates &
Schlaich, Bergermann und Partner, 2003). This cable-net wall is 46m
tall by 25m wide and both horizontal and vertical cables are 28mm
in diameter. The Beijing New Poly Plaza in Beijing, China
(Skidmore, Owings & Merrill LLP, 2006). The cable-net wall is
90m tall by 60m wide and consists of 34mm diameter horizontal
cables at 1333mm on center, and 28mm vertical cables at 1500mm on
center. The very large spans of this cable-net wall were achieved
by faceting the net by folding it across large diameter cables
(235-275mm). This solution will be described in more detail later
in this paper.
Figure 3. AOL Time Warner, New York, USA
Figure 4. The New Beijing Poly Plaza, Beijing, China
Service deflections of a cable-net wall can be significantly
reduced by curving the wall in an anticlastic fashion: cables
running in the two principal are curved in opposing directions,
creating a stiff grid of intersecting nodes. In this arrangement
lateral deformations due to wind and seismic loadings are resisted
with less deflection than for a comparable flat net because the
wall has been built with a partially deflected form. This
pre-curved configuration of cables avoids the softest portion of
the non-linear lateral response of a planar cable-net (the
undeformed, initial condition). When the anticlastic cable-net is
subjected to lateral loads, only half of the cables resist the
loads applied in each direction. The cable-net behaves essentially
as two separate one-way cable-nets, rotated 90 degrees from each
other, and each optimized to resist lateral loads in a given
direction. Because of this configuration the support points on each
side of the cable-net must be able to resist half the total
-
applied wind loads on the gross area of the wall, necessitating
strong boundary conditions on all four sides. Despite only half
portion of the cables being loaded for a given direction of wind
loading, the cables which are mobilized offer such an increase in
stiffness over planar cable-nets, that curved cable-nets can
efficiently be designed to deflection limits as high as L/120. They
may also be designed in the range of L/40-L/50 using less
pre-tension than a comparable planar cable-net. As with planar
cable-nets occupant comfort and perception are often the
determining factors in establishing the deflection limit. Double
Curved cable-net projects include: The Station Place/Securities
& Exchange Commission Headquarters building in Washington, USA
(Kevin Roche John Dinkeloo and Associates LLC & ASI Advanced
Structures Inc., 2005). This anticlastic cable-net consists of a
wall 27.5m tall by 19m wide and a roof portion 19m wide by 16m deep
with a curved delta truss to transfer loads at the corner where the
two nets meet. All cables are 28mm in diameter and deflections are
limited to 250mm. The Seattle-Tacoma International Airport Central
Terminal Expansion in Seattle, USA (Fentress Bradburn Architects
Ltd. & ASI Advanced Structures Inc., 2005). This wall runs 108m
in length and spans 16m in height. Both horizontal and vertical
cables are 20mm diameter.
Figure 5. Station Place / SEC HQ, Washington, USA
Figure 6. Seattle-Tacoma Intl. Airport, Seattle, USA
-
CABLE-NET TECHNOLOGIES
Cables and Cable Fittings The cable-net is made up of cables
held together at their intersections by cable clamps, which also
serve as the point of attachment for the glazing, typically
supported only at its corners. Plain, threaded, turnbuckle, or eye
hook terminations are swaged or speltered onto the ends of cables
and anchor them to the base building structure. Swaging is a
process in which a fitting is mechanically pressed onto the cable
end. The less commonly used spelter socket connection consists of a
cone shaped termination into which the splayed wires of a cable are
inserted and bound by a poured zinc or resin wedge. Each cable is
composed of individual cold-drawn wires twisted together in a
variety of arrangements, the most basic of which is called wire
strand. Strand consists of individual wires twisted about a central
core wire. Wire rope is made by twisting strand cables about a
central core strand. Cables are named for the number of strands and
wires they contain: 1x37 describes wire strand composed of
thirty-seven individual wires. 6x19 describes wire rope consisting
of 6 strands of 19 wires each. In addition to the standard strand
and rope constructions, individual manufacturers also offer a
variety of special locked windings designed to increase the
constructions stiffness and improve its resistance to corrosion by
making the surface less permeable. Cables are either galvanized
steel or stainless steel. Untreated cable is not generally used in
cable-net applications. In most designs, the cables are on the
interior of the building and corrosion is only an issue during
construction. Cables are specified and ordered pre-stretched with
end fittings to meet or exceed 110% of the cables minimum breaking
load (MBL). Pre-stretching removes tightens the helical
construction of the cable and significantly reduces creep
(relaxation) after installation. The designer determines a cables
allowable working load based on the MBL, and must apply additional
strength reduction factors based on the end fitting type and angle
of deviation at saddle supports. These factors are based both on
code requirements and on manufacturers recommendations. Other
sources of capacity reduction may include effects of fatigue or of
fire. Fatigue can be pronounced in places where cables are
subjected to changes in their curvature, especially if a sharp edge
is present. Such an edge will have a tendency to bite into the
outermost wires of the cable. For this reason, design codes give
recommendations about the maximum allowable angle of deviation of a
cable across a support, and the German DIN code specifies edge
radii for cable clamps to eliminate sharp edges. The heat of a fire
can reduce a cables strength both by softening it and by annealing
the cable from its cold-drawn state, thus permanently reducing its
strength. In this manner cables which have survived a fire may be
over-stressed after the event due to a reduction in their
capacity.
Figure 7. 1x19 wire strand
Figure 8. 6x19 wire rope
Figure 9. Swaged cable fittings
-
Glass Attachments Drilled glass bolt fittings or patch plates
are typically used to fasten the glass to the cable nodes. These
attachments must be designed to accommodate the environmental
loads, in addition to the resulting deflections. For this reason
rotational glass bolts are a common solution, allowing upwards of
ten degrees of rotation between the glass and its support point.
Patch plates are a more economical solution because a single plate
can take the place of four bolts, and the glass does not need to be
drilled. The plate penetrates the glass joint to clamp multiple
pieces of glass to a common node. Deflections and rotations are
accommodated by a neoprene bearing pad between the glass and patch
plate and by localized deformation of the glass.
Figure 12. Rotational glass bolt
Figure 13. Glass patch plate
Glass Technologies Glass can be annealed, heat-strengthened, or
fully tempered. Heat strengthening and tempering are treatments in
which annealed glass is heated then rapidly cooled, placing its
surface in compression and center in tension. This increases the
strength of the glass as higher applied loads can be resisted
before the outer surface fractures. Issues of concern when heat
treating glass include nickel-sulfide inclusion, roller wave, and
bow or edge warping. Of these, nickel-sulfide inclusion is the only
problem with structural implications; it can cause spontaneous
breakage in fully-tempered glass. Heat-soaking after tempering will
usually cause glass with inclusions to break, so the process is
often specified in contract documents to reduce the likelihood of
breakage after installation. Most cable-nets employ laminated glass
as a safety measure against breakout. Broken panels remain in
place, held by the polyvinyl butyral (PVB) interlayer.
Heat-strengthened and fully tempered glass sheets have different
breakage patterns giving added strength after glass breakage to a
laminated panel containing both.
Figure 10. Heat treated glass
Figure 11. Laminated glass breakage
-
CABLE-NET DESIGN TEAMS
Roles and Responsibilities The design team for a cable-net
structure tends to consist of a variety of entities who are
involved in the design of the cable-net wall system, the base
building structure or both. For each portion an entity may be
involved as the Architect or Engineer for the design phases of the
work and/or as the Architect of Record (AOR) or Engineer of Record
(EOR) for the construction documentation phase of work. The
principle roles in the design team are as follows: Design
Architect: Lead architectural designer of the building in the
Schematic and Design Development phases. Architect of Record:
Architect responsible for preparation of the construction documents
for the building structure, often the
Design Architect. Design Engineer: Lead engineering designer of
the building in the Schematic and Design Development phases.
Engineer of Record: Engineer responsible for preparation of the
construction documents for the building structure, (Base Building)
often the Design Engineer. Cable-Net Designer: Lead Designer of the
cable-net wall system. This could be the Design Architect, the
Design Engineer
an associated designer, or a design-build contractor. Engineer
of Record: Engineer responsible for preparation of the construction
documents for the cable-net structure. (Cable-Net) This could be
the Engineer of Record for the Base Building, but more commonly is
the cable-net
design-build contractor. As can be seen from the above, there
are many possible arrangements of different entities that can make
up a team for the design of a cable-net wall system. Several
arrangements that have been employed in the past are highlighted in
a following section. Contractor Engineered Systems In any large
building project there will likely be several elements and
components of the structure which are defined as Contractor
Engineered Systems. The items could be a single component, such as
a cable with end fittings that is specified to be provided
engineered by the contractor to resist the load demands shown on
the structural engineering drawings, from pin-to-pin. At the
opposite end of the spectrum an entire system can be thus
specified, such as the entire exterior wall of a building. The
reasons for specifying Contractor Engineered Systems are as varied
as the elements and systems thus specified, and include: Design
Efficiency: Any structural engineer can design an open web steel
roof truss. But it is not an efficient use of
resources when the truss manufacturer can do the detailed design
in a fraction of the time, allowing the structural engineer to
select from a catalogue of pre-designed components.
Proprietary Items: The tension capacity of a swaged steel cable
connection is greatly influenced by the exact production
process specific to each manufacturer. As the structural
engineer cannot determine this, the cable assembly is usually
provided engineered pin-to-pin as described above.
Design Expertise: Certain elements or systems may require very
specific knowledge to be safely designed, and may
therefore be beyond the experience of the typical structural
engineer. In this case the structural engineer would wisely defer
the design of these elements or systems to a specialist. Note that
when the complicating factor is difficulty of design, the chosen
course of action may be to place the design responsibility on a
specialist design-build contractor, or to employ the services of a
specialist engineering sub-consultant to assist the structural
engineer in the design.
-
Contractor Expertise: Certain elements or systems may not be
difficult to design, but may require specialized knowledge and
skills to safely construct. In such situations the success of
the project hangs directly on the ability of the Contractor to
perform the work correctly. In such situations designating this
particular portion of the work as a Contractor Engineered System is
a useful tool to ensure that only suitably skilled entities are
contracted to perform the work.
Due to a combination of the reasons listed above, cable-net wall
systems are typically designated as Contractor Engineered Systems
in the building design documents, making the design-build
contractor the EOR for the cable-net wall system. However the
extent of early involvement in the design by the design-build
contractor, and therefore the extent of development of the initial
design by the Design Architect and Design Engineer, vary greatly
depending on the team setup employed. Design Team Setup A
traditional design-build approach recognizes the value of the
expertise provided by a specialty design-build contractor.
Potentially also in part due to a lack of familiarity of the
systems involved, many architectural and engineering design
practices will follow this approach and involve a the design-build
contractor as early as possible in the conceptual design of a
cable-net wall project. The design of the cable-net can be
separated from the design of the rest of the building almost as
soon as the decision has been made to include one in the overall
design of the project. Typically the cable-net design-build
contractor will wish to be involved early as their experience can
be beneficial in guiding the design in the critical initial phases
when decisions are made that will set constraints on the design of
the net. The design of the cable-net, the glass and the glass
attachments will then be undertaken by the design build contractor
who will act as the Cable-Net Designer as well as the Cable-Net
EOR, working in parallel with the AOR of the base building, to
ensure that the net is designed in accordance with their original
conceptual design intent. The design-build contractor will also
work closely with the EOR of the base building to ensure that all
load and displacement interactions that occur at the interface
between the cable-net structure and the base building structure are
duly considered. An alternate design approach that can be employed
has the Design Architect and Design Engineer of the base building
structure performing the role of the Cable-Net Designer. This
approach may be employed for a number of different reasons
including an evaluation that the design of the cable-net is so
inextricably linked to the architectural and engineering design of
the base building, thus making it impractical to separate this
portion of the work; a desire on the part of the Design Architect
and Design Engineer to maintain direct creative control on the
cable-net design; or in the case of a Design Architect and Design
Engineer with experience in the field of design of cable
structures, a situation where this type of work falls within the
range of work undertaken by these entities. However for the reasons
of difficulty of construction listed in the previous section it is
still typical to designate the cable-net wall as a Contractor
Engineered System, making the design-build contractor the EOR of
the cable-net wall. However as the design of the cable-net has been
completed, the role of the design-build contractor is typically
limited to one of engineering verification prior to the
construction phase. An example of a project designed under this
engineering verification approach is the New Beijing Poly Plaza
project, which is described in more detail as a cable-net project
example later in this paper. While the traditional design-build
approach and the engineering verification approach represent
perhaps the two clearest conditions in terms of separation of
responsibilities, they do represent two ends of a spectrum and each
project may lie somewhere between these two ends. The majority of
cable-net projects are completed closer to the traditional
design-build end of the spectrum. Construction Team Setup Early in
the buildings design phase the cable-net designer and EOR should
work with the design architect and engineer to establish the wall
geometry, deflection limits, and perimeter reactions. A flat wall
typically requires more pre-tension than a curved one; a one-way
cable wall will load the building in fewer locations but with
greater force, and will allow more deflection unless its
pre-tension is increased. Depending on the wall geometry and
deflection limit, cable reaction loads can easily range from 10 to
100 kips on intervals of five to ten feet. Thus it is critical that
the team establish the design parameters and ballpark reaction
values early in the design process.
-
Building movement, stiffness, and expansion joints must also be
coordinated. Preliminary deflection and stiffness information must
be provided to the cable-net designer for use in their modeling, as
support displacement can affect the walls stiffness. Because the
cable-net needs a rigid boundary designers try to avoid placing
expansion joints across the wall opening. However, differential
building movement can be accommodated through use of springs or
hinged elements. Such issues must also be discussed at the
beginning of design. As the design of the building and the
cable-net proceed the cable-net designer coordinates the location
of each cable anchor and associated reaction forces with the design
engineer, who in turn supplies support displacement information
based on the cable loads. Design of the attachment detail is
usually coordinated between the two engineers, though the
engineering responsibility typically rests with just one. The
cable-net EOR always bears responsibility for the cable and swage,
beyond which point responsibility is split on a case by case basis.
Embeds in concrete are most often designed by the building EOR.
Depending on the amount of anticipated support deflection, the
cable-net designer may coordinate with the base building EOR just
before beginning cable fabrication. Large building deflections may
necessitate ordering cables slightly short to ensure that
architectural tolerances or cable thread travel are not
exceeded.
CABLE-NET PROJECT DESIGN Applicable Codes, and Design and
Performance Criteria As with any development in engineering
technology, there is a period of time where the system may still be
considered to be an unconventional system. As such, typical
building codes, which evolve over time to address the building
systems in conventional use, often do not provide requirements or
guidance for cable-net systems. Therefore cable-net designers must
look to the intent of the typical building codes and look to a
wider range of codes which provide guidance in the design of
components of the system. Knowing that cable-net walls systems are
flexible and deform out-of-plane when subject to lateral loads, the
primary design criteria to establish at the start of the project is
the span to deflection ratio that will be acceptable under the
design lateral loading condition. The 1997 edition of the Uniform
Building Code (UBC97), provides minimal guidance for deflection
control: Table 16-D restricts the live load deflection of floors
and roofs supporting plaster to L/360. The 2006 edition of the
International Building Code (IBC2006) provides more detailed
information concerning deflection criteria: Table 1604.3 lists
deflection criteria for gravity and lateral loads, including wind
loads on exterior walls. Again the focus on the deflection limits
is the protection of finishes from damage due to deformations of
the supporting structure, but the recommended limit of L/120 for
exterior walls with flexible finishes could arguably be considered
applicable for the design of cable-net walls. However for cable-net
wall systems, damage to finishes (excluding the glass panes
themselves) is generally not a consideration. The cable-net wall
system, including all of its components, is specifically designed
for the anticipated deflections, and the system is typically
detailed to avoid any conflicts with unrelated parts of the
building structure. The most important practical consideration for
establishing deflection criteria for a cable-net are related to
ensuring that the wall will remain air and water-tight as it
deforms, ensuring that the deformations are not large enough to
result in the flexural failure of any of the panes of glass, and
more general considerations of human perception and comfort.
Typically, before systems are too flexible to allow the first two
technical issues to be solved, the more subjective considerations
of human comfort limit the design. No building owner wishes to
construct a glass wall which feels unsafe to the building
occupants. For design of footbridges and floor systems human
discomfort can arise due to the accelerations felt by the person
traversing the span. In the case of cable-net wall systems, human
discomfort is most often associated with the visual observation of
large deflections in the glass wall. Although the appropriate
limitation is very difficult to quantify, established practice has
shown that a deflection range of L/40-L/50 is generally acceptable.
There are some notable exceptions to this rule-of-thumb, most
importantly that of proximity. A typical floor-to-floor exterior
wall system will have its maximum deflection occurring close to
occupant eye level in a location where the occupant can usually
stand immediately adjacent to the glass. In such cases the L/120
limit for exterior walls per IBC2006 may be appropriate. However
the typical cable-net wall is an atrium wall spanning several
floors. In this case the building occupants can only be adjacent to
the cable-net at the base of the wall where deflections are small.
Care should be taken when designing long-span cable-net walls when
building occupants may approach the net in an area where
deflections are large (such as an atrium footbridge at mid height
of the wall).
-
The design wind pressure that needs to be considered when
calculating the deflections of the cable-net wall is also a subject
of application of the intent of the code. The design wind event
should be that prescribed by the governing code (0.02 probability
of being exceeded in any given year per UBC97), and the appropriate
wind pressures can be established based on the location and
physical form of the building. Some engineers may determine that a
code-based approach for establishing the design wind pressure is
acceptable, however due to the unusually flexible behavior of the
walls, wind engineering studies are often recommended. For very
large walls aero-elastic wind tunnel studies that account for the
flexibility of the cable-net system in the wind tunnel model are
beneficial. Note that wind engineering study reports will generally
present recommended cladding design wind pressures, and structural
design wind pressures. In long-span cable-net structures it is
general practice to design the glass and glass attachments for
local effects due to the local application of cladding pressures on
each pane, and to design the system as a whole for the global
application of structural pressures (cable forces, and stresses in
the glass due to global deformations). This approach is reinforced
by IBC2006 table 1604.3 note f which allows the calculations of
deflections of supporting members to be made on the basis of
applied wind pressures of 0.7 times the component and cladding wind
loads. This design philosophy is intended to ensure that each pane
can withstand the application of localized peak gusts pressures,
whereas the system as a whole need only be designed to withstand
the maximum pressure likely to occur when averaged over the full
area of the wall. For the design of the components of the system,
specialist codes and guidelines must be used for each item. The
design of steel cables is not well covered in the typical steel
design codes used in the United States, but is well covered in
ASCE-19 Structural Applications for Steel Cables in Buildings
published by the American Society of Civil Engineers. The German
standard DIN 18800-1 Structural Steelwork, Design and Construction,
also provides design procedures for the design of steel cables. DIN
18800-1 is commonly the code used in the development of load tables
included in the product catalogues produced by the European cable
manufacturers. Analysis Methods For the simplest of cable-nets,
one-way spanning planar systems, hand calculations can be performed
to accurately calculate the behavior of the net under lateral loads
(see section concerning cable-net fundamental theory later in this
paper). However for more complicated conditions such as two-way
nets, irregular geometries, curved nets, or nets with non-rigid
boundary conditions, computer analysis modeling of the system is
required. Due to the highly non-linear response of cable-net
systems under out-of-plane loading, an analysis program with full
geometric non-linearity capabilities is essential. Additionally an
analysis program that has been specifically developed to include a
cable element as an inbuilt standard element type is usually a
significant advantage. This allows cables to be modeled as single
line elements in the analysis model from pin-to-pin. Some analysis
models require that cables be modeled as a series of individual
elements connected together in series, significantly complicating
the analysis model. Programs which have been successfully used by
SOM & ASI in the analysis of cable-net walls include S-Frame
written by Softek Services Ltd, and Space Gass written by
Integrated Technical Software Pty Ltd. Other programs include
RS-Tab by Ing.-Software Dlubal GmbH and Strand7 by Strand7 Pty Ltd.
It should be noted that due to the non-linear response of cable-net
systems, linear combinations of analysis load cases are not
applicable and all individual load cases and load combinations must
be analyzed in turn. Therefore analysis of complicated systems
subject to many load cases can result in very long analysis run
times. This is especially true when the analysis of the cable
system also includes an element of form-finding. The goal of the
analysis model is to represent the cable-net structure at the end
of the completion of construction and then investigate the effect
of additional loads that may be applied to the cable-net during its
service life. Generally the initial shape of the cable-net is a
known architectural form, and the Cable-Net Designer establishes
the initial pre-tension levels that are required to give the
cable-net sufficient stiffness to meet the deflection criteria when
subject to the design lateral load. This is a relatively simple
process when the initial geometry of cable arrangements and the
initial state of stress of the cables are independent variables.
This is best visualized by considering a planar rectilinear two-way
cable-net (such as the Kempinski Hotel cable-net described earlier
in this paper), after installation of the cables but prior to
installation of the clamps at cable intersections. At this point in
time the geometry of the nodes is fixed (including end points and
crossing points of all cables), but as each cable connects directly
between support points at opposite sides of the cable-net without
being physically connected to any of the other structural elements,
the level of pre-tension in any cable can be varied without
affecting any of the other structural elements. The process of
establishing the initial state of the cable-net is more complicated
if the initial geometry and initial stress state are not
independent. A simple example of this would be a anticlastic
cable-net. In this case each vertical cable forms a parabolic shape
curve in one direction, and each horizontal cable
-
forms a parabolic shape curved in the opposite direction. The
initial tension in the vertical cable and horizontal cables react
against each other at each of the cable crossing points. In this
example any change of initial tension in any one cable will result
in force redistribution to possibly all of the other cables, and
importantly a change in the initial geometry of the system.
Therefore establishing the initial geometry and initial stress
state is a complicated, often time consuming iterative process of
establishing a balanced configuration of initial pre-tension values
in the cables, maintaining the desired initial geometry, while
achieving the stiffness required to resist lateral loads. As
complicated as this form-finding process is in the analysis model,
the process is repeated at full scale in the construction of the
wall. A planar wall allows each cable to be stressed to its initial
pre-tension more or less independently, whereas the complex curved
wall will require a complex installation sequence taking into
consideration the effect of stressing one cable on all the other
cables. Interactions with Base Building Structure A significant
portion of the design of a cable-net wall is related to the design
of the areas around the perimeter of the cable-net wall. Due to the
parabolic displaced shapes typical of cable-net walls under lateral
loads, the relative rotations between adjacent glass panes are
small, but the rotations between the perimeter panes and support
conditions are large. Therefore the majority of architectural
detailing considerations relate to maintaining suitable movement
capacity at the perimeter to avoid glass damage as the cable-net
displaces. The structural design of both the cable-net and the base
building structure is significantly affected by the loads which are
transferred across and the displacements that occur at the
perimeter of the cable-net wall. Cable-net gain their out-of-plane
stiffness due to the high levels of pre-tension that is installed
in the cables during installation of the wall. These forces must be
transferred to the base building structure around the perimeter of
the wall. For larger cable-net walls these force levels can be a
significant contribution to the overall design demand on the main
lateral force resisting elements. The EOR needs to take into
consideration the forces applied to the structure in the permanent
condition (cable pre-tension) and the maximum cable force levels
that occur during the design wind event. The design of the
cable-net itself is also greatly affected by the structural
solution that is employed at the perimeter of the cable-net. There
are two principal base-building characteristics that influence the
design of the cable-net. The first relates to the stiffness of the
perimeter boundary condition elements. The cable-net is a flexible
structure, therefore the rigidity of the cable termination points
is critical in its efficient design. The second important point is
the careful consideration of the deformations of the support points
of the cables due to base building movement. This is particularly
important for tall cable-net walls and cable-net walls spanning
between separate structures. Racking of the cable-net wall due to
drift of the base building, and changes in cable tension due to
supporting structures at either side of the wall moving towards or
apart from each other must be carefully considered in the design.
Interactions with Building Officials Because the cable-net is
rarely integral to the stability of the building and its design may
lag that of the base structure, it is commonly treated as a
deferred submittal, approved in principle on the strength of the
base building AOR and EORs drawings and calculations at the time of
permitting for the building structure. When its design is complete,
drawings and calculations describing the cable-net are submitted.
Aspects of the net which have bearing on the AOR and EORs scope
should be addressed in their submittals at the time of permitting.
For instance, glass adjacent to a walking surface is required to be
safety glazing, and overhead glass must be laminated. These aspects
of the wall are depicted in the architectural plans submitted for
review. Structural plans and calculations should demonstrate that
support requirements of the cable-net wall have been met. Many
buildings with cable-nets are permitted on the basis of these
documents alone, however the cable-net designer retains liability
for his design. In cases where the wall and buildings performance
are linked by interaction effects or the building department has
concerns about the design of such an unusual feature, code
officials often take stronger interest in the design of the
cable-net system. Its designer may have to meet with them to
explain the technology and analysis methods, review case histories
of similar projects, and discuss the approval process and required
submittals. Especially on large projects, owners faade consultants
may play a supervisory role to supplement the checks of the
building department. They work to ensure that the design meets
code, project specification, and architectural requirements.
Because they specialize in faades, consultants often have a better
understanding of the design requirements and constraints of
cable-net walls and can play a constructive role in bringing the
project to successful completion. Large projects also often include
wind tunnel testing and faade mock-ups, both of which can be used
to help substantiate the cable-net wall design.
-
CONSTRUCTION IMPLEMENTATION
Construction Means & Methods Engineering. Because cable-nets
are relatively uncommon, few installers have experience erecting
them. Indeed, this is one of the primary reasons that cable-nets
are typically constructed on a design-build basis. The installation
sequence and procedure are planned in tandem with the design of the
wall. Clearances need to be allowed for the tensioning apparatus,
and provisions made for tension adjustment during the buildings
service life, should it be required. Planning also includes
determining the exact cable length to order, usually specified as a
length at a specific load. Pre-stretched cables are used to
minimize creep over their installed lifetime, but their effective
modulus of elasticity varies by cable construction and batch. Also
crucial to ensuring their fit is the base building EORs estimate of
deflection resulting from cable installation and the position
tolerance of that supporting structure. If cables are ordered after
the support structure has been installed and surveyed its tolerance
need not be considered. Ordering cables at their service tension
and having a reasonable estimate of the support deflection ensures
they will fit properly. However, it is still important to know
their approximate modulus of elasticity to ensure that tensioning
is possible. A cable expected to stretch 50mm during installation
needs to have at least 50mm of free thread to tension by. In
practice it needs far more thread than that to accommodate erection
tolerance, jacking apparatus and permanent connection hardware.
Temperature loads are a further factor to consider in planning an
installation. Indeed, they must be considered throughout the walls
design. Typical operating temperature ranges for buildings are
relatively well defined and controlled, but until construction is
complete and the building is enclosed and occupied, the range can
be quite large. This affects both the cable tension at time of
installation as well as the installation sequence. If the site is
very cold, the cables must be installed with a higher tension value
than their service tension since they will relax once the building
is enclosed and conditioned. This can affect the tensioning
sequence if the required tension exceeds the allowable temporary or
permanent load for the cables, depending on the installation
duration. The tensioning sequence represents the final component of
means and methods engineering, and can be used to solve issues
related to temperature limitations. If need be, the cables might be
tensioned to a percentage of their service tension, the building
then enclosed and conditioned, and the cables finally brought to
their full tension. In such a scenario the cable-net designer would
need to verify the walls ability to perform at a reduced tension
for a specified period of time. ASCE 37-02, Design Loads on
Structures During Construction, gives guidance on load adjustments
based on various durations. Installation Sequence and Tensioning
Layout and survey of the cable anchor positions are the first and
arguably most important steps in the installation of a cable-net.
Small changes in length or geometry can dramatically affect the
cable tension, ability to properly tension the net, or the fit up
of the glass, so it is essential that the anchors are placed in the
correct positions. By designing adjustable connection points and
allowing an additional length of threaded cable end, the cable-net
designer can ease this first step. Provided that the anchors have
been properly located, the remainder of installation can be
relatively simple. Cables are hung, tensioned, and clamped
together. Selected nodes may then be surveyed and the glass
installed and caulked. Though the process is simple, it is
important that the cable-net installer work with the buildings
general contractor (GC) to schedule and coordinate the
installation. The base building EOR should be notified sufficiently
in advance of the planned tensioning to be able to plan a
structural observation visit to the job site. Though the visit may
be informal, its focus should be to ensure that the perimeter
structure supporting the wall has been properly installed,
necessary welds completed, and concrete sufficiently placed and
cured. Because ultimate responsibility for proper installation
rests with the GC, it is important that the cable-net installer
educates the GC about the installation procedure and coordinate its
scheduling. Cable hanging and preparation for jacking may take just
a few days or weeks depending on the size of the wall, but when
ready the actual tensioning operation can take just a few hours.
Hydraulic jacks are required to bring the cables to full tension
for all but the smallest of walls. In a typical arrangement a
hollow-core jack is mounted on a jacking chair that straddles the
threaded cable end swage. On the swage are a permanent nut, the
jack, and a temporary nut used during
-
tensioning. The jack is extended, engaging the temporary nut and
tightening the cable. The permanent nut is run down snug against
the cables ultimate bearing surface and pressure is released from
the jack, allowing it to be disassembled. Commonly, jacks are
installed on multiple cables and pulled simultaneously, linked to a
common hydraulic reservoir. In this manner the actual tensioning
can be completed with relative speed.
Figure 14. Cable jacking
Figure 15. Cable tension measurement
Installation is completed with affixing or tightening the cable
clamps, which are often installed at the same time the cables are
hung, and with placement of the glass. Provided that the cable
anchors were properly located and installation correctly planned,
the glass often installs very easily. Here, again, the cable-net
designer can do much to ease installation by detailing adjustable
connections between the nodes and the glazing. This serves as
further evidence of the advantage of design-build contractors in
completing a successful cable-net project.
Figure 16. Glass installation
Figure 17. Caulking of joints
Post Construction Performance. Once construction is complete and
the building enclosed, the cable-net has relatively few
requirements beyond occasional cleaning and tension monitoring.
Cable tension is generally checked one hundred hours after initial
tensioning, and record tensions are taken once glass has been
installed. The record tensions should be noted on as-built drawings
submitted at the completion of the job. Typically tension
measurements are then performed after one year and every five years
thereafter to ensure that the wall is working as it was designed
and no significant creep or other factors have affected its
capacity.
-
CABLE-NET FUNDAMENTAL THEORY
Planar cable-net walls derive their out-of-plane stiffness from
the geometric non-linearity behavior of a flexible element spanning
between pinned supports. The element has negligible bending
stiffness, but its axial stiffness provides resistance to lateral
deformation into an alternate configuration that will necessarily
be of a longer length that the original straight line connection
between two points. Therefore, the elastic potential energy stored
in the extended elements in the deformed shape can be equated to
the work performed by the applied load displacing from the original
to the deformed shape. Although the cables can deform into any
number of configurations due to uneven load conditions, the
deformed shape of a single cable under a uniform distributed
lateral load w, can be shown to be a parabola of the form of
equation (1). This differs from the typical hanging chain catenary
profile due the fact that the wind load can be assumed to be
uniform along the length that is a horizontal projection of the
deformed shape: 2xay = (1) The parabolic displaced shape under a
constant projected horizontal load can be verified with the
following proof:
Figure 18. Parabolic free body diagram
The horizontal component of force in the cable (TH) is constant.
The vertical component of force in the cable (Tv) increases
linearly with respect to x from zero at the center to wL/2 at the
support: xwTV = (2) Taking moments around the origin for a free
body extending from the origin to an arbitrary point on the curve
(figure 14):
( )xxwTyxxw H =+
2
(3)
22
xTwy
H
= (4)
As the applied load and the horizontal cable tension is
constant, the cable will deflect to a parabolic form, with the
parameter:
HT
wa2
= (5)
-
If we consider the maximum allowed ratio of deflection under
wind loading to span be a constant, R.
RLy =max when 2
Lx = (6)
Equating (1) & (6):
2
2
=
LaRL
(7)
LR
a 4= (8)
The angle of deviation the cable makes at the intersection with
its support point is:
=
H
VMAX
TT1tan (9)
Equating (5) & (8)
8
LRwTH = (10)
2
wLTVMAX = (11)
Gives:
=
R4tan 1 (12)
For any given span to deflection ratio R, the shape of the
deflected cable is similar: parabolic with a fixed angle of
deviation at the supports that is independent of the span. For the
condition R = 45, as used in the design of the New Beijing Poly
Plaza project described in more detail later in this paper, the
angle of deviation at the supports is approximately 5.1 degrees. As
the deflected shape is similar for a given value of R, we know that
the ratio of extended length to initial length is constant. The
length of the parabolic shape can be established through the
summation of a series of small sections of the parabola.
( ) dxdsS L= 2/02 (13) By Pythagoras rule: 222 dydxds +=
(14)
+= 2
2
1dxdy
dxds
(15)
dxxaSL += 2/0 22 )41(2 (16)
-
The integral is can be shown to equate to:
( )
++=
aaLLaLS
4sinh1
42
122 (17)
Substituting with equation (8) gives:
++=
16
4sinh116
412
1
2R
R
RLS
(18)
That average geometrical strain in the cable due to the
deformation under lateral load is constant for a given value of
R:
00132.01 == L
SAVG when 45=R (19)
The strain varies with the tension in the cable, from a minimum
at mid-span, to a maximum at the supports:
( ) ( )
+
=2
2
2xw
awxT (20)
( ) ( )22412
xaa
wxT += (21)
The average tension in the cable will be:
dxxTL
TL
AV = 2/0 )(2 (22) By analogy to the integration of equation 16
is:
++
=
16
4sinh116
412
8
1
2R
R
RLRwTAV (23)
HAV TT 00132.1= when 45=R (24) The average tension in the cable
and the average geometrical strain in the cable due to its
deformation under lateral load are both independently fixed for a
design solution that meets the design span to deflection ratio.
This apparent incongruity is explained by the fact that although
the average tension in the cable is fixed by the geometry and
loading condition, this tension can be achieved by a combination of
initial pre-tension in the cable and additional tension due to
elastic strain: EATT AVGiAV += (25)
-
For a given geometry and loading condition, there are a series
of compatible pairs of axial stiffnesses and pre-tensions which
will exactly meet the deflection criteria. These range from the
impractical: zero pre-tension and large axial stiffness, to the
implausible: pre-tension equal to the average tension in the cable
under lateral load and effectively zero axial stiffness. As the
elastic modulus of a given material is fixed, reducing the
stiffness requires reducing the cable area. As the maximum cable
tension is defined by the loading condition and geometry, there
becomes a point when the cable size is reduced to the point of not
having adequate strength capacity to resist the design load
conditions. Knowing the material characteristics of the proposed
cable elements, we can establish the minimum cross-section that can
resist the design tension. This will result in the compatible pair
with the highest pre-tension, however there is generally no
negative economic effect on the design of the adjacent supporting
structure. Although the pre-tension is high, the design of the
supporting structure is typically controlled by the maximum in
service tension and not the pre-tension force. Special conditions
such as flexible support conditions consisting of materials
adversely affected by high permanent load conditions (concrete or
timber) may warrant the selection of a compatible pair of higher
axial stiffness and lower pre-tension. For R = 45: kNLwTH 625.5=
(26)
kNLwTVMAX 5.0= (27)
kNLwTAV 632.5= (28)
kNLwTMAX 647.5= (29) If we use Pfeifer GmbH 1x61 and 1x91
stainless steel spiral strand cables in the diameter range of 20mm
to 36mm (a range which includes the most common sizes in cable-net
wall construction), we can then establish from the manufacturers
published technical data the elastic modulus of the cables and an
appropriate design stress limit in the cables. The design stress
limit value does not vary significantly for the range of cable
diameters considered:
2.130 = mmkNE (30)
2, .688.0 = mmkNA
Z dR (31)
For the above example the minimum cable area shall be:
22 208.8688.0
mmLwmmTA MAXMIN == (32)
And maximum compatible pre-tension value shall be: kNLwEATT
MINAVAVMAXi 224.4== (33) The above results confirm that the minimum
required cable area, the compatible pre-tension value, and the
maximum cable tension under design loading conditions are all
linearly proportional to both the length of span under
consideration and the uniform lateral load. As an example, a
one-way spanning cable-net consisting of 22mm diameter cables (A =
281mm2) could be designed to span 22.8m when subject to a uniform
lateral load of 1.5kN.m-1 per cable. The pre-tension for this
solution would be 145kN, and the maximum design tension in the
cables would be 193kN.
-
PARAMETRIC ANALYSIS STUDIES
To verify the theoretical results of the previous section, a
series of parametric studies on the required cable sizes and levels
of pre-tension that would be required to install cable-net systems
of varying sizes were performed. Analysis models were created to
study both one-way and two-way spanning cable-net systems. To
minimize the number of variables involved the following parameters
were set for each of the models considered: y The design loading
condition was set at 1kN.m-2. y The span to deflection ratio was
set at 45 under the design loading condition. y The cables were
limited to Pfeifer GmbH stainless steel spiral strand cables in the
following configurations: 1x37 (6-
18mm), 1x61 (20-28mm) and 1x91 (30-36mm). y The cable-net
spacing was set at 1.5m. y For two-way models the cable-net model
was always square with equal cable sizes and pre-tensions in
each
direction. The analysis models were built using S-Frame version
6.22 (written by Softek Services Ltd.), a three-dimensional
analysis program capable of accurately modeling the geometric
non-linearity of cable elements under lateral loads. All elements
were modeled as S-Frame cable elements, each 1.5m long between
nodes. Lateral loads were applied as node loads at 1.5m on center.
This loading condition represents the load transfer to the cables
through the glass support fittings.
Figure 19. Span vs. cable area (one-way)
Figure 20. Span vs. cable pre-tension (one-way)
The results of the one-way cable-net analysis models support the
theoretical relationships established in the previous section. A
clear linear relationship is observable in the data points
resulting from the analysis models (figures 19 & 20). When
plotted against the theoretical linear relationships established in
the previous section, we see that the data points differ from the
theoretical relationship by varying degrees. The reason for this
variation is that the cable selection is limited to the 16 discrete
cable sizes available in the diameter range from 6-36mm (note that
the 75m span analysis model requires the use of a cable diameter
larger that those available an estimated cross sectional area was
used for a 40mm diameter in this case although limitations on the
cable end fitting technology may preclude the use of such a cable).
The cable-net models were built using cable lengths that were
multiples of the typical glass size, and the cable size selected
was the next larger size available than the minimum cable area
theoretically required. Certain data points which are close to the
theoretical relationship represent situations when the required
area was just less than an available cable, for other data points
the next largest cable size was significantly larger than the
minimum required. All analysis model cable area data points are
above the theoretical relationship. A similar situation can also be
observed in the data points relating required pre-tension to span
length. As the modeled cable sizes are all larger than the minimum
required, the compatible pre-tension values are all lower than the
theoretical maximum pre-tension values. Given these limitations the
correlation between analysis model and theory is very strong.
-
A further investigation into the behavior of two-way cable-net
configurations has also been performed to investigate the
additional efficiency and span capability that can be achieved by
running pre-tensioned cables in two-directions across a square
wall, rather than in one direction alone. We observe from the
analysis results that the relationship between span and required
cable area as well as between span and required pre-tensioning,
appear to maintain the linear relationships observed in the one-way
theoretical and analytical studies (figures 21 & 22). The
analysis results indicate that the two-way cable-net system is
capable of achieving a certain span to the same deflection criteria
and resisting the same lateral loading condition, employing the use
of both smaller cables and lower pre-tension values. This does not
however necessarily indicate that the two-way cable-net system is
more efficient. As both analysis models considered a cable spacing
of 1.5m, the two-way system uses twice as many cables to support a
square cable-net wall as the one-way cable-net system of equivalent
dimensions. To evaluate the relative efficiencies of the two
different cable-net systems, a more telling comparison is between
the two-way system and a one-way system with an equivalent density
of cables per unit area of wall supported. Doubling the horizontal
cable density in a one-way cable-net system is equivalent to
reducing the applied lateral load per cable by one half. As shown
in equations (32) & (33), the effect of this reduction in
lateral load per cable is a 50% reduction in minimum area and
maximum pre-tension required.
Figure 21. Span vs. cable area (two-way)
Figure 22. Span vs. cable pre-tension (two-way)
Plotting the theoretical relationships determined for the
one-way cable-net system with a reduced cable spacing of 750mm we
see that the two-way analysis model requires greater cable sizes
and pre-tension loads that the one-way system. This suggests that
the two-way system is less efficient than the one-way system of
equivalent cable density. This is supported by an evaluation of the
status of each of the cables in the two-way system under the
lateral load condition. When the center cables in each span
direction exactly meets the specified defection criteria, the other
cables running parallel to these deflect to lesser degrees. If all
the cables are designed to the same criteria, most of the cables
are under utilized, reducing the efficiency of the system. All the
cables in the one-way system can be simultaneously fully utilized.
If we design each cable in a two-way system with a span to
deflection ratio that is compatible with the deflection of the
whole system, we can hypothesize that the efficiency of the one-way
system can be equaled. This would require varying cable sizes and
levels of pre-tension which would complicate the detailing and
installation, potentially resulting in higher overall costs. While
the efficiency of the one-way system is high, the detailing of the
boundary conditions is complicated. Two sides of the cable-net
deflect through the know angle of deviation of the parabolic
displaced shape, however the other two sides must be detailed to
accommodate a sliding condition caused by the maximum cable-net
displacement also occurring close to two sides of the net. This
difficult problem is avoided with a two-way system which has small
deflections at all sides of the cable-net.
-
PROJECT EXAMPLE THE NEW BEIJING POLY PLAZA
Architectural Concept The clients goal is for a new headquarters
building that represents the companys disparate subsidiaries as a
unified whole. The program for the building contains a wide range
of spaces including office, retail, restaurants and the Poly
Museum. The museum, established by one of the companys
subsidiaries, has the unique purpose of repatriating Chinas
cultural antiquities through purchases at international auctions.
The project is prominently located at a major intersection along
Beijings second ring road, northeast of the Forbidden City. The
sites primary orientation is northeast towards the intersection and
beyond to the clients existing headquarters building. The
triangular form minimizes the perimeter length exposed to the
elements, while a series of interior atria provide additional
interior surface area to give office areas maximum access to
daylight. The result is a simple L shaped office plan that cradles
a large atrium (figure 23).
Figure 23. Atrium concepts.
Figure 24. Museum lantern.
Figure 25. Northeast rendering
The Poly Museum is suspended within a lantern in the main atrium
space (figure 24). Its crystalline surface of laminated patterned
glass is pleated to increase its light reflecting/refracting
qualities (figure 25). Inside the lantern, exhibit and lease spaces
are enclosed by wood walls which control daylight while common
circulation areas occupy the void between the solids and the glazed
perimeter walls. Secondary sunset and all-day atria cut through the
west (figure 26) and south (figure 27) legs of the L to act as
daylight chambers for bringing direct sunlight into the main
atrium. The exterior walls of these atria are comprised of minimal
glass membranes, supported by two-way cable-nets in order to
maximize visual and solar transparency. The main atriums cable-net
is stiffened by two V-cables that are in turn counterweighted and
kept in tension by the self-weight of the suspended museum
lantern..
-
Base Building Structural System The base building is a composite
concrete and steel structure, roughly triangular in shape, and 24
stories tall above grade. The lateral system is a dual system
consisting of reinforced concrete shear wall cores at the three
corners of the building, (figure 28), and steel moment resisting
frames in the north-south and east-west wings. The floor framing
system above grade consists of structural steel trusses acting
compositely with metal deck slabs and lightweight concrete fill.
The building also has a rectangular four-story basement, the lowest
slab being located at approximately 20 meters below surrounding
grade. Gravity framing in the basement consists of conventional
concrete beam and slabs framing. The structure is underlain by a
mat foundation anchored against hydrostatic uplift using tie-down
anchors, where required. Two areas of the base building structure
required special treatment. The first area was the entire south
wing of the building. To open the atrium up to direct sunlight from
the south, steel columns in the southern wing do not continue below
the tenth floor creating a bridge between the cores and columns at
the east and west ends. The bridge structure is supported by
vierendeel trusses over its entire height from level 10 to level 24
(figure 26). The bridge structure is considered part of the lateral
system, acting, along with the columns at each end as a mega frame.
The bridge and floor slab diaphragms tie the three cores of the
structure together to form a monolithic structure, modeled and
analyzed as such (figure 28). Lightweight concrete fill was
typically used on metal deck floor slabs, but critical connecting
diaphragms at the bottom of the vierendeel structure and at the top
of the tower, used a thickened normal weight slab with supplemental
diaphragm shear reinforcement..
Figure 26. Typical high-rise plan
Figure 27. Typical low-rise plan
-
Figure 28. Reinforced concrete cores
Figure 29. Lanternstructural system
The second area requiring special engineering treatment was the
museum occupancy termed the lantern, which protrudes from the
southeast core towards the building atrium. The lantern consists of
an eight-story tall (starting at level 2) cross-braced steel frame
that cantilevers 24m from the building core. There are no column
elements underneath the lantern. The tip of the cantilevered frame
is effectively propped by its connection to the primary diagonal
cables which simultaneously stiffen the cable-net wall (figure 29).
The gravity load bearing elements of the lantern are the southeast
building core, and the primary diagonal cables which transfer
gravity loads back to the cores at the top of the building. To
provide a redundant gravity load path, the braced frame of the
lantern has been designed to achieve a life-safety performance
level when cantilevered from the shear-wall core without the load
supporting benefit of the primary diagonal cables. Lateral forces
in the lantern are resisted by the shear wall core at the
south-east side acting as a torsion box. The shear wall core is
torsionally restrained by the ground floor slab at level 1 and by
its connection to the main building through the level 12 and higher
level diaphragms. The lantern floor diaphragms transfer the lateral
force to the core on a level by level basis. The Cable-Net Wall The
New Beijing Poly Plaza project includes a 90 meter-tall atrium
enclosed by a cable-net glass wall, 90 meters high by 60 meters
wide. The scale of this wall greatly exceeds that which has been
built before, introducing specific challenges that are not critical
in smaller walls. SOMs preliminary analysis showed that the
cable-net spans were too large to be economically achieved using a
simple two-way cable-net design. SOM determined however that the
cable-net could be achieved by subdividing the large cable-net area
into three smaller zones by folding the cable-net into a faceted
surface, and introducing a relatively stiff element along the fold
lines. The faceted cable-net solution allows the individual
sections of the cable-net to span to a virtual boundary condition
at the fold line, effectively shortening the spans. Rather than
introduce a major beam or truss element to stiffen the fold line, a
large diameter cable under significant pre-tension is used. The
cable-net wall system was designed to meet a span to deflection
ratio limit of 45, when subjected to the service level wind load
condition (50-year wind event). The cables were designed to meet
the requirements of ASCE 19-96: Structural Applications of Steel
Cables for Buildings. The design strength load factors of ASCE
19-96 were increased from 2.0 and 2.2 (depending on load condition)
to 2.5 to meet additional requirements set by the committee of
Chinese Structural
-
Engineering Experts reviewing the design of the project. In
addition to the application of increased load factors, the cable
design forces were based on the internal forces resulting from a
higher level wind condition (100-year wind event). The 50-year and
100-year wind loading conditions were determined through careful
wind engineering studies performed by Beijing University. The wind
studies included a traditional rigid model of the building massing
placed within a proximity model, and an aero-elastic wind tunnel
study. The aero-elastic study was performed on a flexible model of
the northeast cable-net wall, constructed using wires and a
flexible membrane and tuned to simulate the anticipated dynamic
response of the cable-net system. This study allowed the effect of
feedback between the dynamic behavior of the cable-net and the wind
forcing function to be considered. This additional study was used
to verify and modify where appropriate the results of the rigid
model study. Analysis and testing shows that the New Beijing Poly
cable-net wall behaves very much as conceived. The results from the
static non-linear analysis (geometric non-linearity) clearly show
that the strategy of subdividing the wall into facets with shorter
individual spans was successful (figure 30). This strategy allows
the overall displacements to meet the L/45 deflection limit between
hard boundary conditions while maintaining the economic viability
of the project.
Figure 30. Deflection under static wind load condition
Figure 31. Sub-division of cable-net wall
The final design solution was achieved with the largest of the
four primary cables 275mm in diameter and consisting of a parallel
strand bundle of 199 individual 15.2mm diameter 1x7 strands. The
largest cable is pre-tensioned to 17,000kN, and experiences a
maximum in service loading of 18,300kN during a 100 year wind
event. Using the faceted design solution, the typical horizontal
and vertical cables are limited in diameter to 34mm and 26mm,
pre-tensioned to 210kN and 100kN respectively. Horizontal and
vertical cables are spaced at 1333mm and 1375mm on center
respectively (figure 31).
-
The Rocker Mechanism The four primary diagonal cables which
support the self-weight of the lantern connect diagonally from the
roof of the museum lantern at level 11, to the top of the atrium at
level 23. As the base building structure will drift under
anticipated seismic loads, the cables will act as braces and
attempt to resist the base building drift unless the force levels
in the cables are limited in some manner. Designing the primary
diagonal cables to resist these brace forces while maintaining an
appropriate factor of safety would have significantly increased the
primary diagonal cable sizes that as employed in the final design
solution. This would also have resulted in the initial level of
pre-tension in the primary diagonal cables being a lower portion of
the cable breaking strength, to accommodate the additional brace
demands. Pre-tensioned cable systems typically rely on a high
initial level of pre-tension to maintain the desired architectural
form in the permanent load condition. When cable systems are
installed with only a nominal level of initial pre-tension, the
tendency of that system to exhibit significant deflections due to
the self-weight of the cables is greatly increased. Therefore, it
was determined that the design solution required that the primary
diagonal cables (the only cables that may act as braces) be
decoupled from the lateral system of the base building structure.
The connection between the primary diagonal cables and the roof of
the lantern is complicated by the need to decouple the primary
cables from the lateral system of the base building structure, and
to simultaneously provide a flexible wall system which allows the
relative lateral movements between the roof of the lantern and the
roof of the building to be incrementally accommodated over the
height of the cable-net. Several connection concepts were evaluated
before the final design solution was determined. One option
connected the main cables to the lantern roof through a sliding
connection (figure 32). This solution was difficult to achieve due
to the resulting eccentric load path of the very large primary
cable forces through the eccentric connection when the connection
was displaced. It also resulted in the upper half of the cable-net
moving with the roof of the building, and one course of glass at
the roof of the lantern being required to accommodate the full
drift between the roof of the building and the roof of the lantern.
This resulted in this course of glass likely to fail given any
significant lateral displacement of the building, causing a safety
hazard in the atrium and street below. A second concept connected
the bottom of the V cables to the top of the lantern through a 4m
tall, pin-ended link element (figure 33). This solved the load
eccentricity issue, but still resulted in the relative lateral
drift of the upper half of the cable-net being concentrated in a
small portion of the wall. This solution also induced tension in
the main cables as the building drifts due to the downward movement
of the lowest point of the cables caused by the rotation of the
link around its base. The concentration of a significant portion of
the lateral drift of the building in a 4m high zone still resulted
in the high likelihood that glass panels would be lost during the
design level lateral drift event, representing an unacceptable risk
to the occupants of the building and adjacent outdoor spaces.
Figure 32. Slider connection concept Figure 33. Link connection
concept The final solution is shown diagrammatically in figure 22.
The decoupling mechanism consists of the equivalent of a pulley at
the lower point of the V cables. As the overall building drifts,
one half of the V tries to lengthen and the other half tries to
shorten. By connecting them together using a pulley or equivalent
mechanism, the strains are able to offset each other, without
inducing additional load in the cables. A cast steel rocker
mechanism was designed to perform the equivalent
-
function of the pulley. By crossing the cables and connecting to
the rocker casting arms, the need to provide curved pulley surfaces
and curved sections of the main cable were eliminated (figure 34).
The rocker mechanism solution allows the load path at the
connection to be concentric, and also allows the relative lateral
drift of the upper half of the building to be distributed through
the upper portion of the cable-net wall. Small relative movements
between adjacent nodes on the main diagonal cables and the
cable-net cables are accommodated using pin-ended tie-rod
connections.
Figure 34. Pulley equivalent concept
Figure 35. Rocker clevis castings on site
Figure 36. The installed rocker mechanism
To evaluate the effectiveness of the design solution prior to
completing in-depth analysis of the system, a physical model of the
rocker mechanism was built along with a model of the link concept
for reference comparison. The models were installed in a
pin-connected frame, with soft springs installed in series with the
diagonal cables. By racking the frame backwards and forwards, the
relative effectiveness of the two concepts could be visually
evaluated. The physical model test demonstrated significant
extension in the springs using the link model and negligible
extension in the springs using the rocker mechanism model,
highlighting the ability of this connection to decouple the main
cables from the base building lateral system. The final design of
the rocker mechanism included five large castings per connection.
The main cable clevis castings are approximately 4m in length. The
clevis castings are designed to pass through each other to maintain
concentric load paths through the connection (figures 35 &
36).
-
Summary At 90m tall by 60m wide, the New Beijing Poly Plaza
represents a significant step in the design of cable-net wall
systems. Completed in December 2006, the wall is believed to be
four times larger than any cable-net wall system built to date. The
engineering challenges of a cable-net wall of this scale required
creative approaches to solving issues that have likely not been
addressed on smaller projects. The design solution for the rocker
mechanism is an example of an innovative design solution that
employs conventional technologies to solve a truly unconventional
problem. The architectural design team quickly embraced the rocker
mechanisms as the central components of the machine that is the
structural system of this atrium. As keystones through which the
lantern and the cable-net support each other in a symbiotic
relationship, the rocker mechanisms are celebrated accordingly.
Prominently located in the center of the atrium picture window,
they are approachable from the lantern rooftop caf and are expected
to become a focal point in the experience of this building.
Figure 37. The New Beijing Poly Plaza
Diameter (mm) Spacing (mm)
Pre-tension (MN)
Main V cables 235-275 - 11.4-17.0
Horizontal 34 1,333 0.18-0.25
Vertical 26 1,375 0.08-0.10
Figure 38. Cable summary statistics
Acknowledgements Client: China Poly Group Design Architect:
Skidmore, Owings & Merrill LLP Design Engineer: Skidmore,
Owings & Merrill LLP AOR / EOR: Beijing Special Engineering
(base building) & Design Institute Cable-Net Yuanda /
Contractor: ASI Advanced Structures Inc.