Top Banner

of 50

3. Project Analysis Tools

Apr 14, 2018

Download

Documents

Chan Siew Chong
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • 7/30/2019 3. Project Analysis Tools

    1/50

    1

    Project Scheduling

    Faculty of Applied Engineering and Urban Planning

    Civil Engineering Department

    Week ( 6 + 7 )

    Lec. ( 11 + 12 + 13 + 14 )

    2nd Semester 2008/2009

    UP Copyrights 2008

    ConstructionProje

    ct

    M

    anagement

    Eng: Eyad Haddad

  • 7/30/2019 3. Project Analysis Tools

    2/50

    2

    CH4: Project Scheduling

    Construction Project management functions:

    Scheduling = Planning + Time

    Scheduling is the determination of the timing of the activities comprising

    the project to enable managers to execute the project in a timely manner.

    1. Planning

    2. Organization

    3. Supervision

    4. Control

    1. Time

    2. Cost

    3. Quality

    4. Performance

    Scheduling

  • 7/30/2019 3. Project Analysis Tools

    3/50

    3

    CH4: Project Scheduling

    The project scheduling is used for:

    1. Knowing the activities timing and the project completion time.

    2. Having resources available on site in the correct time.

    3. Making correction actions if schedule shows that the plan will result in

    late completion.

    4. Assessing the value of penalties on project late completion.

    5. Determining the project cash flow.

    6. Evaluating the effect of change orders on the project completion time.

    7. Determining the value of project delay and the responsible parties.

  • 7/30/2019 3. Project Analysis Tools

    4/50

    4

    4.2 The Critical Path Method (CPM)

    The critical path can be defined as

    the longest possible path through the "network" of project activities.

    (CPM) is the most widely technique used for scheduling, it calculates the

    minimum completion time for a project along with the possible start and

    finish times for the project activities.

  • 7/30/2019 3. Project Analysis Tools

    5/50

    5

    4.2 The Critical Path Method (CPM)

    The critical path itself represents the set or sequence of activities

    which will take the longest time to complete.

    The duration of the critical path is the sum of the activities'

    durations along the path.

    Duration of the critical path represents the minimum time required

    to complete a project.

    Any delays along the critical path would delay the project.

    More than one critical path may be among all the project activities,

    so completion of the entire project could be delayed by delaying

    activities along any one of the critical paths.

  • 7/30/2019 3. Project Analysis Tools

    6/50

    6

    4.2 The Critical Path Method (CPM)

    For example,

    a project consisting of two activities performed in parallel that each

    requires three days would have each activity critical for a completion in

    three days.

    Critical path scheduling assumes that a project has been divided into

    activities of fixed duration and well defined predecessor relationships.

    A predecessor relationship implies that one activity must come

    before another in the schedule

  • 7/30/2019 3. Project Analysis Tools

    7/50

    7

    The CPM is a systematic scheduling method for a project network and involves

    four main steps:

    1. A forward path to determine activities early-start times;

    2. A backward path to determine activities late-finish times;

    3. Float calculations ( Free & Total ) float; and

    4. Identifying critical activities.

  • 7/30/2019 3. Project Analysis Tools

    8/50

    8

    4.3.1 Activity-on-node networks calculations

    The objective of arrow network analysis is to compute each event in the

    network its early and late timings. These times are defined as

    Early event time (ET) is the earliest time at which an event can occur,

    considering the duration of preceding activities.

    Late event time (LT) Is the latest time at which an event can occur if the

    project is to be completed on schedule.

    i jx

    ETj LTjETi LTi

    dx

    . Forward Path:1

    ETj = ETi + dx

  • 7/30/2019 3. Project Analysis Tools

    9/50

    9

    . Forward Path:1

    1 3

    5

    7

    9 11

    0

    Project

    Start=0

    A

    d=3

    C4

    E

    5

    B

    3

    D

    6 d2

    d13

    Es+d=EF

    6

    3+3=60+3=3

    9

    6+0=6

    3+4=7

    9+0=9

    14

    9+5=14

    9

    3+6=9

    1A

    Project

    Start=0

    1A

  • 7/30/2019 3. Project Analysis Tools

    10/50

    10

    . Backward Path2LS = LF d

    1 3

    5

    7

    9 11

    0 0

    3-3=0

    A3

    C4 E5

    B

    3

    D

    6 d2

    d13 3

    9-4=5

    6 9

    9-0=9

    9-6=3

    9 9

    14-5=9

    LF-d=LS

    14 14

    9 9

    9-0=9

    9-3=6

  • 7/30/2019 3. Project Analysis Tools

    11/50

    11

    3. Float Calculations:

    First, let's tabulate the information we have as shown in next Table

    One important aspect is Total-Float (TF) calculations, which determine the

    flexibility of an activity to be delayed.

    Total Float (TF) = LF EF

    = LS ES

    :TF.

    Free Float (FF) = ETj ETi d

    or FF = smallest ES (of succeeding activities) EF (of current activity)

    :FF.

  • 7/30/2019 3. Project Analysis Tools

    12/50

    12

    3. Float Calculations:

    Total Float (TF) = LF EF

    = LS ES

    :TF.

    Free Float (FF) = ETj ETi d

    or FF = smallest ES (of succeeding activities) EF (of current activity)

    :FF.

    i j

    ES EF

    A

    LS LF

    AOA

    ES EF

    ES EF

    A

    B

    LS LF

    LS LF

    ES EF

    A

    LS LF

    AON

    TF

    i j

    ES EF

    A

    LS LF

    AOA

    i j

    ES EF

    B

    LS LF

    AOA

  • 7/30/2019 3. Project Analysis Tools

    13/50

    13

    Total Float (TF) = LF EF = LS ES

    Free Float (FF) = ETj ETi d

    or FF = smallest ES (of succeeding activities) EF (of current activity)

    Critical

    Activity

    TotalFloat

    (TF)

    LateFinish

    (LF)

    EarlyFinish

    (EF)

    Late Start

    (LS)

    EarlyStart

    (ES)

    DurationActivity

    Yes033003A

    No396633B

    No297534C

    Yes099336D

    Yes01414995E

  • 7/30/2019 3. Project Analysis Tools

    14/50

    14

    4.3.2 Precedence Diagram Method (PDM):

    Precedence Diagram Method (PDM) is the CPM scheduling method used for AON

    networks and it follows the same four steps of the CPM for AOA method.

    Forward PathForward path can proceed from one activity to the other; the process is as

    follow .

    3 6

    B(3)

    3 7

    C(4)

    3 9

    D(6)

    0 3

    A(3)

    9 14

    E(5)

    Earlystart

    Name(duration)

    Earlyfinish

    Latestart

    Latefinish

    6,7,or 9

    Fig. 4.8: Forward Path in PDM Analysis

  • 7/30/2019 3. Project Analysis Tools

    15/50

    15

    Backward Path:

    3 6

    B(3)

    3 7

    C(4)

    3 9

    D(6)

    0 3

    A(3)

    9 14

    E(5)

    Earlystart

    Name(duration)

    Earlyfinish

    Latestart

    Latefinish

    6,5, or 3

    149

    96

    95

    93

    30

  • 7/30/2019 3. Project Analysis Tools

    16/50

    16

    Floats

    Activity A7 days Activity B13 days Activity C4 days

    Start CompletionProject duration = 24 days

    CASE 1: All activities are critical: total float and free floats for all activities = 0

    Activity A

    7 days

    Activity B

    13 days

    Activity C

    4 days

    Start CompletionTotal Float = 5Free Float = 5

    CASE 2: Activity sequence in which one activity has total and free float

    Activity D

    8 days

    Activity A

    7 days

    Activity B

    13 days

    Activity C

    4 days

    Start Completion

    Total Float of D = 5 Total Float of E = 5

    Free Float of D = 0 Free Float = 5

    CASE 3: Activity sequence illustrating total and free float

    Activity D

    5 days

    Activity E

    3 days

  • 7/30/2019 3. Project Analysis Tools

    17/50

    17

    2-Floats

    Areas of shared float

    Activity duration Total Float

    Start Event Finish Event

    TLi TEjTEi TLj

    Activity duration Free Float

    Activity duration Independent Float

  • 7/30/2019 3. Project Analysis Tools

    18/50

    18

    Float Calculations:

    Total Float (TF) = LF EF= LS ES

    Free Float (FF) = ETj ETi d

    Duration

    3

    3

    46

    5

    ES

    0

    3

    33

    9

    LF

    3

    9

    99

    14

    LS

    0

    6

    53

    9

    EF

    3

    6

    79

    14

    TF

    0

    3

    20

    0

    Activity

    A

    B

    CD

    E

    Critical Act.

    Yes

    No

    NoYes

    Yes

    MDPPDM C l l ti

  • 7/30/2019 3. Project Analysis Tools

    19/50

    19

    A

    3

    B

    3

    C

    5

    D

    7

    E

    4

    F

    6

    G

    4

    I

    9

    H

    6

    J

    8

    Fn

    12 20

    10 166 10

    6 12

    8 12

    10 19

    3 6

    3 8

    3 10

    0 3

    12 20

    14 208 12

    6 12

    8 12

    11 20

    3 6

    3 8

    4 11

    0 3

    Act

    Dur

    ES EF

    LS LF

    TF/FF

    ethod)MiagramDrecedenceP(PDM =PDM Calculations

    Example

    0/ 0

    0/ 0

    0/ 0

    1/ 0

    2/ 0

    0/ 0

    0/ 0

    1/1

    4/4

    0/0

    TF/FF

    TFi = LFi - EFi

    Free Float (FF) = ETj

    ETi

    dor FF = smallest ES (of succeeding activities) EF (of current activity)

  • 7/30/2019 3. Project Analysis Tools

    20/50

    20

    Precedence Relationships - Lead & LagFFij Lag time for a finish-to-finish relationship. (The succeeding

    activity finishes this amount of time after the completion of thepreceding activity.)

    SSij Lead time for a start-to-start relationship. (The preceding

    activity starts this much earlier than the start of the

    succeeding activity.)

    FSij Lag time for a finish-to-finish relationship. (The succeeding

    activity starts this amount of time after the completion of the

    preceding activity.)

    SFij Lead time for a start-to-finish relationship. (The preceding

    activity starts this much earlier than the completion of the

    succeeding activity.)

  • 7/30/2019 3. Project Analysis Tools

    21/50

    21

    PRECEDENCE LOGIC1. Preceding Activities.

    Which activities must be finished before this activity may begin ?

    What is the time lag? (finish to start.)

    Which activities must be started before this activity may begin?

    What is the lead time (start to start.)

    Which activities must be finished before this activity may be completed?

    What is the lag time? (Finish to finish)

    Which activities must be started before this activity is completed?What is the lead time ? (start to finish.)

  • 7/30/2019 3. Project Analysis Tools

    22/50

    R. RUSTOM 22

    Follow: PRECEDENCE LOGIC

    2. Succeeding Activities

    Which activities can begin after the finish of this activity?

    What is the time lag? (finish to start.)

    Which activities can begin after the start of this activity?

    What is the lead time? ( Start to start )

    Which activities can be completed after the finish of this activity?

    What is the lag time? (Finish to finish.)

    Which activities can finish after the start of this activity? What is

    the lead time? (Start to finish.)3. Concurrent Activities.

    Which activities can be carried out at the same time?

    (Start to start equals zero, that is, SS = 0 in this case.)

  • 7/30/2019 3. Project Analysis Tools

    23/50

    23

    Lead/Lag Relationships

    ES DESC.EF ES DESC. EF

    FF ij

    FS ij

    SS ijSF ij

    Forward Pass

    Backward Pass

    i Di jDj

    LS DESC.LF LS DESC. LF

    FF jk

    FS jk

    SS jk

    SF jk

    j Dj kDk

  • 7/30/2019 3. Project Analysis Tools

    24/50

    24

    PDM Activity Diagramming Methods

    Activity No.

    Duration RESP.StartSide

    Finish

    Side

    METHOD 1

    Activity No.

    Duration RESP.StartSide

    Finish

    Side

    METHOD 2

    DESCRIPTION DESCRIPTION

    ES

    LS

    EF

    LF

    Activity No.

    LS LF

    Sta

    rtSide

    Finish

    Side

    METHOD 3

    Activity No.

    Sta

    rtSide

    Finish

    Side

    METHOD 4

    DESCRIPTION DESCRIPTION

    ES

    LS

    EF

    LF

    DUR TF

    ES EFDuration RESP.

  • 7/30/2019 3. Project Analysis Tools

    25/50

    25

    Logical Relationships of PDM

    12

    FINISH - TO - START

    Layout & Excavate

    2 GO

    12Install exterior

    Conduit & piping

    5 EL

    20

    FINISH - TO - FINISH

    Install fuel tanks

    2 GO

    12Install exterior

    Conduit & piping

    5 EL

    10Contract

    Award

    2 GO

    10Layout &

    Excavate

    2 GO

    START - TO - FINISH

    12

    Layout &

    Excavate

    2 GO

    18

    Install fuel

    tanks

    2 ME

    START - TO - START

    12

    Layout & Excavate

    2 GO

    12Install exterior

    Conduit & piping

    5 EL

    Relationship with Lag

    1

  • 7/30/2019 3. Project Analysis Tools

    26/50

    PDM Calculation Procedure(Assumes no splitting of activity is allowed)

    FORWARD PATH

    Step 1

    jiji

    jiji

    iji

    iji

    j

    DSFES

    DFFEF

    SSES

    FSEF

    MaxES

    1

    Step 2

    jjj DESEF

  • 7/30/2019 3. Project Analysis Tools

    27/50

    27

    Follow PDM Calculation Procedure

    BACKWARD PATH

    Step 1

    iijj

    iijj

    ijj

    ijj

    i

    DSFLF

    DSSLS

    FFLF

    FSLS

    alTimeTer

    MinLF

    min

    Step 2

    iii DLFLS

  • 7/30/2019 3. Project Analysis Tools

    28/50

    28

    Calculation of Total Float and Free Float

    Total Float

    iii EFLFTF

    Free Float

    iijj

    iijj

    iijj

    iijj

    ESSFEF

    EFFFEF

    ESSSES

    EFFSES

  • 7/30/2019 3. Project Analysis Tools

    29/50

    29

    A

    10

    B

    7

    C

    10

    D

    10

    E4

    F

    3

    G

    10

    H

    15

    I

    7

    K

    5

    L

    5

    J

    3

    M

    6

    N

    8

    SS5

    FS2

    FF2

    SS5

    FF1

    FS5

    FS3

    SF7

    SS2

    SS10, FF2

    FS2

    SS3

    FF2, SS1

    FS1

    FF0

    1 11

    6 13

    11 21

    11 21

    7 11

    15 18

    21 31

    16 31

    16 23

    23 28

    28 33

    11 14

    31 37

    38 46

    38 46

    ESi + SSij

    1 +5 = 6

    EFi + FFi - Di

    11 + 0 - 4

    FS0

    FS0

    EFi + FSij

    13 + 2

    ESi + SFij - Dj

    15 + 7 -5

    EFi + FFij - Dj

    28 + 2 - 8

    ESi + SSij

    23 + 1

    EFi + FFij-Dj13 + 2 -10

    FS0

    ESi +SSij

    11 + 5

    EFi + FFij - Dj

    21 + 1 - 7

    EFi + FSij

    11 +5

    ESi + SSij

    21 + 2

    ESi + SSij

    16 + 10

    EFi + FFij - Dj

    31 + 2 - 5

    EFi+FSij

    23 + 2

    FS0

    EFi + FSij

    14 + 3

    ESi+SSij

    28+3EFij+FSij

    37+1

    FORWARD PASS

  • 7/30/2019 3. Project Analysis Tools

    30/50

    30

    A

    10

    B

    7

    C

    10

    D

    10

    E4

    F

    3

    G

    10

    H

    15

    I7

    K

    5

    L

    5

    J

    3

    M

    6

    N

    8

    SS5

    FS2

    FF2

    SS5

    FF1

    FS5

    FS3

    SF7

    SS2

    SS10, FF2

    FS2

    SS3

    FF2, SS1

    FS1

    FF0

    38 46

    38 46

    31 37

    31 37

    23 28

    37 42

    28 33

    28 33

    11 14

    25 28

    15 18

    35 38

    21 31

    35 45

    16 31

    16 31

    16 23

    19 26

    6 13

    26 33

    11 21

    11 21

    11 21

    15 25

    7 11

    11 14

    1 11

    1 11

    LFj - FFij

    46 - 2

    LSj - SSj - Di

    38 - 1 + 5

    LSj - FSij

    38 - 1

    LSj - SSij + Di

    31 - 3 + 5

    LSj - FSij

    31 - 3

    LFj - Sfij + Di

    42 - 7 + 3

    LSj - SSij + Di

    37 - 2 + 10

    LFi - FFij

    33 - 2

    LSj - SSij + Di

    28 - 10 + 15

    LSj - FSij

    28 - 2LSj - FSij

    19 - 5

    LFj - FFij

    26 - 1

    LSj - SSij + Di

    16 - 5 + 10

    FS0

    LSj - FSij

    35 - 2

    LSj - SSij + Di26 - 5 + 10

    SF0

    SF0

    SF0

    LFj - FFij

    45 - 2

    BACKWARD PASS

  • 7/30/2019 3. Project Analysis Tools

    31/50

    31

    A

    10

    B

    7

    C

    10

    D

    10

    E

    4

    F

    3

    aG

    10

    H

    15

    I

    7

    K

    5

    L

    5

    J

    3

    M

    6

    N

    8

    SS5

    FS2

    FF2

    SS5

    FF1

    FS5

    FS3

    SF7

    SS2

    SS10, FF2

    FS2

    SS3

    FF2, SS1

    FS1

    FF0

    38 46

    38 46

    31 37

    31 37

    28 33

    28 33

    11 14

    25 28

    23 28

    37 42

    15 18

    35 38

    21 31

    35 45

    16 31

    16 31

    1623

    19 26

    6 13

    26 33

    11 21

    11 21

    11 21

    15 25

    7 11

    11 14

    1 11

    1 11

    ESj - SSij - ESi

    6-5-1

    ESj - FSij - EFi

    15 - 2-13

    ESj - Sfij - ESi

    28 - 7 - 15 ESj - SSij - ESi

    38 - 1 - 23

    EFj - FFij - EFi

    46 - 2 - 28

    ESj - FSij - EFi

    38 - 1 - 37

    ESj - FSij - EFi31 - 3 - 14

    ESj - FSij - EFi

    11 - 0 - 11

    ESj - FFij -EFi11 - 0 - 11

    EFj - FFij - EFi

    31 - 2 - 13

    ESj - SSij - ESi

    16 - 5 - 11

    ESj - FSij -EFi

    21 - 0 - 21

    FS0

    ESj - FFij - EFi

    23 - 1 - 21

    ESj - FSij - EFi

    16 - 5 - 11

    FS0

    ESj - SSij - ESi

    23 - 2 - 21

    ESj - FSij - EFi

    28 - 2 - 23

    EFj - FFij - EFi

    33 - 2 - 31

    ESj - SSij - ESi

    28 - 10 - 16

    ESj - SSij - ESi

    31 - 3 28

    0/0

    20/0

    0/0

    4/1

    3/0

    20/0

    14/0

    0/0

    3/3

    14/14

    0/0

    14/14

    0/0

    0/0

    FS0

    FS0

    ESj - FSij - ESj

    11 - 0 - 1

    ESj - FSij - Efi

    11 - 0 - 11

    TF/FF

    TFi = LFi - EFi

  • 7/30/2019 3. Project Analysis Tools

    32/50

    32

    4.4 Time-Scaled Diagrams:

    Time-scaled diagrams are used extensively in the construction industry.

    Such diagrams enable one

    to determine immediately which activities are scheduled to

    proceed at any point in time .to monitor field progress.

    it can be used to determine resources need.

    The time scale used in time-scaled diagrams can be either the calendar datesor the working periods (ordinary dates), or using both at the same time.

    Its disadvantage is that it needs a great effort to be modified or updated. Also,it can not be used to

    represent overlapping activities.

    A

    3

    C

    4

    B3

    D

    6

    E

    5

    3

    2

    Time-scaleddiagram

    1 2 3 4 5 6 7 8 9 10 11 12 13 14

  • 7/30/2019 3. Project Analysis Tools

    33/50

    33

    The TF for activity A equals the smallest of the sum of the floats along all pathsfrom the end of activity A to the end of the project. The float on path ABE = 3,path ACE = 2 and path ADE = 0, then the TF of activity A = 0. The calculationsare shown in Table 4.2.

    Table 4.2 Time-scaled diagram calculations

  • 7/30/2019 3. Project Analysis Tools

    34/50

    34

    Schedule Presentation:4.5

    After the AOA and AON calculations are made, it is important to present theirresults in a format that is clear and understandable to all the parties involved in

    , named afterBar chart or Gantt chartthe project. The simplest form is thethe person who first used it. A bar chart is a time versus activity chart in which

    activities are plotted using their early or late times.

    a) Earlybar chat

    b) Latebar chart

  • 7/30/2019 3. Project Analysis Tools

    35/50

    35

    The bar chart representation:

    It shows various details. Float times of activities, critical activities can be shownin a different color, or bold borders, as shown in Figure 4.12. The bar chart canalso be used for accumulating total daily resources and / or costs, as shown atthe bottom part of Figure 6.13. In this figure, the numbers on each activity

    represent the number of labors needed.

    Figure 4.13: Using bar chart to accumulate resources

  • 7/30/2019 3. Project Analysis Tools

    36/50

    36

    4.6 Criticisms to Network Techniques:

    1- Assume all required resources are available:

    The CPM calculations do not incorporate resources into their formulation. Also,

    as they deal with activity durations only, it can result in large resourcefluctuations. Dealing with limited resources and resource leveling, therefore,has to be done separately after the analysis.

    2- Ignore project deadline:

    The formulations of CPM and PDM methods do not incorporate a

    deadline duration to constrain project duration.

    3- Ignore project costs:

    Since CPM and PDM methods deal mainly with activities durations, they do notdeal with any aspects related to minimize project cost.

    4- Use deterministic durations:

    The basic assumption in CPM and PDM formulations is that activity durationsare deterministic. In reality, however, activity durations take certain probabilitydistribution that reflect the effect of project conditions on resource productivityand the level of uncertainty involved in the project.

  • 7/30/2019 3. Project Analysis Tools

    37/50

    37

    Solved Examples4.7

    3.1Example

    For the project data in Table 4.3, answer the following questions:

    a) Draw an AOA network of the project?

    b) Perform forward path and backward path calculationsc) What is the effect of delaying activity D by 3 days?

  • 7/30/2019 3. Project Analysis Tools

    38/50

    38

    Solution:

    a, b

    0

    1 A 2

    3

    5 6

    0

    2

    4

    2 2

    8 8

    14 14 16 16

    9 11

    B

    6

    E

    6

    C

    3 F

    3

    G

    21D

    8,or10

    14,or122,or 8

    9,or 5

    c) Total float of activity D = LF ES d = 11 8 1 = 2.

    3 2l

  • 7/30/2019 3. Project Analysis Tools

    39/50

    39

    3.2Example

    Perform PDM calculations for the small project below and determine activitytimes. Durations are shown on the activities.

    S l ti 7 9

  • 7/30/2019 3. Project Analysis Tools

    40/50

    40

    Solution:

    1 5

    B(4)

    1 5

    5 6

    D(1)

    5 6

    6 7

    G(1)

    6 7

    7 14

    J(7)

    7 14

    14 16

    L(2)

    14 16

    1 2

    C(1)

    6 7

    2 4

    E(2)

    7 9

    4 5

    H(1)

    9 10

    2 4

    F(2)

    8 10

    5 9

    K(4)

    10 14

    0 1

    A(1)

    0 1

    7 9

    I(2)

    12 14

    7or85or4

    9or9or14

    1or6

    12or7

    3 3E l

  • 7/30/2019 3. Project Analysis Tools

    41/50

    41

    3.3Example

    For the activities listed in the table below, draw the time-scaled diagram andmark the critical path. Determine the completion time for the project. Tabulateactivities times and floats.

    S l ti

  • 7/30/2019 3. Project Analysis Tools

    42/50

    42

    Solution:

    3 4E l

  • 7/30/2019 3. Project Analysis Tools

    43/50

    43

    3.4Example

    Perform PDM calculations for the small AoN network shown here. Pay specialattention to the different relationships and the lag times shown on them.

    Solution:

    0 3

    A(3)

    0 3

    2 5

    B(3)

    4 7

    3 7

    C(4)

    3 7

    3 9

    D(6)

    4 10

    7 12

    E(5)

    7 12

    SS2

    FF2

    5 or 7 or

    2=9-2-5

    12-2=10

    4 or 3 or5=4-2+3

    4Exercise

  • 7/30/2019 3. Project Analysis Tools

    44/50

    44

    (Cont.)4Exercise

  • 7/30/2019 3. Project Analysis Tools

    45/50

    45

    (Cont.)4Exercise

  • 7/30/2019 3. Project Analysis Tools

    46/50

    46

    (Cont.)4Exercise

  • 7/30/2019 3. Project Analysis Tools

    47/50

    47

    (Cont.)4Exercise

  • 7/30/2019 3. Project Analysis Tools

    48/50

    48

    (Cont.)4Exercise

  • 7/30/2019 3. Project Analysis Tools

    49/50

    49

    (Cont.)4Exercise

  • 7/30/2019 3. Project Analysis Tools

    50/50

    50