1 3PM3_T_B – Planning Time Inspect work Start: 4/13/ ID: 2 Finish: 4/17/ Dur: 3 days Res: Phone customs Start: 4/16/ ID: 4 Finish: 4/16/ Dur: 1 day Res: Prepare shipping paperw Start: 4/16/ ID: 3 Finish: 4/17/ Dur: 2 days Res: Ship Start: 4/18/ ID: 5 Finish: 4/18/ Dur: 1 day? Res: Complete work Start: 4/9/0 ID: 1 Finish: 4/12/ Dur: 4 days Res: ID Task Name Duratio 1 Toronto Nuclear Power Plant Design 890 day 2 Phase 1: Site Selection 110 day 3 Environmental Assessment 30 days 4 Hydrological Surveys 1 mon 5 Review of impacts to wildl 2 wks 6 Rough thermal emission ana 1.5 mon 7 Political Consultation 100 day 8 Obtain federal development 1 mon 9 Meetings with regulatory b 2 mon 10 Consultation with local re 2 mon 11 Geological Survey 60 days 12 RFP for survey firm 3 wks 13 Bid process and selection 6 wks 14 Review of candidate areas 3 wks 15 Power Transmission Assessment 110 day 16 Review of usage 2 wks 17 Model for future demand 9 wks 18 Trade studies for potentia 8 wks 19 Final report and review 3 wks 20 Phase 2: Reactor Preliminary De 140 day 21 Selection of Reactor Type 4 mon 22 Rough Reactor Sizing 5 mon 23 Selection of Prime Subcontrac 3 mon 24 Phase 3: Reactor Detailed Desig 8 mon 25 Phase 4: Construction 18 mon 26 Phase 5: Commissioning 6 mon Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 2007 2008 2009 2010 2011 Activity List Resource Plan Finish-to-Start39 D ata M anagem ent 2h 1d Subm itthrough D ata M anagem ent 40 Finish-to-Start38 ProjectManager 3h 1d ProjectM anagerR eview 39 Finish-to-Start37 M echanical Engineering 8h 2d C heck R eport 38 Finish-to-Start36 Engineering Publications 45h 2w Prepare R eport 37 Finish-to-Start35 TestEngineering 2h 1d Provide D ata Package to Publications 36 Finish-to-StartTestCompletion TestEngineering 9h 3d C ollate TestR esults 35 LogicalD ependency R esource C ost D uration D escription Q ualification TestR eport BCA Finish-to-Start39 D ata M anagem ent 2h 1d Subm itthrough D ata M anagem ent 40 Finish-to-Start38 ProjectManager 3h 1d ProjectM anagerR eview 39 Finish-to-Start37 M echanical Engineering 8h 2d C heck R eport 38 Finish-to-Start36 Engineering Publications 45h 2w Prepare R eport 37 Finish-to-Start35 TestEngineering 2h 1d Provide D ata Package to Publications 36 Finish-to-StartTestCompletion TestEngineering 9h 3d C ollate TestR esults 35 LogicalD ependency R esource C ost D uration D escription A ctivities Q ualification TestR eport BCA W ork Package: Network Diagram Integrated Schedule Finish-to-Start39 D ata M anagem ent 2h Subm itthrough Data M anagem ent 40 Finish-to-Start38 ProjectM anager 3h ProjectM anagerR eview 39 Finish-to-Start37 M echanical Engineering 8h C heck R eport 38 Finish-to-Start36 Engineering Publications 45h Prepare R eport 37 Finish-to-Start35 TestEngineering 2h Provide D ata Package to Publications 36 Finish-to-StartTestC om pletion TestEngineering 9h Collate TestResults 35 LogicalD ependency R esource C ost D escription Qualification TestR eport BCA Finish-to-Start39 D ata M anagem ent 2h 1d Subm itthrough Data M anagem ent 40 Finish-to-Start38 ProjectM anager 3h 1d ProjectM anagerR eview 39 Finish-to-Start37 M echanical Engineering 8h 2d C heck R eport 38 Finish-to-Start36 Engineering Publications 45h 2w Prepare R eport 37 Finish-to-Start35 TestEngineering 2h 1d Provide D ata Package to Publications 36 Finish-to-StartTestC om pletion TestEngineering 9h 3d Collate TestResults 35 LogicalD ependency R esource C ost D uration D escription A ctivities Qualification TestR eport BCA W ork Package: Duration Estimate Activity Definition Activity sequencing Activity Resource Estimating Activity Duration Estimating Schedule Development