Page 1
8/3/2019 2nd River Basin Stakeholder Workshop: Presentation
http://slidepdf.com/reader/full/2nd-river-basin-stakeholder-workshop-presentation 1/12
RETA 6470 Update
nd Workshop4-Ps River Basin Cambodia
12-14 August 2010
Dennis Von Custodio
TA Coordinator and IWRMSpecialist (Consultant)
1/18
ADB RETA 6470
Page 2
8/3/2019 2nd River Basin Stakeholder Workshop: Presentation
http://slidepdf.com/reader/full/2nd-river-basin-stakeholder-workshop-presentation 2/12
Context
RETA 6470: Managing Water in Asia's River Basins:Charting Progress and Facilitating Investment
• RBO knowledge service
• IWRM performance assessment
• RBO performance improvement
ADB
Page 3
8/3/2019 2nd River Basin Stakeholder Workshop: Presentation
http://slidepdf.com/reader/full/2nd-river-basin-stakeholder-workshop-presentation 3/12
ADB’s Water Financing Program
Urban WaterRural Water Basin Water
Focuses on investments to improve health and livelihoods in rural communities, including those forwater supply and sanitation, and irrigation and drainage
Urban WaterConcentrates on sustaining economic growth in cities through investments in water supply, sanitation
an wastewater management, an env ronmenta mprovementBasin Water
Promotes IWRM, covering healthy rivers through investments in infrastructure and management ofmultifunctional water regulation and hydropower facilities, flood management, watershed andwetlands conservation
http://www.adb.org/Water/WFP/investment.asp
Page 4
8/3/2019 2nd River Basin Stakeholder Workshop: Presentation
http://slidepdf.com/reader/full/2nd-river-basin-stakeholder-workshop-presentation 4/12
RETA 6470 – 5 pilot basins
Baitarani,Orissa
Vu Ghia-Thu Bon,Viet Nam
4-Ps,Cambodia
e u,
Philippines
Bengawan Solo,Indonesia
Baitarani Solo CentralCebu
4Ps VGTB
Catchment2
14,218 16,100 480 12,470 10,350
6/22
population 4,400,000 16,000,000 210,325 163,000 1,400,000
Page 5
8/3/2019 2nd River Basin Stakeholder Workshop: Presentation
http://slidepdf.com/reader/full/2nd-river-basin-stakeholder-workshop-presentation 5/12
-
Mekong River
Tonle Sap
4-Ps River Basin
2/18
4 main Preks and their streams connecting to the MekongRiver
Page 6
8/3/2019 2nd River Basin Stakeholder Workshop: Presentation
http://slidepdf.com/reader/full/2nd-river-basin-stakeholder-workshop-presentation 6/12
RETA 6470 Activities
in the 4Ps River Basin
• national consultant engaged
• documents prepared insupport to 4-Ps basindevelopment andmanagement
- draft IWRM investmentroadmap
- draft river basin profile
- case studies on goodIWRM practices
•
workshops: (i) 18-20 Jan,Kratie; and (ii) 12-14 Aug,Mondulkiri
Page 7
8/3/2019 2nd River Basin Stakeholder Workshop: Presentation
http://slidepdf.com/reader/full/2nd-river-basin-stakeholder-workshop-presentation 7/12
1st Basin Stakeholder Workshop, 4-Ps River Basin,
Cambodia, 18-20 January 2010
66 total participants
- ,
Cebu (PHI) and Vu Gia–Thu Bon (VIE), ADB consultants- national level: CNMC; Ministries of Agriculture, Industry
and Mines, Forestr and Fisheries, Environment, Plannin ,Rural Development, Water Resources and Meteorology
- local level: Kratie and Mondulkiri Provinces; line
agencies/sector departments; local community
- national consultant
9/18
Page 8
8/3/2019 2nd River Basin Stakeholder Workshop: Presentation
http://slidepdf.com/reader/full/2nd-river-basin-stakeholder-workshop-presentation 8/12
1st Basin Stakeholder Workshop, 4-Ps River
Basin, Cambodia, 18-20 January 2010
•
• initial ideas on IWRM development needs,options and potential for the four PreksIWRM investment roadma
More inputs on the draft IWRM
stakeholder workshop!
9/18
Page 9
8/3/2019 2nd River Basin Stakeholder Workshop: Presentation
http://slidepdf.com/reader/full/2nd-river-basin-stakeholder-workshop-presentation 9/12
1st Basin Stakeholder Workshop, 4-Ps River Basin,18-20 January 2010
Half-day study visit
Kohsakrom irrigation scheme and dialogue with
farmers
Visit to Prek Kampi (driving along the Mekong
River) – tourism development in the basinrelated to dolphin spotting
Page 10
8/3/2019 2nd River Basin Stakeholder Workshop: Presentation
http://slidepdf.com/reader/full/2nd-river-basin-stakeholder-workshop-presentation 10/12
Status of Implementation – In comparison
Progress by Pilot Basin
OutputsPP Baitarani Solo C Cebu 4Ps VGTB
Over-all progress 25 pct 70 pct 90 pct 90 pct 25 pct
Kick-off meeting 10 Aug ’09 Apr ’09 Sep ’09 Feb ’09 Feb ’09
Basin profile outline 10 Aug ’09 Apr ’09 Sep ’09 May ’09 Mar ’09
1st stakeholder workshop 20 X May ’09 May ’10 Jan ’10 x
Roadmap outline 10 X Sep ’09 Jun ’10 Jun ’10 x
’ ’
Consolidated basin profile 5 X X x X x
Consolidated roadmap 5 x X x X x
Case studies 1=5 pp, SPS-4 SPS-5, 10, 3 case SPS-2, 9 SPS-14
>1=10 pp, s u es
Country assessmentoutline
10 x Jun ’10 July ’10 Dec ’09 x
pp = percentage point
Page 11
8/3/2019 2nd River Basin Stakeholder Workshop: Presentation
http://slidepdf.com/reader/full/2nd-river-basin-stakeholder-workshop-presentation 11/12
Key Messages in IWRM Implementation
• Political will is a key for IWRM success
• oca now e ge s mpor an o a ress wa erchallenges
• Active community involvement in the development andmanagement of the river basin is crucial
• Capacity of the 4Ps RBO should be strengthened
Page 12
8/3/2019 2nd River Basin Stakeholder Workshop: Presentation
http://slidepdf.com/reader/full/2nd-river-basin-stakeholder-workshop-presentation 12/12
Thank You!
20/20