3 FEATURES OF PUBLIC PARTICIPATION IN INDONESIA EIA SCHEME RIKA FAJRINI INDONESIAN CENTER FOR ENVIRONMENTAL LAW
9

3 FEATURES OF PUBLIC PARTICIPATION IN INDONESIA EIA …greenaccess.law.osaka-u.ac.jp/wp-content/uploads/2018/09/rfajrini... · (2) Strong consequence on lack of public participation

Mar 12, 2019

Download

Documents

lamkhanh
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: 3 FEATURES OF PUBLIC PARTICIPATION IN INDONESIA EIA …greenaccess.law.osaka-u.ac.jp/wp-content/uploads/2018/09/rfajrini... · (2) Strong consequence on lack of public participation

3 FEATURES OF PUBLIC PARTICIPATION IN INDONESIA EIA SCHEMERIKA FAJRINI

INDONESIAN CENTER FOR ENVIRONMENTAL LAW

Page 2: 3 FEATURES OF PUBLIC PARTICIPATION IN INDONESIA EIA …greenaccess.law.osaka-u.ac.jp/wp-content/uploads/2018/09/rfajrini... · (2) Strong consequence on lack of public participation

Indonesia EIA Procedure

Page 3: 3 FEATURES OF PUBLIC PARTICIPATION IN INDONESIA EIA …greenaccess.law.osaka-u.ac.jp/wp-content/uploads/2018/09/rfajrini... · (2) Strong consequence on lack of public participation

SELECTED FEATURES OF PUBLIC PARTICIPATION

Broad range of public

participants

Strong consequence

on lack of public participation

Community’s representative in

EIA Appraisal Committee

Page 4: 3 FEATURES OF PUBLIC PARTICIPATION IN INDONESIA EIA …greenaccess.law.osaka-u.ac.jp/wp-content/uploads/2018/09/rfajrini... · (2) Strong consequence on lack of public participation

(1) Broad range of public participants

• Directly affected (both positively and negatively)

• Exist in the EIA study area (social boundaries)

Affected communities

• Not affected• Those who care about the environmentEnvironmentalists

• Affected• Exist outside the EIA study area

All parties who will be affected by the

decision in EIA

Law no 32 year 2009 article 26 paragraph 3 ; Government Regulation no 27 year 2012 article 9, paragraph 1; MoE regulation no 17 year 2012, guideline chapter II,

Page 5: 3 FEATURES OF PUBLIC PARTICIPATION IN INDONESIA EIA …greenaccess.law.osaka-u.ac.jp/wp-content/uploads/2018/09/rfajrini... · (2) Strong consequence on lack of public participation

(2) Strong consequence on lack of public participation

Mandatory requirement in EIA scoping study (KA-ANDAL) appraisal

•Result of public participation (consultation and written submission) shall be incorporated/attached in KA-ANDAL

•Absence of public participation result in KA-ANDAL will make the scoping study rejected by technical team in EIA Appraisal Committee

Ground for filing lawsuit against the permit

•Lack of public participation can be a legal reason to argue that EIA is procedurally defect thus the environmental permit shall be revoked

Page 6: 3 FEATURES OF PUBLIC PARTICIPATION IN INDONESIA EIA …greenaccess.law.osaka-u.ac.jp/wp-content/uploads/2018/09/rfajrini... · (2) Strong consequence on lack of public participation

(3) Community’s representative in EIA Appraisal Committee

EIA Appraisal Board Committee consist of:

a. environmental agency;

b. relevant technical agency;

c. expert in the knowledge of types of undertakings and/or activities that are being assessed

d. Affected community’s representatives

e. Environmental organization

Article 30 paragraph (1) Law no 32 year 2009

Page 7: 3 FEATURES OF PUBLIC PARTICIPATION IN INDONESIA EIA …greenaccess.law.osaka-u.ac.jp/wp-content/uploads/2018/09/rfajrini... · (2) Strong consequence on lack of public participation

(3) Community’s representative in EIA Appraisal Committee

Pointers:

´ Affected community chose their representatives to be the member of EIA Appraisal Committee

´ The election is done along with public consultation

´ Number of representatives are varied, decided proportionally and taking into account the interest they represent

´ Result of representatives election is formalized in the form of agreement letter/power of attorney letter

´ EIA initiator deliver the result of representative election to the EIA Appraisal Committee

MoE regulation no 17 year 2012

Page 8: 3 FEATURES OF PUBLIC PARTICIPATION IN INDONESIA EIA …greenaccess.law.osaka-u.ac.jp/wp-content/uploads/2018/09/rfajrini... · (2) Strong consequence on lack of public participation

(3) Community’s representative in EIA Appraisal Committee

The Challenge : How loud is their voice to be listened to?

Page 9: 3 FEATURES OF PUBLIC PARTICIPATION IN INDONESIA EIA …greenaccess.law.osaka-u.ac.jp/wp-content/uploads/2018/09/rfajrini... · (2) Strong consequence on lack of public participation

(3) Community’s representative in EIA Appraisal Committee

Success story:

Gombong Cement Mining Case (Kebumen, Central Java)

Lesson learnt:- Counter scientific evidence from community